This document is a Task Assignment Change Order Form from the Florida Department of Environmental Protection (FDEP) for a Continuing Services Contract (CN202) under a statewide indefinite delivery vehicle. The change order involves Michael Baker International, Inc., serving as the consultant, with FDEP project management conducted by Ralph Perkins and Del Cobb of the Bureau of Design and Construction, Division of Recreation and Parks. The project concerns site grading improvements and erosion control measures at Wekiwa Springs State Park in Orange County (Apopka), Florida.
Change Order No. 2 adds scope to include the design of a waterline extension and irrigation system for the final design plans under Subtask 6.1. The fixed price cost increase for this change order is $5,860.16, consisting of 44 billable hours across project management (4 hours at $238.84/hour), senior engineering (8 hours at $149.58/hour), and design services (32 hours at $115.88/hour). The original task amount was $64,631.89, and with this change order, the total task cost increases to $70,492.05. The task end date was extended by 63 days from February 25, 2023, to April 28, 2023, with deliverables including digitally signed and sealed construction plans in PDF and .DWG formats plus estimated construction costs. Payment is contingent upon FDEP approval of deliverables for each subtask.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN202 TA36 2 61378C
Wekiwa Springs State Park Wekiwa Springs Erosion Control & Access
Michael Baker International
Jeff Roberts, P.E., RSP1 (850) 701-2303 jeff.roberts@mbakerintl.com
Ralph Perkins (850) 245-2460 Ralph.Perkins@FloridaDEP.gov
Change to add waterline extension & irrigation plans to the final design for erosion control & stabilization improvements at the park. (See proposal dated 2/14/23.)
$ 15,058.20 $ 15,058.20 $ 64,631.89 $ 64,631.89 $ 5,860.16 $ 5,860.16
$ 0.00 $ 70,492.05 $ 70,492.05
10/14/2021
2/25/23
2/25/23
4/28/23
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.02.17 11:51:39 -05'00'
Del Cobb Del Cobb Digitally signed by Del Cobb Date: 2023.02.17 10:00:11 -05'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.02.17 12:55:10 -05'00'
Jeff Roberts, P.E. Jeff Roberts Digitally signed by Jeff Roberts Date: 2023.02.17 14:02:07 -05'00'
Michael W. Foster Jr., P.E.
61378C 37503006080 080039/22 423001 U3200 131500 QK $ 5,860.16
$ 5,860.16
Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2023.02.21 15:24:28 -05'00'
From: DeFrancisco, Joey To: Cobb, Del L Cc: Roberts, Jeff; Davidson, Kaitlin Subject: CN 202: Task 36 Time Extension Date: Tuesday, February 21, 2023 1:55:30 PM
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Hello Mr. Cobb, On behalf of Jeff Roberts and team, I am emailing to request a time extension for the FDEP Continuing Services Contract (CN202), Task assignment 36: Wekiwa Springs Erosion control. We would like to request an extension until the end of April, 4/28. Can you please let us know if this can be provided?
Thank you, Joey
Joey DeFrancisco P.E. | Senior Transportation Engineer 2316 Killearn Center Blvd. Suite 201-A | Tallahassee, FL 32309 | [O] 850-701-2319 | [M] 941-724-joey.defrancisco@mbakerintl.com | www.mbakerintl.com mailto:Joey.DeFrancisco@mbakerintl.com mailto:Del.L.Cobb@FloridaDEP.gov mailto:Jeff.Roberts@mbakerintl.com mailto:Kaitlin.Davidson@mbakerintl.com mailto:joey.defrancisco@mbakerintl.com https://secure-web.cisco.com/1sx3qC33KrlzDWkuDuPuAzDCl-KM16stqfcjXRWcpDKR7GYMtuBbnkUNGNWmmxmuOxQCugBbSosk5bpxrkwsFjf3SfLmZJ2V3x8j4UoAY9_zGjfqOOjFN0GYua6nPO2IQFbiV8AIYjepJSzSJz5rXCbp51O_TixRVl3KC-CKa04Qegx1k4AAg5_2-R7IBkusL4P9zpcpD3MkgzqEisQ-rQ-JzU5mbQ4jKc18mfI1LrYinOCBCLbq_Wiqap76GDNlKo3iQ_v_0xSln9bMnVnR78BEth3_MS4ulYDfzwn2lJbNCTZ3NefSeQxS0aGuZHkiP/https%3A%2F%2Fwww.mbakerintl.com
February 14, 2023
Mr. Del Cobb Project Manager Bureau of Design and Construction Division of Recreation and Parks 3900 Commonwealth Boulevard Tallahassee, FL 32399
RE: Statewide Contract: CN202, Task Assignment 36, Change Order 2 Addition of Irrigation Plans and Extension of Waterline Wekiwa Springs Erosion Control & Access, Orange County (Apopka), FL
Dear Mr. Cobb:
For your review, Michael Baker International, Inc., is attaching a change order proposal summary and man-hour documentation for amending the current task assignment to include irrigation plans and a waterline extension.
Please review the attached Proposal Summary and deliverables and let me know if there are any questions or comments.
Sincerely, Jeff Roberts, PE, RSP1 Associate Vice President / Sr. Project Manager
Wekiwa Springs State Park – Site Grading Improvements Wekiwa Springs, Apopka, FL
Statewide Contract CN202, Task Assignment 36, Change Order 2
This Change Order #2 adds in additional scope and subtasks to the original task assignment signed 10/14/2021.
Project Objective: Under the original contract and Change Order #1, Michael Baker (Consultant) completed Plans for grading improvements at the Wekiwa Springs State Park is in Orange County, Florida. Conceptual Plan Option 1 was selected as the path forward for improvements at the park under the original agreement, and final plans were designed under Change Order #1.
This change order will add a waterline extension and irrigation plans to the final design for erosion control and stabilization improvements at the park. No additional survey or data collection (pressure testing, etc.) will be performed under this scope of services. The subtasks outlined below will be amended as follows:
Subtask 6 – Final Design Plans o Addition of Subtask 6.1 Waterline Extension & Irrigation System (NEW SUBTASK)
Subtask 6.1: Waterline Extension & Irrigation System
The Consultant will design and implement a waterline extension and irrigation system into the approved 90% plans completed under Task 5 and prepare for final plans. The waterline extension will be placed down the center of Area 1, terminating at a hose bib connection in a locked valve box near the back of existing retaining wall.
MBI will also design an irrigation system for the grassed center portion of Area 1.
Assumptions:
FDEP will provide approximate location, type and size of existing waterline location via a marked-up site plan.
The Consultant can assume the condition of the existing water line is acceptable for a wet tap.
Existing water pressures are adequate to accommodate additional discharge point.
Existing water pressures are within typical range and adequate for proposed irrigation system.
FDEP Park staff will provide location of existing electrical panel to tap into, as well as photos of the panel and other information (verification of active circuits, Amperage ratings, etc).
The existing electrical panel is assumed to have sufficient capacity to accommodate a new irrigation system control panel. If it is determined electrical upgrades are required to the electric panel to provide sufficient capacity for the irrigation controls, a change order will be required to provide this upgrade.
Deliverables:
Digitally Signed and Sealed Construction Plans (PDF Format) and .DWG format.
Estimated Construction Costs for final plans.
Performance Measure: Final deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost (Change Order #2 Only):
Subtask 6.1: Waterline Extension & Irrigation System
Company Classification Rate Hours Cost MBI Project Manager $238.84 4 $955.36
MBI Sr. Engineer $149.58 8 $1,196.64
MBI Designer $115.88 32 $3,708.16
Sub-Total (Subtask 6.1) 44 $5,860.16 ORIGINAL Subtask 6 TOTAL $8,965.70
NEW Subtask 6 TOTAL (This Change Order) $14,825.86
Summary of Fees:
Subtask
Original
TA 36
Fixed Price Cost (incl. CO #1)
New
TA 36
Fixed Price Cost (w/ CO #2)
Subtask 1: Conceptual Site Plans $15,058.20 -- Subtask 2: Site Survey $19,515.50 --
Subtask 3: Geotechnical Exploration $4,103.06 -- Subtask 4: Environmental Assessment/Data
Collection $2,268.23 --
Subtask 5: 60% Design Level Review $14,721.20 -- Subtask 6: 100% Design Level Review $8,965.70 $14,825.86
Total Fixed Price Cost $64,631.89 --
Change Order No. 02 Increase -- $5,860.16
New Total Cost w/ CO 02 $70,492.05
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Project Schedule:
Project Schedule is based on estimated duration of calendar days to complete each subtask. Schedule dates will be established after approved and executed contract has been received. Where most practical, subtasks will be worked on concurrently.
Activity
Subtask Duration
(Calendar Days) Subtask 6: 100% Design Level Review 30
| CN202 TA36 CO2 Wekiwa Springs - Erosion Control Access.pdf |
| CN 202_ Task 36 Time Extension |
| CN202 TA36 CO2 Wekiwa Springs - Erosion Control Access |
File details come from the government source that posted it. Updated .