This document is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP). The change order modifies an existing contract (CN202, Task Assignment No. 20) between FDEP and Michael Baker International, a consulting firm. The project involves design services for the Equestrian Campground at River Rise Preserve State Park, located in Florida. Key personnel include Chad Schroeder as the consultant representative and Jack Brady as the FDEP Contract Manager.
The change order extends the task completion timeline by 549 days, shifting the task end date from December 31, 2019 to June 30, 2020. This extension allows the consultant to incorporate final plan comments and update plans to current codes. The financial terms remain unchanged, with no net increase or decrease in task amounts. The total task amount, including all previous change orders, is $85,275.96, consisting of $2,225.00 in reimbursable expenses and $83,050.96 in fixed fees. The change order was approved on November 21, 2019, as documented by signatures from FDEP leadership and the consulting firm's senior project manager.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .