This is a Questions and Answers document for the Survivability Test Stand (STS) solicitation that addresses clarifications on pricing, scheduling, and site visit logistics.

Regarding pricing submissions, the Government confirmed that while it is flexible on Basis of Estimates (BOE) format within the Price Narrative, it will compare quantities in Attachment 4.7 against the technical proposal during realism evaluation. The Government amended Attachment 4.7 to include a dedicated profit/fee column within the Labor Categories tab. For subcontractor costs, offerors must notate which labor categories will be performed by subcontractors and provide a fully burdened unit price that combines the subcontractor's labor rates with any prime contractor additive rates; Attachment 4 Section L was amended to reflect this instruction. No certified pricing data is required from subcontractors. On scheduling, the Government provided expected milestone dates: Kick-off Meeting approximately 10 days after contract award, System Requirements Review at approximately 30 days after award, Preliminary Design Review at approximately 6 months after SRR, and Critical Design Review at approximately 9 months after PDR. Regarding the Industry Day site visit on February 25-26, the Government clarified that companies are limited to 6 persons per team for the White Sands Missile Range (WSMR) portion due to limited bus transportation capacity, while attendance at the Holloman portion has no stated limit. The site visit is intended to show vendors the test site location relative to other buildings, the current condition of buildings to be reused, and the distance between the main base and test site, with technical details to be discussed during presentations. Industry Day was scheduled to conclude on February 25.

View the file

Other files

File Type Posted
STS JA Final_Redacted Amendment 0002.pdf PDF
Atch 4 - Section L Amendment 0002.pdf PDF
Atch 8 - Delivery Order 1 SOO Amendment 0002.pdf PDF
Solicitation Amendment FA910126RB0050002 SF 30.pdf PDF
EXHIBIT A - STS CDRLs Amendment 0002.pdf PDF
STS Solicitation QA Amendment 0002.pdf PDF
AEDC Industry Day STS Slides Rev. 3.pdf PDF
Survivability Test Stand Industry Day Itinerary.pdf PDF
Solicitation Amendment FA910126RB0050001 SF 30.pdf PDF
Atch 4 - Section L Amendment 0001.pdf PDF
Atch 5 - Section M Amendment 0001.pdf PDF
Atch 4.7 - STS Initial Order Pricing Sheet.xlsx XLSX spreadsheet
Atch 4.7 - STS Initial Order Pricing Sheet Amendment 0001.xlsx XLSX spreadsheet
Atch 4 - Section L.pdf PDF
STS Solicitation QA.pdf PDF
Atch 4 - Section L.pdf PDF
Atch 4.7 - STS Initial Order Pricing Sheet.xlsx XLSX spreadsheet
Atch 5 - Section M.pdf PDF
Atch 4.7 - STS Initial Order Pricing Sheet Amendment 0001.xlsx XLSX spreadsheet
Solicitation Amendment FA910126RB0050001 SF 30.pdf PDF
Atch 4 - Section L Amendment 0001.pdf PDF
Atch 5 - Section M Amendment 0001.pdf PDF
STS Solicitation Questions V2.xlsx XLSX spreadsheet
STS Solicitation Questions.xlsx XLSX spreadsheet
Solicitation-FA910126RB005-.pdf PDF
Atch 4.1 PPI Tool - Attachment for Section L.pdf PDF
Atch 4.5 - STS Subcontractor Consent Letter.pdf PDF
Atch 1 - Survivability Test Stand SOO.pdf PDF
SOO Attachment 1 - Survivability Test Stand Use Cases.pdf PDF
SOO Attachment 2 - Survivability Test Stand KPPs KSAs.pdf PDF
SOO Attachment 3 Initial Operating Capability.pdf PDF
Atch 3 - STS GFP List.pdf PDF
Atch 4 - Section L.pdf PDF
Atch 4.4 - STS Client Authorization Letter.pdf PDF
Atch 4.6 - STS Relevancy Matrix.xlsx XLSX spreadsheet
Atch 6 - Holloman Specific Language STS.pdf PDF
EXHIBIT A - STS CDRLs.pdf PDF
Atch 4.3 - PPQ Cover Letter.pdf PDF
Atch 5 - Section M.pdf PDF
STS Cover Letter.pdf PDF
SOO Attachment 4 Full Operating Capability.pdf PDF
Atch 2 - DRAFT STS DD254.pdf PDF
Atch 4.2 Past Present Performance Quest.pdf PDF
Atch 4.7 - STS Initial Order Pricing Sheet.xlsx XLSX spreadsheet
Atch 4.8 - SB Participation Commitment Document.pdf PDF
Atch 7 - Form 5000.pdf PDF
Atch 8 - Delivery Order 1 SOO .pdf PDF
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q# Solicitation/ Attachment Subject

Page #, Paragraph Reference Question / Comment Response/Document Edits

1 Pricing Does the Government have a preferred format for BOEs within the Price Narrative? While the Government is flexible in terms of the format of the submission, Offerors are cautioned that as a part of the Realism evaluation, the Government will compare the quantities entered in Atch 4.7, along with any BOEs to the technical proposal to ensure the Offeror has demonstrated an understanding of the work to be performed.

2 Pricing Atch 4.7 Attachment 4.7 does not appear to have a dedicated place for fee/profit. Does the Government have a preference of how this is broken out or built into the inputs?

The Government has amended Atch 4.7 to include an additional column within tab 'Labor Categories' for Offerors to include their profit/fee.

3 Pricing What level of detail is required from subcontractors for the cost proposal? In lieu of certified pricing data being required, does the Government want them to submit unsanitized cost proposals at the same time as the prime contractors?

The Government requests Offerors notate instances where the labor category would be performed by a subcontractor.

Further, the unit price displayed should include the subcontractor's fully burdened labor rates plus any additive rate on behalf of the prime so that the total unit price reflects the combined price. Atch 4 Section L has been amended to reflect this instruction.

4 Are there expected end dates for the System Requirements Review as well as the various PDRs and PDR Reporting that we should use for proposal purposes?

Kick-off Meeting ~10 Days ARO SRR ~30 Days ARO PDR ~6 Months after SRR CDR ~9 months after PDR

5 Site Visit Cover Letter I'm assuming that you intend that to be three persons per team. We may have representatives from four of five companies on our team interested in attending. But I think your intent is that only three persons from our Corvid Team can go on the site visit. Is that interpretation correct?

We are utilizing buses from Base Transportation to take everyone through WSMR and to the site. Space is limited, therefore we are limiting companies to 6 persons per team.

6 Site Visit Cover Letter I read paragraph 7 as there is not a limit on the number of attendees for the Holloman portion of the trip. Is this correct? If it is correct, do you have any info on what will be discussed during the Holloman portion? The reason that I'm asking is that if we have 4 or 5 team members who would like to attend, but only 3 can go to WSMR, it would be good to know if it's worth their time, or if we should just limit ourselves to 3 for the entire trip.

Yes, we are using a bus to transport folks to and from the site. The bus has limited seating. The point of the trip to the test site is to show vendors where the system will be located in reference to other buildings, show them the current condition of the buildings we intend to reutilize, and get a good understanding of the distance between main base and the test site. The technical details will be discussed during the presentations.

Site Visit Is the agenda for Feb 26 set well enough to know when you expect to finish? We are working on arranging travel. If it's a full day, we'll arrange accommodations for that night and fly home on Friday, but if the plan is for only a half day, we may be able to fly home that evening. Either way is great, just wanted to ask before we lock anything in.

Industry Day will now conclude 25 February.

Survivability Test Stand (STS) - Solicitation Questions

Table 1

File details come from the government source that posted it. Updated .