This memorandum documents a site visit for a federal construction contract solicitation to construct bath houses at an outdoor running track on Ellsworth Air Force Base. The solicitation will be for multiple award construction contracts with an indefinite delivery indefinite quantity structure. It will have a small business set-aside for service disabled veteran owned small businesses, SBA certified 8(a) small disadvantaged businesses, and HUBZone firms. The work will include new construction, renovation, alteration, demolition and repair projects. The contract period will be from date of award to June 2021 with a minimum value of $500 and maximum of $18 million across all awards. Proposals are due by March 1, 2019.
2nd Site Visit Minutes, 24 Jan 19
View the file
Other files for this federal contract opportunity
Show all 50
Multiple Award Construction Contract (MACC) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
HEADQUARTERS 28TH MISSION SUPPORT GROUP (AFGSC)
ELLSWORTH AIR FORCE BASE SOUTH DAKOTA
24 January 2019
MEMORANDUM FOR RESPONDENTS TO SOLICITATION FA469019RA003
FROM: 28 CONS/PKB
1000 Ellsworth Street, Suite 1200 Ellsworth AFB SD 57706-4904
SUBJECT: Site Visit Minutes for Construct Bath Houses at Outdoor Running Track on Ellsworth AFB, SD
1. This documents the second Site Visit which was conducted at 0900 on 24 January 2019, which provided an additional opportunity to view the Construct Bath Houses at Outdoor Running Track project.
2. Those in attendance for the site visit were as follows:
NAME AGENCY/COMPANY PHONE TITLE
David Goff 28 CONS/PKB 605-385-1748 CO Samantha Hough 28CONS/PKB 605-385-1749 CA Capt Will Page 28 CES/CEN 605-385-2533 Deputy Flight Chief Mike Towey KTM Design 605-791-5866 CE DaShaun Howard DTH Corporation 757-245-0458 President Leah Berg ACES 605-545-1120 President/CE RC Scull RCS Construction 605-342-3787 Vice President Josiah Scull RCS Construction 605-342-3787 Project Manager Julie Suhr Quinn Construction 605-787-6500
3. All parties met in the 28th Contracting Squadron Conference Room at 0900. Mr. David Goff, 28 CONS/PKB, gave a brief overview of the MACC ON-ramp solicitation. Steve Lynn, 28 CONS/PKB, reminded contractors on questions/proposals due date. Also any questions will not be considered as part of the official contract file unless they were submitted in writing. All attendees met at the Construct Bath Houses at Outdoor Running Track project location.
Contractors were allowed to take pictures at the location. After approximately thirty minutes, the site visit for this project concluded. Contractors were reminded any questions were not an official part of the contract file and any questions they wanted included would have to be submitted via email. Any questions that arise from the second site visit must be submitted via email to Samantha Hough at samantha.hough.2@us.af.mil NLT Wednesday, 30 January 2019, 5:00 PM Mountain Standard Time.
4. The proposal due date remains NLT Friday, 1 March 2019, 5:00 PM Mountain Standard Time.
5. If you have any questions please contact Samantha Hough at extension 385-1749 or via email at samantha.hough.2@us.af.mil.
DAVID M. GOFF
Contracting Officer mailto:samantha.hough.2@us.af.mil mailto:samantha.hough.2@us.af.mil
| DEPARTMENT OF THE AIR FORCE |
| HEADQUARTERS 28TH MISSION SUPPORT GROUP (AFGSC) |
| ELLSWORTH AIR FORCE BASE SOUTH DAKOTA |
| FROM: 28 CONS/PKB |
| DAVID M. GOFF |
| Contracting Officer |
| 2019-01-24T13:52:00-0700 | |
| GOFF.DAVID.M.1136770736 |
File details come from the government source that posted it. Updated .