B.2 - 01005 - Statement Of Work.doc

DOC document 36 KB Posted

Attached to
A&E DESIGN/BUILD FIRST ARTICLE TESTING STORAGE FACILITY
Solicitation number
F3QCCL1025A008
Issued by

About this file

Statement of Work (17 Jan 2010)

View the file

Other files

File Type Posted
Site Visit Attendees.pdf PDF
First Article Testing Storage Facility questions 06APR11.docx DOCX document
BFS Part 7 - Communications 2007.pdf PDF
BFS Part 4 - Architectural General and Compatibility.pdf PDF
K - 01560 - Environmental Requirements - Jun 10.doc DOC document
O - UHHZ 100138 Appendix C Safety Plan.docx DOCX document
BFS Part 3 - Civil-Structural.pdf PDF
J.1 - 01540 - Green Procurement ATTACHMENT 2.doc DOC document
F - 01310 - CADD As-Built Drawings.doc DOC document
BFS Part 5 - Mechanical.pdf PDF
E.1 - 01300A - AF Form 66_Example.pdf PDF
N.0 - 133419 - Pre-engineered Metal Building.doc DOC document
BFS Part 6 - Electrical.pdf PDF
BFS Part 2 - Environmental .pdf PDF
J.2 - 01540 - Green Procurement ATTACHMENT 3.doc DOC document
001 Index of Drawings.pdf PDF
L - 01580 - Safety Requirements.doc DOC document
301 Bldg Section.pdf PDF
J.3 - 01540 - Green Procurement ATTACHMENT 7.doc DOC document
B.3.0 - 01020 - Construction Design Performance Requirements.doc DOC document
Wage Determination.pdf PDF
I.1 - 01503 - Contract Administration.doc DOC document
E.0 - 01300 - Submittals Contractor-Furnished Items.doc DOC document
BFS Part 1 - Intro and General .pdf PDF
101 Floor Plan.pdf PDF
B.3.3 - 01020C - Appendix C GEC Soils Report - First Art TestStor Fa.pdf PDF
B.3.1 - 01020A - Appendix A References.doc DOC document
M - 01730 - Operations and Maintenance Data.doc DOC document
J.0 - 01540 - Green Procurement.doc DOC document
B.3.2 - 01020B - Appendix B Fire Protection Life Safety.doc DOC document
201 Elevations.pdf PDF
101 Site Demolition Plan.pdf PDF
B.3.5 - 01020E - Appendix D NFPA 780 LP Requirement Determination.xls XLS spreadsheet
FA8501-11-R-0018 solicitation.doc DOC document
D - 01040 - Site Requirements.doc DOC document
G - 01501 - Temporary Services - Contractor.doc DOC document
102 Site Plan.pdf PDF
B.3.4 - 01020D - Appendix D NFPA 780 LP Determination Explanation.doc DOC document
C - 01030 - Design-Build Design After Award.doc DOC document
H - 01502 - Temporary Services - Cont Occupancy.doc DOC document
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01005- STATEMENT OF WORK

UHHZ 100138, Construct First Article Testing Storage Facility, Near Building 323

PART 1 - GENERAL

1.01 STATEMENT OF WORK: This is a general overview of the project. Also see Section 01020, (Design Build) Construction Performance Requirements, and 01030, (Design-Build) Design after Award.

A. Location: Accomplish Work at Robins AFB, GA.

B. Preaward Submittals. Submit the following before award during non-competitive negotiations:

Cost - Cost breakout with base bid, design cost, and options on separate sheets. Provide complete breakouts in similar fashion for each subcontractor.

Schedule - A schedule from award to construction complete in MS Project or Excel format

AE Firm - The name of the AE firm and any subs they will be using. Note that the Government reserves the right to approve/disapprove the lead design firm and the design subcontractors. See section 01030 for details.

C. Price: The original contracted price includes special work times for utility outages and repair of damages. The words "at no additional cost to the Government" apply to all such situations whether stated or not.

D. Contract Documents: Follow details shown by the specifications and drawings, interpreted in accordance with contract clauses. The DFARS clause 252.236-7001, Contract Drawings and Specifications, is hereby incorporated by reference if not listed in the Standard Form 1442 of the contract. Note especially the clause's instructions regarding designer intent.

E. Project Scope, Objectives, and Criteria. This is not the usual contract for construction, but is a contract for both Design and Construction. (Design/Build) The work includes the following:

1. Construct a new pre-engineered metal Building Storage Facility south of Building 323 with standing seam metal roof of approximately 4,500 square foot.

2. Exterior envelope shall be 26 gage metal wall panels and 24 gage roof panels.

3. New Ventilation, Fire Detection and Suppression, Electrical, and Communications Equipment.

4. The Civil site development will include minor site clearing, demolition of existing site features, saw-cutting of existing concrete to effect drainage, exterior utilities (electrical, water, and storm runoff), and roof drainage system.

F. General Congestion:

1. Work area is restricted to the area shown. It is heavily congested.

2. Some factors that may restrict work include cars entering and leaving parking areas near the construction site.

G. Evacuation: Before fencing off the construction area, notify the Contracting Officer in writing 21 days before ready to start.

1.02 CONTINUED OCCUPANCY:

A. Access: Buildings 323 and 324 shall remain in full operation during the time of the project. The contractor will be given full access to the project area. Access to Building 324 and its electrical panels shall be coordinated with CMXG personnel.

B. Beneficial Occupancy: The Government reserves the right to take beneficial occupancy of parts of the project area before the total project completion date. This is not final acceptance, and identified deficiencies must still be corrected.

1.03 HOURS OF WORK:

A. Standard work hours for this project are the base normal work hours of 7:00 AM to 4:30 PM local time, Monday through Friday. Work must stop on official Government holidays and work curtailment days, unless specifically approved in advance.

B. Alternate Work Hours

1. If the Contractor desires to work another set of standard hours, such as four 10-hour days, submit written request five (5) workdays before the date desired to work the different standard.

2. To work special hours or days such as to continue exterior painting until dark, request verbal approval from the Contracting Officer at least four hours in advance.

3. The Government reserves the right to refuse these requests. However, they will usually be approved unless they negatively affect the base or the using activity. For example, the using activity may have difficulty paying overtime for escorts in controlled areas. In addition, work requiring inspector presence such as placing concrete may not be possible outside normal hours on short notice. Digging outside of normal hours will normally not be approved.

C. All references to days mean calendar days unless otherwise noted.

1.04 SUBMITTALS:

A. General: Provide the following submittals in accordance with instructions found in Section 01300, Submittals and Contractor Furnished Items. The contractor may submit manufacturer’s data in lieu of the required certificate of compliance if he desires. The government requires manufacturer’s data if an “X” appears under the “Mfg. Data Required” column.

B. Material Submittals: Omitted.

C. Other Submittals: Provide the following submittals as required by the contract or as directed by the Contracting Officer.

Inspector

Para #

Description

Date Required

Check Mark

1.01 E

Evacuation Notice

21 days prior

1.03 B

Alternate Work Hours

5 days prior

PART 2 - PRODUCTS - OMITTED

PART 3 - EXECUTION

3.01

COMMENCEMENT OF WORK

A. Project Schedule: See the schedule requirements detailed in Section 01300 and in Section 01030, paragraph 7. No design or construction shall commence until the Government has approved the schedule at the Kickoff Meeting after Award.

B. Construction Prohibition: Do not order any materials or start any construction until all submitted drawings are stamped and signed by the contractor's professional architects or professional engineers, and they subsequently are signed by Robins AFB approval personnel that are indicated in Section 01030, paragraph 7.

C. Noncompliance Impacts: Any contractor costs resulting from noncompliance with these requirements are the sole expense of the contractor. Noncompliance shall not be cause for contract extensions or other considerations, but they may be cause for the Government to charge the contractor for liquidated damages for all negative impacts upon the Government.

3.02 COORDINATION: The superintendent (or contractor on-site project manager) shall coordinate work between different disciplines.

A. Avoid conflicts between new mechanical, electrical, architectural, and civil systems. Also, avoid conflicts between new work and existing structural or physical aspects or features of the facility. Request guidance from the Technical Representative of the Contracting Officer, and then perform such work at no additional cost to the Government.

B. Locations shown are approximate and may be moved if approved by the Technical Representative of the Contracting Officer. Show such variations on as-built drawings and do them at no additional cost to the Government.

C. Manufacturers' recommendations and/or requirements, if more stringent than the specifications and drawings, shall be followed at no additional cost to the Government.

3.03 GOVERNMENT-FURNISHED PROPERTY: None.

3.04 AS-BUILTS: Also see Section 01300 for submittal items such as as-builts that apply to all projects.

<<<<< END OF SECTION >>>>>

01005 - 4 of 4 B.2 - 01005 - Statement Of Work >> 17 January 2010

File details come from the government source that posted it. Updated .