This document contains questions and answers from a pre-solicitation site visit for a federal construction contract opportunity. The opportunity will be for multiple indefinite delivery indefinite quantity construction contracts at Ellsworth Air Force Base in South Dakota. The work will include new construction, renovation, alteration, demolition, and repair projects in various trades. The NAICS code is 237990 and annual size standard is $36.5 million. The solicitation will be set aside for Service Disabled Veteran Owned Small Businesses, SBA certified 8(a) Small Disadvantaged Businesses, and HUBZone businesses. The contract period is from date of award to June 2021, with a minimum guarantee of $500 and maximum value of $18 million total across contracts. The solicitation number is FA469019RA003 and will be issued on the Federal Business Opportunities website.

Atch 25 Q&A

View the file

Other files for this federal contract opportunity

Other files attached to Multiple Award Construction Contract (MACC), newest first.
File Type Posted
Atch_31_Follow_on_Q&As_26APR19.pdf PDF
Atch_30_Follow_on_Q&A_25APR19.pdf PDF
Atch_20b_SOW_Updated_23APR19.pdf PDF
Atch_29_Follow_on_Q&As_23APR19.pdf PDF
Solicitation_Amendment_FA469019RA0030009_SF_30.pdf PDF
Solicitation_Amendment_FA469019RA0030008_SF_30.pdf PDF
Atch_28_-_Follow_on_Q&As.pdf PDF
Solicitation_Amendment_FA469019RA0030005_SF_30.pdf PDF
Atch_26_X-XX_PROJECT_TITLE.dwg DWG drawing
Solicitation_Amendment_FA469019RA0030003_SF_30.pdf PDF
Atch_24_Site_Visit_Minutes_24JAN19.pdf PDF
Atch_23_Site_Visit_Minutes.pdf PDF
Atch_20_FOPR_Construct_Bath_House_3JAN19.pdf PDF
Solicitation_Amendment_FA469019RA0030001_SF_30.pdf PDF
Atch_12_General_Provisions_-_8NOV18.pdf PDF
Atch_16b_-_WD_SD180006_Residental-Meade_5_Jan_18.pdf PDF
Atch_20b_SOW_6NOV18.pdf PDF
Atch_17_Determination_of_Resp.pdf PDF
Atch_20_FOPR_Construct_Bath_House.pdf PDF
Atch_20c_Drawing_1_Track_Utilities_Latrine_6NOV18.pdf PDF
Atch_15_Non-Nuclear_Intrusion_Det.pdf PDF
Atch_20g_AF_Form_3052.xls XLS spreadsheet
Atch_4_Spec_Section_01000_-20_Aug_15.pdf PDF
Atch_20d_RMD_KTR_to_Complete.pdf PDF
Atch_18_Past_Performance_Information.docx DOCX document
Atch_22,_SECTION_M_-_EVALUATION_BASIS_FOR_AWARD_2JAN19.pdf PDF
Atch_5_Spec_Section_01800_-20_Aug_15.pdf PDF
Atch_11_Underground_Electrical_20Aug15.pdf PDF
Atch_16a_-_WD_SD180002_Residental-Penn_5_Jan_18.pdf PDF
Atch_1_Utility_Outages.pdf PDF
DRAFT_Atch_4_Spec_Section_01000_-20_Aug_15.pdf PDF
DRAFT_Atch_20d_RMD_KTR_to_Complete.pdf PDF
DRAFT_Atch_21_SECTION_L_Instructions,_Conditions,_and_Notices_to_Offerors.pdf PDF
DRAFT_Atch_12_General_Provisions_-_8NOV18.pdf PDF
DRAFT_Atch_16b_-_WD_SD180006_Residental-Meade_5_Jan_18.pdf PDF
DRAFT_Atch_20b_SOW_6NOV18.pdf PDF
DRAFT_Atch_16c_-_WD_SD180001_Heavy-Highway_6_Apr_18.pdf PDF
DRAFT_-_FA469019RA003.pdf PDF
DRAFT_Atch_8_Exterior_Signs_-_10_Jun_05.pdf PDF
DRAFT_Atch_19_PPQ.docx DOCX document
DRAFT_Atch_20f_Bid_Schedule-17_Oct_18.doc DOC document
DRAFT_Atch_13_NAFGeneral_Provisions-21Jan15.pdf PDF
DRAFT_Atch_16e_-_WD_SD180035_Building-Penn_5_Jan_18.pdf PDF
DRAFT_Atch_20_FOPR_Construct_Bath_House.docx DOCX document
DRAFT_Atch_18_Past_Performance_Information.docx DOCX document
DRAFT_Atch_17_Determination_of_Resp.pdf PDF
DRAFT_Atch_14_Contractor_Guide_-_16_Jun_15.pdf PDF
DRAFT_Atch_9_Submittal_Form_3000-1_Sep_03.pdf PDF
DRAFT_Atch_20a_GIPR_6NOV18.pdf PDF
DRAFT_Atch_22_SECTION_M_Evaluation_Factors.pdf PDF
Show all 50

Multiple Award Construction Contract (MACC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question 1: Are there suitable fill materials stockpiled or located on the base that could be used on this project?

Answer 1: There is not any suitable fill material on base. 28 CES recommends use of SDOT-grade fill for use on site.

Question 2: Per Atch 21 Section L – Instructions, Condition, and Notice to Offerors, 3.3 Section III - Past Performance is there only a 15 page maximum for this factor?

Answer 2: The 15 page limit (5 projects @ 3 pages each) is just for Tab C (3.3.2.4). Tab A (3.3.2.2) and Tab B (3.3.2.3) do not have a page number limit.

Question 3: Item 12 of the GIPR indicates that the specification need to be UFGS format. At the Jan 10 meeting MasterSpec was also indicated as an approve specification format. Is MasterSpec an approved format?

Answer 3: For this solicitation, no, please submit in accordance with UFGS standards as found here:

http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs. In the future, MasterSpec may be used if identified in the solicitation.

Question 4: Should security style plumbing fixtures (stainless steel) be provided or are porcelain acceptable?

Answer 4: Porcelain fixtures are acceptable.

Question 5: Should wall hydrants be provided on the exterior of the building? Should hose bibbs be provided for cleaning inside the bathrooms?

Answer 5: No, the SOW does not mention the use of wall hydrants. Hose bibbs are not required due to the inclusion of a janitor’s closet with mop sink in the SOW, section 2CC.

Question 6: Regarding the Past Performance Questionnaire: What is the correct due date for the PPQ’s? The solicitation states two different dates: “ten (10) calendar days prior to the required due date” (pg. 1 , Attachment 21), which would be February 19 or February 25th (pg. 4, Attachment 21)?

Answer 6: The Government is requesting that PPQs be submitted early to allow the Government to organize the past performance information received in preparation for the Past Performance evaluation conducted after the solicitation closing. As stated in section L Failure to receive PPQs by the earlier date will not result in offeror disqualification. Any PPQs that are received prior to past performance evaluation and are considered Recent and Relevant will be included in the past performance evaluation.

Question 7: Will all future task orders require 65% drawings for submission of bids?

Answer 7: No, future task orders will not typically require a design at the time of proposal submission.

Project dependent design phases will occur after task order award, upon issuance of applicable Notice to Proceed.

Question 8: Do you have existing soil testing?

Answer 8: We do not have any geotechnical reports for soil testing. We highly recommend planning to bring appropriate fill (SDOT) for use on site.

Question 9: Many of our references for the Past Performance Evaluation Questionnaires are on furlough due to the government shutdown. Will prior project PPQ’s be acceptable to submit?

Answer 9: PPQ provided as attachment 19 is specific to this solicitation. PPQs from prior solicitation will not include the same information and prevent an equal evaluation. No questionnaire submittals will be accepted from the offeror being evaluated, evaluators shall send questionnaires directly to the Government. As stated in http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs section L Failure to receive PPQs by the earlier date will not result in offeror disqualification. Any PPQs that are received prior to past performance evaluation and are considered Recent and Relevant will be included in the past performance evaluation.

Question 10: Many of our references for the Past Performance Evaluation Questionnaires are on furlough due to the government shutdown. Will you accept questionnaire submittals directly from the offeror being evaluated?

Answer 11: Evaluators shall send questionnaires directly to the Government. No questionnaire submittals will be accepted from the offeror being evaluated. Once the evaluator completes the questionnaires, the information shall be considered sensitive and shall not be released to the offeror.

Question 12: Is master spec acceptable?

Answer 12: See question 3.

Question 13: Do you intend for the bathroom doors to face the existing parking lot or the track?

Answer 13: The doors shall face the parking lot.

Question 14: Can Section II and Section III be combined in one PDF as 1 portion of the technical proposal?

Do you want all three sections in their own separate PDF?

Answer 14: No, Section II and Section III may not be combined into one PDF. Please provide all three sections as their own PDFs as outlined in the solicitation.

Question 15: Is there a set percentage for overhead and a percentage for profit we are allowed to use on the AF Form 3052?

Answer 15: No, there is no set percentage. It is up to each contractor to determine their overhead and profit rates.

Question 16: Would the owner be able to provide a sample of a filled out AF3052 to show how much detail they expect the project to be broken down into?

Answer 16: The Government will not provide a sample of a filled out AF3052. It is up to each contractor to determine what the major cost elements are for their proposal.

Question 17: Should the labor costs on the front page of the AF3052 include wage rate, fringe benefits, and burden for total cost?

Answer 17: It is only necessary to provide major cost elements. The Government is not expecting a breakdown of pricing for each labor category, however if a contractor were to elect to provide labor hours it would be appropriate to provide the fully burdened labor costs.

Question 18: Section L Para 3.3.5 - If the projects referenced already hold a CPAR evaluation, do you still need a PPQ? Also, will we need to provide you with a copy of the CPAR?

Answer 18: PPQ’s can be used for projects not already covered by CPAR reports so if there is already a completed CPAR report, a separate PPQ is not necessary. If you do not anticipate any PPQ’s because all of your projects are covered under existing CPAR reports please state this in your proposal when submitted. The Government will pull CPAR reports for all contractors whose past performance is evaluated.

File details come from the government source that posted it. Updated .