This document is a Questions and Answers (Q&A) file for the Cleetwood Trail and Marina Improvements project at Crater Lake National Park, involving multiple technical and operational aspects of a federal construction contract. The solicitation covers complex infrastructure work including soil nail walls, rockfall barriers, mesh installations, marina improvements, and slope stabilization, with key specifications around mesh types, anchor systems, and construction methodologies. Significant technical details include requirements for multi-year road construction projects over $15 million, specific mesh and rockfall barrier technical specifications, and design requirements for various structural components.
The Q&A document reveals several important project parameters, including an extended solicitation date to 11/06/2025 at 1400 PST, multiple planned amendments (A002-A005), and specific technical constraints such as Class A corrosion protection, 75-year design life for soil nail walls, and strict requirements for mesh and barrier installations. Contractors are required to provide detailed designs, potentially stamped professional engineering documents, for components like rock bolts, micropiles, and rockfall protection systems. The project involves complex geotechnical work with specific placement and scaling requirements, and places significant emphasis on precise technical compliance with federal highway and national park engineering standards.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OR NPS CRLA 2018(1)
Cleetwood Trail and Marina Improvements
# General Technical Question Answer Date
1 X I'd like to confirm the correct contact phone number for FHWA, as I am seeing multiple used in the RFP
For questions on this solicitation please use the following: 360.619.7520
8/21/2025
2 X Floating Docks are Specifies 50 PSF live Load which far Exceeds Industry Standard, Can this be Readjusted to 20 PSF or 30 PSF?
No change in the live loading specified, bid as shown
9/15/2025
3 X Are live load and Snow Load to be Considered Concurrent Loads for the Docks and Gangway.
Snowload is not considered concurrent with live load
9/15/2025
4 X
The listed requirements for Technical Evaluation Factor 1 are overly restrictive and will preclude some capable / qualified contractors from bidding on this opportunity. Please consider relaxing the requirements for Technical Evaluation Factor 1 by modifying the current requirement to meet all of the Construction Elements and Operational Elements with experience on previous projects. A suggestion might be to modify the language to ‘a minimum of six
(6) of the Construction Elements and a minimum of four (4) of the Operational Elements are collectively represented.’
This will be addressed in Amendment A002.
Proposed subcontractors' experience may be used for Construction and Operational Elements. There will be no other changes at this time.
9/19/2025
5 X
The listed requirements for Technical Evaluation Factor 1 are overly restrictive and will preclude some capable / qualified contractors from bidding on this opportunity. Please consider relaxing the requirements for Technical Evaluation Factor 1 by reducing the project value required for Operational Element 3, ‘Performance heavily dependent on air support for delivery of equipment and materials’ to $1 million and remove the multi-year requirement
At this time, there are no changes. Please submit proposal accordingly.
9/19/2025
6 X
The listed requirements for Technical Evaluation Factor 1 are overly restrictive and will preclude some capable / qualified contractors from bidding on this opportunity. Please consider relaxing the requirements for Technical Evaluation Factor 1 by allowing subcontractors to carry the experience for the Construction Elements and Operational Elements.
This will be addressed in Amendment A002.
Proposed subcontractors' experience may be used for Construction and Operational Elements.
9/19/2025
7 X
In the event that the Prime Contractor meets the General Requirements, all of the Operational Elements, and all but 1 of the Construction Elements, (specifically Construction Element Item 1), can this requirement be meet utilizing the experience of a Listed Qualified Subcontractor who would be performing that portion of the work?
This will be addressed in Amendment A002.
Proposed subcontractors' experience may be used for Construction and Operational Elements.
9/22/2025
Check General or Technical
8 X Can you provide a full prime bidders list for the above referenced project?
The Government does not provide this since bidders may obtain the Interested Vendors List (similar to prime bidder list) from sam.gov after linking their entity to their registration. If you are signed into SAM.gov with your registered entity and you cannot see the Interested Vendors List, you will need to be assigned the Contract Opportunities Administrator role for your entity in SAM.gov.
Link to Federal Help Desk on how to view and add your company to the Interested Vendor List:
https://www.fsd.gov/gsafsd_sp/en/how-do-i-add-myself-to-the-interested-vendors-list?id=kb_article_v…
If you need additional assistance, you can reach the Federal Service Desk at 866-606- 8220.
9/22/2025
9 X
For the anchored wired mesh can you verify that two layers of mesh, DTWM and G65 mesh, are required for the Type II anchored area? Is there any offset of these meshes required?
No, we do not need a double twist wire mesh (DTWM) backing fabric in the Type II anchored wire mesh. Amendment A003 will address this.
9/22/2025
10 X
Are the trailside rockfall fence, anchored mesh and draped mesh liens shown on the topographic sheets anywhere? The line shapes, curves, etc are important for proper take-off.
No, they are not in the solicitation documents and will not be made available.
9/22/2025
11 X Would gunite be an accepted alternative to shotcrete provided the required specifications are met?
Please refer to Table 566-1 in Section 566 of the SCRs. Wet, wet (AE), and dry options are allowed for shotcrete mixtures.
9/24/2025
12 X Is the contractor permitted to utilise small tractors/ ATVs and trailers for transporting materials, equipment and waste up and down the trail?
Yes 9/24/2025
13 X
Are all scaled rocks to be chased right down to the water’s edge, or completely removed from site? If not ,please advise under what circumstances and where they could be left on the slope.
Please refer to Subsection 623.02A(e) “Continue scaling until all unstable, loose, or detached rock inside the general scaling limits is disposed of in the location shown on the plans. Do not leave scaled debris in proposed construction areas.” Please also refer to Subsections 6.1.3 and 6.2.5.2 of Geotechnical Report 05-24 for additional information on reuse of scaled materials and the general approach to scaling, respectively. “In particular, large boulder-sized rocks that are firmly embedded into soil deposits and that are stable should be left in place, as the scaling of these rocks will create more soil erosion and slope instability.”
9/24/2025
14 X Please advise what is to be done with removed trees and vegetation that are not determined to become landscaping logs?
Blasting is not allowed in Crater Lake National Park. Blasting is allowed at Summit Quarry.
9/24/2025
15 X I am enquiring to find out whether any contracting licence would be required to perform works as a subcontractor on the above-mentioned project?
The Government will not review contracting licenses, please refer to the State's requirement.
9/24/2025
16 X
If a subcontractor’s experience is used:
a.What documents must the subcontractor turn in to satisfy Technical Factor 1?
b.Does the proposed subcontractor need to have been the prime contractor on previous relevant work?
c.Does the same size standard sƟll apply to the previous relevant work?
a. Please refer to Page B-20, part b.
b. No, the subcontractor does not need to have been the prime.
c. Previous response was in error, project must be a multi-year road construction project with excess of $15 million (either as a prime or subcontractor).
9/24/2025
17 X Please clarify options available to the Contractor for disposal of excess soil generated from wall excavations?
The material may be reused, however the contractor is responsible for testing these materials and meeting the requirements as described in the applicable FP-14 sections prior to use. Excess and unsuitable material from structure excavations must be disposed of according to Subsection 209.03, which in turn refers to 204.14, which in turn refers to Subsection 203.05(a). “(a) Remove from project. Recycle or dispose of material legally off the project. Submit a statement documenting the nature and quantity of material processed or sold for recycling. Otherwise, submit a signed copy of the disposal agreement before disposal begins.”
9/24/2025
18 X Can the contractor side cast wall excavation spoils for permanent disposal?
No. See response to question #17 above. 9/24/2025
19 X
Due to the complex nature of this project, numerous logistical challenges, and continued clarification of bidder questions, please provide an extra month for this solicitation (i.e. please extend the bid date).
We will be extending the solicitation date by 30 days to 11/06/2025 1400 PST. This will be addressed in Amendment A004.
9/24/2025
20 X Please consider bidding this project on a Thursday or Friday and not a Monday. Mondays are difficult days to conduct bids.
We will be extending the solicitation date by 30 days to 11/06/2025 1400 PST. This will be addressed in Amendment A004.
9/24/2025
21 X Is the FHWA Subcontracting Plan due at time of bid?
If not, when is it due?
Please refer to page A-6. Subcontracting plans are not due with the proposals submitted; only right before award.
9/24/2025
22 X Please clarify if there are any revegetation requirements
Revegetation to be performed by others (the Park).
9/24/2025
23 X What is the warranty period at the completion of the project?
There are no project warranty requirements defined in the FP-14. Project warranty requirements are defined in the Special Contract Requirements
9/25/2025
24 X Please confirm the new question close date now that the bid has been extended?
Question due date has been updated through Amendment A004
9/26/2025
25 X What is the design life of the soil nail walls, and specifically the soil nails?
Refer to Plan Sheet I.9. 75 years. 9/26/2025
26 X
I notice the soil nails in the typical section have double encapsulation, is this necessary or is corrosion protection determined by the contractor to satisfy the required design life?
Refer to Table 6-13 of GR 05-24. Class A corrosion protection is required.
9/26/2025
27 X If the double encapsulation is required, does this need to be pregrouted before insertion in the hole?
Refer to GR-5-24 and Sections 257 and 259 for design and installation requirements.
9/26/2025
29 X Please confirm the new question close date now that the bid has been extended?
See Amendment A004. 9/26/2025
30 X Is specific work scope required or desired to be completed each season, or is that at the discretion of the contractor?
We do not require certain things to be done each season. There are limitations on the sequencing of work items in various SCRs.
Please review SCRs and bid accordingly.
9/26/2025
31 X
Are you able to provide any photos with associated vicinity/ plan view map showing the soil nails wall locations, as well photos as existing walls that are to be removed?
Please review Plan Sheets D.16 to D.32 for soil nail location locations. Refer to GR 05- 24 and the Geotechnical Assessment Report by Golder for pictures of the existing walls.
Amendment A005 will address this by including additional physical data.
9/26/2025
32 X
We are trying to decipher if we meet the minimum Technical Evaluation Factor 1 requirements or not.
The document appears to require that all projects utilized to meet the construction and operational elements must be in excess of $15 million. Q&A answer no. 16 c. seems to contradict this when you state, “No, we will not look at the size standard for previous relevant work”.
Previous response was in error, project must be a multi-year road construction project with excess of $15 million (either as a prime or subcontractor).
9/30/2025
33 X
Our question is if we can list multiple projects over $15 million, however we will need to list several smaller projects to cover all the construction and operational elements required. Will this approach be compliant with technical requirements?
A minimum of two but no more than seven projects may be submitted to address all the construction and operational elements.
Each project submitted must be a multi-year road construction project with excess of $15 million (either as a prime or subcontractor).
9/30/2025
34 X Is there an engineer's estimate on Type I pinned mesh compared to type II pinned mesh?
No. The two mesh types are combined into a single pay item.
10/6/2025
35 X
Section 710.12(g) specifies that the wire mesh utilized for draped and pinned mesh applications must be capable of accommodating a 2.5-inch diameter circle within the mesh opening. We seek clarification regarding the necessity of this parameter, as it appears that the specification may have been drafted in a manner that, perhaps inadvertently and along with other requirements, limits competition. Would the engineer consider accepting an equivalent product that satisfies all other requirements outlined in this section, but with a slightly smaller opening size (1.96 inches square), in order to encourage broader competition in the supply of these materials? From an engineering perspective, the smaller opening size may be considered advantageous, as it enhances system performance by reducing the likelihood of smaller fragments escaping through the mesh.
You are correct, a smaller opening size would be more advantageous in this case.
Alternative products with a smaller opening size will be considered if they meet the other salient characteristics in 710.12.
10/6/2025
36 X
Section 717.01(h) specifies requirements for “diamond-shaped spike plates” that are not performance-based and can only be supplied by a single manufacturer, thereby restricting competition.
We respectfully request that the design engineer consider permitting an alternative complete system (comprising high-tensile mesh and spike plates that are designed for the alternative system) that delivers equivalent structural performance, regardless of the geometric configuration of the spike plate.
Under 717.01(h)(4), it states that it is specified as part of the anchored wire mesh system, a system using the mesh specified in
710.12. Therefore, we will consider an
alternative geometric configuration of the spike plate if it works in conjunction with a proposed alternative 710.12 mesh.
10/6/2025
37 X
Location US7 calls for a 750kJ rockfall barrier with up to 15 feet of elongation permitted. Would the engineer consider allowing up to 16 feet of elongation for a system rated to 1000 kJ with the understanding that a modeled lower energy impact of 750 kJ would theoretically result in less than 16 feet of elongation.
Negative. The max elongation requirements must be based on EAD 340059-00-0106 tested values, not theoretical. See 654.04(c).
10/6/2025
38 X
Section 654.04(c) states, "Include evidence no more than 1 year old from the manufacturer that the flexible rockfall barrier system supplied has been tested and verified to equal or exceed the flexible rockfall barrier system requirements as shown in the plans." Can the engineer please verify that what is required is a valid ETA certificate for the rockfall fence and not that the system has to have been tested within the last year as this is not possible nor does it have any bearing on validity of certification.
You are correct. A valid ETA certificate for the rockfall fence is required, the rockfall fence system itself is not required to have been tested in the past year.
10/6/2025
39 X
Would the design engineer consider relocating the 750-kJ barrier approximately one foot upslope to allow for up to 16 feet of system elongation, thereby enabling additional material suppliers to provide competitive quotations for this barrier system? As currently specified, it appears that only one commercially available system appears capable of meeting the requirements as written.
Yes. This is acceptable. 10/6/2025
40 X
Specification 646C.07 requires the float manufacturer to fabricate structural steel in a fabricating plant that is Certified Bridge Fabricator – Simple under the AISC Quality Certification Program and use steel erectors certified under the AISC Quality Certification Program. The floating dock structure is not a bridge and most fabricators and installers with similar project experience are not certified under these programs. Please consider waiving this requirement and allowing the use of alternate fabricators / erectors if sufficient qualifications are submitted for approval.
Special Contract Requirement 555.07 Fabrication will be amended to permit fabricators that have BU (Certified Building Fabricator) AISC certification. See Amendment A005
9/24/2025
41 X
Section 646C.04 requires tank, immersion, and incline test results for EPS foam-filled polyethylene drums be submitted 7 days before transportation. Please clarify the intent of this requirement.
This sentence will be removed from the Special Contract Requirement. See Amendment A005
9/24/2025
42 X Is the restroom being removed and the rockfall fence starting and ending in its location?
The restroom is being removed under an option to the contract. So if that option is not exercised, it will remain. The fence is required to be offset 20 feet minimum upslope from the existing restroom location.
10/6/2025
43 X Can the two barriers, both ending and starting at 64+20 and offset 20 feet, be one continuous system?
Yes, that is the intent. The only difference is the reference point for the offset. The first reference point is the uphill edge of the trail (until approximately Station 64+20), the other is the restroom because the restroom is closer to the uphill slope than the trail is beyond Station 64+20
10/6/2025
44 X
It appears the end of the barrier at 64+70 and a 20 ft offset is at elevation 6165, while the elevation at station ~64+65 is ~6188. Rockfall barriers cannot be installed on slopes this steep. Modifications to the barrier layout (shorter) and other system changes will be required. Is this acceptable?
Yes. 10/6/2025
45 X Can you confirm that rockfall barriers, mesh, and spike plates need to be Natina stained?
That is correct. 10/16/2025
46 X How do you anticipate maintaining the tension of the rock bolts (i.e. to 25 and 50 kips) after they are flush cut?
Two-staging is required. Fill the minimum bond zone length under stage one, and fill the free-stressing (unbonded) length with grout under stage two, after successful post tensioning of the bolt. Refer to Subsections 260.07, 260.08, and 260.09
10/17/2025
47 X
Will plan and profile views as well as associated wall surveys and grading in the field based on the profiles be provided for each soil nail wall? Or are these required to be provided by the contractor
No additional information will be provided.
See Sections 257 and 259 for submittal requirements.
10/17/2025
48 X
Is contractor furnished design required for any component of the works other than the soil nails and rock bolts? E.g. temp shoring, marina micropiles, rockfall barriers, or rockfall mesh?
Refer to the FP-14 and project SCRs for each project element for the contractor design and submittal requirements.
10/17/2025
49 X What is the estimated volume of riprap to be placed at the marina?
321 CUYD, plan sheet B.1, D.2 10/17/2025
50 X What is the estimated volume of bulkhead demolition and excavation at the marina?
Approximately 767 CUYD, contractor to verify bulkhead removal material
10/17/2025
51 X Does the Government have preferred manufacturers or models for items listen in Section 725 – Miscellaneous Materials?
Materials/Manufactures are specified within each 725 subsection. If nothing is listed, no preferred manufacture. Material supplied must meet specification requirements of 725 Subsection.
10/17/2025
52 X Are existing floats or gangways at the marina to be removed as a part of this contract?
Section 203; remove existing marina railing.
Existing floating dock will remain with the Park.
10/17/2025
53 X
For subcontractors who meet one of the construction or operational elements, is there a minimum requirement for the duration the subcontractor is onsite?
No, please submit accordingly 10/17/2025
54 X
6.The response to quesƟon 33 included “Each project submitted must be a multi-year road construction project with excess of $15 million (either as a prime or subcontractor).” This limitation might exclude projects that meet Construction Elements or Operational Elements as some of these projects might not be road construction projects. Construction Element 1 will be very difficult to achieve on a road construction project. Operational Element 3 will be difficult to achieve on a road construction project and/or a project over $15 million in contract value.
Will projects performed by specialty subcontractors that meet these requirements be exempt from the road construction or dollar value classification?
No, please submit accordingly 10/17/2025
55 X 8.Will the Contractor be allowed to move large boulders at the marina out of the way instead of removing them completely?
Yes, need to be placed a natural setting 10/17/2025
56 X
There seems to be some overlap in the SCRs with general labour and slope scaling labour. 623.01 General labour states the work will also consist of slope scaling – is this correct or will all slope scaling be captured under 623.02 hourly rate?
All slope scaling work, apart from safety scaling (refer to Section 623, safety scaling is not tracked or paid for), is represented by 62302-0100 pay items (Line item number A1020 on Plan Sheet B.2 and Line item number Z0220 on Plan Sheet B.6.) Slope scaling work is not included in 62301-0000 pay items.
10/21/2025
57 X Area estimated areas for type 1 vs type 2 mesh able to be provided?
We are unable to provide them. Please refer to the plan sheets H.2 and HA.1 to HA.14 and Subsection 6.2.5.6 of Geotechnical Report 05-24. “Two different patterns of anchor nail spacing with minimum depths are proposed for the anchored wire mesh. A more tightly spaced pattern with longer anchor nails is required in areas of the Lower Cliff with larger rock block sizes, while areas of smaller rock block sizes use shorter anchor nails in a more widely spaced pattern.” Site visits are also permitted.
10/21/2025
58 X
Regarding the design for the rock bolts, will the free length be provided to the contractor? And hence the contractor would only be required to confirm the bond stress over the bond length?
The Slope Stabilization Layout sheets in the plans show the design bolt and dowel locations and minimum total lengths. Refer to the following:
Plan Sheet G.3. The free stressing length of the rock bolts varies based on the field conditions, and the bond zone must be placed entirely in stable rock.
Subsections 260.04(d) and 260.07. From 260.07(a) “Adjust total bolt and dowel lengths as directed to address existing subsurface conditions encountered.”
10/21/2025
59 X
Are we correct in assuming the contractor is not “designing” the rock bolt-dowel system as that would require and over all assessment of slope stability of all of the slopes containing rock bolts and dowels?
That is correct. Assessment of the slopes and the placement of rock bolts and dowels was designed by WFLHD.
10/21/2025
60 X Will placement / spacing of all rock bolts and dowels be determined by CO/WLF?
That is correct. From Subsection 6.2.5.3 of Geotechnical Report 05-24 “Although WFLHD has identified strategic rock blocks and rock structures typically greater than 3 feet in dimension for rock reinforcement, the rock scaling will likely change the slope configuration, and therefore the rock reinforcement layout will need to be reevaluated and modified following the rock scaling work. We require discussing this process during the scaling and rock reinforcement work item kick off meeting recommended in the above subsection. We also require notifying the WFLHD GEO Division when scaling is nearing completion to assist the project engineer in revising the rock reinforcement locations, as needed.”
10/21/2025
61 X
Anchored wire mesh: Appears to be installed per plans and manufacturer’s recommendations. Does the contractor only need to provide design and calculations for bond stress and spacings for anchors?
We do not think there is any “design work” for the mesh system itself?
The mesh system was designed by WFLHD.
Install the system per the plans, Section 655 specifications, and manufacturer’s recommendations. The contractor needs to only provide design for the drill hole diameter and bond zone, and any temporary works. Refer to Subsection 655.04.
10/21/2025
62 X Drape rockfall mesh: Please confirm what design work 651.04 (a) exactly entails? E.g. anchors loads, mesh system suitability calcs?
Design for the anchors given the load requirements (20 kips, see Subsection 651.08) and the manufacturer’s system drawings. Refer to Plan Sheets H.5 to H.7.
10/21/2025
63 X Will placement/ mark out of all rockfall mesh (including anchors) and barrier systems be determined/ approved by CO/WLF?
Yes 10/21/2025
64 X Roadside rockfall barriers, 654.04 – is the contractor required to design the anchors e.g. lengths and diameters?
Yes 10/21/2025
65 X
Roadside rockfall barriers, 654.04 (e) - Is this item asking simply for the contractor to provide shop drawings for the barrier systems? Are we correct in assuming the barrier is already designed by others and we do not need to provide any design, modelling or calculations for the barrier systems themselves?
The intent is for the contractor to design and furnish a barrier system that meets the requirements of Section 654 and Plan Sheet H.4. The requirements on Plan Sheet H.4 for the fence minimum height, maximum mesh elongation after design impact, and minimum energy level are based on WFLHD rockfall modelling analyses. No further rockfall modelling is required from the contractor. Design and calculations for the barrier system however are required.
10/21/2025
66 X Are all designs provided by the contractor required to be stamped?
Yes 10/21/2025
67 X
Are micro pile designs (bond calcs, and plans etc) required to be provided by the contractor or just the actual lengths based off the distance to groundline at each pile location with design provided by others?
Yes 10/22/2025
68 X What is the spacing for the turbidity curtain(s)?
Per manufacture recommendations; Special Contract Requirement 157.11(f)
10/24/2025
69 X Can the turbidity curtain(s) be reused for years two and three?
Meet requirements listed in FP-14 Section 157, and Floating turbidity curtains in Section 713.21
10/24/2025
70 X Is it the Owner's intent to use three rows of turbidity curtain and monitor water quality between each curtain directly off shore from construction activities?
Refer to Special Contract Requirements 157.04A
10/24/2025
71 X Is the type of turbidity curtain used up to the Contractor?
Refer to FP-14 Section 157 and SCR 713.21 10/24/2025
72 X
Is the Contractor required to monitor water quality directly off shore from construction activities? If there are more than one construction activity is the contractor required to monitor directly off shore form each activity?
Refer to Special Contract Requirements 157.04A
10/24/2025
73 X How high is the davit off the float deck (725.41)? Plan sheet T.1 thru T.19 10/24/2025
74 X How high is the gangway off the float deck (646B)? Plan sheet T.1 thru T.19 10/24/2025
75 X What is the difference between davits listed in line item A1220 Quantity (2) and X00300 Quantity (1)?
Location 10/24/2025
76 X Please provide additional davit details: 1) height off deck? 2) boom length? 3) weight rating?
Refer to Special Contract Requirements 646A & 725.41
10/24/2025
77 X
Other than those stated on the document titled "Crater Lake No Fly Zone Map," are there any seasonal or environmental restirctions to when helicopters can be used?
Refer to Special Contract Requirements 107.10(e)
10/24/2025
78 X Will a fire watch be requied by the Contractor? Refer to Permits Section H 10/24/2025
79 X
Will trees damaged by scaling be required to be removed by the Contractor? Communication of specific expectated damage would be had prior to scaling, but who will ultimately make the decision on damaged tree removal, or not?
Additional trees or other vegetation will be removed at the direction of the CO. See Subsection 623.02A(f)(4).
10/24/2025
80 X
The GBR states that lateral loading will govern micropile design, but the Specifications and Contract Drawings allude to a tension verification and/or proof test. Will a lateral load verification (or proof) test be required? The setup for a lateral test is very different from a tension test.
Lateral load testing not required. 10/24/2025
81 X Is there any existing infrastucture on Wizard Island that can be utilized for this project?
No 10/24/2025
82 X Can Wizard Island be utilized for anything other than temporary fuel storage?
No 10/24/2025
83 X
Machinery maintenance and refueling is required (per Spec Section 107.10.e.10 - page 242 of RFP document) to be at a distance of 200 feet or greater from water. Section 646E discusses specifics of the Temporary Fuel Storage System and mentions the use of a "hose." Is the Owner's itent that all equipment that needs re-fueling must be transported to Wizard Island (or elsewhere, 200 feet from the water, for example the Cleetwood Cove Trailhead Parking Lot) via Contractor's means/methods to be fueled 200 feet from the shore on the island and then trasnported back to the work space?
Refer to Section 646E Temporary Fuel Storage System to be used for Crater Lake National Park only, not for Contractor use.
Contractor responsible for own fueling onsite per requirements and Permits.
10/24/2025
84 X Can anchors be installed as personnel anchors and/or equipment anchors to include wedge anchors into existing rock formations?
Refer to Subsection 623.02A(f)(5). 10/24/2025
85 X Can trees be used as personnel and/or equipment anchors?
Refer to Subsection 623.02A(f)(5). 10/24/2025