This document outlines fire protection standards for facilities at Ellsworth Air Force Base in South Dakota. The standards require all facilities to comply with UFC 3-600-01 and the ACC Supplement, including building code analysis, life safety code analysis, and water supply analysis. Plans must show fire walls, rated assemblies, fire and smoke dampers, and exit and emergency lighting. Specifications require schedule 40 piping for sprinkler systems, radio transmitters matching the base system, 16 AWG minimum wire, and combination speaker/strobes with the word "alert." The fire protection designer of record must review shop drawings and witness all tests. Training of four hours or more is required for firefighters, shop personnel, and craftsmen on testing, maintenance and operation of systems.

The related federal contract opportunity is a solicitation for multiple award construction contracts at Ellsworth Air Force Base. The solicitation will award an estimated three indefinite delivery indefinite quantity contracts for new construction, renovation, repair and related work between $500,000 and $18 million from date of award through June 2021. The opportunity is set aside for service disabled veteran owned small businesses, 8(a) small disadvantaged businesses, and HUBZone businesses. The NAICS code is 237990 and size standard is $36.5 million. The solicitation will be issued via FBO.gov on or about November 14, 2018.

FA469019RA003 Atch 7

View the file

Other files for this federal contract opportunity

Other files attached to Multiple Award Construction Contract (MACC), newest first.
File Type Posted
Solicitation_Amendment_FA469019RA0030013_SF_30.pdf PDF
Atch_32_-_Follow_on_Q&A_Updated_1MAY19.pdf PDF
Solicitation_Amendment_FA469019RA0030012_SF_30.pdf PDF
Atch_20f_Bid_Schedule-25_Apr_19.doc DOC document
Solicitation_Amendment_FA469019RA0030011_SF_30.pdf PDF
Atch_20a_GIPR_23APR19.pdf PDF
Solicitation_Amendment_FA469019RA0030010_SF_30.pdf PDF
Solicitation_Amendment_FA469019RA0030007_SF_30.pdf PDF
Attach_27_a_Site_Vist_QAs_as_of_6_Mar_19.pdf PDF
Solicitation_Amendment_FA469019RA0030006_SF_30.pdf PDF
Attach_27_bTrack_with_Contours_and_Utilities.pdf PDF
Attach_27_c_CE_Track_Manholes.pdf PDF
Solicitation_Amendment_FA469019RA0030004_SF_30.pdf PDF
Solicitation_Amendment_FA469019RA0030002_SF_30.pdf PDF
Atch_3_Submittal_Schedule_-20_Aug_15.pdf PDF
Atch_14_Contractor_Guide_-_16_Jun_15.pdf PDF
Atch_8_Exterior_Signs_-_10_Jun_05.pdf PDF
Atch_6_Design_CompatibilityStandards.pdf PDF
Atch_16d_-_WD_SD180033_Building-Meade_5_Jan_18.pdf PDF
Atch_21,_SECTION_L-_INSTRUCTIONS_TO_OFFERORS_18DEC18.pdf PDF
Atch_20f_Bid_Schedule-17_Oct_18.doc DOC document
Atch_16e_-_WD_SD180035_Building-Penn_5_Jan_18.pdf PDF
Atch_10_Electrical_Systems-15_Jan_15.pdf PDF
Atch_9_Submittal_Form_3000-1_Sep_03.pdf PDF
Atch_20a_GIPR_6NOV18.pdf PDF
Solicitation_-_FA469019RA003.pdf PDF
Atch_19_Past_Performance_Questionairre.docx DOCX document
Atch_2_AF_Form_103_Work__BCE_Clearance_Request_-_1_Aug_94.pdf PDF
Atch_16c_-_WD_SD180001_Heavy-Highway_6_Apr_18.pdf PDF
Atch_13_NAFGeneral_Provisions-21Jan15.pdf PDF
Atch_20e_6_Percent_Limit_on_Design_Fee_for_Contractors.pdf PDF
DRAFT_Atch_14_Contractor_Guide_-_16_Jun_15.pdf PDF
DRAFT_Atch_9_Submittal_Form_3000-1_Sep_03.pdf PDF
DRAFT_Atch_20a_GIPR_6NOV18.pdf PDF
DRAFT_Atch_22_SECTION_M_Evaluation_Factors.pdf PDF
DRAFT_Atch_16a_-_WD_SD180002_Residental-Penn_5_Jan_18.pdf PDF
DRAFT_Atch_6_Design_CompatibilityStandards.pdf PDF
DRAFT_Atch_1_Utility_Outages.pdf PDF
DRAFT_Atch_10_Electrical_Systems-15_Jan_15.pdf PDF
DRAFT_Atch_15_Non-Nuclear_Intrusion_Det.pdf PDF
DRAFT_Atch_7_Ellsworth_Fire_Protection.pdf PDF
DRAFT_Atch_16d_-_WD_SD180033_Building-Meade_5_Jan_18.pdf PDF
DRAFT_Atch_20e_6_Percent_Limit_on_Design_Fee_for_Contractors.pdf PDF
DRAFT_Atch_20c_Drawing_1_Track_Utilities_Latrine_6NOV18.pdf PDF
DRAFT_Atch_5_Spec_Section_01800_-20_Aug_15.pdf PDF
DRAFT_Atch_2_AF_Form_103_Work__BCE_Clearance_Request_-_1_Aug_94.pdf PDF
DRAFT_Atch_11_Underground_Electrical_20Aug15.pdf PDF
DRAFT_Atch_20g_AF_Form_3052.xls XLS spreadsheet
DRAFT_Atch_3_Submittal_Schedule_-20_Aug_15.pdf PDF
DRAFT_Atch_4_Spec_Section_01000_-20_Aug_15.pdf PDF
Show all 50

Multiple Award Construction Contract (MACC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BASE FIRE PROTECTION STANDARDS

Ellsworth AFB, South Dakota

Fire protection for all facilities shall comply with the following:

Design

All facilities shall be designed to comply with UFC 3-600-01 and the ACC Supplement. The fire protection engineer designer of record (FPDOR) shall meet the requirements of UFC 3-

600-01 and shall be in attendance at all design review meetings. If COE or NAVFAC is not the construction agent, the FPDOR shall review all shop drawings for approval and shall witness all operational tests for acceptance of the fire protection systems. FPDOR shall be identified at the beginning of the project.

All projects shall include building code analysis, life safety code analysis and a water supply analysis in accordance with UFC 3-600-01. These shall be included in the 35% submittal.

1. Building code analysis shall use the current edition of International Building Code as outlined in UFC 4-021-01. Analysis shall compare the allowable area and height and the actual area and height.

2. Life Safety Code analysis shall be based on latest edition of NFPA 101. Analysis shall show allowable and actual data such as travel distances, occupant loading, exits, etc.

3. Water supply analysis shall use the attached format for determining the adequacy of the water supply. Designer is responsible for conducting water tests to use in the analysis.

Plans

Life Safety Code:

Life Safety Code analysis and Building Code analysis shall be included as separate plans including the information shown in the ACC Supplement.

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text Attachment 7

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

Civil Plans:

The civil drawings shall show all fire water mains to include positive identification of the test hydrants (both pressure and flow hydrants).

Plans must show water main from the test point to the building riser.

Show all fire hydrants and control valves. See UFC 3-600-01 for criteria.

Roads shall comply with UFC 3-600-01 and NFPA 1 for accessibility to building by emergency vehicles. Coordinate with the fire department.

Architectural Plans

The architectural plans and the Life Safety Code plans shall both show the fire walls and partitions and architectural plans shall identify the UL number or other standard such as

FM for fire rated assemblies.

Door plan shall identify the fire rating of any fire doors. Make sure fire doors match firewalls shown on drawings.

Mechanical Plans

Mechanical plans shall positively identify all fire and/or smoke dampers and provide a detail for installation. Any smoke damper shall include a smoke detector for activation of the damper. Fire dampers shall be shown to comply with NFPA 90A and smoke dampers shall comply with NFPA 101.

Mechanical plans shall include duct smoke detectors on the control diagram. Smoke detectors shall not activate the building evacuation alarm system but shall report as an alarm to the fire department as a separate zone on the fire alarm panel.

Electrical Plans

Plans must show the exit and emergency lights.

Switchgear shall show the power for the fire alarm system as a separate breaker.

Fire Suppression Plans

Plans must show the hazard classification for each area.

Provide a chart showing the density, area of application and hose stream demand for each hazard classification. This data must comply with UFC 3-600-01.

Provide a riser diagram for the sprinkler system. Make sure to include a test connection for the backflow preventer. The Air Force uses “shotgun” risers.

Fire Alarm Plans

Plans shall show all fire alarm and Mass Notification devices. Visual devices shall show the candela rating of each device.

Riser diagram shall show all power connections, initiating devices, alarm devices and any interconnections of such as AHU shutdown or door releases.

Provide a matrix showing what action each device will initiate.

Locate the fire alarm panel as dictated by the fire department. Panel shall be located in a conditioned space accessible to the fire department when the building is not occupied.

Provide transmitter zone schedule

Specifications

Civil

Make sure all fire protection devices such as fire hydrants, control valves, etc over five feet from the building are included in the civil specifications.

Fire Suppression

Either the specifications or the plans must indicate the hazard classification including density, area of application and hose stream demand. If shown on plans, indicate that information is shown on the plans.

Provide the water supply data or show it on the plans. If shown on plans, indicate that in the specifications. If not shown on plans, be specific as to the location of the water test such as at Hydrant 100 or the base of the riser. Designer must include the loss from the test connection to the base of the riser.

All sprinkler piping shall be schedule 40 for dry pipe and preaction systems.

Training of shop personnel will consist of one four- hour training sessions that will include the testing and maintenance of the systems. Training shall be separate from the testing of the systems.

Fire Alarm

The fire alarm reporting system is a radio type system using Monaco transmission. All transmitters or transmission devices shall match the base reporting system. Specifications shall specifically state the make and model of the transmitter.

Fire alarm system shall be class B system unless prior approval is given by ACC FPE.

Minimum wire size shall be 16 AWG.

The building fire alarm system shall be an addressable system and shall be a combination fire alarm/Mass Notification system. System shall use combination speaker/strobes and the strobes shall be clear with the word ALERT on them.

Manual stations shall be key reset only-no other type reset will be allowed. Manual stations shall NOT have glass rods.

Base firefighters and craftsmen shall be trained on the operation and maintenance of the control panel and devices with minimum 4 hours training. Two sessions will be required on separate days to make sure all personnel can attend training. This training will be separate from the testing of the systems.

Testing:

Specifications must clearly indicate the testing of the fire protection systems and the A/E shall develop a commissioning plan that indicates how each system will be tested and who will witness the testing for acceptance. The FPDOR shall be the lead for the commissioning plan and the plan shall be approved by contracting officer prior to testing. The FPDOR shall write a commissioning letter stating that the systems are in full compliance with the plans and specifications.