RFI Response 161-166.doc

DOC document 188 KB Posted

Attached to
Multiple Award Construction Contract (MACC) Federal contract opportunity
Solicitation number
FA8101-09-R-0021
Issued by
Department of the Air Force Materiel Command Air Force Sustainment Center

About this file

Request for Information 161-166

View the file

Other files for this federal contract opportunity

Other files attached to Multiple Award Construction Contract (MACC), newest first.
File Type Posted
MACC SOW WWYK070088 Revision 5.pdf PDF
RFI Response 168.doc DOC document
FA8101-09-R-0021-0009.pdf PDF
SOW070244 SOW Rev 3.pdf PDF
FA8101-09-R-0021-0008.doc DOC document
SOW070088 SOW Rev 4.pdf PDF
Question-Answers #5 to FBO.pdf PDF
070094 Dwg M3 00 redline Rev 2.pdf PDF
2009 Base Facility Standard with 2007 ACP Included in Chap 13.pdf PDF
Electrical Base Stds 2007.pdf PDF
MACC Curtain Wall Model-1.pdf PDF
fa8101-09-r-0021-0004.doc DOC document
060367 Dwgs - Rev 1.pdf PDF
070088.zip ZIP file
060367 Spec 01 11 00 - Rev 1.pdf PDF
070094 Spec 01110 - Rev 1.pdf PDF
070295 Spec 01 11 00 - Rev 1.pdf PDF
070085 Spec 01 11 00 - Rev 1.pdf PDF
070088 SOW - Rev 1.pdf PDF
070244 SOW - Rev 1.pdf PDF
Amendment 0002.pdf PDF
070244 As-Builts 1.zip ZIP file
MACC Presolicitation Bus Tour 7-16-09.pdf PDF
SEED PROJECT PRICING Revision 1 7AUG.pdf PDF
Ventilation Bldg 3001 Tinker.doc DOC document
Asbuilts 950028 AHU_5-6-7.pdf PDF
Pre-Proposal Charts - Final.ppt PPT presentation
070244 Spec 09612.pdf PDF
B3001 070094 KTR Route.pdf PDF
060367 AF66 Rev 1.pdf PDF
070295 AF66 Rev 1.pdf PDF
070094 AF66 Rev 1.pdf PDF
070244 AF66 Rev 1.pdf PDF
back shop foot print.xlsx XLSX spreadsheet
070088 AF66 Rev 1.pdf PDF
Attachment14.zip ZIP file
Attachment14B.zip ZIP file
Attachment14C.zip ZIP file
Attachment 1 - Current Davis Bacon Wage.pdf PDF
Attachment 17.zip ZIP file
Attachment 16.zip ZIP file
Attachment 15.zip ZIP file
Attachment 12.zip ZIP file
Attachment 13.zip ZIP file
Atch 8 - subteam consent to release PP info to prime.doc DOC document
SEED PROJECT PRICING.docx DOCX document
Atch 4 - POC listing.doc DOC document
AF 66 SAMPLE.pdf PDF
Atch 9 - PP Questionnaire.doc DOC document
Atch 11 - past perf inform.doc DOC document
Show all 50

Multiple Award Construction Contract (MACC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

72d CONTRACTING SQUADRON

TINKER AIR FORCE BASE, OKLAHOMA

25 Nov 09

FROM: 72 CONS/PKBA

7858 5TH STREET, SUITE 1

TINKER AIR FORCE BASE OK 73145FILLIN "LAST 1 OR 2 DIGITS OF YOUR RETURN OFFICE SYMBOL"

SUBJECT: FA8101-09-R-0021, Multiple Award Construction Contract

RFI 161-166

1. The following RFIs are offered and incorporated in the subject solicitation as follows:

RFI 161: SEED B – WWYK070244, B2122

Is the existing man door located between column 42 and 43 currently rated?

RFI Response:

There are two dorrs between column lines 42 and 43. The door on the north side is labeled as a 45 minute door. The door on the south side is not a rated door.

RFI 162: SEED A – WWYK07088, B3001

The existing break room shares a wall with existing electrical rooms containing high voltage transformers. Is the currently shared wall rated for fire separation? If not, is it the intent of Tinker AFB that it be rated?

RFI Response:

The Government’s requirement is for a code compliant breakroom. The existing wall shared by the breakroom and electrical area is constructed of metal studs with 5/8” gyp on either side. The Contractor shall use this information to determine if the wall is required to be fire rated.

RFI 163: SEED A – WWYK07088, B3001

Currently a metal cage with door is constructed at the platform steps which will be considered the second egress from the break room. An existing exit sign is currently directing egress from the platform into the break room. The platform is outside of the scope. The directional exit sign can no longer direct egress through the break room after it is enclosed due to the fact that the break room will be egressing onto the platform. An exit light must be installed over the stairs to direct egress from the platform. Shall the new egress light be included in this project even though it is not currently shown in the scope of work?

RFI Response:

The Government provided a 15% level statement of work which requires the Contractor to complete the design per the codes cited in paragraph 1.1.5 of the Statement of Work for this seed project.

RFI 164: CONTRACTING

At the site visit, it was mentioned that all questions are due no later than 18 November 2009. Will any other questions be considered after that time?

RFI Response:

Questions may be submitted any time until closing; however, the Government requests that all questions be submitted no later than 25 November 09.

RFI 165: CONTRACTING

If there are changes to a proposal that would affect content and page numbers from the Table of Contents all the way through one of the volumes, is it possible to send replacement volumes instead of requesting 90 percent of the pages removed and replaced?

RFI Response:

Yes, you may send replacement volumes. Please note that any changes can be made to proposals until the proposal close date and time. As noted in Amendment 0008, “the Contractor shall submit information highlighting any proposal changes, and include the location of changes or modifications within the amended proposal.”

RFI 166: CONTRACTING

Do Amendments 0007 and 0008 open the solicitation to new offerors that did not submit at the original due date?

RFI Response:

Yes. When the Amendments were issued, the solicitation opened for changes to current proposals as well as new offerors that did not submit at the original due date.

2. Any further question may be referred to the undersigned at 405-739-4189 or email at sharla.flowers@tinker.af.mil OR janice.hammonds@tinker.af.mil.

SHARLA FLOWERS