MACC RFP FA9401-12-R-0002 Q A Round 5.pdf

PDF 86 KB Posted

Attached to
Multiple Award Construction Contract (MACC)
Solicitation number
FA9401-12-R-0002
Issued by

About this file

MACC RFP FA9401-12-R-0002 Q A Round 5

View the file

Other files

File Type Posted
Attch_1_-_Wage_Determination_(Bernalillo_County)__Building_dated_7-20-2012.pdf PDF
MACC_RFP_FA9401-12-R-0002_Amendment_10.pdf PDF
Attch_2_-_Wage_Determination_(Bernalillo_County)__Residential_dated_4-6-2012.pdf PDF
Attch_3_-_Wage_Determination_(Bernalillo_County)__Heavy_dated_7-20-2012.pdf PDF
MACC_RFP_FA9401-12-R-0002_Amendment_9.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 8.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 9.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 7.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 8.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 6.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 6-Conformed Copy.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 6.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 7.pdf PDF
RFP FA9401-12-R-0002 Pre-Proposal Conference-Site Visit Final Sign-in Sheet.pdf PDF
MACC Pre-Proposal Brief.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 4.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 3.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 2.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 5-Conformed Copy.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 5.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 4.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 4-Conformed Copy.pdf PDF
Attch 5 - Past Performance Information Questionnaire Package.docx DOCX document
MACC RFP FA9401-12-R-0002 Amendment 3-Conformed Copy.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 3.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 2-Conformed Copy.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 2.pdf PDF
MACC RFP FA9401-12-R-0002 Q A Round 1.pdf PDF
MACC RFP FA9401-12-R-0002 Amendment 1.doc DOC document
Attch 32 - Seed Project Bid Schedule.xlsx XLSX spreadsheet
Attch 20 - Appendix 9 - Environmental Requirements KAFB.pdf PDF
Attch 10 - Appendix 4.1 - 13280 Asbestos Containing Materials Remediation.pdf PDF
Attch 40 - Kirtland AFB-West Map.pdf PDF
Attch 37 - Seed Project - Future Expansion Power Requirements Table.pdf PDF
Attch 13 - Appendix 4.4 - 16721 New Construction Automatic Fire Detection and Alarm System.pdf PDF
Attch 26 - Appendix 14.2 - Guidance and Standards-Backflow Prevention.pdf PDF
Attch 15 - Appendix 4.6 - Native Grass Seeding Specification.pdf PDF
Attch 9 - Appendix 3 - DUSD —
Attch 23 - Appendix 12 - Waste Diversion Report.pdf PDF
Attch 25 - Appendix 14.1 - Guidance and Standards-Irrigation.pdf PDF
Attch 18 - Appendix 7 Air Force Federal Mandates Quick Reference.pdf PDF
Attch 35 - Seed Project Water flow Test Results.pdf PDF
Attch 31 - Seed Project Price Schedule - AF3052.xlsx XLSX spreadsheet
Attch 36 - Seed Project - Westside Shoppette Geotechnical Report.pdf PDF
Attch 39 - AF Form 3065 - Progress Report.pdf PDF
Attch 30 - Seed Project Statement of Work.pdf PDF
Attch 22 - Appendix 11 - DoD Minimum Antiterrorism Construction Standards Pre-Final Checklist.pdf PDF
Attch 41 - Historical Data by Project Type and Cost.pdf PDF
MACC RFP FA9401-12-R-0002.doc DOC document
Attch 14 - Appendix 4.5 - 16721 Existing Bldg Remodel-Automatic Fire Detection and Alarm System.pdf PDF
Show 40 more

Latest 50 of 71 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Multiple Award Construction Contract (MACC)

RFP, Pre-Proposal Conference and Site Visit Questions

Solicitation FA9401-12-R-0002

4 April 2012

ROUND 5

MACC FA9401-12-R-0002

The purpose of this document is to provide answers to RFP, Pre-Proposal Conference and Site

Visit questions for Solicitation FA9401-12-R-0002.

43. In regards to the economic monetary impact slide, what spending is available for small businesses in the local area and how much of this amount will actually be available and awarded on the MACC contract?

ANSWER: There will be funded and unfunded projects each year. Funding is based on what is allocated by appropriation by Congress each year and the amount will change from year to year. Kirtland AFB also receives funding from mission partners in addition to appropriations.

44. What exactly needs to be submitted in the proposals?

ANSWER: Proposal must consist of the complete signed solicitation document (do not return attachments), Page 1 and 2 of each Amendment signed and acknowledged.

45. Volume III is due in on 3 Apr 2012, what if the PPQ’s have not been forwarded to the contracting office by this due date, will the Offeror be disqualified?

ANSWER: No.

46. Volume III is due on 3 April 2012, do we resend the volume with the rest of the proposal on 19 April 2012?

ANSWER: No.

47. How is Volume III supposed to be structured?

ANSWER: Past Performance Volume III should be structured like the Past Performance

Questionnaires (PPQ).

48. Do we submit Past Performance for each Joint Venture (JV) company?

ANSWER: If an Offeror is submitting a proposal as a JV, then the Offeror needs to demonstrate their past performance as a JV company.

49. If an Offeror has an on-call with Kirtland AFB, will they be disqualified from this contract?

ANSWER: Any entity that has participated in a design project for Kirtland AFB will not be allowed to compete on the MACC. No contract for the construction of a project shall

Solicitation FA9401-12-R-0002

4 April 2012

ROUND 5

be awarded to the firm that designed the project, this includes subcontractors on the design effort, see FAR 36.209.

50. Why does an Offeror have to submit their past performance documentation in advance?

ANSWER: Past performance is being requested earlier in order to expedite the validation and possible clarifications of the submitted information.

51. How do we tie in experience and past performance into the seed project?

ANSWER: Past performance does not have to be specific to the seed project. Past performance should be tied to the dollar range given in the RFP.

52. Please considered extending the response due date for this RFP to allow more time for development of required design packages and cost estimates.

ANSWER: At this time, no extension is being provided.

53. Referencing Attachment 5, within is Attachment 1: Past Performance Information. Our understanding is this is included in Volume III, but does not need to be sent to our references. Is this correct?

ANSWER: Correct, Included in Volume III.

54. Referencing Attachment 5, within is Attachment 2: Consent Letter. Our understanding is this is included in Volume III, but does not need to be sent to our references. Is this correct? Also, if we are participating in a Joint Venture, do both parties fill out this consent letter?

ANSWER: Correct, Included in Volume III. Include for all parties in the Joint Venture.

55. Referencing Attachment 5, within is Attachment 3: Client Authorization Letter. Our understanding is this letter goes to the reference and is not included in Volume III. Is this correct?

ANSWER: Correct, Included in Volume III. Include for all parties in the Joint Venture.

56. Referencing Attachment 5, within is Attachment 4: Past Performance Evaluation

Questionnaire and Attachment 5: Performance Questionnaire Letter. Our understanding is that both of these get sent to the reference and are not included in Volume III. Is this correct?

ANSWER: Correct, Attachment 4 and 5 sent to references not included in Volume III.

Solicitation FA9401-12-R-0002

4 April 2012

ROUND 5

57. The design analysis page 3 states colored split face CMU. Page 9 states stucco exterior finish. Statement of work page 3 states colored split faced block. Please verify colored split faced block is what is wanted.

ANSWER: The color should match as close as possible the existing building, which is light beige. Within the ACP (Attachment 8) Concrete Masonry Unit approved light beige colors are El Paso Buff and #220 Elk Horn (page 53).

58. The design analysis page 10 states fire sprinkler systems to be expanded into the exiting work room. Page 27 hazard and fire sprinkler design criteria s1st paragraph additional fire sprinkler into the exiting building is not required. 2nd paragraph fire sprinkler coverage will be expanded into existing workroom. Please verify if the system will be expanded into the existing work area?

ANSWER: FS System will be required for expansion only.

59. Will the existing primary power be able to support the new transformer load?

ANSWER: The existing primary power can support the additional load.

60. Please verify where the new power will be tied in (12470)?

ANSWER: Annotated aerial photo entitled "Existing Site Analysis - Location, Parking and Utility Connections" show a proposed location for the new transformer. This will only be verified during Type B design.