This is Amendment 0001 to Solicitation FA441826R0004, issued by the U.S. Air Force 628th Contracting Squadron at Charleston Air Force Base, South Carolina, effective 24 April 2026. The amendment incorporates revised solicitation sections (Section L dated 22 April 2026 and Section M dated 21 April 2026), a revised Statement of Work for DKGV 1148855 Repair HVAC System B-58, drawings and photos, a Question and Answer Form, a pre-proposal conference sign-in sheet from 22 April 2026, and historical data from previous SABER contracts FA441816D0002 and FA441821D0002. The contracting officer is Brandy M. Stroud, with administrative contact Lisa Mitchell.

The amendment modifies attachments related to wage determinations for Orangeburg, Berkeley, Charleston, Dorchester, and Sumter counties in South Carolina, converts several standard SOW attachments to Statement of Work Attachments (including architectural compatibility requirements, cable management policy, environmental controls, security requirements, quality control standards, and sole source equipment specifications), and adds new attachments including Schedule B and a Tree Ordinance. The previous versions of Attachment 08 (HVAC repair SOW), Section L, and Section M have been deleted and replaced with revised versions. All other terms and conditions of the original solicitation remain in full force and effect. Offerors must acknowledge receipt of this amendment prior to the proposal submission deadline.

View the file

Other files

File Type Posted
Attachment 12 Section M Rev 2.pdf PDF
Questions and Answers 20260505.xlsx XLSX spreadsheet
Attachment 11 Section L Rev 2.pdf PDF
Attachment 8B B-58 Drawings.pdf PDF
Attachment 01 Statement of Work (Rev2).pdf PDF
Solicitation Amendment FA441826R00040002 SF 30.pdf PDF
Attachment 14 Sign-In Sheet 20260422.pdf PDF
Attachment 12 Section M Rev 1.pdf PDF
Attachment 8 Sample Project DKGV 1148855 Repair HVAC System B-58 (WS) SOW.pdf PDF
Attachment 13 Question and Answer Form.xlsx XLSX spreadsheet
Attachment 11 Section L Rev 1.pdf PDF
Attachment 16 FA441816D0002 HISTORICAL INFORMATION.pdf PDF
Attachment 15 FA441821D0002 HISTORICAL INFORMATION.pdf PDF
Attachment 8A HVAC Zones Floor Plan.pdf PDF
SOW Attachment 12C Generator Sole Source.pdf PDF
SOW Attachment 09 014500 QUALITY CONTROL FOR MINOR CONSTRUCTION.pdf PDF
SOW Attachment 07 Brig Security Requirements (Fillable)(Official)2023.pdf PDF
Attachment 09 Past Performance Projects List.pdf PDF
Attachment 04 Charleston County WD SC20260023.pdf PDF
SOW Attachment 12B FAP Sole Source.pdf PDF
SOW Attachment 05 JBCGS 017419 Construction Waste Management and Disposal.pdf PDF
SOW Attachment 01 Joint Base Charleston Achitectural Compatibility Plan.pdf PDF
Attachment 07 Green Procurement Form.pdf PDF
Attachment 05 Dorchester County WD SC20260024.pdf PDF
SOW Attachment 13 - JB CHS Transmittal Form 4025.pdf PDF
SOW Attachment 04 JBCGS 015720 Att A - Sustainable Procurement Program.pdf PDF
SOW Attachment 03 JBCGS 015720 Environmental.pdf PDF
SOW Attachment 02 JBC Cable Management Policy 2021.pdf PDF
Attachment 12 Section M.pdf PDF
Attachment 11 Section L.pdf PDF
Attachment 10 Schedule B.pdf PDF
Attachment 08 DKGV 1148855 Repair HVAC System B-58 (WS).pdf PDF
Attachment 06 Sumter County WD SC20260030.pdf PDF
Attachment 02 Orangeburg County WD SC20260016.pdf PDF
Attachment 01 Statement of Work.pdf PDF
SOW Attachment 12A Chiller Sole Source.pdf PDF
SOW Attachment 11 Tree Ordinance New.pdf PDF
SOW Attachment 10 JBCGS 013526 GOVERNMENTAL SAFETY REQUIREMENTS.pdf PDF
SOW Attachment 08 NPTU Contractor Special Conditions 2020.pdf PDF
SOW Attachment 06 JBCGS 015719 Temporary Environmental Controls.pdf PDF
Attachment 03 Berkeley County WD SC20260022.pdf PDF
Solicitation - FA441826R0004.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

J

2. AMENDMENT/MODIFICATION NUMBER

3. EFFECTIVE DATE

24 Apr 2026

4. REQUISITION/PURCHASE

REQUISITION NUMBER

5. PROJECT NUMBER (if applicable)

Assigned at Task Order Level

6. ISSUED BY CODE FA4418

FA4418 628 CONS LGC

101 E HILL BLVD, CP 843 963 5155

CHARLESTON AFB, SC 29404-5021

UNITED STATES

Lisa Mitchell, Email: BRANDY.STROUD@US.AF.MIL Telephone: 843-963-5166 Brandy Stroud, Email: BRANDY.STROUD@US.AF.MIL Telephone: 843-963-5166

7. ADMINISTERED BY (if other than Item 6)

CODE

SCD: PAS:

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code)

CODE: FACILITY CODE:

9A. AMENDMENT OF SOLICITATION NUMBER

FA441826R0004

9B. DATED (SEE ITEM 11)

08 Apr 2026

10A. MODIFICATION OF CONTRACT/ORDER

NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; 1 or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (if required) See Section G - Contract Administration Data

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK

ONE

A.THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.)

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

See Schedule

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Brandy M. Stroud, Contracting Officer

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

24 Apr 2026

Computer generated. Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA-FAR (48 CFR) 53.243

SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

The purpose of this amendment is to incorporate the following: Block 14 (Description of Amendment/Modification):

1) Revised Sections L dated 22 April 2026 and Section M dated 21 April 2026 (.pdf).

2) Revised Attachment 08, DKGV 1148855 Repair HVAC System B-58 (WS) Statement of Work (SOW) (.pdf).

3) Attachment 08a, Drawings and Photos from B-58 (.pdf).

4) Attachment 13 Question and Answer (Q&A) Form (.xlsx).

5) Sign-in / Attendee List from 22 April 2026 Preproposal Conference and Site Visit (.pdf).

6) Historical Data from Previous & Current SABER Contracts (FA441816D0002 & FA441821D0002) (.pdf).

Section J - List of Attachments

The following Attachment(s) were added:

Attachment 11 Section L Rev 1 Attachment 12 Section M Rev 1 Attachment 13 Question and Answer Form Attachment 8 Sample Project DKGV 1148855 Repair HVAC System B-58 (WS) SOW Attachment 8A HVAC Zones Floor Plan

FA441816D0002 HISTORICAL INFORMATION

FA441821D0002 HISTORICAL INFORMATION

Sign-In Sheet 20260422

The following Attachment modifications were made:

Attachment 02 Orangeburg County WD SC20260016

Information From To StandardAttachment Statement of Work Wage Determination

Attachment 03 Berkeley County WD SC20260022 Information From To StandardAttachment Statement of Work Wage Determination

Attachment 04 Charleston County WD SC20260023 Information From To StandardAttachment Statement of Work Wage Determination

Attachment 05 Dorchester County WD SC20260024 Information From To StandardAttachment Statement of Work Wage Determination

Attachment 06 Sumter County WD SC20260030 Information From To StandardAttachment Statement of Work Wage Determination

Attachment 10 Schedule B Information From To StandardAttachment Proposal OtherAttachment Schedule B

SOW Attachment 01 Joint Base Charleston Achitectural Compatibility Plan Information From To StandardAttachment Statement of Work OtherAttachment Statement of Work Attachment

SOW Attachment 02 JBC Cable Management Policy 2021 Information From To StandardAttachment Statement of Work OtherAttachment Statement of Work Attachment

SOW Attachment 03 JBCGS 015720 Environmental Information From To StandardAttachment Statement of Work OtherAttachment Statement of Work Attachment

FA441826R00040001

SOW Attachment 04 JBCGS 015720 Att A - Sustainable Procurement Program Information From To StandardAttachment Statement of Work OtherAttachment Statement of Work Attachment

SOW Attachment 05 JBCGS 017419 Construction Waste Management and Disposal Information From To StandardAttachment Statement of Work OtherAttachment Statement of Work Attachment

SOW Attachment 06 JBCGS 015719 Temporary Environmental Controls Information From To StandardAttachment Statement of Work OtherAttachment Statement of Work Attachment

SOW Attachment 07 Brig Security Requirements (Fillable)(Official)2023 Information From To StandardAttachment Statement of Work OtherAttachment Statement of Work Attachment

SOW Attachment 08 NPTU Contractor Special Conditions 2020 Information From To StandardAttachment Statement of Work OtherAttachment Statement of Work Attachment

SOW Attachment 09 014500 QUALITY CONTROL FOR MINOR CONSTRUCTION Information From To StandardAttachment Statement of Work OtherAttachment Statement of Work Attachment

SOW Attachment 10 JBCGS 013526 GOVERNMENTAL SAFETY REQUIREMENTS Information From To StandardAttachment Statement of Work OtherAttachment Statement of Work Attachment

SOW Attachment 11 Tree Ordinance New Information From To StandardAttachment Statement of Work OtherAttachment Statement of Work Attachment

SOW Attachment 12A Chiller Sole Source Information From To StandardAttachment Statement of Work OtherAttachment Statement of Work Attachment

SOW Attachment 12B FAP Sole Source Information From To StandardAttachment Statement of Work OtherAttachment Statement of Work Attachment

SOW Attachment 12C Generator Sole Source Information From To StandardAttachment Statement of Work OtherAttachment Statement of Work Attachment

SOW Attachment 13 - JB CHS Transmittal Form 4025 Information From To StandardAttachment Statement of Work OtherAttachment Statement of Work Attachment

The following Attachment(s) were deleted:

Attachment 08 DKGV 1148855 Repair HVAC System B-58 (WS) Attachment 11 Section L Attachment 12 Section M