MACC RFP FA9401-12-R-0002 Q A Round 6.pdf

PDF 116 KB Posted

Attached to
Multiple Award Construction Contract (MACC)
Solicitation number
FA9401-12-R-0002
Issued by

About this file

MACC RFP FA9401-12-R-0002 Q A Round 6

View the file

Other files

File Type Posted
Attch_1_-_Wage_Determination_(Bernalillo_County)__Building_dated_7-20-2012.pdf PDF
MACC_RFP_FA9401-12-R-0002_Amendment_10.pdf PDF
Attch_2_-_Wage_Determination_(Bernalillo_County)__Residential_dated_4-6-2012.pdf PDF
Attch_3_-_Wage_Determination_(Bernalillo_County)__Heavy_dated_7-20-2012.pdf PDF
MACC_RFP_FA9401-12-R-0002_Amendment_9.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 8.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 9.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 7.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 8.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 6.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 6-Conformed Copy.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 7.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 5.pdf PDF
RFP FA9401-12-R-0002 Pre-Proposal Conference-Site Visit Final Sign-in Sheet.pdf PDF
MACC Pre-Proposal Brief.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 4.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 3.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 2.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 5-Conformed Copy.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 5.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 4.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 4-Conformed Copy.pdf PDF
Attch 5 - Past Performance Information Questionnaire Package.docx DOCX document
MACC RFP FA9401-12-R-0002 Amendment 3-Conformed Copy.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 3.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 2-Conformed Copy.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 2.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 1.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 1.doc DOC document
Attch 32 - Seed Project Bid Schedule.xlsx XLSX spreadsheet
Attch 20 - Appendix 9 - Environmental Requirements KAFB.pdf PDF
Attch 10 - Appendix 4.1 - 13280 Asbestos Containing Materials Remediation.pdf PDF
Attch 40 - Kirtland AFB-West Map.pdf PDF
Attch 37 - Seed Project - Future Expansion Power Requirements Table.pdf PDF
Attch 13 - Appendix 4.4 - 16721 New Construction Automatic Fire Detection and Alarm System.pdf PDF
Attch 26 - Appendix 14.2 - Guidance and Standards-Backflow Prevention.pdf PDF
Attch 15 - Appendix 4.6 - Native Grass Seeding Specification.pdf PDF
Attch 9 - Appendix 3 - DUSD —
Attch 23 - Appendix 12 - Waste Diversion Report.pdf PDF
Attch 25 - Appendix 14.1 - Guidance and Standards-Irrigation.pdf PDF
Attch 18 - Appendix 7 Air Force Federal Mandates Quick Reference.pdf PDF
Attch 35 - Seed Project Water flow Test Results.pdf PDF
Attch 31 - Seed Project Price Schedule - AF3052.xlsx XLSX spreadsheet
Attch 36 - Seed Project - Westside Shoppette Geotechnical Report.pdf PDF
Attch 39 - AF Form 3065 - Progress Report.pdf PDF
Attch 30 - Seed Project Statement of Work.pdf PDF
Attch 22 - Appendix 11 - DoD Minimum Antiterrorism Construction Standards Pre-Final Checklist.pdf PDF
Attch 41 - Historical Data by Project Type and Cost.pdf PDF
MACC RFP FA9401-12-R-0002.doc DOC document
Attch 14 - Appendix 4.5 - 16721 Existing Bldg Remodel-Automatic Fire Detection and Alarm System.pdf PDF
Show 40 more

Latest 50 of 71 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Multiple Award Construction Contract (MACC)

RFP, Pre-Proposal Conference and Site Visit Questions

Solicitation FA9401-12-R-0002

10 April 2012

ROUND 6

MACC FA9401-12-R-0002

The purpose of this document is to provide answers to RFP questions for Solicitation

FA9401-12-R-0002.

61. Is there a soil report for the referenced project? Is there possible contamination?

ANSWER: A soils report suitable that may be used for the RFP response has been included on the website. There is no known contamination at the project site.

62. Does the RFP require goals for like minority owned, HUBZone etc firms as subcontractors to the 8(a) firm selected?

ANSWER: There is no requirement for a small business subcontracting plan in an 8A set-aside.

63. Can the relocated A/C move to the roof of the existing building?

ANSWER: To be determined during design. If place on roof, ACP must be observed.

64. Clarify the demo requirements, page 10 of 31 talks about removal of walls?

ANSWER: Walls, doors, etc. must be removed and remodeled as required to provide circulation from the existing space at the north into the addition.

65. Need geotechnical input to accurately design structure, is there one for existing building?

ANSWER: Negative. Soils reports from nearby sites will be made available, and will be acceptable for design.

66. Are any of the new systems connecting other than the fire alarm?

ANSWER: Affirmative. There is a building security system that will need to be extended.

67. Assume site work will be limited to revisions to the fire lane, is there semi-access required at the new OH door?

ANSWER: NO

68. It appears the existing roll-up doors are 20’ high, is that correct and is that the height needed at the new OH door?

ANSWER:YES

Solicitation FA9401-12-R-0002

10 April 2012

ROUND 6

69. Does the containment trench need a cover grate at all locations?

ANSWER: Affirmative

70. Where is the source for primary electrical distribution located?

ANSWER: See answer to Question 97

71. What are the connections requirements at this primary electrical source point (i.e. loop feed or radial)?

ANSWER: To be determined during design Question 10 - Primary voltage is listed in the

DA Question 11 - The base bid should include the circuit breakers. The rough-in, wiring and receptacle/switches should be included under Alt #2.

72. What is the primary voltage?

ANSWER: The primary voltage is 480V, 3Ph.

73. For the required power outlets listed in the Design Analysis Package and B9809 Future

Expansion Power Requirements Table, is a circuit breaker provision for each circuit all that is required?

ANSWER: For the base bid, a circuit breaker provision is all that is required. Alternate

#2 should include rough-in, wiring, receptacles, switches, etc. for each circuit.

74. If special power outlets or connection means are required for the listed outlets please identify the connection requirements.

ANSWER: Detailed outlet information is not available at this time. Will be made available during design.

75. Where are the locations in the building for the listed laboratory power outlets.

ANSWER: To be determined during design.

76. Will the building be LEED Certified? To what level if applicable? Is it currently registered if applicable?

ANSWER: The design must follow AF Memorandum dated 02 June 2011, subject “AF

Sustainable Design and Development (SDD Implementing Guidance)” included with the

RFP material.

Solicitation FA9401-12-R-0002

10 April 2012

ROUND 6

77. What will be the level of commissioning required for the building?

ANSWER: To be determined during design.

78. Are existing structural building drawings available?

ANSWER: Affirmative. These will be made available during design.

79. What are the purpose of the skylights at the doors? Can transom windows be used instead?

ANSWER: The DA (Attachment 33) specifically indicates skylights.

80. Will the addition require restroom facilities?

ANSWER: Negative.

81. Is access to the Anechoic chamber required? If so how… Ladder?..... Stairs?

ANSWER: To be determined. Access requirements for accommodation of anechoic chamber will be developed during design.

82. Can Clerestory windows or fiberglass panels (Kal Wall) be incorporated into the elevations?

83. Is the building required to be separate from the other structures?

ANSWER: See structural sections of the DA(Attachment 33).

84. What is the required finish on the interior of the CMU throughout?

ANSWER: The interior finish of the block walls is to be paint.

85. What are the required design documents for the seed project submittal?

ANSWER: Design document required for the seed project are clearly defined it the

Statement of Work.

Solicitation FA9401-12-R-0002

10 April 2012

ROUND 6

86. Are roof top mechanical units or other roof top equipment allowed on this new building or the adjacent existing buildings?

ANSWER: Affirmative. Screening must be included to the extent required in the KAFB

Architectural Compatibility Plan.

87. Is there a topographical survey available?

ANSWER: Negative

88. Can rainwater harvesting be used in NM?

ANSWER: See Design Analysis (Attachment 33), 3-2 first paragraph.

89. Is there a landscape master plan or guide that should be followed? Is it acceptable to return disturbed area to pre-construction conditions?

ANSWER: There is no KAFB Landscape Master Plan. It is acceptable to return the site to pre-construction conditions.

90. Are there any utility as-builts available for the area of the new structure? Duct bank relocation?

ANSWER: There are utility maps available, but not as-builts per se. Water line location has been described in another amendment. Gas and Electrical utility locations are shown in the DA.

91. How will the building meet standoff distances for ATFP requirements?

ANSWER: Proposed addition will be in compliance with AF/FP standoff distances, if located as shown in the DA (Attachment 33).

92. Will the glazing units require blast glazing or other ATFP provisions?

93. The systems description discusses variable air volume terminal units yet the space appears to be a single open room? Is it acceptable to provide a single zone VAV system?

Or other systems?

ANSWER: The mechanical engineer will be responsible for determining the final design and configuration of the HVAC.

Solicitation FA9401-12-R-0002

10 April 2012

ROUND 6

94. What is the purpose of the general exhaust system?

ANSWER: Indeterminate.

95. The documentation indicates that “process systems requirements have not yet been determined”. Will there be a process requirement for this space?

ANSWER: Process systems requirements have not yet been determined. That is still the case.

96. What is “Laboratories” vs. “Utility Areas” when considering that the addition is a one room addition?

ANSWER: The addition may be considered a "Laboratory."

97. There is a pad-mounted switch/sectionalized near an electrical manhole on the north side of the building, labeled “211A244”. Please describe the contents of this enclosure, with the possible intent of primary connection here. Please describe the size of both transformers and services that serve the building.

ANSWER: There are 2 connection points for the new 2mva transformer by Bldg 909..

The first is Z10244, It is currently feeding 2 transformers on the SW corner of 909..

There are no spare 200A connection points unless the new transformer feeds the existing load of one of the existing transformers, otherwise this Z-box would need to be replaced by a new one with 3-200A connection points..

The second is Z11244, It is currently feeding 1 load consisting of a single Z-box supplying 3 transformers, one of them is the newest 1500kva transformer.. It has no spare

200A connection points so it would also need replaced with a new Z-box consisting of 2-

200A connection points.. Both of these proposed connection points are fed from Sub

24A, Fdr 4, which currently has a load of 55 amps and a capacity of 600 amps..

98. Attachment 7, pages 72-74 of 77, lists the applicable UFC requirements, but does not mention any 3-500 series electrical UFCs. Please confirm that UFC 3-501 Electrical

Engineering, UFC 3-520 Interior Electrical Systems, UFC 3-530 Lighting, UFC 3-550

Exterior Electrical, and similar are required design/installation criteria.

ANSWER: The design must comply with all applicable codes and regulations. If the

Engineer of Record determines that this facility meets the criteria that bring it under the control of a particular UFC, then it is the responsibility of that individual to properly apply that code, document it in the construction documents and DA for the project, and submit it for review. A final confirmation of which codes apply to this project will arise from that process. Please consult the following web site for more information:

www.wdbg.org.

Solicitation FA9401-12-R-0002

10 April 2012

ROUND 6

99. Attachment 33, Electrical Part 3, identifies several loads in narrative and table. This coordinates with loads listed in Attachment 37. Please confirm there are no additional load types (i.e. 400Hz Aircraft Systems power) other than those listed.

ANSWER: There are no additional load types.

100. The Base Bid requirements appear to include the installation of 2MW fullcapacity power service. Please confirm the Alternate requirements include only the additional devices in Attachment 37, and not front end power service size capacity.

ANSWER: Confirmed.

101. Please advise whether the electrical additive alternate (per Attachment 37) includes breakers only, or also feeder circuits/step-down transformers/etc.

ANSWER: See the answer to Question No.73, above.

102. Where do we connect for the additional power required for Alt # 2

ANSWER: Power for Alt #2 will connect at the new panel.

103. Is the D/B contractor required to install sprinkler piping within the anechoic chamber? If so, are there any prohibitions on piping material?

ANSWER: The D/B contractor will not be required to install sprinkler piping into the anechoic chamber.

104. The RFP indicates that the need for a fire pump should be evaluated by the D/B contractor after award. However, a fire pump is a costly unknown, so it may be preferred to provide a recent a flow test. Is a recent flow test available?

ANSWER: A flow test has been included in the RFP as attachment 35.

105. The RFP requires the existing building’s fire alarm system to be extended to the new addition, but the RFP does not mention mass notification systems.

Is a mass notification system required for the new addition?

ANSWER: Standard notification devices will be required per code. No additional notification will be required.

Solicitation FA9401-12-R-0002

10 April 2012

ROUND 6

106. Does the containment trench in the building have any connection to the site sewers (sanitary or storm)?

107. Do the EISA section 438 requirements apply to the addition only or to the entire site? In other words, are we retrofitting the existing site to comply with the EISA law which was passed in 2007?

ANSWER: The EISA requirements apply to the project area only, and not the entire facility/site.

108. Where are the existing fire hydrants? What is the distance to the closest fire hydrant to the farthest point of the addition? Will there be a new fire department connection for the addition?

ANSWER: See the attached aerial photograph for FH Locations.

109. The RFP mentions detention basins to the south of the site. Are there any storm sewers from this site that drain into the basins or are all drainage overland flow into the basin? What are the dimensions/depth of the basins?

ANSWER: There are no storm sewers connecting the site to the detention basins. The site currently drains overland to these basins. The dimensions and depth will be established during design.

110. Is the anechoic chamber part of the equipment to be constructed, or do we just build the pit for the chamber?

ANSWER: Chamber will be furnished and installed by others.

111. What is the loading on walls of the anechoic chamber, and are hand rails, and metal grates needed for fall protection?

ANSWER: This information is not available at this time. There will likely be metal grating required to cover the trench.

112. Is any electromagnetic, RF, or X-Ray shielding required as part of the building construction? If so what and where?

ANSWER: No shielding will be required for the project.

Solicitation FA9401-12-R-0002

10 April 2012

ROUND 6

113. Are any support utility connections to the anechoic chamber required?

ANSWER: Affirmative. At a minimum, electrical power and fire detection will be required.

114. Is the 5” thick X-ray shield wall part of the equipment to be constructed?

ANSWER: The 5" Shield is not a part of this project.

115. Is any energy absorbing material required as part of the equipment to be constructed?

ANSWER: No energy absorbing material will be a part of this contract.

116. Is there a metal grate that will cover the secondary containment trench?

ANSWER: Affirmative

117. What is the height of the overhead bridge crane?

ANSWER: This will be determined during design.

118. Does the Overhead door need to be specially insulated?

ANSWER: The addition must comply with current AF and Building Code guidance on energy consumption.

119. Confirm that only the 30’x30’x6’ anechoic chamber pit is part of our scope and the anechoic chamber is provided by others.

ANSWER: Confirmed.

File details come from the government source that posted it. Updated .