Robins AFB Facility Standard
BASE FACILITY STANDARD (BFS) -- ROBINS AFB, GA
(Also known as Installation Design Guide)
FOR ARCHITECT-ENGINEER FIRMS AND CONTRACTORS
PERFORMING DESIGN SERVICES AND CONSTRUCTION FOR ROBINS AFB
PART 3 - CIVIL-STRUCTURAL
Revised 24 Aug 2005
CIVIL (SITE, STRUCTURAL, WATER, WASTE, AND IRRIGATION)
1. GENERAL: This is one part of the Robins AFB Base Facility Standards. Refer questions or exception requests to the Design Chief in 778 CES/CECE. Any exceptions granted to these requirements shall be noted clearly in the project design analysis by using a Deviation Request.
2. LOCATION PLAN: (Scale 1” = 400’):
a. Facility/project location: The project will be located at Robins AFB, GA.
b. Site access: All commercial construction traffic must enter at Gate 4. Construction projects on the Flightline may be permitted to use Gate 1 only when approved by the Base. The peak traffic flows at the site are from 0700 to 0830 and from 1530 to 1700.
c. Construction material storage areas: The proposed construction storage areas shall be shown on the site plan and shall be available for storage of construction materials throughout the construction contract. The Contractor will be responsible for security measures.
3. SITE PLAN: (Scale 1” = 50’).
a. Existing grades and contours shall be shown on the site plan.
b. The facility orientation shall be shown on the site plan.
c. Show construction contractor laydown area adjacent to the site. Coordinate with CECC or CECM to determine whether the contractor will be allowed to have a trailer at the site, or whether it must be located elsewhere on the base, then show or describe the trailer location.
d. Erosion Control: The "Manual for Erosion and Sediment Control in Georgia" shall be used to design all erosion control measures. Details shall be included in the plans.
e. Pavements: Existing and proposed pavements shall be shown on the site plan. Describe pavements in detail.
(1) Streets, parking lots, and sidewalks:
(a) All sidewalks shall be constructed of rigid pavement (concrete). Rigid pavement shall be designed in accordance with AFM 88-6, Chapter 3, while flexible pavements (such as asphalt) shall be designed in accordance with AFM 88-7, Chapter 3.
(b) Striping parking spaces: Use larger than minimum space widths and aisle widths in commercial areas such as the Base Exchange and Commissary. Many patrons have SUV’s, so the widths must allow for wider and deeper vehicles, as well as greater turning radii. In low turnover areas, the parking stalls shall be 9' wide by 18.5' long. On high turnover areas, the parking stall shall be 9.5' wide by 18.5' long. The parking stripe shall be one stripe only (not doubled) and 4" wide.
(c) Road cuts: Road cuts have to be approved by the Base Civil Engineer. If asphalt road is cut, replacement pavement required will be a minimum of 8" of concrete and 1 1/2" of asphalt. If concrete road is cut, replacement pavement required will be a minimum of 8" of concrete or the thickness of the existing pavement, whichever is greater. The replacement shall rest on no less than 12" of undisturbed soil on each side.
(2) Curbs, gutters, culverts, and pads: Provide sufficient curbs, gutters, culverts and other facilities to insure adequate drainage. No pipe smaller than 15" will be allowed. Do not paint curbs.
(3) Runways, taxiways, aprons, overruns, and shoulders: If the project involves construction of new, or alteration of existing, airfield pavement (including runways, taxiways, aprons, overruns, and shoulders), then the design must be reviewed for technical adequacy by the Base Pavements Engineer.
f. Bridges and fences: If the project involves construction of bridges, the design shall be in accordance with the latest edition of American Association of State Highway and Transportation Officials (AASHTO). If the project involves construction of fences, such fences shall be constructed in accordance with latest AF guidance in AFI's and ETL's.
g. Structures and existing trees over three inches diameter shall be shown on the site plan.
Remove only those trees necessary for the construction of the building. The designer shall incorporate as many of the remaining trees as possible into an effective landscaping plan in conjunction with a parking lot plan to accommodate the maximum number of vehicles. Specifically, show these on the site plan:
1) Existing railroads. No new railroads are required or anticipated.
2) Existing sanitary sewers.
3) Existing drainage ditches and headwalls.
4) Existing gas service lines.
5) Existing water lines.
6) Existing communication lines.
7) Existing EMCS lines.
8) Existing electrical lines.
9) Existing cathodic protection cables and equipment.
10) Existing heat service/steam lines.
11) Existing chilled water lines.
12) Existing POL facilities.
13) Existing fire hydrants.
14) Contractor construction limits for the project.
4. NARRATIVE DESCRIPTION:
a. Site restrictions: If the project site is in a restricted area, or the type of construction requires some site restrictions, then identify them in accordance with Air Force Standards.
b. Subsoil conditions: The soil in the area generally consists of poorly graded mixtures of sand clays and silty sands with the exception of the Flightline East Area where the soil generally consists of organic gray silty clay. The design Agent shall arrange for soil borings, plate-bearing tests, and CBR tests as required for a thorough subsoil investigation prior to final design. The water table varies basewide but is generally within 15-20 feet of the existing ground surface, with the exception of the Flightline East Area where the water table is generally within 0-5 feet of the existing ground surface.
c. Flood hazard evaluation: The existing elevation of the project site shall determine if is above or below the 100 year flood plain, which is at 258 feet above mean sea level. (In prior years, the level had been 257 feet.)
d. AICUZ (Air Installation Compatible Use Zone) noise level criteria: The project site shall be evaluated for AICUZ noise level criteria to determine if any noise reduction will be required for this project.
e. Erosion/dust control requirements: Erosion control measures shall be designed in accordance with the latest edition of the "Manual for Erosion and Sediment Control in Georgia." Disturbed areas, including trenches, shall receive erosion control in the form of permanent turf established by seeding.
Grasses and seeds shall be suitable for the area and season it is to be planted. Seeds shall be either Centipede or Bermuda if planted between April and August and Penntine or Falcon fescue if planted between September and March.
f. Base Comprehensive Plan (BCP) coordination: Describe conformance or nonconformance with BCP, such as future land use conflicts, etc.
g. Relationship of proposed siting to identified Installation Restoration Program sites. The project site location shall be identified by distance and direction (North, South etc.) from the IRP sites.
h. The use of cranes by construction personnel within the area around the airfield and runway requires formal crane permits. Contact 778 CES/CECP for assistance and information on the amount of advance notice required.
i. Digging Permits are required to do any excavation or earthwork. The weekly meetings are chaired by 78 CES and are usually held Monday mornings.
5. WETLANDS (AFI 32-7064): The project site shall be evaluated for the requirements of EO 11990.
6. FLOODPLAINS (AFI 32-7064): The project site shall be evaluated for the requirements of EO 11988.
7. ARCHAEOLOGICAL AND HISTORICAL SITES (LEE LTR, 4 JAN 82, PARA 1d): Consultation with State Historic Preservation Officer (SHPO) is required to determine if survey or evaluation indicates the project will or will not affect eligible property.
8. EO 12372, COORDINATION (AFI 32-7064): The project shall be coordinated with all intergovernmental departments as applicable.
9. FAA (AFI 32-7064): The project shall be reviewed for clearance requirements from the regional
FAA.
10. NOISE SITING COMPLIANCE (AFI 32-7064): The project shall be reviewed for noise reduction requirements of AFM 19-10. If noise reductions apply, they shall be incorporated into the design and construction.
11. AIRFIELD CLEARANCE CRITERIA COMPLIANCE (AFR 86-14): The project shall be reviewed for compliance with airfield clearance criteria including clear zone and accident potential zones (AFR 86-14).
12. EXPLOSIVE QUANTITY/DISTANCE (Q/D) SITING AND SAFETY CRITERIA (AFR 127-100,
CHAPTERS 5 AND 11): If a project involves munitions storage and explosives or other related facilities, it shall be reviewed for explosive quantity/distance siting and safety criteria (AFM 127-100, Chapters 5 and 11). If project does not involve explosives, it shall be reviewed for Q/D clear zone criteria from any explosives facilities.
13. SOLAR APPLICATIONS: The designer shall review for energy conservation measures. (See Mechanical Considerations)
14. CIVIL DESIGN CONSIDERATIONS: The design shall incorporate civil design work necessary to cover all site preparation included in the project. Civil design shall comply with the following Government design standards:
a. AFM 88-5, Chapter 4, Drainage for Areas other than Airfields
b. AFM 88-6, Chapter 8, Standard Practice for Concrete Pavements
c. AFM 88-6, Chapter 9, Bituminous Pavements Standard Practice
15. CIVIL CALCULATIONS: In addition, provide all civil design calculations at preliminary design submittal.
16. STRUCTURAL DESIGN CONSIDERATIONS: The A-E Design shall incorporate all structural design work necessary to construct a new facility, or to repair or modify an existing facility. Structural design shall comply with the following design standards in addition to those listed in Section G-1:
a. ASCE 7 (Latest Edition)-Minimum Design Loads for Buildings and Other Structures (excluding Chapter 9-Earthquake Loads).
b. TM 5-809-2/AFM 88-3, Chapter 2, Structural Design Criteria for Buildings
c. TM 5-809-3/AFM 88-3, Chapter 3, Masonry Structural Design for Buildings
d. TI 809-04, Seismic Design for Buildings (Dec 1998)
e. TI 809-05, Seismic Evaluation and Rehabilitation for Buildings (Nov 1999)
17. STRUCTURAL CALCULATIONS: In addition, the A-E shall provide all structural calculations at preliminary design submittal. The structural calculations shall include the following items:
a. Dead Load Break Down
b. Wind Load Calculation
c. Seismic Load Calculation
d. Comparison of Wind and Seismic Loads
e. Design of All Structural Elements: Roof Members, Walls and/or Columns and Foundations (Footings and Slabs)
f. Design of Building for Wind or Seismic Loads
18. SPECIAL STRUCTURAL REQUIREMENTS:
a. Unusual floor loads: The designer shall review the project for floor-loading conditions not normally encountered such as safes, industrial equipment, etc.
b. Clear span or height requirements: The project shall be designed for long span or height requirements as necessary.
c. Overhead support requirements: The project shall be designed for overhead support requirements including hoists, cranes, etc. as necessary.
d. Special bay sizes and access dimensions: The project shall be designed for special bay sizes with excessive dimension requirements as necessary.
e. Mezzanines: The project shall be designed for special floor loading requirements for all mezzanine areas as necessary.
f. Comply with force protection requirements as specified.
19. SUBSOIL INVESTIGATIONS: The soil investigation report shall include the following information about the soil:
a. Drilling tests
b. Soil layer classifications
c. Water content
d. Soil density based on standard penetration resistance
e. Recommended allowable soil bearing capacity or single pile capacity
f. A sketch of the area with the approximate location of soil boring holes
20. FOUNDATIONS: No foundation shall be constructed over existing or new water, sewer, steam, natural gas, chilled water, industrial waste, and foundation drain lines. All foundations shall be stepped down to an elevation below the bottom of pipe invert elevation, or the pipe relocated.
21. ANTENNAS AND OTHER EXTERIOR USER EQUIPMENT:
a. No antennas or other user equipment are to be mounted on the roof or walls, unless the item was identified during the initial construction of the building with complete structural analysis and design included in the project design analysis and the construction drawings. No user equipment may be installed on the roof or walls of an existing building, since the original structural design did not provide for the weight and wind loads associated with any such equipment.
b. Exceptions may be granted only for small items approved on a case-by-case basis by the
Structural Engineer in 778 CES/CECE or CECM. Request and approval must be in writing.
22. WATER SUPPLY:
a. The existing rated fire flow will be analyzed under a separate design section. See Fire Protection Standards.
b. All potable water on Robins AFB has been treated. The designer shall review to see if any additional treatment is required.
c. If the proposed project discharges any mixture of chemicals or solid waste into the industrial or water waste systems, the project shall be reviewed to determine if any additional chemical analysis of water is required to meet the EPA requirements for industrial or waste water treatment.
d. The existing Base water storage and distribution system will provide the water for the facility.
The system consists of 5 or more wells producing up to 4200 gpm at 55 psig. This is currently insufficient to meet our needs in certain situations. The Base is attempting to obtain additional well capacity. The designer shall design the facilities to ensure adequate water for potable, industrial, and fire fighting requirements.
e. The designer shall review to see if there will be any unusual peak demand requirements.
f. Cathodic protection shall be provided on all new underground steel systems and piping.
Insulating devices shall be used as necessary to isolate dissimilar metal common to an electrolyte (soil, water, etc). All underground steel systems shall be coated and/or wrapped to minimize cathodic protection current requirements. See Corrosion Control Standards.
g. All water lines serving a facility shall be equipped with a water meter and a backflow preventer.
h. Adequate controls shall be established to provide for wellhead protection from pollution. An area 25 ft in diameter minimum around the well called a control zone shall be fenced and the gate locked. No sources of pollution shall be allowed within this area including generator storage tanks and electrical transformers. However, electrical generators may be allowed within the area. Inner Management Zones of 100 ft. diameter shall also be established around each well. This area shall be maintained in such a way as to preclude pollution sources wherever possible.
23. WASTEWATER TREATMENT:
a. The designer shall project the industrial and/or functional wastewater discharge for the project.
The quantity and quality of wastewater discharged shall be evaluated to see if it can be adequately handled by the existing Base wastewater treatment system. All efforts to incorporate recycling/reuse of wastewater shall be included.
b. All the existing sewer lines shall be shown on the site plan. Existing flow capacity shall be determined and the type of treatment required. The project shall evaluate the existing wastewater flow and available design capacity for treatment. The existing systems limitations such as wastewater compatibility and required wastewater segregation shall be determined for this project.
c. The project designer shall determine if the treatment system requires any improvements in the following areas: treatment plants, trunk mains, lift stations, fuel/oil-water separator, or storage and bypass restrictions. The existing sewer lines shown on the site plan that will be under the proposed new facility shall be removed and relocated. No interruption of sewage flow shall occur.
d. Laboratory: The designer shall review to see if any new laboratory requirements will require modifications or additions to the existing laboratory facilities.
24. LAWN SPRINKLER SYSTEM:
a. General: Provide an underground sprinkler irrigation system as required to irrigate turf and planted areas associated with new facilities or projects that affect the building exterior landscaping. The design shall concentrate on ease of maintenance and durability of the working parts.
b. Modify standard specifications and drawings as needed to incorporate these requirements.
CEAEC maintains a complete and detailed specification for irrigation system installation that may be obtained upon request.
c. The water supply for the sprinkler system shall be the Base potable water system. The design of the system shall provide adequate pressure to all sprinkler heads and not adversely affect the pressure required by the facility.
d. Submittals: All material submittals shall be coordinated with 78 CES/CEA for review.
(1) Electronic Drawings: The contractor shall provide three disk sets of electronic drawings in MicroStation *.dgn 2-D file format, compatible with the Robins AFB GeoBase system, and three (3) paper drawings that include a complete list of equipment and materials, and manufacturer’s descriptive and technical literature, and installation instructions. Drawings shall show proposed system layout, type and number of heads and emitters, zone valves, drain pockets, backflow devices, controllers, and mounting details of controllers. Design(s) shall be in strict accordance with published manufacturer’s design guidance.
(2) The contractor shall install laminated (40-mil plastic) “as-built” drawings in the building mechanical room indicating all underground lines and the location of heads and valves.
(3) Operating manuals shall detail the step-by-step procedures required for system startup, operation, and shutdown. Operating manuals shall include the manufacturer’s name, model number, parts list, and brief description of all equipment and their basic operating features. Maintenance manuals shall list routine maintenance procedures, possible breakdowns and repairs, and troubleshooting guides. Maintenance manuals shall include piping and equipment layout, simplified wiring and control diagrams of the system as installed, and system programming schedule.
e. Components: The components listed here have been proven to provide reliable and maintainable irrigation systems at Robins AFB.
(1) System shall operate with a minimum water pressure of 50 psi at connection to main backflow prevention device. All systems shall be automatic and shall be installed with a rain sensor and rain shut off valve.
(2) Sprinklers – The base standard (design basis) is Hunter I-20 Stainless Steel, Hunter I-
25 Stainless Steel, Hunter Pop-Up Mist Heads 10A nozzle, 12A nozzle, 15A nozzle, 17A nozzle spraying capabilities, and Hunter Spray Heads in the following specifications: PS0410A, PS0412A, PS0415A, or PS0417A, Hunter SS nozzle, Hunter PS045SS Spray Head, Hunter SRS 12 spray head spraying capabilities, whichever is applicable, and Irritrol Drip Irrigation Products or equivalent.
(3) Emitter Heads: Emitter heads shall be self-cleaning with pressure compensating diaphragm with one or six self-piercing barbed outlets. Each shall be capable of emitting from ¼ to 2 gallons per hour flow. Emitter body shall be ultraviolet stabilized, algae, and heat resistant plastic construction.
(4) Remote Control Valves – The base standard (design basis) is Hunter HPV series, Hunter ICV with filter sentry in the applicable size, Rain Bird PGA and PEB series in the applicable size, and Weathermatic in applicable size.
(5) Automatic Controllers – The base standard (design basis) is Hunter ICC Commercial
Controller 8 or equivalent.
(6) Control Wire – The base standard is 12-gauge single or multi-strand, whichever is applicable, UF type designed for direct burial. Wires shall be buried beside pipe in same trench and shall be attached to the piping in increments of every 15-20 feet. Rigid conduit shall be provided where wires run under paving. Each zone shall use different color wire, to facilitate zone identification. Zone wire color shall be continuous for the entire length of the circuit. One control circuit shall be provided for each zone and a circuit to control sprinkler system. A minimum loop of 24 inches shall be left at each valve, at each splice, at each change in direction, at every 500 feet of straight run, and at each controller for expansion and servicing. Splices and connections shall be watertight and leak-proof; and shall be indicated on the “as built” plan. Wire shall be within a protective sleeve for bridge or water crossings, and where other conditions make it necessary.
(7) Pipe and Fittings – Pipe shall conform to the requirements of ASTM D 1785, PVC
1120 Schedule 40 (solvent welded) or Schedule 80 (threaded), as applicable. All joints shall be primed with a purple colored primer (for inspection purposes) and cleaned before final assembly. All above ground pipe shall be coated galvanized steel. Solvent welded socket type fittings shall conform to requirements of ASTM D 2466, Schedule 40. Threaded type fitting shall conform to requirements of ASTM D2464, Schedule 80.
(8) Backflow Prevention Equipment: Use double check valve and pressure reducing assembly in the appropriate size, to be placed above ground on a concrete pad, 12 to 36 inches above grade. The assembly shall be covered by an insulated enclosure. Backflow preventer shall conform to the requirements of ASSE 1015 and shall be of brass construction, with two check valves, field test cocks, and two resilient seat full port ball valves. Install so that maintenance and service can be performed.
Include freeze protection. The backflow preventer shall be tested in accordance with Backflow Device Test Report, the Double Check Valve Assembly portion (obtained from the base Civil Engineer Plumbing Shop). A Certified Backflow Prevent Assembly Tester shall accomplish these tests. The tests results shall be provided to the Civil Engineer Plumbing Shop backflow prevention monitor.
(9) Pressure Regulating Master Valve: Pressure regulating master valve shall be automatic mechanical self-cleaning; self-purging control system having an adjustable pressure setting operated by a solenoid on alternating current with 0.70 amperes at 24 volts. Valve shall close slowly and be free of chatter in each diaphragm position, have manual flow stem to adjust closing speed and internal flushing, and one inlet tapping capable of being installed as straight pattern valve. Body shall be cast bronze or brass with removable brass seat serviceable from top without removing valve body from system. Valve shall operate at 150 psi working pressure and pilot range from 10 to 125 psi.
f. Extra Stock: The following extra stock shall be provided to the government at the time of acceptance of the system.
(1) Two sprinkler heads of each size and type.
(2) Two valve keys for operating manual valves.
(3) Two wrenches for removing and installing each type of head.
(4) Two quick coupler keys and hose swivels.
(5) Four irrigation controller housing keys.
g. Installation: The irrigation system design shall meet the manufacturer’s requirements and incorporate the following:
(1) Minimum depth of cover shall be at least 24” for pressure main piping and 12” for lateral discharge piping, or at a sufficient depth to accommodate valves and other equipment, whichever is greater.
(2) In turf areas where grass has not yet been established, sprinklers shall be initially installed on risers above grade level. When grass is established, the contractor shall lower sprinkler head to their permanent positions flush with the finished grade. This elevation is critical and care shall be taken to set them exactly at, or slightly above the finished grade, never below.
h. Warranty – Additional Requirements: The contractor shall maintain the system for a period of one year after acceptance by the government. At the end of the one-year maintenance period, the contractor shall prove that system is fully functional and free from all defects, and shall schedule a 100% walk-thru inspection with 78 CES/CEAC. The contractor shall continue to maintain the system, at no additional cost to the Government, until all defects found at the one-year inspection are corrected and repaired.
25. TERMITE PRE-TREATMENT: For all new buildings or additions to existing buildings, include termite pre-treatment of the ground along the new exterior walls.
<<<<< END OF BFS PART 3 >>>>>
Revision History
24 Aug 2005 Separated from combined BFS into its own document
BASE FACILITY STANDARD (BFS) -- ROBINS AFB, GA
File details come from the government source that posted it. Updated .