File Type Posted
Attachment_46_-_Past_Performance_Information_Sheet_20_May.pdf PDF
FA485518R0003_Amendment_5.pdf PDF
Attachment_45_-_Education.Experience_Matrix_20_May.pdf PDF
FA485518R0003_Amendment_0004.pdf PDF
FA485518R0003_Amendment_0003.pdf PDF
Attachment_41_-_Sample_Project_Attachment_-_18_Jan_2018.pdf PDF
FA485518R0003_Q&A_Part_5.pdf PDF
Attachment_01-_SABER_General_Requirements_-_12_Jan_2018.pdf PDF
FA4855-18-R-0003_Amendment_0002.pdf PDF
Attachment_42_-_Seed_Project_Statement_of_Objectives_-_18_Jan_2018.pdf PDF
Attachment_40_-_Sample_Project_Statement_of_Objectives_-_18_Jan_2018.pdf PDF
Attachment_43_-_Seed_Project_Attachments_-_18_Jan_2018.pdf PDF
FA485518R0003_Q&A_Part_4.pdf PDF
Pre-Proposal_Site_Visit_Memo.Addendum.pdf PDF
FA485518R0003_Q&A_Part_3.pdf PDF
Attachment_43_-_Seed_Project_Attachments_-_10_Jan_2018.pdf PDF
Attachment_42_-_Seed_Project_Statement_of_Objectives_-_10_Jan_2018.pdf PDF
FA485518R0003_Amendment_1.pdf PDF
FA485518R0003_Q&A_Part_2.pdf PDF
Site_Visit_Sign_In_Sheet_Redacted.pdf PDF
Pre-Proposal_Site_Visit_Memo.Part2.MAFR.pdf PDF
Pre-Proposal_Site_Visit_Memo.Part1.CAFB.pdf PDF
FA485518R0003_Q&A_Part_1.pdf PDF
Attachment_32-_WD_NM5_Residential_Curry_&_Roosevelt_-_6_Jan_2017.pdf PDF
Attachment_03_-_Example_Drawings_-_May_1975.pdf PDF
Attachment_19_-_CAFB_Labeling_Standards_for_Communications_-_29_Jan_2009.pdf PDF
Attachment_30-_NMGRT_Invoice_Certification_-_no_date.pdf PDF
Attachment_14_-_AF_Form_66_Schedule_of_Material_Submittals_-_no_date.pdf PDF
Attachment_01-_SABER_General_Requirements_-_6_Oct_2017.pdf PDF
Attachment_38-_Financial_Reference_Worksheet_-_no_date.pdf PDF
Attachment_12_-_AF_Form_3064_-_Progress_Schedule_-_1_Sep_2003.pdf PDF
Attachment_10_-_US_Army_Corps_Of_Engineer_Design_Manual_-_Mar_2007.pdf PDF
Attachment_06_-_CAFB_Landscape_Development_Plan_-_3_Feb_2012.pdf PDF
Attachment_33-_WD_NM50_Highway_Curry_&_Roosevelt_-_6_Jan_2017.pdf PDF
Attachment_28_-_Cost_Estimate_Example_-_no_date.pdf PDF
Attachment_02_-_SABER_Specifications_-_14_Nov_2017.pdf PDF
Attachment_05_-_CAFB_Hardware_Specifications_Guideline_-_Nov_2016.pdf PDF
Attachment_34-_WD_NM23_Building_Curry_-_22_Sep_2017.pdf PDF
Attachment_36-_WD_NM7_Heavy_Curry_-_15_Sep_2017.pdf PDF
Attachment_37-_WD_NM12_Heavy_Roosevelt_-_15_Sep_17.pdf PDF
Attachment_08_-_AFSOC_Facility_Excellence_Guide_-_2008.pdf PDF
FA485518R0003_-_SABER.pdf PDF
Attachment_31-_NMGRT_Proposal_Certification_-_no_date.pdf PDF
Attachment_22_-_CAFB_MAFR_Contractor_Env_Guide_-_2_Jul_2015.pdf PDF
Attachment_09_-_GeoBase_Initial_Operating_Capability_-_19_May_2010.pdf PDF
Attachment_44_-_Additional_Contractor_Information_-_no_date.pdf PDF
Attachment_40_-_Sample_Project_Statement_of_Objectives_-_31_Aug_2017.PDF PDF
Attachment_42_-_Seed_Project_Statement_of_Objectives_-_21_Nov_2017.pdf PDF
Attachment_25_-_AF_Carpet_Standard_-_ETL_07_4_-_28_Mar_2007.pdf PDF
Attachment_04_-_CAFB_Electrical_Standards_-_Apr_2016.pdf PDF
Show 40 more

Latest 50 of 68 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA485518R0003 – SABER Solicitation Questions and Answers Part 6

1. Since Amendment 03 extended the due date again, should we expect any further addenda as a reason for this extension?

Answer: No further addendums are associated with amendment 03.

2. Per SABER General Requirements Section 5.2.1.3 - A site plan (or plans) depicting project location, site boundaries and access, building footprints and orientation, stand-off distances, utility types, sizes and locations, and schematic grading and drainage strategies. Include a parking plan with quantities and basic dimensions, and depicting site access. However, the SOW for the sample project does not specify parking lot and or plan. Will a parking plan including, parking quantities, basic dimensions and site access be required as part of the Sample project, site plan?

Answer: The general requirements are an overview of requirements for projects, and as such, may not be applicable to all task orders. Per the sample project SOO, there is no requirement for a parking plan for this task order.

3. Per SABER General Requirements Section 5.2.1.7 – At least three perspective renderings to illustrate building massing and fenestration, colors and basic materials. Is this required for the Sample project? If so, could you be more specific on what the requirement would be as the above statement is fairly ambiguous.

Answer: The general requirements are an overview of requirements for projects. This may not be applicable to all task orders and shall be identified as part of the project requirements.

4. Per RFP, Page 60 of 65, Section 6.3.1 specifies the Evaluation factors for Sample project. This section indicates that the evaluation will be based on items listed in Section L paragraphs 5.5.1.2 through

5.5.1.11. This indicated elimination of the first items listed 5.5.1.1 “Design Narrative and Scope of

Work.” Is it the Government’s intention to eliminate this requirement?

Answer: Section M, paragraph 6.3.1 has been amended to read “The ability to provide detailed design narrative, plans, drawings, and specifications adequately addressing the items listed in Section L, paragraph 5.5.1.1 through paragraph 5.5.1.11”, which was accomplished through solicitation amendment

04.

5. There is not a reference to how many sets of drawings are required for the proposal. Is one set of drawings sufficient?

Answer: Drawings requirements are outlined in solicitation Attachment 1, SABER General

Requirements, paragraph 1.13 and paragraph 5.0. Additional information regarding number of required copies are outlined in Section L, Instructions to Offerors, paragraph 3.5 and paragraph 5.

File details come from the government source that posted it.