MACC RFP FA9401-12-R-0002 Amendment 2-Conformed Copy.pdf

PDF 1 MB Posted

Attached to
Multiple Award Construction Contract (MACC) Federal contract opportunity
Solicitation number
FA9401-12-R-0002
Issued by
Department of the Air Force Global Strike Command

About this file

Solicitation FA9401-12-R-0002 Amendment 2 - Conformed Copy

View the file

Other files for this federal contract opportunity

Other files attached to Multiple Award Construction Contract (MACC), newest first.
File Type Posted
Attch_2_-_Wage_Determination_(Bernalillo_County)__Residential_dated_4-6-2012.pdf PDF
MACC_RFP_FA9401-12-R-0002_Amendment_10.pdf PDF
Attch_1_-_Wage_Determination_(Bernalillo_County)__Building_dated_7-20-2012.pdf PDF
MACC_RFP_FA9401-12-R-0002_Amendment_9.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 8.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 9.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 8.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 6-Conformed Copy.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 6.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 6.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 7.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 5.pdf PDF
RFP FA9401-12-R-0002 Pre-Proposal Conference-Site Visit Final Sign-in Sheet.pdf PDF
MACC Pre-Proposal Brief.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 5-Conformed Copy.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 4.pdf PDF
Attch 5 - Past Performance Information Questionnaire Package.docx DOCX document
MACC RFP FA9401-12-R-0002 Amendment 3.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 2.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 1.doc DOC document
Attch 40 - Kirtland AFB-West Map.pdf PDF
Attch 37 - Seed Project - Future Expansion Power Requirements Table.pdf PDF
Attch 35 - Seed Project Water flow Test Results.pdf PDF
Attch 25 - Appendix 14.1 - Guidance and Standards-Irrigation.pdf PDF
Attch 18 - Appendix 7 Air Force Federal Mandates Quick Reference.pdf PDF
Attch 2 - Wage Determination —
Attch 16 - Appendix 5 - AF Form 592 —
Attch 28 - Appendix 14.4 Guidance Standards-Minimum Communication Standards.pdf PDF
Attch 6 - MACC General Provisions.pdf PDF
Attch 5 - Past Performance Information Questionnaire Package.docx DOCX document
Attch 23 - Appendix 12 - Waste Diversion Report.pdf PDF
Attch 36 - Seed Project - Westside Shoppette Geotechnical Report.pdf PDF
Attch 31 - Seed Project Price Schedule - AF3052.xlsx XLSX spreadsheet
Attch 30 - Seed Project Statement of Work.pdf PDF
Attch 22 - Appendix 11 - DoD Minimum Antiterrorism Construction Standards Pre-Final Checklist.pdf PDF
Attch 39 - AF Form 3065 - Progress Report.pdf PDF
Attch 21 - Appendix 10 - Base Access Procedures KAFB.pdf PDF
Attch 24 - Appendix 13 - AF LEED SDD Implementation Guidance.pdf PDF
Attch 12 - Appendix 4.3 - 16710 Communications.pdf PDF
Attch 27 - Appendix 14.3 - Guidance and Standards-Toilet Accessory Requirements.pdf PDF
Attch 7 - Appendix 1 - General Design Guidelines.pdf PDF
Attch 17 - Appendix 6 - AF Form 103 Digging Permit.pdf PDF
Attch 29 - Appendix 14.5 - Guidance and Standards-Metering.pdf PDF
Attch 3 - Wage Determination —
Attch 1 - Wage Determination —
Attch 34 - Seed Project ACM-LCM Survey Report B909.pdf PDF
Attch 8 - Appendix 2 - Architectural Compatibility Plan.pdf PDF
Attch 38 - AF Form 3064 - Progress Schedule.xls XLS spreadsheet
Attch 11 - Appendix 4.2 - 13281 Lead Containing Materials Remediation.pdf PDF
Attch 19 - Appendix 8 - Recycling Specification for KAFB.pdf PDF
Show all 50

Multiple Award Construction Contract (MACC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA9401-12-R-0002-0002

A. Project Title: Multiple Aw ard Construction Contract (MACC) – Indefinite Delivery/Indefinite Quantity (IDIQ)

B. This acquisition is a Competitive 8(a) Set-Aside. Competition is restricted to 8(a) companies w ith a * bona f ide place of business in the State of New Mexico. * Definition provided in 13CFR124.3

C. Project performance period is scheduled for a Base one (1) year plus four (4) one-year Option periods.

D. The Guaranteed minimum amount over the life of this contract is $2,000.

E. The total aggregate amount expendable under all MACC contracts aw arded shall not exceed $64 Million for Base and all Option Periods.

F. The “Seed Project” magnitude is betw een $1,000,000 and $5,000,000. The Seed Project w ill be aw arded to the highest rated offeror. All subsequent Task Orders w ill be issued no earlier than 1 June 2012.

G. A Bid Bond in the amount of 20% w ill be required for the Seed Project. See Section H, Special Contract Requirements.

H. Reference Section L, “Instruction, Conditions and Notice to Offerors” for proper proposal preparation and Section M – “Evaluation Factors for Aw ard”.

I. A Pre-proposal conference/site visit is scheduled for 9:00AM on 30 March 2012.

GILBERT MARTINEZ (505)846-2921

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

09-Mar-2012

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______ calendar days and complete it w ithin ________ calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________ Section F

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________4 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________19 Apr 2012 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

AFNWC/PKOD

2000 WYOMING BLVD SE

BLDG 20604

ALBUQUERQUE NM 87117

FA9401

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

01:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued)

(Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

FA9401-12-R-0002

Section B - Supplies or Services and Prices

NOTE

Prices are not required for this section. Prices will be requested for each Task Order.

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 999 Lot Base Period (Design/Repair)

FFP

MACC is a multiple award, competitive, design-build, Indefinite

Delivery/Indefinite Quantity (IDIQ) Firm-Fixed Price construction acquisition based on a general Statement of Work further defined with each individual task order. The work consists of multiple disciplines in general construction categories of on-base facilities at Kirtland AFB, New Mexico. Minimum/Maximum Contract

Amount: Award of the Seed Project constitutes the minimum for the first contract awarded. A minimum of $2,000 is guaranteed over the life of the contract and will be satisfied by attending the MACC Orientation Seminar. The total aggregate maximum amount of this program including all contracts and Option Periods shall not exceed $64,000,000. Base Period (1 Jun 2012 - 31 May 2013)

FOB: Destination

NSN: Y1QA-12-030-CONSTS

SIGNAL CODE: A

NET AMT

0002 999 Lot Base Period (Minor Construction)

FFP

MACC is a multiple award, competitive, design-build, Indefinite

Delivery/Indefinite Quantity (IDIQ) Firm-Fixed Price construction acquisition based on a general Statement of Work further defined with each individual task order. The work consists of multiple disciplines in general construction categories of on-base facilities at Kirtland AFB, New Mexico. Minimum/Maximum Contract

Amount: Award of the Seed Project constitutes the minimum for the first contract awarded. A minimum of $2,000 is guaranteed over the life of the contract and will be satisfied by attending the MACC Orientation Seminar. The total aggregate maximum amount of this program including all contracts and Option Periods shall not exceed $64,000,000. Base Period (1 Jun 2012 - 31 May 2013)

FOB: Destination

1001 999 Lot OPTION Option Year 1 (Design/Repair)

FFP

MACC is a multiple award, competitive, design-build, Indefinite

Delivery/Indefinite Quantity (IDIQ) Firm-Fixed Price construction acquisition based on a general Statement of Work further defined with each individual task order. The work consists of multiple disciplines in general construction categories of on-base facilities at Kirtland AFB, New Mexico. Minimum/Maximum Contract

Amount: Award of the Seed Project constitutes the minimum for the first contract awarded. A minimum of $2,000 is guaranteed over the life of the contract and will be satisfied by attending the MACC Orientation Seminar. The total aggregate maximum amount of this program including all contracts and Option Periods shall not exceed $64,000,000. Option Yr 1 (1 Jun 2013 - 31 May 2014)

FOB: Destination

1002 999 Lot OPTION Option Year 1 (Minor Costruction)

FFP

MACC is a multiple award, competitive, design-build, Indefinite

Delivery/Indefinite Quantity (IDIQ) Firm-Fixed Price construction acquisition based on a general Statement of Work further defined with each individual task order. The work consists of multiple disciplines in general construction categories of on-base facilities at Kirtland AFB, New Mexico. Minimum/Maximum Contract

Amount: Award of the Seed Project constitutes the minimum for the first contract awarded. A minimum of $2,000 is guaranteed over the life of the contract and will be satisfied by attending the MACC Orientation Seminar. The total aggregate maximum amount of this program including all contracts and Option Periods shall not exceed $64,000,000. Option Yr 1 (1 Jun 2013 - 31 May 2014)

FOB: Destination

2001 999 Lot OPTION Option Year 2 (Design/Repair)

FFP

MACC is a multiple award, competitive, design-build, Indefinite

Delivery/Indefinite Quantity (IDIQ) Firm-Fixed Price construction acquisition based on a general Statement of Work further defined with each individual task order. The work consists of multiple disciplines in general construction categories of on-base facilities at Kirtland AFB, New Mexico. Minimum/Maximum Contract

Amount: Award of the Seed Project constitutes the minimum for the first contract awarded. A minimum of $2,000 is guaranteed over the life of the contract and will be satisfied by attending the MACC Orientation Seminar. The total aggregate maximum amount of this program including all contracts and Option Periods shall not exceed $64,000,000. Option Yr 2 (1 Jun 2014 - 31 May 2015)

FOB: Destination

2002 999 Lot OPTION Option Year 2 (Minor Costruction)

FFP

MACC is a multiple award, competitive, design-build, Indefinite

Delivery/Indefinite Quantity (IDIQ) Firm-Fixed Price construction acquisition based on a general Statement of Work further defined with each individual task order. The work consists of multiple disciplines in general construction categories of on-base facilities at Kirtland AFB, New Mexico. Minimum/Maximum Contract

Amount: Award of the Seed Project constitutes the minimum for the first contract awarded. A minimum of $2,000 is guaranteed over the life of the contract and will be satisfied by attending the MACC Orientation Seminar. The total aggregate maximum amount of this program including all contracts and Option Periods shall not exceed $64,000,000. Option Yr 2 (1 Jun 2014 - 31 May 2015)

FOB: Destination

3001 999 Lot OPTION Option Year 3 (Design/Repair)

FFP

MACC is a multiple award, competitive, design-build, Indefinite

Delivery/Indefinite Quantity (IDIQ) Firm-Fixed Price construction acquisition based on a general Statement of Work further defined with each individual task order. The work consists of multiple disciplines in general construction categories of on-base facilities at Kirtland AFB, New Mexico. Minimum/Maximum Contract

Amount: Award of the Seed Project constitutes the minimum for the first contract awarded. A minimum of $2,000 is guaranteed over the life of the contract and will be satisfied by attending the MACC Orientation Seminar. The total aggregate maximum amount of this program including all contracts and Option Periods shall not exceed $64,000,000. Option Yr 3 (1 Jun 2015 - 31 May 2016)

FOB: Destination

3002 999 Lot OPTION Option Year 3 (Minor Costruction)

FFP

MACC is a multiple award, competitive, design-build, Indefinite

Delivery/Indefinite Quantity (IDIQ) Firm-Fixed Price construction acquisition based on a general Statement of Work further defined with each individual task order. The work consists of multiple disciplines in general construction categories of on-base facilities at Kirtland AFB, New Mexico. Minimum/Maximum Contract

Amount: Award of the Seed Project constitutes the minimum for the first contract awarded. A minimum of $2,000 is guaranteed over the life of the contract and will be satisfied by attending the MACC Orientation Seminar. The total aggregate maximum amount of this program including all contracts and Option Periods shall not exceed $64,000,000. Option Yr 3 (1 Jun 2015 - 31 May 2016)

FOB: Destination

4001 999 Lot OPTION Option Year 4 (Design/Repair)

FFP

MACC is a multiple award, competitive, design-build, Indefinite

Delivery/Indefinite Quantity (IDIQ) Firm-Fixed Price construction acquisition based on a general Statement of Work further defined with each individual task order. The work consists of multiple disciplines in general construction categories of on-base facilities at Kirtland AFB, New Mexico. Minimum/Maximum Contract

Amount: Award of the Seed Project constitutes the minimum for the first contract awarded. A minimum of $2,000 is guaranteed over the life of the contract and will be satisfied by attending the MACC Orientation Seminar. The total aggregate maximum amount of this program including all contracts and Option Periods shall not exceed $64,000,000. Option Yr 4 (1 Jun 2016 - 31 May 2017)

FOB: Destination

4002 999 Lot OPTION Option Year 4 (Minor Costruction)

FFP

MACC is a multiple award, competitive, design-build, Indefinite

Delivery/Indefinite Quantity (IDIQ) Firm-Fixed Price construction acquisition based on a general Statement of Work further defined with each individual task order. The work consists of multiple disciplines in general construction categories of on-base facilities at Kirtland AFB, New Mexico. Minimum/Maximum Contract

Amount: Award of the Seed Project constitutes the minimum for the first contract awarded. A minimum of $2,000 is guaranteed over the life of the contract and will be satisfied by attending the MACC Orientation Seminar. The total aggregate maximum amount of this program including all contracts and Option Periods shall not exceed $64,000,000. Option Yr 4 (1 Jun 2016 - 31 May 2017)

FOB: Destination

CONTRACT MINIMUM/MAXIMUM QUANTITY AND CONTRACT VALUE

The minimum quantity and contract value for all orders issued against this contract shall not be less than the minimum quantity and contract value stated in the following table. The maximum quantity and contract value for all orders issued against this contract shall not exceed the maximum quantity and contract value stated in the following table.

MINIMUM

QUANTITY

MINIMUM

AMOUNT

MAXIMUM

QUANTITY

MAXIMUM

AMOUNT

$2,000.00 $10,000,000.00

DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND ORDER VALUE

The minimum quantity and order value for each Delivery/Task Order issued shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for each

Delivery/Task Order issued shall not exceed the maximum quantity and order value stated in the following table.

QUANTITY

MINIMUM

AMOUNT

MAXIMUM

QUANTITY

MAXIMUM

$2,000.00 $3,000,000.00

CLIN DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND CLIN ORDER VALUE

The minimum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not exceed the maximum quantity and order value stated in the following table.

CLIN

QUANTITY

MINIMUM

AMOUNT

MAXIMUM

QUANTITY

MAXIMUM

Section C - Descriptions and Specifications

SECTION C

See Attachment 6, Section J, MACC General Provisions

See Attachment 30, Section J, Seed Project Requirements Documents, LRPD Advanced HPM Research Facility

Expansion (Project # MHMV 110112)

Section E - Inspection and Acceptance

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Destination Government Destination Government

0002 Destination Government Destination Government

1001 Destination Government Destination Government

1002 Destination Government Destination Government

2001 Destination Government Destination Government

2002 Destination Government Destination Government

3001 Destination Government Destination Government

3002 Destination Government Destination Government

4001 Destination Government Destination Government

4002 Destination Government Destination Government

CLAUSES INCORPORATED BY REFERENCE

52.246-12 Inspection of Construction AUG 1996

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC

0001 POP 01-JUN-2012 TO

31-MAY-2013

N/A 377 MSG/CE - F2K2AC

BRENT WILSON

2050 WYOMING BLVD SE

KIRTLAND AFB NM 87117-5663

505-846-7911

FOB: Destination

F2K2AC

0002 POP 01-JUN-2012 TO

31-MAY-2013

N/A (SAME AS PREVIOUS LOCATION)

1001 POP 01-JUN-2013 TO

31-MAY-2014

N/A (SAME AS PREVIOUS LOCATION)

1002 POP 01-JUN-2013 TO

31-MAY-2014

N/A (SAME AS PREVIOUS LOCATION)

2001 POP 01-JUN-2014 TO

31-MAY-2015

N/A (SAME AS PREVIOUS LOCATION)

2002 POP 01-JUN-2014 TO

31-MAY-2015

N/A (SAME AS PREVIOUS LOCATION)

3001 POP 01-JUN-2015 TO

31-MAY-2016

N/A (SAME AS PREVIOUS LOCATION)

3002 POP 01-JUN-2015 TO

31-MAY-2016

N/A (SAME AS PREVIOUS LOCATION)

4001 POP 01-JUN-2016 TO

31-MAY-2017

N/A (SAME AS PREVIOUS LOCATION)

4002 POP 01-JUN-2016 TO

31-MAY-2017

N/A (SAME AS PREVIOUS LOCATION)

52.247-34 F.O.B. Destination NOV 1991

CLAUSES INCORPORATED BY FULL TEXT

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within * calendar days after the date the

Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than **. The time stated for completion shall include final cleanup of the premises.

*The Contracting Officer shall specify in each task order number of days after the date the contractor receives the notice to proceed.

** The Contracting Officer shall specify in each task order the completion no later than date.

(End of clause)

52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of * for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

* Note: Liquidated Damages for the Seed Project will be charged, for each calendar day of delay beyond authorized performance period, at a rate of $310.37 per day. All subsequent Liquidated Damages amounts will be specified on each individual task order.

Section G - Contract Administration Data

CONTRACT ADMINISTRATION DATA

1.1 ADMINISTRATIVE MATTERS

The Address and telephone number for the AFNWC/PKOD:

AFNWC/PKOD

2000 Wyoming Blvd SE, Bldg. 20604 Rm. B-9

Kirtland AFB, NM 87117

(505) 846-2921

1.2 CONTRACTOR’S CONTRACT ADMINISTRATION

To Be Completed By The Contractor:

Name and Title: _________________________________________________________________

Responsible Office: ______________________________________________________________

Address: _______________________________________________________________________

Telephone Number: ______________________________________________________________

Email: _________________________________________________________________________

Cage Code: _____________________________________________________________________

Duns Number: __________________________________________________________________

Tax Identification Number: ________________________________________________________

1.3 INDVIDUAL(S) AUTHORIZED TO NEGOTIATE OR DISCUSS PROPOSAL

Name of Primary: __________________ _ Name of Alternate: _______________________

Address: _________________________ _ Address: _______________________________

Telephone #: ______________________ Telephone #: ____________________________

Alternate #: _______________________ Alternate #: _____________________________

Fax No: ___________________________ Fax No: ________________________________

Email: ____________________________ Email: _________________________________

WIDE AREA WORKFLOW

WIDE AREA WORKFLOW – RECEIPT AND ACCEPTANCE (WAWF-RA)

ELECTRONIC RECEIVING REPORT AND INVOICING INSTRUCTIONS

IN ACCORDANCE WITH DFARS 252.232.7003, USE OF ELECTRONIC PAYMENT REQUESTS IS

MANDATORY. USE OF WAWF WILL SPEED UP YOUR PAYMENT PROCESSING TIME AND

ALLOW YOU TO MONITOR YOUR PAYMENT STATUS ONLINE. THERE ARE NO CHARGES OR

FEES TO USE WAWF.

Requests for payments must be submitted electronically via the Internet through the Wide Area Workflow- Receipt and Acceptance (WAWF-RA) system at https://wawf.eb.mil.

Questions concerning payment should be directed to the Defense Finance Accounting Services (DFAS) Columbus through the DFAS Centralized Customer Service number (800) 756-4571 (select option 2) or faxed to (866) 392-

7091. Please have your order number and invoice number ready when contacting DFAS about payment status. You can also access payment information using the DFAS myInvoice web site at http://www.dod.mil/dfas/contractorpay/myinvoice.html.

THE FOLLOWING CODES WILL BE REQUIRED TO ROUTE YOUR RECEIVING REPORTS,

INVOICES AND ADDITIONAL E-MAILS CORRECTLY THROUGH WAWF.

CONTRACT NUMBER:

DELIVERY ORDER NUMBER:

TYPE OF DOCUMENT: Construction Payment Invoice

CAGE CODE:

ISSUE BY DODAAC: FA9401

ADMIN DODAAC: FA9401

PAY OFFICE DODAAC: F03000

SERVICE ACCEPTOR / SHIP TO:

THESE ARE NOT TYPICIALLY USED – VERIFIED PRIOR TO INSERTING INTO CONTRACT

INSPECT BY DODAAC:

LOCAL PROCESSING OFFICE:

SEND MORE E-MAIL NOTIFICATIONS:

CONTRACT ADMINISTATOR:

CONTRACT OFFICER:

ADDITIONAL NOTIFICATION:

ADDITIONAL NOTIFICATION:

Please contact the POCs above if you have any questions regarding the invoice process http://www.dod.mil/dfas/contractorpay/myinvoice.html

Section H - Special Contract Requirements

SECTION H

1.1 AFNWC/PKOD – HAZMAT HAZARDOUS MATERIAL

All HAZMAT contemplated for use or brought on base for the purpose of this contract, must be coordinated through the Environmental Compliance 377MSG/CEANC. Contractor must provide the Quality Assurance Personnel and CO with a copy of the MSDS (Material Safety Data Sheet) prior to using the HAZMAT and maintain a copy at the work site at all times that work is being performed. Failure to comply with these requirements may result in withholding of payment.

1.2 CONTRACTOR PASSES, SECURITY AND ANTITERRORISM

(a) The contractor shall obtain base identification and vehicle passes for all contractor personnel who make frequent visits to or perform work on Kirtland Air Force Base.

Due to heightened security requirements, prior to obtaining base identification and vehicle passes, each person desiring to work on base must undergo a background screening. The following information is required in order to conduct background checks: Full Name, date of birth, social security number, and driver’s license number and state (only if requesting to drive). The preceding information may be transmitted to the cognizant contracting officer or administrator via e-mail, USPS, or fax. Please allow up to 14 days for completion of the background check for U.S. Citizens and 30 days for all others and response from the contracting office. If any individual is disapproved for base access, the contractor will be notified of the failure, but this does not excuse them from performance of the contract.

(b) After receiving notification of a successful background check, the contractor shall submit a written request on company letterhead (sample formats are available upon request) to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. Individual letters must be accomplished for each employee. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes.

(c) When reporting to the registration office/visitor center, the authorized contractor individual(s) should provide a valid and current drivers license, vehicle registration, and proof of vehicle insurance certificate/card.

(d) The possession and use of the AF Form 75 is intended solely for individuals performing contractual related duties. Any other use or transfer of the pass is strictly prohibited.

(e) Contractor personnel are required to wear or prominently display installation identification badges, or contractor-furnished identification badges, while visiting or performing work on the installation.

(f) Upon completion or termination of contract requirements, all base identification, vehicle/visitor passes, and

Common Access Cards (CACs), if applicable , must be returned to the contracting officer prior to issuance of final payment.

(g) The prime contractor shall provide an antiterrorism awareness brief to all employees, including subcontractors, their employees and all temporary day laborers. The use of the Contractor Antiterrorism

Awareness pamphlet, provided by the Contracting Officer, suffices for this brief. This brief is an annual requirement for contracts which have exercised options. The contractor shall document training and provide records to the Contracting Officer upon request.

1.3 FEDERAL LEGAL HOLIDAYS

The following Federal legal holidays are observed by this base:

New Year’s Day 1 January

Martin Luther King’s Birthday 16 January

President’s Day 20 February

Memorial Day 28 May

Independence Day 4 July

Labor Day 3 September

Columbus Day 8 October

Veterans Day 12 November

Thanksgiving Day 22 November

Christmas Day 25 December

NOTE: Any of the holidays falling on Saturday will be observed on preceding Friday; holidays falling on Sunday will be observed on the following Monday.

1.4 MINIMUM/MAXIMUM CONTRACT AMOUNTS

The contract minimum guarantee is $2,000 per contract applicable to the base year of performance only. All contractor’s receiving award, with the exception of the highest rated awardee receiving a Task Order for the “seed project”, will receive a Task Order with a value of $2,000 for the MACC orientation seminar to satisfy the contract minimum requirement. No additional travel costs will be in reimbursed. The seminar is an open forum discussion on the MACC program and shall provide a contract overview covering several program requirements and procedures to include partnering, contract administration, design/engineering perspectives, quality control program, security/base access processes, construction management processes and site specifics associated with each base. Attendance is mandatory. It will be up to the Contractors to determine which members of their team attend. It is highly encouraged that key team members attend that are intimately involved with design/build, superintendence, quality control and program/project management. The Government makes no representation as to the number of Task Orders or actual amount of work to be ordered in excess of the minimum guarantees specified herein. The maximum aggregate amount of the MACC program, inclusive of all awarded MACC contracts and Task Orders, including options, shall not exceed $64,000,000.00.

1.5 COMMENCEMENT OF WORK

No work under this contract will commence until such time as the Contracting Officer issues a written Task Order and Notice to Proceed under the Task Order.

1.6 PLACE OF PERFORMANCE

The Place of Performance will be designated on each individual Task Order.

1.7 PROPOSAL PREPARATION COSTS

The costs for preparation of Task Order proposals shall be the responsibility of the contractor and not directly reimbursable. Each Task Order awarded will include at a minimum all labor wages, management, supervision, mobilization, material and equipment costs, and any costs associated with any required design effort. The contractor shall furnish all project management, planning, estimating, labor, transportation, materials, equipment, tools, supervision, design if applicable, and all other associated costs necessary to fulfill the requirements of the Task

Order.

1.8 REQUIRED INSURANCE (IAW FAR 28.306(b))

Reference FAR clause entitled “52.228-5 Insurance – Work On A Government Installation” the Contractor shall, at its own expense, procure and thereafter maintain the following kinds of insurance with respect to performance under the contract.

(a) Workman’s Compensation and Employers Liability Insurance as required by law except that if this contract is to be performed in a State which does not require or permit private insurance, then compliance with statutory or administrative requirements in any such State will be satisfactory. The required Workman’s

Compensation insurance shall extend to cover employer’s liability for accidental bodily injury or death and for occupational disease with a minimum liability limit of $100,000.

(b) General Liability Insurance. Bodily injury liability insurance, in the minimum limits of $500,000 per occurrence shall be required on the comprehensive form of policy.

(c) Automobile Liability Insurance. This insurance shall be required on the comprehensive form of policy and shall provide bodily injury liability and property damage liability covering the operation of all automobiles used in connection with the performance of the contract. At least the minimum limits of $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage shall be required.

(d) The Certificate of Insurance shall provide for thirty (30) days written notice to the Contracting Officer by the insurance company prior to cancellation or material change in policy coverage. Other requirements and information are contained in the aforementioned “Insurance” clause.

1.9 INSURANCE CERTIFICATE

The contractor agrees to execute an insurance certificate with the Contracting Office in accordance with Section H, Required Insurance. This certificate shall be executed on the form entitled “Acknowledgment and Certification of compliance with Contract Insurance Requirements”.

1.10 DAVIS BACON WAGE DETERMINATION

Individual Task Orders will be subject to one or more of the applicable Wage Determinations at the time of contract award (see Section J, List of Attachments).

1.11 SUBCONTRACTING RESPONSIBILITIES

The contractor shall be responsible for the management and performance of all subcontracts. The contractor shall ensure Task Orders are completed within the stated requirements. The contractor is responsible for ensuring subcontracting opportunities are made available to small, small disadvantaged, women owned businesses, service disabled veterans, and HUBZone businesses in accordance with the goals of the contract. Reporting responsibilities for Large Business Concerns, if applicable, shall be in accordance with FAR Clause 52.219-9.

1.12 NOTICE OF CONSTRUCTIVE CHANGES

No order, statement or direction of the Contracting Officer, an authorized representative of the Contracting Officer whether or not acting within the limits of his authority, or any other representatives of the Government, shall constitute a change order under the “Changes” clause of this contract or entitle the contractor(s) to an equitable adjustment of the price or delivery schedule, unless such a change is issued in writing and signed by the Contracting

Officer.

1.13 PRE-DESIGN AND/OR PRE-CONSTRUCTION CONFERENCE

Prior to commencing work under a Task Order, the Contractor shall meet with the Contracting Officer and/or designated technical personnel at a mutually agreeable time to discuss and develop mutual understandings concerning schedule and administering work.

1.14 PARTNERING

Partnering is a structured process, as well as philosophy of doing business with contractors and customers, that recognizes common goals through communication and teamwork. It helps create an environment where trust and teamwork prevents disputes, fosters good working relationships to everyone’s benefit, and facilitates the completion of a successful contract. In support of the command’s goals of teamwork and customer satisfaction, our policy is to practice the philosophy of Partnering on every contract we administer. Formal partnering may be required prior to and/or during performance of an individual Task Order, if determined necessary by the Government. Partnering shall be held during normal work hours.

1.15 PERFORMANCE EVALUATIONS

At the conclusion of each Task Order for construction over $500,000.00, the Contracting Office will complete a contractor’s performance evaluation and input into CCASS/ACCAS. The evaluation will take into account all aspects of the contractor’s performance. Performance evaluations may be completed at any time the Contractor’s performance is considered less than satisfactory. Contractors will be provided a copy of the performance evaluation and an opportunity to discuss the evaluation. The performance evaluations may have an impact on the award of future Task Orders.

1.16 SUBSTITUTIONS OF KEY PERSONNEL AND KEY SUBCONTRACTORS

The Contractor shall provide complete resumes for proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced and shall be no less than the standard established in the hiring criteria described in the contractor’s proposal. No change in Task Order pricing may occur as a result of key personnel substitutions.

The contractor shall notify the contracting office of the proposed substitution of key subcontractors (including design subcontractors) at least 30 days in advance of the substitution.

1.17 PAYMENT FOR MATERIALS STORED ON SITE

(a) This clause implements, but does not replace, FAR 52.232-5, Payment Under Fixed-Price Construction

Contracts, with regard to material payments.

(b) Consideration for payment under this contract for materials stored on site is subject to the following conditions:

1) The Contractor shall furnish the Contracting Officer a list of the major high-cost items to be incorporated into the contract and for which payment, prior to installation, will be requested. Those items approved by the Contracting Officer will be entered on the AF Form 3064, Contract Progress

Schedule, as a percentage factor, or factors if items are listed individually.

2) Payment is limited to major high-cost items. Payment of major high-cost items does not include

Contractor overhead and profit. Such costs as sales tax, freight, handling, pallets, etc., are excluded.

3) Payment requests shall be consistent with approved material submittals and shall be supported by the following documents:

Certified paid vendor invoices.

Inventory checklists, jointly validated by the contractor, contract administrator, and/or construction inspector.

Accepted delivery tickets, if applicable.

4) All material for which payment is requested shall be delivered to an approval location on-site, and certified that none will be removed without written permission of the Contracting Officer. Materials may also be stored in a bonded warehouse offsite if there is no adequate storage space on base.

5) Payments will be made monthly, or at more frequent intervals as determined by the Contracting

Officer.

6) The Contractor shall remain responsible and retain title to the materials until incorporated into the work.

1.18 TASK ORDER PROCEDURES

(a) Work under this contract will be ordered by written Task Orders issued on DD Form 1155 (Order for

Supplies or Services) by the Contracting Officer.

(b) Each award as a result of this solicitation will cite an individual contract number. Individual Task Orders will be placed in sequential numbering system, which relate back to the basic contract and their assigned

Task Order number.

(c) The Government will not be obligated to reimburse the contractor for work performed, items delivered, or any costs incurred, nor shall the contractor be obligated to perform, deliver, or otherwise incur costs except as authorized by duly executed Task Orders. Requests for proposals will indicate funds availability. The

Government may request proposals with no assurance of funding and provides no assurance that Task

Orders will be issued.

(d) Task Orders will be firm fixed price and clearly define the specific services to be performed or the performance desired. Each Task Order may contain additional, site or project specific, provisions. Any such additional provisions shall be part of the Request for Proposal.

(e) Task Order projects may be non-complex performance oriented tasks requiring minimal design, may be construction of Government provided design, may be complex construction requiring design development for design-build construction, or a combination thereof. The Task Order may or may not have traditional plans and specifications but may include sketches, and requests for catalog cuts, and other submittals. The following describes the procedures for each type of requirement the Task Order could present:

1) Contractor-Provided Design/Design-Build: MACC Contractors shall provide an initial ‘Concept’ design consisting of drawings, sketches, outline specifications, design analysis, and/or other documentation as required by the Task Order Statement of Work. MACC Contractors shall also provide a price proposal and may be required to include a proposed performance period. The

Government will evaluate submitted proposals in accordance with Task Order requirements. Only the successful offeror will be required to proceed with subsequent design effort (i.e. 35%, 65%, 95%, and or 100% as stated in each Task Order) and execute construction.

2) Government-Provided Design/Design-Build: MACC Contractors shall provide a ‘Concept’ design consisting of drawings, sketches, outline specifications, design analysis, and/or other documentation as required by the Task Order Statement of Work. Based on the ‘Concept’ design, MACC Contractors shall provide a price proposal and may be required to include a proposed performance period. The

Government will evaluate submitted proposals in accordance with Task Order requirements. Only the successful offeror will be required to proceed with subsequent design effort (i.e. 35%, 65%, 95%, and or 100% as stated in each Task Order) and execute construction.

3) Construction Only: MACC Contractors shall be provided a periously accomplished design which may be representative of a 35%, 65%, 95%, or 100% design consisting of drawings, specifications, design analysis and/or other documentation as required by the Task Order Statement of Work. Based on this completed design, MACC Contractors shall provide a price proposal and may be required to include a proposed performance period (as stated in each Task Order). The Government will evaluate submitted price proposals in accordance with Task Order requirements. Only the successful offeror will proceed with construction.

The design levels stated above are defined in the basic MACC Statement of Work.

(f) Task Orders may be modified by the Contracting Officer. Modifications to Task Orders will be issued on

Standard Form (SF) 30 and cite the Task Order number.

(g) Submission of proposals for Task Orders is not required. However, contractors are required to contact the

Contracting Officer within two days after receipt of Task Order Request for Proposal (TORFP) if a contractor will not participate in the walk through or submit a proposal on a Task Order.

1.19 Competition

(a) Only the contractors awarded contracts as a result of this RFP will compete for subsequent Task Orders.

These contractors are encouraged to participate in all site visits and submit proposals. Failure by offerors to participate responsibly in site visits and submit proposals may result in the Government not exercising the option to extend the contract or exclusion of the contractor from further competition.

Occasionally, (generally during the last quarter of the fiscal year) the Government will solicit offers for projects for which funds are not certified nor readily available. Air Force Material Command refers to these acquisitions as “Special Advance Authority” (SAA) or “Normal Straddle Bid” (NSB) projects. Under SAA funds are not available and may not become available. The Government makes no promise to award a contract. If funds do not become available for SAA projects, the Request for Quote is cancelled and no award is made. Under NSB funds may be available in the current fiscal year or the next fiscal year. If a contract is not awarded in the current fiscal year, it will be awarded in the following fiscal year. (See AFFARS MP5332.7, Contract Funding). Submission of proposals for these acquisitions is at the sole discretion of the respective MACC contractors and their declination to participate in any or all such solicitations will not reflect negatively upon them. This includes projects that are in whole or in part “SAA” projects.

(b) A minimum of two proposals on Task Orders will satisfy competition requirements and preclude the necessity of soliciting for a replacement contractor if for any reason one of the contracts is terminated or one of the contractors is excluded from participation in the process.

(c) Unless the Contracting Officer applies the exceptions noted below, each Task Order will be awarded, as a result of competition to the contractor who offers the best value to the Government considering the criteria specified. The Contracting Officer’s decision as to the selection for award of a Task Order is not protestable unless the protest is on the grounds that the order increases the scope, period, or maximum value of the contract program.

(d) The Contracting Officer reserves the right to award a Task Order without competition based upon a determination that:

1) The agency need for the supplies or services are so urgent that providing a fair opportunity would result in unacceptable delays;

2) Only one awardee is capable of providing the supplies or services required at the level of quality required because the supplies or services being ordered are unique or highly specialized;

3) The order must be issued on a sole-source basis in the interest of economy and efficiency as a logical follow-on to an order already issued under the contract, provided that all awardees were given a fair opportunity to be considered for the original order.

1.20 DESCRIPTION OF SUBSEQUENT TASK ORDERS

Task Orders will range from $2,000.00 to $3,000,000.00, with most Task Orders falling in the range below

$200,000. Task Order projects may require either a single discipline or multi-disciplined design services for airfield pavement or any aspect of general building construction for new, renovation and addition type projects. Projects may also require comprehensive interior design, lead and asbestos abatement and incorporation of sustainable features.

Some projects may require only minimal design or no design.

1.21 SUBSEQUENT TASK ORDER EVALUATION CRITERIA

Subsequent Task Orders may be awarded on price, past performance, best value, performance price tradeoff process or low price, technically acceptable basis. If the Government decides to issue the Task Order as a best value using the trade off process, award factors will vary depending on the unique requirements of each Task Order. The following sample criteria may be evaluated, in addition to price or cost:

(a) Past Performance – Task Order past performance or prior past performance on other contracts

(b) Quality of Deliverables

(c) Ability to Meet Schedule Requirements

(d) Relevant Experience

(e) Cost Control

(f) Potential impact on other orders placed with the contractor

(g) Current Workload

(h) Design

(i) The Contractor’s technical understanding of the work.

(j) The most efficient and effective plan to accomplish the work.

(k) Rational for the proposed materials, type, and quantities.

(l) Sustainable design features

1.22 PERFORMANCE AND PAYMENT BONDS – APPLICABLE TO INDIVIUAL TASK ORDERS

Contractors shall furnish Performance and Payment Bonds (Standard Form 25/25A) with good and sufficient surety or sureties, acceptable to the Government. The penal sums of the bond will be as shown below has been received and accepted by the Contracting Officer.

(a) Performance Bond: Unless the Contracting Officer determines that a lesser amount is adequate for the protection of the Government, the penal sum of the performance bonds (Standard Form 25) shall equal one hundred percent (100%) of the contract price for each Task Order.

(b) Payment Bond:

1) Shall equal 100% of the contract price for each Task Order.

2) One of the following is required:

i. A payment bond.

ii. An irrevocable letter of credit (ILC).

iii. A tripartite escrow agreement. The prime contractor establishes an escrow account in a federally insured financial institution and enters into a tripartite escrow agreement with the financial institution, an escrow agent, and all of the suppliers of labor and material.

The escrow agreement shall establish the terms of payment under the contractor’s escrow account, and the escrow agent distributes the payments in accordance with the agreement, or triggers the disputes resolution procedures if required.

iv. Certificates of deposit. The contractor deposits certificates of deposit from a federally insured financial institution with the Contracting Officer, in an acceptable form, executable by the Contracting Officer.

v. A deposit of the types of security listed in FAR 28.204-1 and 28.204-2.

3) Bonds are due within 10 days of the receipt of the Task Order.

1.23 PROPOSAL GUARANTEE (BID BOND)

SEED PROJECT: A bid bond for 20% of the proposed price is required for the “seed project”.

SUBSEQUENT TASK ORDERS: Individual proposal guarantees (bid bonds) of at least 20% of the proposed price may be required from all offerors competing for award of all subsequent Task Orders. The requirement for a guarantee will be included in the Task Order Request For Proposal (TORFP).

Bid bonds will only be waived for those projects designated “Special Advance Authority” as stated on the TORFP and at the discretion of the Contracting Officer.

1.24 REPLACING MACC CONTRACTORS

Should one or more of the incumbent MACC contractor’s options not be exercised, or if termination of contract(s) occurs, the process for selecting replacement contracts shall follow the same process and procedures as used in selecting and awarding the basic MACC awards.

1.25 ENVIRONMENTAL COMPLIANCE

Offerors are reminded of the environmental requirements contained in the solicitation to comply with all applicable federal state, and local environmental statutes and regulations. In addition to the scrutiny of civil environmental regulatory agencies, environmental compliance incidental to Air Force activities or on Air Force property is subject to Air Force scrutiny. The Air Force routinely investigates environmental violations and compliance.

1.26 INSTALLATION RULES AND REGULATIONS

The rules and regulations of the installation where services are performed shall apply to the contractor and its employees while on the premises of such installation. These regulations include but are not limited to: presenting valid identification for base entrances, obtaining and using vehicle passes for all contractor-owned and/or privately owned vehicles, obeying all posted directives, and providing strict adherence to security police direction in instances where security police have been dispatched to a particular location.

1.27 UTILITY SERVICES (IAW FAR 36.514)

The Contractor will be required to participate in all Air Force energy conservation programs. Utility services furnished to the contractor by the Government from the Government’s existing system outlets and supplies will be at no cost to the contractor, but see contract clause titled FAR 52.236-14, “Availability and Use of Utility Services” in

Section I.

1.28 SPECIAL UTILITY PROVISION

The contractor shall be responsible for any and all damages to accurately marked utilities resulting from its operations. Further, the contractor shall be held liable for all costs associated with such damages. Such costs include not only the costs to properly repair the damaged utility, but any direct costs incurred by the Government to provide emergency response to the site, as well as for any other monetary losses. Such loss may also include the value of loss of productivity experienced by the Government due to loss of power and/or facility evacuation arising from the utility damage. Contractors are to field verify and mark location of utilities shown on construction permit.

1.29 DESIGNATION OF GOVERNMENT INSPECTOR

The Base Civil Engineer or his authorized representative (Base Maintenance Contract (BMC) contractor) is designated as the representative of the Contracting Officer for the purpose of performing Construction Contract

Quality Assurance for the Government, which includes performing technical surveillance and monitoring workmanship and compliance with the plans and specification under this contract. This provision in no way authorizes anyone other than the Contracting Officer to commit the Government to changes in the terms of this contract.

1.30 PREPARATION OF SCHEDULES FOR CONSTRUCTION CONTRACTS

The reports contemplated by FAR Clause 52.236-15 titled “Schedules for Construction Contracts” in Section I shall be accomplished on and in accordance with instructions pertaining to AF Form 3064, “Contract Progress Schedule” and AF Form 3065, “Contract Progress Report” unless a…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .