060367 Spec 01 11 00 - Rev 1.pdf

PDF 15 KB Posted

Attached to
Multiple Award Construction Contract (MACC) Federal contract opportunity
Solicitation number
FA8101-09-R-0021
Issued by
Department of the Air Force Materiel Command Air Force Sustainment Center

About this file

WWYK060367 Revised Summary of Work

View the file

Other files for this federal contract opportunity

Other files attached to Multiple Award Construction Contract (MACC), newest first.
File Type Posted
FA8101-09-R-0021-0009.pdf PDF
rfi 167 and 163 update.pdf PDF
FA8101-09-R-0021-0007.doc DOC document
Question-Answers #5 to FBO.pdf PDF
FA8101-09-R-0021-0006.pdf PDF
070094 Dwg M5 01 redline Rev 1.pdf PDF
BoilerPlateLanguage.pdf PDF
070094 Dwg A6 00 Rev 1.pdf PDF
070094 Spec 15400 - Rev 1.pdf PDF
FA8101-09-R-0021-0005.doc DOC document
2009 Base Facility Standard with 2007 ACP Included in Chap 13.pdf PDF
Electrical Base Stds 2007.pdf PDF
fa8101-09-r-0021-0004.doc DOC document
070094 Dwgs - Rev 1.pdf PDF
950028 Asbuilt.pdf PDF
070244.zip ZIP file
Question-Answers #2 to FBO.pdf PDF
FA8101-09-R-0021-0003.pdf PDF
070094 Spec 01110 - Rev 1.pdf PDF
070295 Spec 01 11 00 - Rev 1.pdf PDF
070085 Spec 01 11 00 - Rev 1.pdf PDF
070088 SOW - Rev 1.pdf PDF
070244 SOW - Rev 1.pdf PDF
Questions-Answers #1 to FBO.pdf PDF
070244 As-Builts 3.zip ZIP file
Amendment 0002.pdf PDF
070244 As-Builts 2.zip ZIP file
Pre-Proposal Conference Minutes.pdf PDF
3001 UTILITIES.zip ZIP file
MACC Presolicitation Bus Tour 7-16-09.pdf PDF
SEED PROJECT PRICING Revision 1 7AUG.pdf PDF
Ventilation Bldg 3001 Tinker.doc DOC document
Asbuilts 950028 AHU_5-6-7.pdf PDF
03_070088 FP01-Layout1.pdf PDF
070085 AF66 Rev 1.pdf PDF
070244 FP02.pdf PDF
070295 AF66 Rev 1.pdf PDF
070094 AF66 Rev 1.pdf PDF
070244 AF66 Rev 1.pdf PDF
back shop foot print.xlsx XLSX spreadsheet
FA8101-09-R-0021-0001.pdf PDF
Attachment14C.zip ZIP file
Attachment 1 - Current Davis Bacon Wage.pdf PDF
Attachment 16.zip ZIP file
Atch 7 - Client auth letter.docx DOCX document
Atch 6 - Consent letter.doc DOC document
Atch 10 - questionnaire cover letter.doc DOC document
SEED PROJECT PRICING.docx DOCX document
Atch 4 - POC listing.doc DOC document
AF 66 SAMPLE.pdf PDF
Show all 50

Multiple Award Construction Contract (MACC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RENOVATE MADPPC SPACE IN B3703 TINKER AIR FORCE BASE WWYK060367

INSTALL NEW HVAC B3703 WWYK060367A

SECTION 01 11 00

SUMMARY OF WORK

Revision 1 08/09

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM E 2114 (2006a) Standard Terminology for

Sustainability Relative to the Performance of Buildings

1.2 DEFINITIONS

Definitions pertaining to sustainable development are as defined in ASTM E 2114, and as specified.

a. "Environmentally preferable products" have a lesser or reduced effect on the environment in comparison to conventional products and services. This comparison may consider raw materials acquisition, production, manufacturing, packaging, distribution, reuse, operation, maintenance, or disposal of the product.

b. "Indoor environmental quality" is the physical characteristics of the building interior that impact occupants, including air quality, illumination, acoustics, occupant control, thermal comfort, day lighting, and views.

c. "Operational performance" is the functional behavior of the building as a whole or of the building components.

d. "Sustainability" is the balance of environmental, economic, and societal considerations.

1.3 SUBMITTALS

All submittals throughout the specifications shall be in accordance with Section 01 33 00 SUBMITTAL PROCEDURES and the AF66 SUBMITTAL REGISTER.

1.4 WORK COVERED BY CONTRACT DOCUMENTS

1.4.1 Project Description

This project will consist of in-fill under the existing mezzanine to create a new administration area (office and training spaces), and will re-paint and re-light the maintenance bay and the upper mezzanine storage under the renovation project. The new administration areas will be fully air-conditioned under the minor new construction portion of the project.

The interior design portion of the renovation will primarily be confined to the new training and office areas. The new administration area under the existing mezzanine will have 2'x2' acoustical tile ceiling and painted gypsum board walls. The training room floor will be VCT and the office area will have carpet tile suitable for a high use area. The new doors shall be stained with an oil based stain and sealed to match the existing doors. The door frames shall be painted Sherwin-Williams #7019. The remaining shop area will receive a fresh coat of paint on the walls and ceiling, suitable for industrial areas. The gyp board on the west wall of the shop area shall be replaced with new and painted to match the rest of the shop area. The interior of the overhead door in the shop area shall be painted Sherwin- Williams #7019. The floor joints in the shop shall be caulked and the entire floor sealed.

New mechanical work shall consist of Plumbing and Heating, Cooling, and Ventilating systems within the new build-out area of existing Building 3703.

The new build-out of existing Building 3703 shall be heated, ventilated and air conditioned with two packaged air conditioning units. Each unit will be hung on the East exterior wall of Building 3703. Unit-1 will be hung on the exterior side of the Office area and Unit-2 will be hung on the exterior side of the Training/Break area. The Shop/Mezzanine area of the new build-out will be heated and ventilated only. Two new unit heaters will be installed. A new wall-type propeller fan w/motorized damper and wall louver will be installed along with a second motorized damper and wall louver for air flow and ventilation of the space.

New plumbing will include a new stainless steel kitchen sink in the Break Room area. The existing cold water line on the other side of the West wall will be tapped and a ¾" cold water line will bring cold water to the new sink and domestic water heater.

New electrical work shall consist of providing new lighting in the maintenance bay. New lighting and power will also be indicated in the new admin area under the mezzanine. In the shop area, the partition wall that supports the lighting shall be demoed along with the lighting.

1.4.2 Location

The work shall be located at the northeast end of existing building 3703, approximately as indicated. The exact location will be shown by the Contracting Officer.

1.5 PROJECT ENVIRONMENTAL GOALS

Contractor shall distribute copies of the Environmental Goals to each subcontractor and the Contracting Officer. The overall goal for design, construction, and operation is to produce a building that meets the functional program needs and incorporates the principles of sustainability.

Specifically:

a. Preserve and restore the site ecosystem and biodiversity; avoid site degradation and erosion. Minimize offsite environmental impact.

b. Use the minimum amount of energy, water, and materials feasible to meet the design intent. Select energy and water efficient equipment and strategies.

c. Use environmentally preferable products and decrease toxicity level of materials used.

d. Use renewable energy and material resources.

e. Optimize operational performance (through commissioning efforts) in order to ensure energy efficient equipment operates as intended.

Consider the durability, maintainability, and flexibility of building systems.

f. Manage construction site and storage of materials to ensure no negative impact on the indoor environmental quality of the building.

g. Reduce construction waste through reuse, recycling, and supplier take-back.

1.6 OCCUPANCY OF PREMISES

The majority of the Building will be occupied during performance of work under this Contract.

Before work is started, the Contractor shall arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.7 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.

Obtain digging permits prior to start of excavation by contacting the Contracting Officer 15 calendar days in advance. Verify the elevations of existing piping, utilities and any type of underground or encased obstruction not indicated to be specified or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.8.1 Notification Prior to Excavation

Notify the Contracting Officer at least 48 hours prior to starting excavation work.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --