This document provides details regarding a Multiple Award Construction Contract solicitation. The solicitation will be issued by Ellsworth Air Force Base in South Dakota and intends to award up to three indefinite delivery indefinite quantity contracts for construction, renovation, alteration, demolition, and repair work at the base. Eligible contractors must be certified as a Service Disabled Veteran Owned Small Business, SBA certified 8(a) Small Disadvantaged Business, or HUBZone business. The North American Industry Classification code is 237990 and the annual size standard is $36.5 million. The contract period will be from date of award to 29 June 2021, with a guaranteed minimum of $500 and maximum value of $18 million across all awards. The solicitation is anticipated to be available on or around 14 November 2018 via the Federal Business Opportunities website.

Question and Answer

View the file

Other files for this federal contract opportunity

Other files attached to Multiple Award Construction Contract (MACC), newest first.
File Type Posted
Atch_32_-_Follow_on_Q&A_Updated_1MAY19.pdf PDF
Atch_31_Follow_on_Q&As_26APR19.pdf PDF
Solicitation_Amendment_FA469019RA0030011_SF_30.pdf PDF
Atch_20b_SOW_Updated_23APR19.pdf PDF
Atch_20a_GIPR_23APR19.pdf PDF
Solicitation_Amendment_FA469019RA0030010_SF_30.pdf PDF
Solicitation_Amendment_FA469019RA0030007_SF_30.pdf PDF
Attach_27_c_CE_Track_Manholes.pdf PDF
Atch_25_Site_Vist_Q&As_14FEB19.pdf PDF
Solicitation_Amendment_FA469019RA0030003_SF_30.pdf PDF
Atch_23_Site_Visit_Minutes.pdf PDF
Solicitation_Amendment_FA469019RA0030002_SF_30.pdf PDF
Atch_20_FOPR_Construct_Bath_House_3JAN19.pdf PDF
Atch_12_General_Provisions_-_8NOV18.pdf PDF
Atch_16b_-_WD_SD180006_Residental-Meade_5_Jan_18.pdf PDF
Atch_20b_SOW_6NOV18.pdf PDF
Atch_17_Determination_of_Resp.pdf PDF
Atch_20_FOPR_Construct_Bath_House.pdf PDF
Atch_20c_Drawing_1_Track_Utilities_Latrine_6NOV18.pdf PDF
Atch_15_Non-Nuclear_Intrusion_Det.pdf PDF
Atch_20g_AF_Form_3052.xls XLS spreadsheet
Atch_4_Spec_Section_01000_-20_Aug_15.pdf PDF
Atch_20d_RMD_KTR_to_Complete.pdf PDF
Atch_9_Submittal_Form_3000-1_Sep_03.pdf PDF
Atch_20a_GIPR_6NOV18.pdf PDF
Solicitation_-_FA469019RA003.pdf PDF
Atch_19_Past_Performance_Questionairre.docx DOCX document
Atch_2_AF_Form_103_Work__BCE_Clearance_Request_-_1_Aug_94.pdf PDF
Atch_16c_-_WD_SD180001_Heavy-Highway_6_Apr_18.pdf PDF
Atch_13_NAFGeneral_Provisions-21Jan15.pdf PDF
Atch_20e_6_Percent_Limit_on_Design_Fee_for_Contractors.pdf PDF
DRAFT_Atch_4_Spec_Section_01000_-20_Aug_15.pdf PDF
DRAFT_Atch_20d_RMD_KTR_to_Complete.pdf PDF
DRAFT_Atch_21_SECTION_L_Instructions,_Conditions,_and_Notices_to_Offerors.pdf PDF
DRAFT_Atch_12_General_Provisions_-_8NOV18.pdf PDF
DRAFT_Atch_16b_-_WD_SD180006_Residental-Meade_5_Jan_18.pdf PDF
DRAFT_Atch_20b_SOW_6NOV18.pdf PDF
DRAFT_Atch_16c_-_WD_SD180001_Heavy-Highway_6_Apr_18.pdf PDF
DRAFT_-_FA469019RA003.pdf PDF
DRAFT_Atch_8_Exterior_Signs_-_10_Jun_05.pdf PDF
DRAFT_Atch_19_PPQ.docx DOCX document
DRAFT_Atch_7_Ellsworth_Fire_Protection.pdf PDF
DRAFT_Atch_16d_-_WD_SD180033_Building-Meade_5_Jan_18.pdf PDF
DRAFT_Atch_20e_6_Percent_Limit_on_Design_Fee_for_Contractors.pdf PDF
DRAFT_Atch_20c_Drawing_1_Track_Utilities_Latrine_6NOV18.pdf PDF
DRAFT_Atch_5_Spec_Section_01800_-20_Aug_15.pdf PDF
DRAFT_Atch_2_AF_Form_103_Work__BCE_Clearance_Request_-_1_Aug_94.pdf PDF
DRAFT_Atch_11_Underground_Electrical_20Aug15.pdf PDF
DRAFT_Atch_20g_AF_Form_3052.xls XLS spreadsheet
DRAFT_Atch_3_Submittal_Schedule_-20_Aug_15.pdf PDF
Show all 50

Multiple Award Construction Contract (MACC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question 54: Clarification to the request for a 10’x15’ storage room and whether it needs to fit into the 20’x30’ footprint

Answer 54: The building dimensions indicated in the SOW are nominal, therefore notional dimensions of the approximate size of the building. Thus, the storage room does not necessarily need to be in a set 20’x30’ footprint. For example, the storage room may be attached to the back of the building and part of the overall structure; or the storage room may be incorporated into the 20’x30’ with necessary increases in the width/length to accommodate. It is up to the contractor to determine the best method to incorporate this new requirement into their design.