CN-370000-CN202-T42.pdf
PDF 509 KB Posted
- Contract number
- CN202
- Issued by
- Florida
About this file
This document is a Task Assignment Notification Form issued by the Florida Department of Environmental Protection (FDEP) under Statewide Contract CN202. The task assignment (TA42) is awarded to Michael Baker International, Inc., a consulting firm providing bridge assessment services for the George Crady Fishing Pier State Park located in Nassau and Duval Counties, Florida. The project is managed by FDEP's Bureau of Design and Construction, with Ralph Perkins serving as the FDEP Contract Manager and Theresa Carron as the Project Manager.
The scope of work involves a post-Hurricane Nicole assessment of the George Crady Fishing Pier, a former AIA bridge structure built in the 1940s that was converted to pedestrian fishing access. Michael Baker International will perform a visual condition assessment of the superstructure and substructure, review previous inspection reports, measure critical safety elements, and utilize watercraft access to evaluate substructure conditions. The deliverable is a memorandum email with findings and recommendations regarding reopening the pier to the public. The fixed price cost is $11,722.60, comprising 66 billable hours allocated to a Project Manager (28 hours at $238.84/hour), Structural Engineer (14 hours at $149.58/hour), and Bridge Inspector I (24 hours at $122.54/hour). The task assignment commenced on November 15, 2022, with a completion date of February 4, 2023, and invoicing will occur upon task completion and approval by the Contract/Project Manager.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN202 TA42 FDEP-BDC 61350C
George Crady Bridge Fishing Pier SP Post Hurricane Nicole Assessment
Michael Baker International, Inc.
Jeff Roberts, PE 850-701-2303 jeff.roberts@mbakerintl.com
Ralph Perkins 850-245-2460 Email:
Ralph.Perkins@floridadep.gov
New task assignment to perform post Hurricane Nicole assessment of the fishing pier and its continued public use per the task assignment dated 11/10/2022.
Theresa Carron
11/15/2022 $ 11,722.60 2/4/2023
$ 11,722.60
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2022.11.16 09:30:26 -05'00'
Theresa Carron T.Carron Digitally signed by T.Carron Date: 2022.11.18 09:08:13 -05'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2022.11.18 10:39:07 -05'00'
Jeff Roberts, PE
Michael W. Foster Jr., PE
61350C FD092 37502002262 080039/22 423001 U3200 131500 QK $ 11,722.60
$ 0.00
Jeff Roberts Digitally signed by Jeff Roberts Date: 2022.11.18 14:14:21 -05'00'
Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2022.11.21 12:03:36 -05'00'
November 10, 2022
Theresa Carron Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard, MS 520 Tallahassee, FL 32399
RE: Statewide Contract: CN202 Task Assignment (42) George Crady Fishing Pier State Park Post-Hurricane Nicole Fishing Pier Assessment Nassau/Duval Counties, Florida
Dear Ms. Carron:
For your review, Michael Baker International, Inc. has provided a proposal summary and man-hour documentation for the services tasks identified below.
Please review the attached Proposal Summary.
Sincerely, Jeff Roberts, PE Michael Baker International, Inc.
Jeeeeeeefffff Roberts PEEEEE
Scope of Work George Crady Fishing Pier Assessment (Structure No. 740055)
Nassau/Duval Counties, Florida
Contract Number CN202, Task Assignment Number (42)
Project Objective: The George Crady fishing pier is located within the George Crady Fishing Pier State Park in Nassau County and Duval County, Florida. The fishing pier structure the former original AIA bridge crossing over the Nassau River. Built in the 1940’s, the bridge has been converted from vehicle traffic and is now accessible to pedestrians only as a fishing pier. A portion of the original bridge is permanently closed to the public due to aging condition and deterioration.
As a result of Hurricane Nicole passing through Florida on November 9th and 10th, 2022, and out of an abundance of caution, the FDEP has temporarily closed the remaining portion of the fishing pier until further assessment can confirm no additional apparent damage that would jeopardize public safety. The Florida Department of Environmental Protection (FDEP) has requested Michael Baker International (Consultant) to perform an assessment to determine if the pier can be reopened to the public or if apparent damage has occurred since the last inspection report.
The Consultant will perform a visual assessment of the structure using qualified bridge inspection staff and provide a summary of findings memorandum or email along with recommendations for reopening the pier. This lump sum fee is split between the Subtasks as shown below.
Subtask 1 – Bridge Assessment Services
1. Structural Assessment – The Consultant will perform a visual condition assessment of the superstructure and substructure using qualified resources. The assessment will be limited to only the spans that are normally open for fishing. The portion of the structure that is permanently closed will not be assessed as part of this scope of services. The inspectors will collect field data documenting the condition of the structure as follows:
a. Most recent inspection reports will be reviewed, previous critical findings will be identified.
b. Critical elements affecting safety will be measured and compared to previous inspection report results.
c. Inspectors will utilize watercraft access provided by the FDEP to assess the substructure elements visible from the water.
d. No lift equipment, non-destructive testing, or destructive testing will be utilized as part of this scope.
e. FDEP will provide Michael Baker with information and plans and inspection reports regarding the structure.
2. Post-Assessment Meeting – Michael Baker will be available for a video conference with the client project manager and other Department staff to discuss post-inspection findings at FDEP’s request.
Assumptions:
1. FDEP will supply the most current inspection reports and any current limitations placed on the piers based on prior findings and/or recommendations from FDOT.
2. The fishing pier does not have any substantial changes in condition in already-noted damaged elements between the most recent inspection and prior to Hurricane Ian.
3. The previous inspection report(s) performed by FDOT consultants have noted all relevant issues and no elements have been missed/omitted from the inspection report(s).
Assignment Deliverables:
1. Memorandum Email Notification of Findings – A letter will be submitted recommending reopening the pier or keeping it closed for further investigation. If no findings of concern are identified during the assessment, the Consultant will recommend reopening the structure. If concerns are identified based on the most recent inspection reports provided by FDEP, Michael Baker will record the assessment findings and recommend further action for the structure. The recommendations will be generated from a qualified licensed structural engineer or certified bridge inspector (CBI).
Performance Measures: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
Fixed Price Cost:
Company Classification Rate Hours Cost
MBI Project Manager $238.84 28 $6,687.52 MBI Structural Engineer $149.58 14 $2,094.12 MBI Bridge Inspector I $122.54 24 $2,940.96
Totals (Subtask 1) 66 $11,722.60
Project Schedule
Tentative Schedule: The assessment services will be performed immediately.
Invoicing
As the task is completed and approved by the Contract/Project Manager an itemized invoice shall be submitted for payment.