CAMMO_Industry_Day_Master_Brief_FBO.pdf
PDF 10 MB Posted
- Attached to
- Consolidated Air Force Satellite Control Network (AFSCN) Modifications, Maintenance & Operations (CAMMO) Contract Federal contract opportunity
- Solicitation number
- FA8823-13-R-0009
About this file
18 Feb 14 CAMMO Industry Day Briefing presenation.
View the file
Other files for this federal contract opportunity
Show all 50
Consolidated Air Force Satellite Control Network (AFSCN) Modifications, Maintenance & Operations (CAMMO) Contract has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Space and Missile Systems Center Space and Missile Systems Center
Consolidated Air Force Satellite Control Network (AFSCN) Modifications, Maintenance, & Operations (CAMMO) Industry Day
18 February 2014
Safety & Facilities
SMC Industry Day
1Lt. Dan Beckett
SMC/RN
S P A C E A N D M I S S I L E S Y S T E M S C E N T E R
Evacuations
• In the event of an emergency, evacuate out the nearest exit
& assemble at the appropriate rally point
– Fire Alarm: southwest parking lot
– Bomb Threat or Gas Leak: Across Stewart Ave, behind the dental clinic
Evacuations
Restrooms
• The closest restrooms to the conference:
Overview
Industry Day, Site Visits, & One-on-Ones
• 18 Feb 2014
– Industry Day Briefings
– ATB & Warehouse Tours
• 19 Feb 2014
– Shriever AFB Site Visit
• 20 & 21 Feb 2014
– One-on-Ones with Industry
• 26 Feb 2014
– Vandenberg AFB Site Visit
Briefing Overview
• Industry Day Rules of Engagement
• Opening Comments
• AFSCN Operations
• AFSCN Sustainment
• CAMMO Programmatic Topics
• CAMMO Contractual Topics
• Closing Comments
Industry Day Rules of Engagement
• The briefings presented today contain preliminary, pre-decisional information only
• All information provided is subject to change
• The government is not currently soliciting proposals
Signing In
• Please ensure that you have signed in with Ms. Vollbracht in the conference room foyer
• In an effort to open up the lines of communication between different businesses, it is the government’s intention to compile the list of attendees (to include contact info) and post it to FedBizOpps
• If you do not wish to have your business information posted, please ensure you have indicated this on the sign in sheet
Questions
• To ensure that important information is available to all parties, including those who weren’t able to attend, many questions will NOT be accepted during the course of the briefings today
• If you have a question, please take detailed notes and submit them to the government POC utilizing the question submission form (posted to FedBizOpps) no later than Friday, 7 March, 2014
– Any questions submitted in this way will be answered and publically released via FedBiZOpps but the question source (the business) will not be revealed
• Government POC:
– Lt Dan Beckett; daniel.beckett@us.af.mil; 719-556-2204 mailto:daniel.beckett@us.af.mil
• Examples of questions to ask via submission form:
– “Can you describe how <technical process> works?”
– “Can you clarify <specific> maintenance process?”
• Examples of questions to ask during briefing:
– “Can you repeat what you just said?”
– “What does <acronym> stand for?”
• Examples of questions to ask via submission form:
– “Can you describe how <technical process> works?”
– “Can you clarify <specific> maintenance process?”
• Examples of questions to ask during briefing:
– “Can you repeat what you just said?”
– “What does <acronym> stand for?”
Opening Comments
Mr. Bruno Mediate
First in Space!
Col William Liquori, Jr.
Commander, 50th Space Wing
50th Space Wing
Mission Command satellites to deliver decisive global effects
Vision
The unrivaled leader in satellite operations prevailing across all environments
Col Sutherland Network Operations Group
Col Rittershaus Vice Commander
50 SW
Leadership Team
Col Barthel Mission Support Group
Col Roberts Operations Group
CMSgt Coles Command Chief
Col Liquori Commander
The unrivaled leader in satellite operations, prevailing across all environments
Col Tommy Roberts Commander, 50th Operations Group
Col Roberts
Det 1
7 SOPS AFRC 19 SOPS AFRC
50th Operations Group
CMSgt Perry Superintendent
2 SOPS
Lt Col Ste. Marie
3 SOPS
Lt Col Igl
Lt Col Claxton Deputy Commander
1 SOPS
Lt Col Doran
4 SOPS
Lt Col Munoz
3 SES
Lt Col Fulmer
Mr. Edwards Technical Director
50 OSS
Lt Col Cantore
148 SOPS CA-ANG
Lt Col Daniels 50 OGV Lt Col Bertsch
6 SOPS
AFRC
Multispectral Imagery and Space Situational Awareness ISR Support to Deployed Forces
Telemetry, tracking and commanding for AF’s only Space Based Surveillance asset
Enhanced Knowledge of On-Orbit Space Object
SBSS
1st Space Operations Squadron Always in Control
ATRR
ORS-1
GPS IIA GPS IIR GPS IIF
Precision Navigation and Timing Key Enabler of Precision Engagement
Location and Timing support to 3B+ Civil Users Worldwide
2nd Space Operations Squadron Pathways for Peace
WGS DSCS
Secure, Wideband Military Communications
Primary military means for long-haul communications
Provides space-borne communications to National Authorities and U.S. and Allied Forces
Secure high-rate data provided to POTUS, SECDEF, Theater Commanders, and strategic and tactical forces worldwide
3rd Space Operations Squadron 1st in Space Communications
Milstar AEHF
Global, secure, survivable, strategic and tactical communication
Provides Communications for POTUS, SECDEF, Combatant Commanders and Deployed Forces
4th Space Operations Squadron Linking the Forces
Execute assigned advanced programs on behalf of USAF
Create/strengthen USAF relations with partner DoD agencies
Develop/sustain a core cadre of space professionals to serve as Subject Matter Experts for future AFSPC space-based endeavors
3rd Space Experimentation Squadron
Premier professionals…Superior Mission Assurance…Global Effects!
Col Jonathan A. Sutherland Commander, 50th Network Operations Group
Provide assured access to space and cyberspace through command and control, operations and maintenance critical to global combat effects
50th Network Operations Group
Worldwide Team of Professionals
Superior Mission Assurance
Global Effects in Space and Cyberspace
50 NOG Leadership Team
Group Superintendent
Col Sutherland Commander
Mr. Diaz Technical Director Lt Col Scott
21 SOPS
Lt Col Jackson
23 SOPS
Lt Col Gibson
22 SOPS
Committed to Mission … Compliance … Innovation
CMSgt Sale
Lt Col Plunkett
50 SCS
Lt Col McGibney Deputy Commander
AFSCN & GPS Locations - 50 NOG
Operational Control Nodes Schriever AFB - HAWK Vandenberg AFB –DICE
PIKE
Schriever
(CTS)
HULA
Kaena Point
(HTS)
COOK
Vandenberg
(VTS)
BOSS
New Boston
(NHS)
LION
Oakhanger
(TCS)
POGO
Thule
(TTS)
BEACH/CAPE
KWAJ
Kwajalein
GUAM
Guam
(GTS)
REEF
Diego Garcia
(DGX)
ASCN
Ascension
ARTS/Legacy Antenna
RBC Antenna/Upgrade In-Progress
MUE Antenna
GPS Antenna
Inactive Antenna
One team, embracing innovation for continues mission success
Lt Col Aaron Gibson Commander, 22 SOPS
22nd Space Operations Squadron
Mission and Vision
Providing assured access to space in all environments
One team, embracing innovation for continued mission success
Comm Relay Satellite
SAFB
Remote Tracking Station
…through the Air Force Satellite Control Network (AFSCN)
Mission Satellite
One team, embracing innovation for continued mission success
Providing assured access to space in all environments
Air Force Satellite Control Network
New Boston, NH (1959)
22 SOPS
23 SOPS
Schriever, CO (1988)
Cape Canaveral, FL (1972)
Kaena Pt, HI (1959)
Diego Garcia, UK (1991)
Guam (1965)
Oakhanger, UK (1970)
Thule, GL (1961)
Operational Control Nodes:
Schriever AFB
Vandenberg AFB
21 SOPS
Vandenberg, CA (1959)
- 16 Ground Antennas
- 2 Transportable Antennas
- 150+ Satellites
- 29 Operations Centers
- 166K Supports in FY13
‘The sun never sets on the AFSCN’
Thule New Boston
Kaena Point
Colorado Tracking Station
Vandenberg
Guam
Diego Garcia
Oakhanger
AFSCN Mission Assurance
R&D 12%
C3 34%
Weather 13% Warning 16%
Intel 22%
GPS 3%
DISA ATM
Network
Schriever
Control Node
Vandenberg
Control Node
Meeting Operational Demand
LONG
TERM
PLANNING
LAUNCH
INTEGRATION
MISSION
PRIORITY
ALLOCATION
FINAL
DECONFLICTION
PUBLICATION
NTO
EXECUTION
(REAL
TIME)
ASSESSMENT
Network Tasking Order
DCC
Cisco Works
Electronic Scheduling Dissemination
Mission Prioritization
Launch Integration
Planning
A Day in the Life…
Cohesive global team focused on mission assurance… cost-effective, innovative, and reliable solutions
Lt Col Sarah Jackson Commander, 23 SOPS
23d Space Operations Squadron and New Boston Air Force Station
23d Space Operations Squadron
Provide assured access to space through operations and maintenance of satellite command and control systems
Cohesive global team focused on mission assurance through cost-effective, innovative, and reliable solutions
Lt Col Sarah Jackson
23 SOPS Leadership
Tim Brecheen Mission Support
Lt Col Cary Belmear Operations Officer
Maj Joel Neuber Det 1 Commander
Maj Nate Case OL-A Ops Officer
23 SOPS AFSCN Locations
The Sun Never Sets on the Air Force Satellite Control Network
BOSS
New Boston
(NHS)
LION
Oakhanger
(TCS)
POGO
Thule
(TTS)
BEACH
CCAFS
(EVCF)
Satellite Operations
Relay Data and Upload Commands
Download Data
Real-time Data
Actionable Information!
Satellite Contact = contacting a satellite from a ground tracking station and receiving and sending data
Telemetry Receive data from a satellite
Payload State of health
Tracking Knowing a satellite’s location
100-450,000 miles above the earth Range accurate to <6.1 meters Range rate accurate to 0.03 m/sec
Commanding Data sent to a satellite
Payload Bus
Det 1 – Thule AB, Greenland Thule Tracking Station (POGO) Tenant Unit of 821 ABG Northernmost AFSCN site
2 Antennas specialize in Polar orbits Personnel:
2 Military personnel provide oversight US contractors providing O&M 2 Greenlandic contractors
OL-A – Oakhanger, UK Telemetry & Commanding Station (LION) Installation owned by MOD
Busiest AFSCN site Personnel:
1 US Military (Operations Officer/Liaison) UK contractors providing O&M 13 Ministry of Defense Police
OL-B – Cape Canaveral AFS, FL Eastern Vehicle Checkout Facility (BEACH)
Housed in the Satellite Assembly Building 6-foot antenna on building roof Supports pre-launch and launch activities for all satellites prior to AFSCN use
Personnel:
Contractor providing O&M
23 SOPS – NBAFS, NH
New Hampshire Tracking Station (BOSS) 2,826-acre installation Infrastructure valued over $100M
Total force mix
9 AD Military 31 DoD Civilians Contractors providing O&M Contractors provide Security
Forces (not CAMMO)
DSCS Terminal (60’) 1976
BOSS-A
(13m) 2007
BOSS-C
(46’) 1972
DMSP
(11m) 1991
Source B (7m) 2007 BOSS-B (RBC)
(13m) 2013
23 SOPS – NBAFS, NH
New Hampshire Tracking Station (BOSS)
Station Support 31-person CE section: infrastructure and facilities support Modernization and energy conservation projects 24/7 security forces Outdoor Recreation and Services activities
Environmental Stewardship
UXO clearance program – 2004-present Managing wildlife and natural resources Provide safe drinking water to station personnel
UXO LIDAR Data
23 SOPS
Operate & maintain
8 AFSCN antennas DSCS SATCOM Terminal
Maintain (not CAMMO) 2 GPS Ground Antennas 2 GPS Monitor Stations
24/7/365 assured access to space 67,000 satellite contacts/year
6 locations - 4 time zones - 3 countries
Flawless Network Operations today… …A path forward into tomorrow
Lt Col Hondo Scott Commander, 21 SOPS
Welcome to the 21st Satellite Operations Squadron
21 SOPS Mission/Vision
Mission Assure access to space by enabling launch, on-orbit operations and specialized communications
Flawless Network Operations today…
…A path forward into tomorrow
21 SOPS AFSCN Locations
The Sun Never Sets on the Air Force Satellite Control Network
COOK
Vandenberg
(VTS)
HULA
Kaena Point
(HTS)
REEF
Diego Garcia
(DGX)
GUAM
Guam
(GTS)
ARTS/Legacy Antenna
RBC Antenna/Upgrade In-Progress
MUE Antenna
GPS Antenna
Inactive Antenna
ARTS/Legacy Antenna
RBC Antenna/Upgrade In-Progress
Detachment 1 (REEF) 21 SOPS, Diego Garcia
Linking the Heavens and Earth
Provides unique AFSCN & GPS S. Equatorial & E.
Hemisphere capability Newest site in the AFSCN (1991) Support nearly all Eastern Range launches GPS Ground Antenna and Monitor Station (Not CAMMO)
24K+ satellite contacts (site record) 99.8% mission success rate
Major Allison Goodspeed
REEF Facilities
8 buildings, 8 acres Operates two AFSCN antennas RBC and ARTS
Operates two GPS antennas Ground Antenna (GA) and
Monitor Station (MS) Host mission equipment for other missions
AFSPC MUE
DGS-A (ARTS)
DGS-B (RBC)
GPS Ground Antenna
Maj Jerome Frederick Jr.
Where America’s Space Ops Day Begins
Activated in 1965 High-power AFSCN uplink Responsible for GPS antennas at Kwajalein
23K+ satellite contacts (site record)
99.7% mission success rate
Detachment 2 (GUAM) 21 SOPS, Guam
GUAM Facilities
12 buildings, 20 acres antennas ARTS and RBC GTS-C (Estimated activation April 14) Hosts mission equipment for several non-AFSCN missions
DRMUE
DRMUE-S
SOURCE-G
AFSPC MUE
DRMUE-S
GTS-B(13m)
Major George Sanderlin
Guardians of Kaena Point and the Heavens
Operational since 1959 Oldest in AFSCN RBC System testing in progress
HULA-A & B support telemetry collection for MDA GPS Monitor Station (CAMMO)
20K+ satellite contacts 99.7% mission success
Detachment 3 (HULA) 21 SOPS, Hawaii
HULA Facilities
37 buildings, 153 acres antennas ARTS and RBC HTS-C – Hybridization (2014)
Operates one GPS Monitor Station
Host mission equipment for several non-AFSCN missions USCG Lighthouse AFWA Solar Observatory
MDA
Pentagon Project AFSPC MUE (in testing)
Bldg 41
HTS-B, CE & Power Plant
Entry Control Point
HTS-A, HTS-C, HQ
& Support bldgs
Capt Josh Failing Flight Commander
Big Sky Ranch
Activated in 1959 First operational RBC Supports all Western Range space launches High-power uplink enhancement Low-power uplink enhancement
21K+ satellite contacts
99.8% mission success rate
Vandenberg Tracking Station (COOK)
21 SOPS
Capabilities:
Provide facilities, redundant/backup power, reliable communications, and security, to support tenant missions.
Tenants supported:
- Alternate Master Control Station (AMCS) for 2 SOPS
- Back-up Space Operation Center-Vandenberg (BSOC-V) for 3 & 4 SOPS
- Back-up Network Operations Center (BNOC) for 22 SOPS
- 148 SOPS, California Air National Guard, MILSTAR Ops Center (MOC-V)
- Source-V
COOK Facilities
EOSOF Operations Centers (DICE)
AFSCN Communications Control Center Monitor communications for ~460 satellite contacts/day Lead for comm link/equipment Fault
Detection/Fault Isolation/Fault Resolution Contractor responsible for C4 & Test
Equipment Maintenance Patch and Test
Operations/Level 1 maintenance for AFSCN Node equipment
DISN Facility of the Year 2011/2012!
COMSEC
DMSP & NAVSOC Comm Equipment
DISA SATCOM
Two Medium Earth Terminals AF SATCOM Runner Up Facility of the Year
Vandenberg East/West
Two 38’ DISA SATCOM Antennas Commissioned Jul 10 AFSCN data Pacific Presidential comm UK comm & data
Providing Assured Access to Space and Cyberspace Assets by Exploiting, Implementing and Sustaining Superior Communication Technologies for Global Customers
Mr. Paul Van Stee Deputy Director
50th Space Communications Squadron Schriever Air Force Base
Get the Right Information to the Right People at the Right
Time…Every time!
Providing Assured Access to Space and Cyberspace Assets by
Exploiting, Implementing and Sustaining Superior Communication Technologies for Global Customers
50th Space Communications Squadron
SCOO– Network Operations
AF Satellite Control Network Administration System Administration Functions Supporting Air Force Satellite
Control Network at 21 Worldwide User Locations Installs, Configures, Maintains, and Administers the Distributed
Communications Controllers and Wide Area Network Interface Units for AFSCN at
Schriever and Remote User Locations AFSCN Database- Maintains, Add/Move/Change and Distribution to Sites
CAMMO
CAMMO Requirements Routing subsystem WANIU maintenance (preventive, corrective, hardware, software maintenance) Distributed Communications Controller (preventive, corrective, hardware, software maintenance) Electronic Scheduling Dissemination (preventive, corrective, hardware, software maintenance) Cryptographic (preventative, corrective, hardware maintenance) Archival Recorder System (preventative, corrective and hardware maintenance) Timing subsystem (only modems, routing, cabling, fault isolation)
SCOT– Transmission Systems
Long-Haul Communications: Tech Control-Circuit Actions-COMSEC Considered one of the Largest Tech Control Facilities in the Air Force
Manages and Maintains 1,650 Circuits, Supporting 150 Satellites \ Supports $6.2B AFSCN System and 8 Remote Tracking Stations World-Wide 7 DoD Space Programs; GPS, DSCS, MILSTAR, NOAA, NAVSOC, MDA, DMSP, and All Tenant Units Impact: Tech Control Facility is Conduit for AFSPC Satellite SA
DISA Node Site Coordinators for Schriever with 70 Nodes--Largest in AFSPC Oversees Circuit/Network Monitoring, Equipment and System Fault Isolation, Troubleshooting, and Path Restoration--Tech Control is 24/7 Circuit Actions Maintains 1650+ Records History, Provides Quality Control and
Tier 2 Maintenance Support, and the Focal Point for all DISA Installations COMSEC Controlling Authority for all AFSCN Circuits and 79 Remote Sites—
289 Items Total
SCXC– Configuration Management
Administers Installation/Modification Process Across the 50th
Space Wing Includes Tenant Units and Geographically-Separated Units (GSU) Provides Facilities and Communications Conveyance Modifications
Planning/Documentation Management Minimizes Operational Impact of Changes and Modifications to Comm
Systems Maintains Baseline Integrity by Ensuring Compliance to Standards and
Codes
SCXS– Base Support
Information Assurance (IA)
Provides Wing and Mission Partners IA Support Conducts Annual IA Assessments for 45 Host, Tenant, and Wing GSU Activities Provides IA and Certification and Accreditation Guidance to ~90 IA Offices Tracks DoD Certification Requirements and Reports Status to AFSPC
Communications Security (COMSEC) Management Office Manages 8K Accountable COMSEC Items Responsible for Six 50SCS Local Elements (LE) Subordinate to Main Account 23 Overall LE Accounts (22- Air Force, 1- Navy) Two Numbered COMSEC Accounts and Two Key Processors
SCXS– Base Support…Continued
Emissions Security (EMSEC) Management
Oversees Wing EMSEC Program (Includes Schriever and Wing GSUs) Conducts EMSEC Assessments of all Info Systems that Process
Classified Data Maintains and Archives EMSEC Documentation for 106 Classified
Systems
Frequency Management Provides Spectrum Management and Consultation for 50 SW Host, Tenant Units and GSUs Wing Focal Point for Spectrum Support and Interference Resolution
The Sun Never Sets on the 50th SCS
SCQ-Wing Chief of Maintenance
Provides Maintenance and Logistics Management to the Network Operations Group Commander
Manages 50 SW Mission Maintenance Programs Maintenance Operations Center GSU Maintenance Management Maintenance Analysis Quality Assurance Material Control Maintenance Scheduling
Manages Wing Maintenance and Logistics Programs Directs Maintenance and Logistics Support to Managers and
Maintenance Technicians for AFSCN, GPS, and MILSTAR
SCQ--Maintenance Management
Ensures Communications and Satellite Systems Maintenance is Accomplished According to Air Force Instructions Tracks, Coordinates, and Reports Maintenance Activities and Provides
Support to 50 SW Units Directs and Manages Unscheduled Maintenance
Depot-Level Maintenance Support Requests Monitors 50 SW Depot-Level Maintenance
Provides Continuity for Operations and Maintenance Conflicts (Contractors, SMC, and Government Agencies) Adjudicates Challenges between Offices
SCQM– Maintenance and Logistics Support
Site Support Conducts Contract Over-Site and Award Fee Input for Network and Space
Operations and Maintenance, Satellite Control Network Monitors and Coordinates Depot-Level Repairs, Single Point-of-Failure Items, Mission Capable Supply Issues and Equipment Bench Stock for 50 SW Systems
Maintenance Control Services Collects System/Equipment Failure
Data Assigns, Tracks, and Documents Status for All Maintenance Requests Processes Urgent and Emergency
Depot-Level Maintenance Requests Tracks Equipment and Maintenance
Status Coordinates Maintenance and Supply
Requests
GPS IIF
SCQX– Maintenance Data Analysis
Hosts Integrated Maintenance Data Systems Database Managers for 50 SW and 13 GSUs
Advises Wing Chief of Maintenance of DLR and O&M Funding Tracks and Reports Maintenance, Performance and Trending
Data on all 50 Space Wing Mission Systems Data Provided to Chief of Maintenance and MAJCOM for
Management Decision Performs Special Studies to Identify Route Causes of Common
Failures Among System Components Data Used to Direct Funding for Parts, Initiate Component
Modifications/Upgrades to Correct Deficiencies
SCQA– Quality Assurance
Wing Technical Order Distribution Office (TODO) and Communications-Electronic Discharge Program
Wing evaluation entity for All 3D cyber-space personnel and C-E equipment
Group and Squadron Exercise Evaluation Team (EET)
Premier professionals … Superior Mission Assurance …
Global Effects!
AFSCN & GPS Locations - 23 SOPS
HULA
Kaena Point
(HTS)
COOK
Vandenberg
(VTS)
KWAJ
Kwajalein
GUAM
Guam
(GTS)
REEF
Diego Garcia
(DGX)
ARTS/Legacy Antenna
RBC Antenna/Upgrade In-Progress
MUE Antenna
GPS Antenna
Inactive Antenna
ARTS/Legacy Antenna
RBC Antenna/Upgrade In-Progress
CAMMO Sustainment
Agenda
• External Contract Integration
• Sustaining Engineering
• Special Engineering Studies
• Modifications
• Electronic Data Interchange
• Information Assurance
• AFSCN Test Bed
• Depot Level Maintenance
• Part Number Warehouse
• Repair
External Contract Integration
Don’el Collier
Several external contracts will impact CAMMO
• Systems Engineering & Integration (SE&I)
• RBC-Hybrid (RBCH)
• Enhanced High Power Amplifier (EHPA)
• Universal S-Band (USB)
• SE&I
– SE&I will develop requirements & architecture for AFSCN
– SE&I will provide IV&V for selected mods
– SE&I will develop DoD Information Assurance Certification &
Accreditation Process (DIACAP) packages for submission to
AFSPC/A6
– CAMMO will sustain/modify the network as required to meet SE&I defined/gov’t approved requirements
– CAMMO will produce IA artifacts supporting DIACAP development by SE&I
– Associate Contractor Agreement (ACA) will be required between SE&I and CAMMO
• RBC Hybrid (RBCH)
– Final RBCH expected to be complete in FY2019, resulting in 8 total systems
– Upon successful ops acceptance of an RBCH system, CAMMO will assume Operations, Maintenance, & Sustainment (OM&S) responsibility
• Enhanced High Power Amplifier (EHPA)
– EHPA (based on RBC Quad HPA) being developed to replace ARTS HPA at VTS-A under the Satellite Control Network Contract
(SCNC)
– An additional 3 EHPA systems are being planned
– CAMMO will assume OM&S responsibility upon successful ops acceptance
• Universal S-Band (USB)
– USB is projected to be in testing by FY15
– Consideration is being given to utilization of Transportable RBC
(TRBC) for testing
• CAMMO will retain maintenance responsibility for TRBC baseline
– Delays to Factory Compatibility Testing (FCT) schedule may result due to unavailability of resources
– Gov’t will adjudicate conflicting USB test & CAMMO FCT efforts
Sustaining Engineering
To implement, document and maintain a disciplined engineering approach for hardware and software sustainment infrastructure that ensures the successful design, documentation, integration, installation & checkout/test and lifecycle support of AFSCN systems and products with minimum downtime to the AFSCN and minimum negative impact to operations.
• Systems Engineering
• Deficiency Reporting
• Modeling and Simulation
• Reliability, Maintainability, and Availability (RMA)
• Environmental
• System Safety
• System Security Engineering
• Configuration Management
• Data Management
Special Engineering Studies
Special Engineering Studies
• Special studies/investigations
– Engineering Analysis/Projections under Systems
Engineering
• Obsolescence & Vanishing Vendor Resolution
• Life Extension Analysis and Requirements
– Additional Studies as Defined by Government via RFI/RFQ
• Types: feasibility studies, predictive performance measurements, detection & prevention of anomalies, impacts on space operations performance, risk assessments, & white papers
Modifications
• New capability modifications are not in-scope of
CAMMO
• Software modifications are considered in-scope of
CAMMO
• Hardware modifications considered in-scope include:
– Retain existing capability, extend service life, correct product quality deficiencies, or retain/restore functional baseline or performance specification
– Improve the operational availability of the item, transform or modernize defense business systems, or reduce ownership costs
– Satisfy an operational mission requirement by removing or adding capability/function/enhancing technical performance/operational suitability
• Requirement for System Modification starts via…
– Change Request Form (CRF) – used to introduce the deficiency to the AFSCN Community
– AF Form 1067, Modification Proposal – document used to obtain approval from A3/4/5 to initiate a modification action
– Joint Deficiency Reporting System (JDRS) – Government database used to track deficiency reports (DRs) within the AFSCN and follows TO 00-35D-54 guidance
RNL Modification Process Flow
• Hardware Modification Initiated with an RFP
– Government proposed specification changes will be provided along with associated AF1067s or DRs
– Contractor will provide proposal in accordance with modification RFP
– Modifications will vary in scope from simple Form-Fit-
Function (FFF) to complex sustainment modifications affecting multiple systems
Electronic Data Interchange
• Electronic Data Interchange (EDI)
– AFSCN resource, providing access to a variety of technical information in support of the network
– Information is used by O&M personnel, engineers, logisticians, and other support functions in locations all over the world
– EDI hosts technical information accumulated over previous several years
Electronic Data Interchange (EDI)
• Multiple Sources Feed into EDI
– Central Data Library (CDL)
– Program Information Management System (PIMS)
– EDI secure environment
– TeamCenter (via secure site)
– Electronic Air Force Technical Order (E-AFTO)
– International Business Machines (IBM) Rational Suite web sites (via secure site)
– Document Management System (via secure site)
– wInsight
– eIRON
Electronic Data Interchange (EDI)
Information Assurance
Capt Christian Morgan
Information Assurance
• AFSCN Information Assurance (IA) Goal
• IA Government Perspective
• Secure Contractor Facility
• AFSCN Certification and Accreditation
• Artifact Creation and Maintenance
• IA Controls Validation Assessments
• Our goal is to ensure the AFSCN and its interfacing components maintain an appropriate level of security that ensures confidentiality, integrity, authentication, non-repudiation, and availability for the network as a whole. The ultimate objective is to guarantee network operation for user traffic during peacetime, crisis, conflict, and natural disaster
• Document, Improve, Secure, Strategize
AFSCN IA Goal
• IA is a requirement which must be integrated into SE processes like any other requirement
• IA considerations must be integrated across operational systems and project life cycles
• IA accreditation strategies require joint government and contractor teaming early and often
• COTS-based mission system and obsolescence issues make IA a challenge within AFSCN
IA Government Perspective
• Software development environment must meet IA control requirements
• All gov’t data must be secured appropriately for level of classification & isolated from contractor networks
• Subject to government assessment
• Software Assurance Best Practices (examples include air gaps, isolated coding terminals, etc.)
• Supply chain risk management
• DFARS Clause 252.204-7012: Safeguarding
Unclassified Controlled Technical Information
Contractor Facility
• 7 DIACAP Packages Impact the AFSCN’s Authority to Operate (ATO)
– ATOs must be re-accomplished every 3 years
– Interim ATO (IATO) may be issued for high/medium risks
(unmitigated) systems & are valid for 6 months
– Interim Authority to Test (IATT) varies with risk & test length
• CAMMO will support development of DIACAP Packages
– Provides IA artifacts to SE&I contractor (through the government)
AFSCN Certification & Accreditation
• Accurate & thorough IA/Engineering Artifacts support DIACAP packages
– Configuration management of artifacts required
– Clearly ID artifact owners & artifact contributors & how they contribute to quality DIACAP artifacts/processes
– Maintaining accurate system boundaries & components are vital
• Need the infrastructure/processes/people to be able to produce/maintain IA artifacts
– Documented mitigation, system configuration, hardware & software lists, scan results, drawings, Ports, Protocols, and Services Management (PPSM) reports, etc.
– IA-certified staff with defined roles & responsibilities
Artifact Creation and Maintenance
• Specific CAMMO IA Responsibilities
– All AFSCN mission systems will be analyzed for IA compliance on an annual basis based on a sampling of sites across the network
– Collected Controls Validation Assessment (CVA) data supports the Certification & Accreditation (C&A) process & is a driver for risk assessments
– Required to handle/process classified information according to Security Classification Guide (SCG)
IA Controls Validation Assessments
AFSCN Test Bed
Ms. Jamie Navarro
• The AFSCN Test Bed (ATB) is a group of test suites used to test, integrate, modify, & update equipment for the AFSCN systems before they are deployed to the RTSs, OCNs, & other locations
• The CAMMO Contractor will be responsible for maintaining ATB baseline & operating within specifications
• The government will adjudicate scheduling conflicts between CAMMO & external contractors requiring access to the ATB
• Components of the AFSCN Test Bed:
– Electronic Schedule Dissemination Test Bed (ESDTB) (ESD 2.7, aka ESD
Legacy, current system)
– Communications (Comm) Segment Sustainment Test Bed (CSSTB)
– Automated Remote Tracking Station (ARTS) Development and Modification
Test Bed (ADMTB) (may also be referred to as ARTS Development Modification Facility [ADMF])
– Remote Tracking Station (RTS) Block Change (RBC) High Powered Amplifier
(HPA)
– ARTS HPA (aka Legacy HPA)
– RBC Integration and Support Suite (RISS)
– ESDTB (ESD 3.0 future scheduling system)
– Orbital Analysis Subsystem (OAS) Secure Lab
– Miscellaneous Support Equipment
• The technical aspects of the test beds will be covered in more detail during the tour at HTSI this afternoon
Depot Level Maintenance
Capt John Nuttall
Depot Level Maintenance Provide responsive technical & maintenance support of systems, subsystems, services and/or special equipment to facilitate swift restoration of the space weapons system to its original operating condition. Provide reliable, accurate & timely support to the AFSCN operations & maintenance customers related to both scheduled & unscheduled on-site maintenance activities.
Duties
– Provide Depot Support to the 7 RTSs, EVCF*, & the 2 OCNs
– Respond to Emergency & Urgent Depot Level Maintenance requests (EDLMs & UDLMs)
– Accomplish Programmed Depot Maintenance Activities
* EVCF is not subject to EDLMs
• Provide Depot Support to 7 RTSs, EVCF, & 2 OCNs
– Depot support is required when the Operations & Maintenance (O&M) technicians have completed troubleshooting in accordance with technical orders & the equipment outage still is not resolved
– Level I & Level II maintenance & support must be delineated
• Respond to EDLMs & UDLMs
– Timely depot support for E/UDLMs is required to return the RTSs/OCNs to full mission capability following mission impacting outages
• Accomplish Programmed Depot Maintenance (PDM) Activities
– Accomplishment of PDMs per government approved schedule
Part Number Warehouse
Capt John Nuttall
Training
TMDE
Storage/ Modulars
Ship/ Rec
Repair Lab
HPA Repair Area •Less transport/handling of completed repairs = greater quality confidence •Quick access to TMDE •Current lab size 6180 ft2
Hands-on Training Workstations:
Trainees are required to perform hands-on assembly to demonstrate proficiency in learned techniques in order to complete certification.
4 Vertical Lift Modular Storage •Modulars have a 250 ft2 footprint •Each unit stores 6000 ft3 •Frees up of 5100 ft2.
Two mezzanines •Increase of 6850 ft2 in overall floor space
Depot Level Item Repairs
Michael Norton
• Depot Level Item Repair Provide off-site depot level repair to restore repairable equipment to appropriate levels of performance & return end items to a serviceable condition. This work includes:
– Type I National Stock Number (NSN) that are Expendability, Recoverability, Repairability Category (ERRC) “T” under the control of Ogden through Material Support Division (MSD)
– Part Number Repair assets
– Contractor Supported Weapon System (CSWS)Type II NSNs that are ERRC T
• MSD Item repair induction authority resides with Ogden-Air Logistics Complex (ALC)
• Part Number & CSWS induction authority resides with AFSCN Program Office
• Duties
– Provide Depot Level Repair for assets where repair capability exists in-house
– Provide Sub-Vendor capability to repair assets that cannot be repaired in-house
• Provide Depot Level Repair for assets where capability exists in-house
– Process repair actions on Type I NSNs that are ERRC T inducted by Ogden-ALC Item Manager (IM) under MSD
– Document repair in Government On-Line Database (GOLD)
– Provide storage of assets in Agile Combat Support (ACS) Warehouse locations
• Provide Sub-Vendor capability to repair assets that cannot be repaired in-house
– Process repair actions on Type I NSNs that are ERRC T that are inducted by Ogden-ALC Item Manager (IM)
– Document repair in Government On-Line Database (GOLD)
– Provide storage of assets in ACS Warehouse locations
Backup Slides
Systems Engineering
• Designing to include testing of the design
• Documenting
• Integrating and installing
Deficiency Reporting
• Recording
• Mitigating
• Tracking
Modeling and Simulation
• Designing
• Manufacturing
• Testing
RMA
• Tracking
• Reporting
• Analyzing
Environmental
• Regulation compliance
• Design
• Integration
System Safety
• Identifying and defining
• Determining probability of occurrence
• Assessment
System Security Engineering
• Information Assurance
• Risk Management
• Certifications and Accreditations (C&A)
Configuration Management
• Control
• Accounting
• Verification and audit
Data Management
• Maintaining
• Improvement recommendations
• Accessibility to Government
15 Minute Break
• We will now take a 15 minute break
• We will resume the briefings promptly on-time
Restrooms
• The closest restrooms to the conference:
Consolidated Air Force Satellite Control Network (AFSCN)
Modifications, Maintenance, and Operations (CAMMO)
Acquisition
Mr. Bruno Mediate CAMMO Project Manager
719-556-7889
Programmatic Briefing 18 Feb 14
• CAMMO Purpose
• Contract Requirements Integration
• Performance Work Statement Summary
• Specific PWS Requirements
• Work Breakdown Structure
• Tasks, Standards, & Performance Incentive
Metrics (PIMs)
• Notional PIMs and Calculations
• Summary
S P A C E A N D M I S S I L E S Y S T E M S C E N T E R S P A C E A N D M I S S I L E S Y S T E M S C E N T E R
CAMMO Purpose
• Vertically integrate all AFSCN contracted weapon system support services under a single acquisition to achieve synergy and incentivize efficiencies while maintaining mission effectiveness:
– Operations, operations support, all maintenance (L1/L2, H/W
& S/W), sustainment, sustainment support
– Item repair
– Replenishment spares procurement
– Space vehicle factory compatibility testing
– Sustainment modifications
– Special studies
• Leverage CAMMO for contracted services at AFSCN operating locations to retain efficiencies, minimize personnel footprint, and achieve savings (Defense Satellite Communication System [DSCS] terminals, Mission Unique Equipment [MUE], remote site services, etc)
S P A C E A N D M I S S I L E S Y S T E M S C E N T E R S P A C E A N D M I S S I L E S Y S T E M S C E N T E R
Contract Requirements Integration
50SW Contract:
Network & Space
Operations & Maintenance
(NSOM)
FA2550-08-C-8011
SMC Contract:
Satellite Control Network
Contract
(SCNC)
F04701-02-D-0006
SMC Contract:
Engineering, Development, & Sustainment
(EDS)
FA8818-06-D-0024
SMC Contract:
CAMMO
NOTE: CAMMO integrates those tasks associated with AFSCN weapon system services and/or services at AFSCN remote operating locations
Notional Performance Work Statement Summary
S P A C E A N D M I S S I L E S Y S T E M S C E N T E R S P A C E A N D M I S S I L E S Y S T E M S C E N T E R
Specific PWS Requirements:
Operations
PWS Paragraphs 3.1 through 3.2
• Operational performance is critical to mission success
• Operational Performance Score defined in 50SWI 10-220
• Contractor operators comply with commander (crew, site, squadron, etc) instructions and communicate/report through operational channels
• Includes operating transportable asset(s) if relocated to AFSCN operational site to perform mission
S P A C E A N D M I S S I L E S Y S T E M S C E N T E R S P A C E A N D M I S S I L E S Y S T E M S C E N T E R
Onsite Maintenance and Logistics Support
PWS Paragraphs 3.3.1 through 3.3.7; 3.4.1 through 3.4.7
• Main task areas associated with vertical integration concept to provide on-site product support for the AFSCN
• Government is seeking industry innovation to integrate these activities to meet system performance for operational mission success, via an efficient and affordable approach
• Potential for additional integration and efficiencies with PWS paragraph 3.2 (Operations) and/or paragraph 3.8 (Remote Site Services)
• Depot Maintenance Actions (paragraph 3.4.6) include configuration changes, equipment moves/removals, form/fit/function replacements, etc. which do not impact AFSCN baseline specifications
S P A C E A N D M I S S I L E S Y S T E M S C E N T E R S P A C E A N D M I S S I L E S Y S T E M S C E N T E R
Off-site Item Repair
PWS Paragraphs 3.4.8.1 through 3.4.8.5
• Three different designations of item repair:
– Stocklisted items: repair in support of government depot (OO-ALC) & funded via separate CLIN
– Non-stocklisted items: repair of non-stocklisted items as required to obtain required system performance; funded under FPIF CLIN
– Interim Supply Support items: repair of items not yet integrated into government supply support system, stocklisted, and assigned designated government depot repair; funded under FPIF CLIN
• Two different performance metrics
– In-house repair average less than 30 days
– Vendor repair average less than 80 days
– Metrics do not apply to stocklisted items, only repairs under FPIF CLINs
S P A C E A N D M I S S I L E S Y S T E M S C E N T E R S P A C E A N D M I S S I L E S Y S T E M S C E N T E R
Sustainment
PWS Paragraphs 3.5 through 3.6.5
• Standard weapon system sustainment services:
– Inventory management, maintenance planning, sustaining engineering, program management, information assurance, technical document management, configuration/data management, etc
– Includes Public-Private-Partnership requirements (Paragraph 3.6.3.17)
• Includes integration of information assurance requirements at AFSCN operating locations (paragraphs 3.6.4.1 through 3.6.4.15) and for AFSCN mission systems (paragraphs
3.6.4.16 through 3.6.4.21)
– Potential for additional integration and efficiencies associated with information assurance of contractor’s information technology systems (paragraphs 3.6.3.8 through 3.6.3.12)
S P A C E A N D M I S S I L E S Y S T E M S C E N T E R S P A C E A N D M I S S I L E S Y S T E M S C E N T E R
Factory Compatibility Testing (FCT)
PWS Paragraphs 3.6.6.1 through 3.6.6.5
• Satellite vehicle testing using AFSCN transportable system(s)
• Offerors will propose “menu pricing” for activities associated with FCT
• Each FCT will be separately proposed and contracted using the menu pricing established at contract award
S P A C E A N D M I S S I L E S Y S T E M S C E N T E R S P A C E A N D M I S S I L E S Y S T E M S C E N T E R
Continuing System Improvements
PWS Paragraph 3.7.1, Modification Projects
• Scope includes temporary modifications, low-cost modifications, and sustainment modifications
• Scope does not include major hardware capability mods
• All mods to be separately proposed during contract execution in response to RFP/RFQ PWS Paragraph 3.7.2, Special Studies
• Analyses, assessments, and investigations
• All special studies will be separately proposed during contract execution in response to RFP/RFQ PWS Paragraph 3.7.3, Software Sustainment/Maintenance
• Maintain, sustain, protect, assure, and improve system performance/capabilities via software releases, upgrades, and database updates
• Included as part of FPIF CLINs
S P A C E A N D M I S S I L E S Y S T E M S C E N T E R S P A C E A N D M I S S I L E S Y S T E M S C E N T E R
Remote Site Services
PWS Paragraph 3.8
• Contracted services at AFSCN operating locations
• Included to create synergy and efficiencies to minimize personnel footprint at remote locations
• Requirements vary by operating location
S P A C E A N D M I S S I L E S Y S T E M S C E N T E R S P A C E A N D M I S S I L E S Y S T E M S C E N T E R
Transition Phase-In
PWS Paragraphs 3.9.1.1 through 3.9.1.12
• Deliver Phase-In Plan 10 days after contract award
• Transition equipment and obtain accountability in 60 days
• All remote site personnel in place and ready to perform duties in 60 days (security clearance, country clearance, etc)
• All transition tasks completed in accordance with PWS paragraph 3.9.1 requirements (none exceed 180 days)
• Contractually responsible to perform all PWS tasks, meet standards, and begin calculation of PIMs at 60 day point
Notional Work Breakdown Structure (2nd Level)
Ref: OSD Operating & Support Cost Estimating Guide & DI-FNCL-81831 NOTIONAL WBS Structure for CAMMO WBS/CES Description PWS Reference
1.0 UNIT-LEVEL MANPOWER (SYSTEM LEVEL COST ONLY)
1.1 OPERATIONS MANPOWER 3.2.1.1-7, 3.2.2.1
1.2 UNIT-LEVEL MAINTENANCE MANPOWER 3.3.1.1-8, 3.3.2.1-15, 3.3.3.1-7, 3.3.7.1-5
1.3 OTHER UNIT-LEVEL MANPOWER 3.3.4.1-6, 3.3.5.1-2
2.0 UNIT OPERATIONS (SYSTEM LEVEL COST ONLY)
2.1 OPERATING MATERIAL 2.12 (Contractor provided materials, supplies, & equipment)
2.2 SUPPORT SERVICES 2.11.1, 2.13, 3.3.1.9, 3.4.7.1, 3.6.4.1-15;
2.3 TEMPORARY DUTY 2.11.2
3.0 MAINTENANCE
3.1 OVERHAUL OF END ITEMS 3.4.1.1, 3.4.2.1, 3.4.3.1, 3.4.4.1
3.2 DEPOT LEVEL REPARABLES (DLR) / REPAIR OF REPARABLES (ROR) 3.4.8.1-5
3.3 CONSUMABLES AND REPAIR PARTS 3.5.1.2
3.4 OTHER MAINTENANCE SERVICES 3.3.1.3, 3.4.5.1, 3.4.6.1, 3.5.3.3
3.5 PACKING, HANDLING, SHIPPING, AND TRANSPORTATION (PHS&T) 3.3.6.1, 3.5.2.1-4
4.0 SUSTAINING SUPPORT
4.1 SYSTEM SPECIFIC TRAINING 3.6.1.1-4, 3.6.3.18
4.2 SUPPORT EQUIPMENT REPLACEMENT 3.5.3.2
4.3 SUSTAINING/SYSTEMS ENGINEERING 3.5.3.1, 3.5.3.4, 3.6.2.1-12, 3.6.3.14-15, 3.6.4.16-21
4.4 PROGRAM MANAGEMENT 2.1-6, 2.8, 2.10, 3.5.1.1, 3.5.1.3, 3.6.3.1-13, 3.6.3.16-17, 3.6.3.20-27
4.5 INFORMATION SYSTEMS N/A
4.6 DATA AND TECHNICAL PUBLICATIONS 3.6.5.1-3, 3.6.3.19
4.7 SIMULATOR OPERATIONS N/A
4.8 OTHER SUSTAINING SUPPORT 3.6.6.1-5
5.0 CONTINUING SYSTEM IMPROVEMENTS
5.1 HARDWARE MODIFICATIONS OR MODERNIZATION 3.7.1.1-2
5.2 SOFTWARE MAINTENANCE OR MODIFICATION 3.7.3.1-7
5.3 Special Studies 3.7.2.1
6.0 INSTALLATION & PERSONNEL SUPPORT (SYSTEM LEVEL COST ONLY)
6.1 Installation Support 3.8.1-5
6.2 Personnel Support N/A
7.0 Transition
7.1 Phase-In 3.9.1
7.2 Phase-Out 3.9.2
Tasks, Standards, and Performance Incentive Metrics (PIMs)
PIMs was performance achieved?
Standards was quality service provided?
All Other Tasks was the work completed?
Incentive Plan
Notional PIMs from Incentive Plan
PIM
No. Description % of Overall
QPI
Score per Evaluation
Period Minimum Level of Performance
Monthly Performance Incentive Metrics
1 Ops Performance Score Source: PWS 3.1.1.1 24%
2% ≥ 0.998 1% ≥ 0.996 0% < 0.996
2 AFSCN AO
Source: PWS 3.1.1.1 12% 1% ≥ 87.0%
0% < 87.0%
3 MTTRF
Source: PWS 3.1.1.1 12% 1% ≤ 2.0 hrs
0% > 2.0 hrs Quarterly Performance Incentive Metrics
Scheduled vs Actual
Downtime Source: PWS 3.4.2.1
8% 2% within +/- 3%
0% outside +/- 3%
5 EDLM Response Source: PWS 3.4.3.1 4% 1% ≤ 24 hrs
0% > 24 hrs
6 UDLM Response Source: PWS 3.4.4.1 4% 1% ≤ 72 hrs
0% > 72 hrs
Off-Site In-House Repairs
Source: PWS 3.4.8.2, 3.4.8.3
4% 1% ≤ 30 days
0% > 30 days
Off-Site Vendor Repairs
Source: PWS 3.4.8.2, 3.4.8.3
4% 1% ≤ 80 days
0% > 80 days
9 CAR Response Time Source: PWS 3.6.3.26 16% 4% = 100%
0% < 100%
Software Delivery
Deficiencies Source: PWS 3.7.3.3, 3.7.3.4, 3.7.3.5 12%
3%
= 0 CAT-I DRs w/in 30 days of field evaluation for all releases
0%
> 0 CAT-I DRs w/in 30 days of field evaluation for all releases
• Pass/Fail metrics (except PIM 1)
• Calculated on monthly or quarterly basis
• Quality Performance Index (QPI) determined quarterly for profit payment associated with performance
NOTE: Annual profit adjusted based on cost performance associated with FPIF share ratio for underrun/overrun
Notional Calculation Scenarios
Standard ≥ 0.998 ≥ 0.996 ≥ 87% 86.00% 87.00% 88.00% 88.00% 90.00% 90.00% 91.00% 90.00% 89.00% 90.00% 90.00% 89.00%
≤ 2.0 hrs 1.8 hrs 1.9 hrs 2.3 hrs 1.3 hrs 0.8 hrs 1.1 hrs 1.8 hrs 0.9 hrs 1.2 hrs 2.4 hrs 1.3 hrs 2.1 hrs
≤ +/- 3.0% ≤ 24 hrs ≤ 72 hrs
≤ 30 days ≤ 80 days
= 0 CAT-I DRs
Score per Eval.
Per.
2% 1% 1% 0% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 0% 1% 1% 1% 1% 1% 1% 0% 1% 0% 2% 1% 1% 1% 1% 4% 3%
Quarterly QPI:
Overall QPI:
Resulting Score (by evaluation period)
Performance Metric Q1 Q2 Q3 Q4
1 - Ops Performance Score 1% 2% 0% 2% 2% 2%
2 - Operational Availability
3 - MTTRF
4 - Scheduled vs Actual Downti 2% 2% 2% 2%
2% 2% 1% 2% 2% 2%
5 - EDLM Response 0% 1% 1% 1% 6 - UDLM Response 0% 1% 1% 1% 7 - Off-Site In-House repair 1% 1% 0% 1% 8 - Off-Site Vendor Repair 0% 1% 1% 1%
0% (17%) 25% 23% 23% 71%
9 - CAR Response Time 4% 4% 4% 4% 10 - Software Delivery Deficien 3% 3% 3% 3%
Measured Performance for each PIM (by evaluation period) Performance Metric Q1 Q2 Q3 Q4
0.998 0.997 0.999 0.999 0.9991 - Ops Performance Score 0.997 0.998 0.995 0.998 0.998
2 - Operational Availability
3 - MTTRF
4 - Scheduled vs Actual Downti -1.20% 2.10% 1.80% -2.20%
0.9980.999
5 - EDLM Response 26 hrs 0 hrs (no EDLMs) 18 hrs 22 hrs 6 - UDLM Response 74 hrs 63 hrs 54 hrs 68 hrs 7 - Off-Site In-House repair 24 days 20 days 32 days 25 days 8 - Off-Site Vendor Repair 92 days 74 days 68 days 47 days 9 - CAR Response Time 100% 100% 100% 100% 10 - Software Delivery Deficien 0 CAT-I DRs 0 CAT-I DRs 0 CAT-I DRs 0 CAT-I DRs
Notional Calculation Scenarios
Target Cost (CLIN 1) $60,000,000 Quarter QPI Target Cost (CLIN 1) $60,000,000 Target Profit 10% $6,000,000 1 0% Target Profit 10% $6,000,000 Target Price $66,000,000 2 25% Target Price $66,000,000 Ceiling % 115% $69,000,000 3 23% Ceiling % 115% $69,000,000 Assigned Share Govt Ktr 4 23% Assigned Share Govt Ktr Under Target 70% 30% Overall QPI: 71% Under Target 70% 30% Over Target 30% 70% Over Target 30% 70%
$58,000,000 $62,000,000 $2,000,000 -$2,000,000
$600,000 -$1,400,000 71% 71%
$4,260,000 $4,260,000 $4,860,000 $2,860,000
$62,860,000 $64,860,000
Quarterly QPI
Total Profit Payment Total Gov Payment Final Contract Price
Over Run Scenerio
Actual Audited Allowable Cost Over run Ktr Share (70% of over run) Total Profit (QPI) %
Final Contract Price
Under run
Under Run Scenerio
Actual Audited Allowable Cost
Ktr Share (30% of under run) Total Profit (QPI) % Total Profit Payment Total Gov Payment
S P A C E A N D M I S S I L E S Y S T E M S C E N T E R S P A C E A N D M I S S I L E S Y S T E M S C E N T E R
Summary
• CAMMO Purpose
• Contract Requirements Integration
• Performance Work Statement
Summary
• Specific PWS Requirements
• Work Breakdown Structure
• Tasks, Standards, & Performance
Incentive Metrics (PIMs)
• Notional PIMs and Calculations
• Summary
Consolidated Air Force Satellite
Control Network (AFSCN) Modifications, Maintenance and
Operations (CAMMO) Solicitation No. FA8823-13-R-0009
SMC Industry Day:
Contracting Overview
18 Feb 2014
Procuring Contracting Officer (PCO):
Christina A. Ming, SMC/PKL
■ Source Selection Objective
■ Notional Source Selection Approach
■ Notional Solicitation
• Contract Line Item Number (CLINs) and Contract Type
• Contract Length & Transition
• Special Contract Requirements
• Organizational Conflict of Interest
■ List of FedBizOpps Postings
■ Key Milestones
“The objective of source selection is to select the proposal that represents the best value”.
FAR 15.302
“The goal of this procedure is to ensure the Department’s source selection process delivers quality, timely products, and services to the Warfighter and the Nation at the best value for the taxpayer.”
DoD of Source Selection Procedures dated 4 Mar 11
Best Value: “The expected outcome of an acquisition that, in the Government’s estimation, provides the greatest overall benefit in response to the requirement.”
FAR 2.101
Source Selection Objective
Trade Off Source Selection Process IAW 15.101-1.
• Allows tradeoffs between non-cost factors and cost/price and allows the Government to accept other than the lowest priced offer.
• Used when in the best interest of the Government to consider award to other than the lowest priced offeror.
• An agency can obtain best value in negotiated acquisition by using any single or a combination of multiple source selection approaches.
Notional Source Selection Approach
Technical Capability & Past Performance Acceptability w/ Technical Risk & Price Trade-off
Risk & Price of Equal Importance Evaluation Factors: Technical Capabilities (Factor 1), Technical Risk (Factor 2), Past Performance (Factor 3), & Price (Factor 4)
Technical Capability: Rate as Acceptable/Unacceptable Technical Risk: Rate as Low/Moderate/High Past Performance: Rate as Acceptable/Unacceptable Price: Reasonableness & Balance
Notional Source Selection Approach (con’t)
Notional CLIN Structure & Contract Type
Fixed Price Incentive--Target Firm (FPIF):
Operations, Maintenance & Sustainment (OM&S)
• Target Profit: 10%
• Ceiling Price: 115%
• Share Ratio: Underrun - 70/30; Overrun - 30/70
Cost Plus Fixed Fee (CPFF): Transition & Special Studies Fixed Fee: 8%
FA28823-13-R-0009 Notional CLIN Structure CLIN Description Type Task Title PWS Paragraph(s)
1400 Transition - Phase-In CPFF Transition – Phase-In 3.9.1 (except 3.9.1.12) 1401 Travel for Transition - Phase-in CR Travel for Transition - Phase-In 3.9.1.12 1500, 1600, 1700, 1800, 1900, 2000, Operations, Maintenance, and Sustainment (OM&S)
FPIF a) General Requirements
b) AFSCN Ops Performance Standards
c) Operations
d) Org Level Mx and Support
e) Depot Level Mx
f) Sustainment Logistics Support
g) Sustaining Support
h) Software Sustainment and Mx
a) 2.0 (except 2.11.2 and 2.12)
b) 3.1.1
c) 3.2.1 and 3.2.2
d) 3.3.1 through 3.3.7
e) 3.4.1 through 3.4.8 (except 3.4.8.1)
f) 3.5.1 through 3.5.3 (except 3.5.1.2)
g) 3.6.1 through 3.6.5
h) 3.7.3 (except 3.7.3.7)
1501, 1601, 1701, 1801, 1901, 2001, Government-directed Travel and Other Direct Costs (ODCs)
CR a) Reimbursable Travel
b) Local Purchase
c) Licenses, Service Contracts, Warranties, and Subscriptions
a) 2.11.2
b) 2.12
c) 3.7.3.7
1502, 1602, 1702, 1802, 1902, 2002, Remote Site Support (RSS) FFP Remote Site Support (RSS) 3.8
2400 Transition - Phase-out CPFF Transition – Phase-Out 3.9.2…
This is the start of the file's text. The full file is on GovTribe.