crla201801_SWPPP-No NPDES Permit.pdf
PDF 6 MB Posted
- Solicitation number
- 69056723R000010
About this file
This document is a Stormwater Pollution Prevention Plan (SWPPP) for the Cleetwood Trail and Marina Project located in Crater Lake National Park, prepared by the Federal Highway Administration's Western Federal Lands Highway Division. The project involves rock scaling, trail rehabilitation, and marina reconstruction, with construction activities planned from July 2025 to November 2027, spanning approximately 2.25 acres with 0.83 acres of disturbed project area. The site is characterized by volcanic rock units and steep terrain within the Crater Lake caldera, requiring extensive erosion and sediment control measures to protect the sensitive environment, including the use of multiple turbidity curtains and rigorous monitoring protocols to prevent sediment discharge into Crater Lake.
The SWPPP details comprehensive environmental protection strategies, including specific construction sequencing across multiple phases: rockfall scaling (9 months over three years), marina construction (10 months over three years), wall construction, and trail rehabilitation. The project involves working near a whitebark pine habitat and requires careful management of potential pollutant sources, with strict inspection and corrective action protocols. The general contractor will be responsible for maintaining the SWPPP, implementing erosion control measures, and ensuring compliance with environmental regulations, with oversight from the FHWA Project Engineer.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Stormwater Pollution Prevention Plan
SWPPP
For:
Federal Highway Administration Western Federal Lands Highway Division g y Federal Lands Highway
OR NPS CRLA 2018(1)
Cleetwood Trail and Marina Project
Crater Lake National Park
Project Engineer - TBD General Contractor - TBD
Table of Contents
SWPPP TABS
TAB 1: SWPPP Narrative
TAB 2: Permit (Construction General Permit)
TAB 3: NOI, Acknowledgement, Other Applicable
TAB 4: Delegation of Authority
TAB 5: aps
TAB 6: Erosion/Sediment Control Plan Sheets ( lan et and BMP ypical etails)
TAB 7: Revegetation Plan (if applicable)
TAB 8: SWPPP Amendment Log
TAB 9: Inspection Reports
TAB 10: Corrective Action Log
TAB 11: Water Quality Monitoring, Reporting Requirements, and Reports
TAB 12: Training Certificat Log
TAB 13: Government-Selected Waste, Borrow, Staging Sites
TAB 14: Grading and Stabilization Log
TAB 15: Hazardous Spill Plan or Spill Prevention, Control, and Countermeasures (SPCC)
TAB 16: Endangered Species Act (ESA) & Cultural Resources (Section 106) Documentation
TAB 17: Quality Assurance Checklist
TAB 18: Notice of Termination (NOT)
Tab 1
Stormwater Pollution Prevention Plan (SWPPP)
For Construction Activities at:
Project Name: Cleetwood Trail and Marina
Project Site Location: Crater Lake National Park
City, County, State, Zip Code: Crater Lake National Park, Klamath County, OR 97064
SWPPP Prepared for:
Organization Name: FHWA, Western Federal Lands Highway Division
Address: 610 East Fifth Street Vancouver, WA 98661-3801
Telephone Number: 360-619-7700
SWPPP Prepared by:
Name, Title: Jennifer Corwin
Company/Organization: FHWA, Western Federal Lands Highway Division
Address:
610 East Fifth Street
Telephone Number: 360-619-7665
SWPPP Preparation Date: February 25, 2025 Estimated Construction Start Date: July 1, 2025 Estimated Construction Completion Date: November 30, 2027 Estimated Revegetation Start Date: To be done by others Estimated Revegetation Completion Date: To be done by others
TAB 1:
SWPPP NARRATIVE
[i]
Table of Contents
SECTION 1: RESPONSIBLE PARTIES/CONTACT INFORMATION
1.1 Operator(s):
1.2 Construction Site SWPPP Contact(s):
1.3 SWPPP Prepared by:
1.4 NPDES Stormwater Permit
1.5 SWPPP Administrator
1.6 Permitting Authority for FHWA/WFLHD Projects
SECTION 2: PROJECT INFORMATION
2.1 Project Name and Location
2.2 Project Site Characteristics
SECTION 3: NATURE OF CONSTRUCTION ACTIVITY
3.1 General Description of Project and Scope of Work:
3.2 Sequence and Estimated Dates of Construction Activities
3.3 Potential Sources of Pollutants
SECTION 4: SITE MAPS
SECTION 5: DISCHARGES
5.1 Allowable Non-Stormwater Discharges
5.2 Receiving Waters:
5.3 Water Quality Monitoring Requirements
SECTION 6: COMPLIANCE WITH OTHER APPLICABLE REQUIREMENTS
6.1 Endangered Species Protection
6.2 Historic Preservation
6.3 Safe Drinking Water Act Underground Injection Control Requirements
SECTION 7: EROSION AND SEDIMENT CONTROLS
7.1 Natural Buffers or Equivalent Sediment Controls (Required for EPA CGP states only – ID, WA) 18
7.2 Perimeter Controls
7.3 Sediment Track-Out
7.4 Stockpiled Soil or Other Erodible Materials
[ii]
7.5 Minimize Dust
7.6 Minimize Disturbance of Steep Slopes
7.7 Topsoil Conservation
7.8 Minimize Soil Compaction
7.9 Storm Drain Inlets and Culvert Inlets
7.10 Constructed Stormwater Conveyance Channels and Culvert Outlets
7.11 Sediment Basins
7.12 Chemical Treatment
7.13 Dewatering Practices
7.14 Erosion Control and Stabilization
7.15 Removal of BMPs
7.16 Post Construction Measures
SECTION 8: OPERATIONAL CONTROLS/GOOD HOUSEKEEPING MEASURES
8.1 Hazardous Spill Plan
8.2 Spills/Releases in Excess of Reportable Quantities
8.3 Equipment/Vehicle Fueling and Maintenance Practices
8.4 Equipment/Vehicle Washing
8.5 Material Handling and Waste Management
8.6 Designate Concrete Washout Areas
SECTION 9: INSPECTIONS
9.1 Inspection Frequency
9.2 Corrective Actions
SECTION 10: DELEGATIONS OF AUTHORITY
SECTION 11: STAFF TRAINING
SECTION 12: CERTIFICATION AND NOTIFICATION
[1]
Section 1: Responsible Parties/Contact Information
1.1 Operator(s):
Organization Name: FHWA, Western Federal Lands Highway Division (WFLHD Address: 610 East Fifth Street
Vancouver, WA 98661-3801 Telephone Number: 360-619-7700
Contractor and PE Note: Fill in all incomplete information following contract award date and prior to start of construction
(AK, ID, WA projects only) General Contractor Name:
TBD
Address: TBD
Telephone Number: TBD Contractor and PE Note: Fill in all incomplete information following contract award date and prior to start of construction
1.2 Construction Site SWPPP Contact(s):
FHWA Contact Name:
Title:
Project Engineer Address: 610 East Fifth Street
Telephone Number: 360-619-7660
General Contractor Company:
TBD
Erosion Control Supervisor Name:
TBD
Address: TBD Telephone Number: TBD
[2]
1.3 SWPPP Prepared by:
Organization/Company: WFL/FHWA
Name, Position: Jennifer Corwin Role/Responsibility SWPPP Preparer Telephone Number: 360-619-7665 Email: Jennifer.corwin @dot.gov
1.4 NPDES Stormwater Permit
NA
1.5 SWPPP Administrator
The General Contractor (section 1.2) is responsible for maintaining the project SWPPP of Record. The General Contractor will provide a qualified Erosion Control Supervisor, who is responsible for managing the installation, maintenance, inspection, and reporting for erosion and sediment control measures, shall maintain and update the project SWPPP of Record.
The Erosion Control Supervisor (ECS) is identified in section 1.2 and his/her qualifications are documented in TAB 12.
The FHWA/WFLHD Project Engineer (PE) is the responsible for the purpose of overseeing compliance with SWPPP at the construction site.
All SWPPP documentation, revisions/updates, and reports will be approved/signed by both the General Contractor’s ECS and the FHWA PE.
1.6 Permitting Authority for FHWA/WFLHD Projects
NA
[3]
Section 2: Project Information
2.1 Project Name and Location
This basic site information is used to file for National Pollutant Discharge Elimination System (NPDES) permit coverage. Permit coverage is obtained by filing the Notice of Intent (NOI) after the SWPPP is complete.
Project Name: Cleetwood Trail and Marina Project
Project Site Location: Crater Lake National Park
City, County, State, Zip Code: Crater Lake National Park, Klamath County, OR 97064
Latitude/Longitude:
(Use only one format, delete excess text) (degrees, minutes, seconds) (degrees, minutes, decimal) (decimal degrees): 42.979623°, -122.083222°
The method used for determining latitude/longitude was: Other Website Google Earth Pro
Township: Range: Section:
T30 R05.5E 14
Is the project located in a American Indian or Alaskan Native area?
(previously referred to as Indian Country) No
If yes, the name of Reservation is:
The project Does Not discharge stormwater into a Municipal Separate Storm Sewer System.
2.2 Project Site Characteristics
The undeveloped site and features of the land that are incorporated into the final soil Erosion and Sediment Control plan sheets (TAB 6) , as well as natural resources that should be protected are described below:
Vegetation, trees, and sensitive areas, such as stream buffers, wetlands, highly erodible soils, and steep slopes at the site include:
[4]
The project is located in the Crater Lake caldera which, due to the nature of the topography and soils, regularly experiences landslides, rockfall and erosion.
Sloughing and sedimentation of rock and soils into Crater Lake is a frequently occurring, natural process. Performing rock scaling first is intended to address the safety concerns associated with the potential for sloughing and slides.
There are no wetlands in the project area. Reconstruction of the Marina will occur in Crater Lake below the ordinary high watermark. Whitebark pine tree, listed under the Endangered Species Act is present in the project area. No other listed species or critical habitat are present
The method and location of discharge points or areas:
Work at the Marina has the potential to discharge construction stormwater into Crater Lake.
Also see TAB 6
Soil type(s) of highly erodible soils and the soil infiltration capacity are identified as:1
The project falls in Mount Mazama volcanic rock units lithic breccia (cb), Wineglass Welded Tuff of Williams (cw), Plinian and other Holocene pumice-fall deposits (cp), Andesite of Grotto Cove (agc), andesite of boat landing (abl, )Pleistocene glacial deposits (g) and Andesite of the gaging station (ags).
(Geotechnical Assessment - Cleetwood Cove Trail & Bulkhead, Crater Lake National Park, Oregon, March 13, 2017).
Any past soil contamination at the site is identified as:
None identified.
Protected Natural Features (natural features include trees, streams, wetlands, slopes, etc.):
Crater Lake..
Also see TAB 6
Measures to protect these features:
Multiple lines of turbidity curtains.
Rainfall:
10-year Mean Annual Precipitation at the Project Site (inches):2 66.7 inches
1 NRCS Web Soil Survey.
2 NRCS Annual Climate Data
[5]
Frequency, intensity, and duration of rainfall for the project site:
(principal factors influencing erosion from a construction site)
The 2-year, 24-hour storm event:3
3.5 inches/day
(Alaska Projects Only – delete if not applicable) Approximate Growing Season at the Project Site:45 June through September
3 Precipitation frequency for Western States 4 Determine USDA Gardening Zone 5 Zone Growing Season Dates
[6]
Section 3: Nature of Construction Activity
3.1 General Description of Project and Scope of Work:
(i.e., highway construction, roadway realignment, highway and bridge reconstruction, etc.):
The Project includes rock scaling, trail rehabilitation and the reconstruction of the Cleetwood Marina and associated facilities.
The type or function of the project is: Other transportation-related
Construction Support Activities: If applicable, describe any construction support activities, such as dedicated concrete or asphalt batch plants, dedicated aggregate sites, equipment staging yards, material storage areas, borrow, or disposal sites (government-selected sites):
To be completed by contractor
NOTE: All Contractor-selected sources and support sites are the sole responsibility of the General Contractor. The SWPPP and NPDES permitting for Contractor-selected sites and sources are separate from this documentation (SCR 107.01A(h)).
Support activities are located on the general vicinity map and/or site map in TAB 5 and TAB 6.
Size of Project Area:
(Including all Government-selected support sites such as staging, borrow, waste, access roads, affected downstream area, noise perimeter, extent of light effects, etc.)
Estimated Area Units
Total project area (within outermost project boundary): 2.25 acres
Disturbed project area (area of digging within total project area): 0.83
Percent Impervious Project Area BEFORE Construction: Click here to enter text. % 0
Runoff Coefficient BEFORE Construction: Click here to enter text. 76 (Stormwater runoff coefficients/curve numbers for different land uses - Minnesota Stormwater Manual)
Percent Impervious Project Area AFTER Construction: Click here to enter text. % 0
Runoff Coefficient AFTER Construction: 76 Stormwater runoff coefficients/curve numbers for different land uses - Minnesota Stormwater Manual
[7]
3.2 Sequence and Estimated Dates of Construction Activities
The intended construction sequencing and timing of major construction activities is detailed here, includmoving the phased grading and stabilization activities used to minimize overall amount of disturbed soil.
Contractor and PE Note: Fill in all incomplete information following contract award date and prior to start of construction
Phase: Rockfall Scaling
Construction sequence description: Duration of sequence:
BMPs associated with this sequence:
Stabilization measures:
Mobilization 2 days Turbidity curtains and perimeter control
None
Perform rockfall scaling and treatment 9 months over three years Turbidity curtains None. Interior of caldera is sparsely vegetated and rockfall may damage vegetation it will not clear vegetation
Winter shutdown 2 days Removal of BMPs and fuel tank on Wizard island
None
Phase: Marina Construction
Construction sequence description: Duration of sequence:
BMPs associated with this sequence:
Stabilization measures:
Mobilization 2 days Turbidity curtains and perimeter control
None
[8]
Marina Construction 10 months over three years Turbidity curtains and monitoring None
Phase: Wall Construction
Construction sequence description: Duration of sequence:
BMPs associated with this sequence:
Stabilization measures:
Clearing Two months None None
Wall construction 10 months over 3 years TBD – Contractor Proposed Performed by others
Phase:Trail Rehabilitation
BMPs associated with this sequence:
Stabilization measures:
Rehabilitation and surfacing 40 days TBD – Contractor Proposed Performed by others.
Phase: Winter shutdown
BMPs associated with this sequence:
Stabilization measures:
[9]
Remove BMPs, fuel station on Wizard Island and all construction equipment and material from Park
2 days for 2025 and 2026 construction seasons
Per Park request, no BMPs are to over winter because heavy snows tend to push BMPs into Crater Lake
None.
[10]
3.3 Potential Sources of Pollutants
The follow table identifies all potential sources (checked activities in column 1) of sediment and other sources of pollution, which may reasonably be expected to affect the quality of stormwater discharges from the construction site.
Se le ct ed
A ct iv ity
(X
Construction Activity
Potential Construction Site Pollutants
Se di m en t
N ut ri en ts
B ac te ri a pH
O il
G re as e
T ra sh
D eb ri s
Pe st ic id es
H ea vy M et al s
O th er
Po llu ta nt s
Clearing, excavating, and grading X X
Fill of roadway embankment, backfill at structures X X
Vehicle/equipment fueling and maintenance X X X
Vehicle/equipment use and storage X X
Sanitary/septic waste X X
Dewatering operations X X
Drilling and blasting operations X X X
Concrete washout and waste X X
Structure construction/painting/cleaning X X X X
Demolition and debris disposal X X X X X
Solid waste (trash and debris) X X
Hazardous waste or contaminated spills X X X
Paving operations X X
Landscaping operations X X X
Mining, rock extraction, crushing X X X
Contractor and PE Note: Fill in all incomplete information following contract award date and prior to start of construction
Construction and waste material expected to be stored on-site includes:
Material Storage Location
[11]
Section 4: Site Maps
Vicinity maps are located in TAB 5.
Site maps and erosion and sediment control plan maps are located in TAB 6.
[12]
Section 5: Discharges
Industrial stormwater discharges associated with industrial activity other than construction at the site (including dedicated asphalt plants and dedicated concrete plants that are covered by this permit) include:
NOTE: An Industrial Activity Multi-Sector General Permit may be required for some activities.
Industrial Activity Stormwater Discharge Location
Multi-Sector General Permit Number (if applicable)
5.1 Allowable Non-Stormwater Discharges
Non-stormwater discharges used at the construction sited are identified below, along with control measures used to eliminate or reduce the discharges and BMPs used to prevent stormwater contamination.
Applicable to this Project
(check all that apply)
Potential Non-Stormwater Discharges Control Measures
To be completed by contractor
Waters used to wash vehicles where detergents are not used Water used to control dust Do not overwater.
Potable water including uncontaminated water line flushings Construction dewatering (uncontaminated) Monitor to ensure sediment laden water does not reach a water body.
Ground water or spring water (uncontaminated) Monitor to ensure sediment laden water does not reach a water body.
Routine external building wash down that does not use detergents Pavement wash waters where spills or leaks of toxic or hazardous materials have not occurred (unless all spilled material has been removed) and where detergents are not used
Foundation or footing drains where flows are not contaminated with process materials such as solvents
Landscape irrigation Monitor to ensure sediment laden water does not reach a water body.
Discharges from emergency fire-fighting activities N/A Fire hydrant flushings Uncontaminated air conditioning or compressor condensate
NOTE: The likely locations of these discharges are identified on the site map TAB 5 and/or
TAB 6
[13]
5.2 Receiving Waters:
Are there any surface waters located within 50 feet of the construction disturbance? Choose an item.
Name(s) of the first surface water that receives stormwater directly from your site and/or from the MS4
1. Crater Lake
Impaired Waters/TMDLs:
Answer the following for each surface water listed in Table 1:
Is this surface water listed as “impaired?”
What pollutant(s) is causing the impairment?
Has a TMDL been completed?
Pollutant(s) for which there is a TDML
1. Yes No NA Yes No NA
Source used to determine whether or not your project discharges into an impaired water:
Click here to enter text.
Tier 2, 2.5, or 3 Waters Answer the following for each surface water listed in Table 1:
Is this surface water designated as Tier 2, 2.5, or 3?
If yes, specify which Tier.
1. Yes No Tier3
If applicable, documentation of consultation with State or Federal TMDL authorities on consistency of SWPPP conditions with the approved TMDL is found in TAB 11. The control measures required to ensure that discharge of pollutants from the site are consistent with the assumptions and requirements of the EPA-established or approved TMDL, including any specific waste-load allocations are included in that documentation.
5.3 Water Quality Monitoring Requirements
Provisions in Permit Conditions associated with §401 certification or other special conditions, define additional monitoring and reporting requirements. Details about water quality monitoring and reporting requirements applicable to this project are included in TAB 11.
Samples and measurements taken for the purpose of monitoring will be representative of the monitored activity. Records of all monitoring information will be retained in TAB 11, including all calibration and maintenance records and all original strip chart recordings for continuous monitoring instrumentation.
Records of monitoring information will include:
[14]
1. The date, exact place, and time of sampling or measurements;
2. The individual(s) who performed the sampling or measurements;
3. The date(s) analyses were performed
4. The individual(s) who performed the analyses;
5. The analytical techniques or methods used; and
6. The results of such analyses.
[15]
Section 6: Compliance with Other Applicable Requirements
6.1 Endangered Species Protection
Under which criterion is project eligible for Endangered Species coverage under the NPDES permit (EPA)?
A B C D E F
Criterion A. No federally-listed threatened or endangered species or their designated critical habitat(s) are likely to occur in your site’s “action area” as defined in Appendix A of EPA permit.
Criterion B. The construction site’s discharges and discharge-related activities were already addressed in another operator’s valid certification of eligibility for your action area under eligibility Criterion A, C, D, E, or F and there is no reason to believe that federally-listed species or federally-designated critical habitat not considered in the prior certification may be present or located in the “action area”. To certify your eligibility under this Criterion, there must be no lapse of NPDES permit coverage in the other operator’s certification. By certifying eligibility under this Criterion, you agree to comply with any effluent limitations or conditions upon which the other operator's certification was based. You must include in your NOI the tracking number from the other operator’s notification of authorization under this permit. If your certification is based on another operator’s certification under Criterion C, you must provide EPA with the relevant supporting information required of existing dischargers in Criterion C in the EPA NOI form.
Criterion C Federally-listed threatened or endangered species or their designated critical habitat(s) are likely to occur in or near your site’s “action area,” and your site’s discharges and discharge-related activities are not likely to adversely affect listed threatened or endangered species or critical habitat. This determination may include consideration of any stormwater controls and/or management practices you will adopt to ensure that your discharges and discharge-related activities are not likely to adversely affect listed species and critical habitat. To make this certification, you must include the following in your NOI: 1) any federally listed species and/or designated habitat located in your “action area”; and
2) the distance between your site and the listed species or designated critical habitat (in miles). You must also include a copy of your site map with the NOI.
Criterion D. Coordination between you and the Services has been concluded. The coordination must have addressed the effects of your site’s discharges and discharge-related activities on federally-listed threatened or endangered species and federally-designated critical habitat, and must have resulted in a written concurrence from the relevant Service(s) that your site’s discharges and discharge-related activities are not likely to adversely affect listed species or critical habitat. You must include copies of the
[16] correspondence between yourself and the Services in your SWPPP and
NOI.
Criterion E. Consultation between a Federal Agency and the U.S. Fish and Wildlife Service and/or the National Marine Fisheries Service under section 7 of the ESA has been concluded. The consultation must have addressed the effects of the construction site’s discharges and discharge-related activities on federally-listed threatened or endangered species and federally-designated critical habitat. The result of this consultation must be either:
i. a biological opinion that concludes that the action in question (taking into account the effects of your site’s discharges and discharge-related activities) is not likely to jeopardize the continued existence of listed species, nor the destruction or adverse modification of critical habitat;
or
ii. written concurrence from the applicable Service(s) with a finding that the site’s discharges and discharge-related activities are not likely to adversely affect federally-listed species or federally-designated habitat.
You must include copies of the correspondence between yourself and the Services in your SWPPP and NOI.
Criterion F. Your construction activities are authorized through the issuance of a permit under section 10 of the ESA, and this authorization addresses the effects of the site’s discharges and discharge-related activities on federally-listed species and federally-designated critical habitat. You must include copies of the correspondence between yourself and the Services in your SWPPP and NOI.
Support Documentation for Endangered Species criterion eligibility is filed in TAB 16.
6.2 Historic Preservation
1. Will the project involve installation of any of the following stormwater controls that entail subsurface earth disturbance? Choose an item.
Dike Berm Catch Basin Pond Ditch, trench, swale, perimeter drain, etc.
Culvert Other ground-disturbing stormwater control Click here to enter text.
If the project involves no installation of earth-disturbing stormwater controls, then no further historic preservation screening is necessary (for NPDES permitting purposes).
2. If answer to step 1 is Yes, have professional surveys or evaluations determined that historic properties do not exist (or have prior disturbances at the site precluded the existence of historic properties)? Yes
[17]
Provide documentation for the basis of this determination. Cultural Resource Surveys and correspondence between SHPO and Crater Lake National Park
3. If answer to step 2 is No, have professional surveys or evaluations determined that installation of stormwater controls will have no effect on historic properties? Choose an item.
Provide documentation for the basis of this determination. Click here to enter text.
4. Has the State Historic Preservation Officer (SHPO), Tribal Historic Preservation Office (THPO) or other tribal representative concurred with the determinations of effects on historic properties? Yes
Provide the nature of their response. Tribes and SHPO have concurred that the project will have no effects to historic properties.
6.3 Safe Drinking Water Act Underground Injection Control Requirements
Will the project plan install any of the following controls? No
Check all that apply:
Infiltration trenches (if stormwater is directed to any bored, drilled, driven shaft or dug hole that is deeper than is widest surface dimension, or has a subsurface fluid distribution system)
Commercially manufactured pre-cast or pre-built proprietary subsurface detention vaults, chambers, or other devices designed to capture and infiltrate stormwater flow.
Drywells, seepage pits, or improved sinkholes (if stormwater is directed to any bored, drilled, driven shaft or dug hole that is deeper than its widest surface dimension, or has a subsurface fluid distribution system)
If yes, provide documentation of communications with the EPA or applicable State agency.
Click here to enter text.
[18]
Section 7: Erosion and Sediment Controls
Control measures at the construction site are selected, installed, implemented, and maintained to minimize pollutants in the discharge as necessary to meet applicable water quality standards.
The objectives of this SWPPP include:
Stabilize the site as soon as possible (targeting the preparation and implementation of erosion and sediment controls to get the site to final grade, and either permanently or temporarily stabilize all bare soil areas as soon as possible).
Perimeter controls will be installed before ground disturbing activities are initiated.
Perimeter protection will remain in place until final stabilization has been achieved.
Slopes and channels will be protected by conveying concentrated stormwater runoff around the top of slopes and stabilize slopes as soon as possible. Avoid disturbing natural channels and the vegetation along natural channels as much as possible.
Divert stormwater coming on to the site by conveying it safely around, through, or under the work area. (Divert the clean water, trap the dirty water.)
Protect receiving waters and other environmentally sensitive waters or areas adjacent to the site.
Follow pollution prevention measures by providing proper containers for waste and garbage at the site. Store hazardous materials and chemicals so that they are not exposed to stormwater.
Minimize the area and duration of exposed soils. Clear only land that will be under construction in the near future.
7.1 Natural Buffers or Equivalent Sediment Controls
(Required for EPA CGP states only – ID, WA)
This section only applies if a surface water is located within 50 feet of the project’s earth disturbing activities.
Are there any surface waters within 50 feet of the project’s earth disturbances? Choose an item.
If No, then no further documentation is required for the SWPPP.
NOTE: Reference EPA CGP appendix G for buffer guidance.
If Yes, check which natural buffer compliance alternative is used at the project site:
The project will provide and maintain a 50-foot wide undisturbed natural buffer.
The location and width of natural buffers are shown on the Erosion and Sediment Control Plan sheets in TAB 6.
[19]
The project will provide and maintain an undisturbed natural buffer that is less than 50 feet in width and is supplemented by additional erosion and sediment controls, which in combination achieves the sediment load reduction equivalent to a 50-foot undisturbed natural buffer.
The location of natural buffers are shown on the Erosion and Sediment Control Plan sheets in TAB 6.
Insert the width of the natural buffer to be retained Click here to enter text.
Insert description of additional erosion and sediment controls to be used in combination with the natural buffer: Click here to enter text.
Document the method used to determine that the above combination of natural buffer and sediment and erosion controls equal the estimated sediment removal capacity of a 50-foot undisturbed natural buffer: Click here to enter text.
It is infeasible to provide and maintain an undisturbed natural buffer of any size, therefore, the project will implement erosion and sediment controls that achieve the sediment load reduction equivalent to a 50-foot undisturbed natural buffer.
Insert rationale for concluding that providing and maintaining a natural buffer of any size is infeasible: Click here to enter text.
Insert description of erosion and sediment controls to be used to achieve the sediment load reduction equivalent to a 50-foot undisturbed natural buffer: Click here to enter text.
The project qualifies for one of the exceptions in EPA CGP Appendix G, Part G.2
For a “linear project”, site constraints (e.g. limited right of way) make it infeasible for the project to meet any of the CGP part 2.2.1.a compliance alternatives.
Other exception (state type): Click here to enter text.
Document why it is infeasible to meet one of the buffer compliance alternatives: This project traverses several miles of roadway and will include in-water work.
Insert description of erosion and sediment controls to be used to achieve the sediment load reduction equivalent to a 50-foot undisturbed natural buffer: Perimeter and work area isolation BMPs will be implemented prior to ground-disturbing or in-water work. For in-water work and rock scaling, three layers of turbidity curtains will be install to ensure sedimented water does not enter the lake. Additionally, rigorous monitoring protocols will be implemented.
7.2 Perimeter Controls
All Perimeter Sediment Controls will be installed prior to ground disturbing activities taking place. There will be no clearing or grubbing outside the physical clearance limits.
Locations and design specifications of BMPs are shown on the erosion and sediment control plan sheets in TAB 6.
[20]
The following perimeter controls will be implemented:
Measure: Sediment logs will be used perimenter control around Cleetwood trail parking lot.
Implementation: These will be installed prior either prior to or concert with project mobilization efforts Maintenance: Remove and appropriately dispose of sediment when it measures a third of the height of the log.
Contractor and PE Note: Add additional measures used during construction.
7.3 Sediment Track-Out
The following methods will be implemented to minimize off-site vehicle tracking of sediment onto paved surfaces. If sediment escapes the construction site, off-site accumulations of sediment will be removed at a frequency sufficient to minimize off-site impacts.
Locations and design specifications of BMPs are shown on the erosion and sediment control plan
Not applicable to this project. Reason: Primary transport of material will be via helicopter.
If applicable:
Measure: Click here to enter text.
Implementation: Click here to enter text.
Maintenance: Click here to enter text.
Note: Add additional measures used during construction.
7.4 Stockpiled Soil or Other Erodible Materials
Stockpile management includes measures to minimize surface erosion and sediment transport from soil stockpiles or other erodible materials.
Locate erodible stockpiles away from drainages including storm sewer inlets and culvert inlets.
Locations of stockpiles are shown on the erosion and sediment control plan sheets in TAB 6.
Not applicable to this project. Reason: Click here to enter text.
If applicable:
Implementation: Click here to enter text.
[21]
Maintenance: Click here to enter text.
Note: Add additional measures used during construction.
7.5 Minimize Dust
Dust control includes practices used to reduce or prevent the surface and air transport of dust during construction
Not applicable to this project. Reason: Click here to enter text.
Implementation: Click here to enter text.
Maintenance: Click here to enter text.
7.6 Minimize Disturbance of Steep Slopes
Describe how disturbance of steep slopes will be minimized. Describe controls (e.g. erosion control blankets, tackifiers) that will be implemented to minimize sediment discharges from slope disturbances.
If applicable, describe how stormwater run-on and run-off will be managed. Flows may be diverted from exposed soils by retaining/detaining flows or otherwise minimizing runoff and the discharge of pollutants from exposed areas of the site. Placement of structural practices in floodplains will be avoided to the degree technologically and economically practicable and achievable.
Not applicable to this project. Reason: Click here to enter text.
[22]
7.7 Topsoil Conservation
Describe how topsoil will be preserved, if feasible. If conservation of topsoil is infeasible, explain why, and describe alternate methods to be used to insure optimum vegetation survival and growth.
Erosion and sediment control measures for topsoil stockpiles (and other erodible materials) are shown in section 4.4.
Conservation of topsoil is Infeasible: NA
Reason: No topsoil will be excavated for this project.
Alternate method: Click here to enter text.
Conservation of topsoil is Feasible:
Implementation: Click here to enter text.
Maintenance: Click here to enter text.
Contractor and PE Note: Add additional measures used during construction.
7.8 Minimize Soil Compaction
Minimize soil compaction in areas where final vegetative stabilization will occur and where infiltration practices will be installed.
Not applicable to this project. Reason: Areas to be revegetated are few and where they exist are on steep slopes where it is not feasible to compact slopes.
If applicable:
Measure: Click here to enter text.
Implementation: Click here to enter text.
Maintenance: Click here to enter text.
Contractor and PE Note: Add additional measures used during construction.
7.9 Storm Drain Inlets and Culvert Inlets
Applicable for stormwater drain inlets which are connected to separate storm sewer systems (usually in urban locations) AND for culvert inlets that discharge stormwater from the project into surface waters.
Locations and design specifications of BMPs are shown on the erosion and sediment control plan sheets in TAB 6.
Not applicable to this project. Reason: There are no storm drain or culvert inlets on this project.
[23]
The following BMPs are applicable to:
Storm Drain Inlets Culvert Inlets
Maintenance: Click here to enter text.
Contractor and PE Note: Add additional measures used during construction.
7.10 Constructed Stormwater Conveyance Channels and Culvert Outlets
Describe velocity dissipation and/or erosion control devices to be installed at stormwater conveyance channels (such as roadside ditches) and culvert outlets. Includes permanent and temporary devices (specify).
Velocity dissipation devices will be placed at discharge locations and along the length of any outfall channel to provide a non-erosive flow velocity from the structure to a water course so that the natural physical and biological characteristics and functions are maintained and protected (e.g., no significant changes in the hydrological regime of the receiving water).
Locations and design specifications of BMPs are shown on the erosion and sediment control plan sheets in TAB 6.
Not applicable to this project.
If applicable:
Measure: Click here to enter text.
Implementation: Click here to enter text.
Maintenance: Click here to enter text.
7.11 Sediment Basins
If applicable, provide site design specifications and other details for design of sediment basins and ponds. This may also include sediment infiltration swales.
Locations and design specifications of BMPs are shown on the erosion and sediment control plan
[24]
At a minimum, sediment ponds must provide storage for either the calculated volume of runoff from the 2-year, 24-hour storm event or 3,600 cubic feet per acre drained. Sediment ponds must also use outlet structures that withdraw water from the surface, unless infeasible.
Not applicable to this project.
If applicable, type of sediment retention/infiltration used: Click here to enter text.
Design description: Click here to enter text.
7.12 Chemical Treatment
If chemical sediment control (such as polymers) will be used, provide design specifications and other details considered when choosing treatment type and locations.
Not applicable to this project.
NOTE: If use of cationic treatment chemicals is planned, separate prior approval is required from EPA.
Locations of chemical treatment sites are shown on the erosion and sediment control plan sheets in TAB 6.
Describe/name treatment chemicals that will be used and why these chemicals are suited to site soil characteristics and other construction site conditions: Click here to enter text.
Describe treatment system specifications and dosage of chemicals to be used: Click here to enter text.
Describe storage of chemicals and other material safety data: Click here to enter text.
Special controls to be used for Cationic treatment chemicals: Click here to enter text.
Describe training that personnel handling/applying treatment chemicals have/will receive: Click here to enter text.
7.13 Dewatering Practices
Discharge of ground water or accumulated stormwater that is removed from excavations, trenches, foundations, etc. into surface waters is prohibited unless such waters are first effectively managed by appropriate sediment controls. Uncontaminated non-turbid dewatering water can be discharge without being routed to a control.
Not applicable to this project
Measure: Accumulated groundwater or stormwater will be pumped to a location distant from Crate Lake to permit infiltration to the extent possible.
Implementation: It will occur on an as needed basis and when sediment from the construction activity threatens to enter Crater Lake (based on monitoring results).
[25]
7.14 Erosion Control and Stabilization
Commence temporary soil stabilization measures immediately if no further disturbance of an area of the site or stockpile is expected within the next 14 days. Complete temporary soil stabilization measures to disturbed sites or stockpiles within 14 days of last disturbance. Provide for temporary stabilization of all exposed soil prior to winter construction shut down.
Specify whether stabilization measure is temporary or permanent.
The interior of the caldera given the types of soils and steep topography, is sparsely vegetated such that mostly exposed soils is naturally occurring.
Temporary Measures:
Measure: Click here to enter text.
Permanent Measures: The Park will be responsible for minor seeding and planting immediately adjacent to the trail.
Practice/Measure: Others responsible
Implementation: Others responsible
Maintenance: Others responsible.
7.15 Removal of BMPs
Remove erosion and sediment control BMPs that are no longer needed and leave in good working order those BMPs that will remain at the construction site after close-out.
BMPs are no longer needed when the site that the BMP is protecting has reached final stabilization as defined in the applicable NPDES Stormwater Permit.
Final stabilization means:
All ground disturbing activities at the site have been completed, AND
[26]
Vegetation has been established that provides a uniform perennial vegetative cover with a density of 70% of the natural vegetative cover prior to construction.
In arid (0-10” annual precipitation) or semiarid (10-20” annual precipitation) areas, final stabilization is considered to be achieved when the area is seeded or planted and vegetation is expected to provide 70% cover within 3 years; AND, erosion controls are in place that provide soil protection for at least 3 years without active maintenance.
Document arid/semi-arid conditions in SWPPP
Effective non-vegetative stabilization is in-place such as rip rap, gabions, geotextiles, rock, aggregate etc.
7.16 Post Construction Measures
Construction close-out will be the responsibility of:
FHWA/WFLHD
Land Management/Owner Agency Specify Agency: Crater Lake National Park
County/State DOT
Applicable permit termination/transfer information is located in TAB 18.
[27]
Section 8: Operational Controls/Good Housekeeping Measures
8.1 Hazardous Spill Plan
Spills and potential stormwater contamination will be controlled to reduce the chance of spills, stop the source of spills, contain and clean up spills, and dispose of materials contaminated by spills.
Spill prevention and response actions are outlined in the Hazardous Spill Plan or Spill Prevention, Control, and Countermeasure Plan (SPCC) whichever is applicable, TAB 15.
Construction sites may be subject to 40 CFR Part 112 regulations that require the preparation and implementation of a Spill Prevention, Control and Countermeasure Plan if the facility is a non transportation-related facility that: has a total storage capacity greater than 1,320 gallons or a completely buried storage capacity greater than 42,000 gallons and could reasonably be expected to discharge oil in quantities that may be harmful to navigable waters of the United States and adjoining shorelines. See EPA website: http://www.epa.gov/OEM/content/spcc/index.htm
Implementation: Prior to construction activities and throughout construction.
8.2 Spills/Releases in Excess of Reportable Quantities
This permit does not provide authorization to discharge hazardous substances or oil resulting from an on-site spill. This permit does not provide relief from the federal reporting requirements of 40 CFR Part 110, 40 CFR Part 117 and 40 CFR Part 302 relating to spills or other releases of oils or hazardous substances.
For a release containing a hazardous substance or oil in an amount equal to or in excess of a reportable quantity established under either 40 CFR Part 110, 40 CFR Part 117 or 40 CFR Part 302, occurs during a 24-hour period:
Notice will be provided to the National Response Center (800–424–8802) in accordance with the requirements of 40 CFR Part 110, 40 CFR Part 117 and 40 CFR Part 302 as soon as site staff have knowledge of the discharge; and written notice will be provided within 7 calendar days of knowledge of the release, provide a description of the release, the circumstances leading to the release, and the date of a release.
Measures to prevent the reoccurrence of such releases will be implemented.
8.3 Equipment/Vehicle Fueling and Maintenance Practices
On-site fueling areas will have a spill kit present, visible, and maintained. Employees and subcontractors will receive training regarding equipment/vehicle fueling and maintenance practices, including proper fueling procedures, proper use of pumps, emergency shutoff valves (training efforts documented in TAB 12).
On-site vehicles and equipment will be inspected daily for leaks, equipment damage, and other service problems.
Designate vehicle/equipment service will be marked and the areas will be located away from drainage facilities and watercourses to prevent stormwater run-on and runoff. Designated washout areas will be shown on the SWPPP plan sheets (TAB 6).
[28]
Drip pans, drip cloths, or absorbent pads will be used when replacing spent fluids. All spent fluids will be collected and store in appropriate labeled containers in the proper storage areas.
Implementation: Prior to construction activities and throughout construction.
8.4 Equipment/Vehicle Washing
Equipment/vehicle washing and allowable non-stormwater will be controlled using procedures and practices include using off-site facilities; washing in designated, contained areas only;
eliminating discharges to the storm drain by infiltrating the wash water or routing to the sanitary sewer. The locations of equipment/vehicle washing areas, storm drains, tributary drainage areas, and surface waterbodies on or near the site are shown and updated on the SWPPP plan sheets
(TAB 6).
Implementation: Prior to construction activities and throughout construction.
8.5 Material Handling and Waste Management
Measures will be put in place and maintained to prevent the discharge of solid materials to receiving waters, except as authorized by a permit issued under the §404 permit.
Designated trash and bulk waste-collection areas on-site (location of areas are shown and updated on plan sheets, TAB 6).
Litter and debris from the construction will be cleaned up on a daily basis.
Waste-collection areas will be located away from streets, gutters, watercourses, and storm drains. Secondary containment around waste collection areas will be implemented if needed to further minimize the likelihood of contaminated discharges.
Portable restrooms will be located away from streets, gutters, watercourses, and storm drains (location of areas are shown and updated on plan sheets, TAB 6). Secondary containment around waste collection areas will be implemented if needed to further minimize the likelihood of contaminated discharges.
Portable restrooms will have tie-downs or stake downs in areas of high winds or susceptibility to vandalism.
Hazardous waste-collection areas will be designated on-site (location of areas are shown and updated on plan sheets, TAB 6). Secondary containment around waste collection areas will be implemented if needed to further minimize the likelihood of contaminated discharges.
Hazardous waste containers will be routinely inspected to ensure that all containers are labeled properly and that no leaks are present.
Implementation: Throughout construction.
[29]
8.6 Designate Concrete Washout Areas
Concrete washout areas on-site, designate specific washout areas, and design facilities to handle anticipated washout water will be installed. Washout areas will also be provided for paint and stucco operations as applicable. Washout areas will be located at least 50 yards away from storm drains and watercourses. If this is not possible, prefabricated washout containers will be used.
Alternatively, constructed washout areas may be used either by digging a pit and lining it with 10 mil plastic sheeting or creating an aboveground structure from straw bales or sandbags with a plastic liner. Designate washout areas will be shown on the erosion control plan sheets (TAB 6).
Not applicable to this project
The following precautions will be implemented:
Concrete trucks or equipment will not be washed out into storm drains, streets, gutters, uncontained areas, or any watercourses.
Washout areas will be established prior to commencing the activity and their locations advertise with signs or delineators.
Adequate containment for the amount of wash water that will be used will be provided.
Washout structures will be routinely inspected to detect leaks or tears and to identify when materials need to be removed.
Materials will be disposed of properly (for example, allow the water to evaporate and to recycle the hardened concrete).
Inspections will include looking for evidence that contractors are using the washout areas and not dumping materials onto the ground or into drainage facilities. If the washout areas are not being used regularly, additional signage will be posted or the facility will be relocated to a more convenient location.
Employees and subcontractors will receive training regarding designated washout areas, including proper handling and storage practices (training efforts documented in TAB 12).
Implementation: Prior to construction activities and throughout construction.
[30]
Section 9: INSPECTIONS
9.1 Inspection Frequency
Inspections will be conducted in accordance with one of the two schedules:
At least once every 7 calendar days and within 24 hours of the end of a storm event of 0.25 inches or greater, as determined by an on-site rain gauge.
At least once every 14 calendar days and within 24 hours of the end of a storm event of 0.25 inches or greater, as determined by an on-site rain gauge.
Other schedule as allowed by State NPDES Permit.
Specify schedule: Click here to enter text.
Inspection frequency may be reduced to at least once every month if:
The entire site is temporarily stabilized, Runoff is unlikely due to winter conditions (e.g., site is covered with snow, ice, or the ground is frozen), or
Construction is occurring during seasonal arid periods in arid areas and semi-arid areas.6
A waiver of the inspection requirements is available, as authorized by the NPDES STORMWATER PERMIT, until one month before thawing conditions are expected to result in a discharge if all of the following requirements are met:
The project is located in an area where frozen conditions are anticipated to continue for extended periods of time (i.e., more than one month);
Land disturbance activities have been suspended; and
The beginning and ending dates of the waiver period are documented in the SWPPP.
See individual EPA/State CGP for other requirements
Inspections will be conducted by qualified personnel as required in SCR Section 157. Inspector qualifications are documented in TAB 12.
The WFL Inspection Report template will be used for all inspections. All completed Inspection Reports will be signed in accordance with the applicable EPA/State CGP and SCR 107.01A.
Completed Inspection Reports are filed in TAB 9.
6 “Arid Areas” means areas with an average annual rainfall of 0 to 10 inches. “Semi-Arid Areas” means areas with an average annual rainfall of 10 to 20 inches.
[31]
9.2 Corrective Actions
Corrective actions will be taken to:
Repair, modify, or replace any stormwater control BMP used at the site;
Replace/modify BMPs that were initially installed incorrectly or never installed;
Replace BMPs that are ineffective in preventing/minimizing sediment discharges in accordance with applicable water quality standards;
Clean up and properly dispose of spills, releases, or other deposits, or
Remedy a permit violation
Corrective actions will be taken the same day the condition is found, or if found late in the work day, corrective actions will be initiated the following work day. Temporary steps may be required to prevent or minimize discharge of pollutants until a permanent solution is installed;
including cleaning any contaminated surfaces so that material will not discharge in subsequent storm events. Permanent replacement or modifications will be completed no later than 7 days from the time of initial…
This is the start of the file's text. The full file is on GovTribe.