STS Solicitation Questions V2.xlsx

XLSX spreadsheet 25 KB Posted

Attached to
Survivability Test Stand
Solicitation number
FA910126RB005
Issued by

About this file

This file is a Solicitation Questions and Answers document for the Survivability Test Stand (STS) contract (FA910126RB005). The document captures clarifications provided by the Government to Corvid Technologies and other potential offerors regarding proposal submission requirements and solicitation logistics.

Key clarifications address pricing submission requirements, including that the Government is flexible on Basis of Estimates (BOE) format within price narratives but will evaluate realism by comparing quantities in Attachment 4.7 against the technical proposal. The Government has added a dedicated profit/fee column to Attachment 4.7's Labor Categories tab. For subcontractor pricing, offerors must notate subcontractor-performed labor categories and provide fully burdened unit prices that combine the subcontractor's rates plus any prime additive charges. Regarding program schedule, the Government provided milestone timing estimates: System Requirements Review approximately 30 days after Kick-off (which occurs ~10 days after contract award), Preliminary Design Review at 6 months post-SRR, and Critical Design Review at 9 months post-PDR. Site visit logistics were clarified to limit attendance to 3 persons per company at the White Sands Missile Range (WSMR) test site due to bus capacity constraints, with no attendance limit stated for the Holloman portion, though all attendees are subject to space availability restrictions. The site visit on February 25-26 will focus on technical discussions, facility tour, and one-on-one meetings, with an agenda to be provided closer to the event date.

View the file

Other files

File Type Posted
Atch 4 - Section L Amendment 0002.pdf PDF
Atch 8 - Delivery Order 1 SOO Amendment 0002.pdf PDF
STS JA Final_Redacted Amendment 0002.pdf PDF
Solicitation Amendment FA910126RB0050002 SF 30.pdf PDF
EXHIBIT A - STS CDRLs Amendment 0002.pdf PDF
STS Solicitation QA Amendment 0002.pdf PDF
AEDC Industry Day STS Slides Rev. 3.pdf PDF
Survivability Test Stand Industry Day Itinerary.pdf PDF
Solicitation Amendment FA910126RB0050001 SF 30.pdf PDF
Atch 4 - Section L Amendment 0001.pdf PDF
Atch 5 - Section M Amendment 0001.pdf PDF
Atch 4.7 - STS Initial Order Pricing Sheet.xlsx XLSX spreadsheet
Atch 4.7 - STS Initial Order Pricing Sheet Amendment 0001.xlsx XLSX spreadsheet
Atch 4 - Section L.pdf PDF
STS Solicitation QA.pdf PDF
Atch 4.7 - STS Initial Order Pricing Sheet.xlsx XLSX spreadsheet
Atch 4 - Section L.pdf PDF
Atch 5 - Section M.pdf PDF
Solicitation Amendment FA910126RB0050001 SF 30.pdf PDF
Atch 4 - Section L Amendment 0001.pdf PDF
STS Solicitation QA.pdf PDF
Atch 4.7 - STS Initial Order Pricing Sheet Amendment 0001.xlsx XLSX spreadsheet
Atch 5 - Section M Amendment 0001.pdf PDF
STS Solicitation Questions.xlsx XLSX spreadsheet
Atch 1 - Survivability Test Stand SOO.pdf PDF
SOO Attachment 1 - Survivability Test Stand Use Cases.pdf PDF
SOO Attachment 2 - Survivability Test Stand KPPs KSAs.pdf PDF
SOO Attachment 3 Initial Operating Capability.pdf PDF
Atch 3 - STS GFP List.pdf PDF
Atch 4 - Section L.pdf PDF
Atch 4.4 - STS Client Authorization Letter.pdf PDF
Atch 4.6 - STS Relevancy Matrix.xlsx XLSX spreadsheet
Atch 6 - Holloman Specific Language STS.pdf PDF
Solicitation-FA910126RB005-.pdf PDF
Atch 4.1 PPI Tool - Attachment for Section L.pdf PDF
Atch 4.5 - STS Subcontractor Consent Letter.pdf PDF
EXHIBIT A - STS CDRLs.pdf PDF
Atch 4.3 - PPQ Cover Letter.pdf PDF
Atch 5 - Section M.pdf PDF
STS Cover Letter.pdf PDF
SOO Attachment 4 Full Operating Capability.pdf PDF
Atch 2 - DRAFT STS DD254.pdf PDF
Atch 4.2 Past Present Performance Quest.pdf PDF
Atch 4.7 - STS Initial Order Pricing Sheet.xlsx XLSX spreadsheet
Atch 4.8 - SB Participation Commitment Document.pdf PDF
Atch 7 - Form 5000.pdf PDF
Atch 8 - Delivery Order 1 SOO .pdf PDF
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table 1

Survivability Test Stand (STS) - Solicitaiton Questions
Q#Contractor / AgencySolicitation/
Attachment SubjectPage #, Paragraph ReferenceQuestion / CommentOPRResponse/Document EditsComments from STS Team
1Corvid TechnologiesPricingDoes the Government have a preferred format for BOEs within the Price Narrative?FMWhile the Government is flexible in terms of the format of the submission, Offerors are cautioned that as a part of the Realism evaluation, the Government will compare the quantities entered in Atch 4.7, along with any BOEs to the technical proposal to ensure the Offeror has demonstrated an understanding of the work to be performed.
2Corvid TechnologiesPricingAtch 4.7Attachment 4.7 does not appear to have a dedicated place for fee/profit. Does the Government have a preference of how this is broken out or built into the inputs?FMThe Government has included an additional column on Atch 4.7, tab 'Labor Categories' for Offerors to include their profit/fee.
3Corvid TechnologiesPricingWhat level of detail is required from subcontractors for the cost proposal? In lieu of certified pricing data being required, does the Government want them to submit unsanitized cost proposals at the same time as the prime contractors?FMThe Government requests Offerors notate instances where the labor category would be performed by a subcontractor. Further, the unit price displayed should include the subcontractor's fully burdened labor rates plus any additive rate on behalf of the prime so that the total unit price reflects the combined price.
4Corvid TechnologiesAre there expected end dates for the System Requirements Review as well as the various PDRs and PDR Reporting that we should use for proposal purposes?Desi CraigKick-off Meeting ~10 Days ARO

SRR ~30 Days ARO PDR ~6 Months after SRR CDR ~9 months after PDR

5Corvid TechnologiesSite VisitCover LetterI'm assuming that you intend that to be three persons per team. We may have representatives from four of five companies on our team interested in attending. But I think your intent is that only three persons from our Corvid Team can go on the site visit. Is that interpretation correct?Desi CraigWe are utilizing buses from Base Transportation to take everyone through WSMR and to the site. Space is limited, therefore we are limiting companies to 3 persons per company, if there are Subs they would be their own company and limited to 3.
6Corvid TechnologiesSite VisitCover LetterI read paragraph 7 as there is not a limit on the number of attendees for the Holloman portion of the trip. Is this correct? If it is correct, do you have any info on what will be discussed during the Holloman portion? The reason that I'm asking is that if we have 4 or 5 team members who would like to attend, but only 3 can go to WSMR, it would be good to know if it's worth their time, or if we should just limit ourselves to 3 for the entire trip.Desi CraigYes, there is a limit due to space restrictions with the buses and the unknown with how many vendors are attending. The point of the trip to the test site is to show vendors where the system will be located in reference to other buildings, show them the current condition of the buildings we intend to reutilize and get a good understanding of the distance between main base and the test site. The technical details will be discussed on the first day.
7Corvid TechnologiesSite VisitIs the agenda for Feb 26 set well enough to know when you expect to finish? We are working on arranging travel. If it's a full day, we'll arrange accommodations for that night and fly home on Friday, but if the plan is for only a half day, we may be able to fly home that evening. Either way is great, just wanted to ask before we lock anything in.Desi CraigYes, in the event that we don't get all the one-on-ones accomplished on Wednesday (the 25th) we have the 26th reserved for the rest of the one-on-ones. We will provide an agenda as we get closer to the industry day.
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71

File details come from the government source that posted it. Updated .