01502 - TEMPORARY UTILITIES AND SERVICES
FOR CONTINUED OCCUPANCY
UHHZ 100138, Construct First Article Testing Storage Facility, Near Building 323
PART 1 - GENERAL
1.01 GENERAL
A. The contractor shall provide temporary utilities and services, as required, to maintain continued occupancy in the building during construction at no additional cost to the Government.
B. Temporary utilities shall include lighting, heating, air conditioning, electrical power, domestic water, waste, and any other service normally available in the occupied area(s) that will be disconnected to allow the contractor's work to proceed.
C. Temporary utilities shall not be required where the interruptions to normal service are limited to times the building will be unoccupied.
D. Utilities: All utilities available at the site such as steam, electricity, and chilled water may be used by the contractor in conjunction with his temporary services.
PART 2 PRODUCTS - OMITTED
PART 3 EXECUTION
3.01 DOMESTIC WATER:
A. Required when service will be interrupted for over 4 hours in more than (25%) of the building.
3.02 HEATING/AIR CONDITIONING:
A. General: Temporary heating shall be provided from 1 October to 31 March. Temporary air conditioning shall be provided from 1 April to 30 September.
B. Heating shall be provided to maintain 65 degrees F in administrative areas and 55 degrees F in shop areas.
C. Air conditioning is required only within administrative areas. Temperature shall not exceed 85 degrees F in any location.
D. Shop Drawings: The contractor shall submit shop drawings for approval indicating the methods and equipment to be used to maintain the space temperature within limits, points of connection, size of pipe(s) and method of support.
E. Removal of temporary equipment: At the completion of the contract or when permanent equipment is made functional the contractor shall remove all temporary equipment. Pipe connections shall be terminated as close to tie-in as practical with a valve, six (6) inch section of pipe and cap. Show on as-builts.
3.03 ELECTRICAL SERVICES
A. Temporary service shall be required prior to the disconnection of existing service to any area occupied by Government personnel.
END OF SECTION
01502 - 1 OF 2