This document is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for Statewide Contract CN202, Task Assignment 34, Change Order #4. The project involves the Anclote Key Preserve State Park Generator Replacement located in Pinellas and Pasco County, Florida. The consultant performing the work is Michael Baker International, Inc., represented by Jeff Roberts, P.E., RSP1. The FDEP Contract Manager is Ralph Perkins, and the project is under the oversight of Construction Project Manager John Goss.
This change order is a time extension only with no modification to the financial terms. The original task execution date was December 8, 2020, with an original end date of June 30, 2022. The task end date was previously extended to December 31, 2022, and this change order further extends it to June 30, 2023, representing a net increase of 181 days. The total task amount remains $60,783.52, comprised of $100.00 in reimbursement and $60,683.52 in fixed fees. The extension was requested to allow for completion of construction assistance tasks and project close-out activities. All required signatures were obtained between December 1 and December 5, 2022.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
(Revised 9-26-2018) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN202 34 4 61276C
Anclote Key Preserve State Park Generator Replacement
Michael Baker International
Jeff Roberts,PE,RSP1 850-701-2303 jeff.roberts@mbakerintl.com
Ralph Perkins 850-245-2460 Ralph.Perkins@FloridaDEP.gov
Extension of time only to allow for project completion and project close-out as per attached email dated 11/29/2022 from Michael Baker International.
$ 7,156.16 $ 7,156.16 $ 100.00 $ 60,683.52 $ 60,783.52
$ 0.00 $ 100.00 $ 60,683.52 $ 60,783.52
12/8/2020
6/30/2022
12/31/2022
6/30/2023
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2022.12.01 13:25:28 -05'00'
John Goss John Goss Digitally signed by John Goss Date: 2022.12.01 15:12:05 -05'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2022.12.01 15:50:31 -05'00'
Jeff Roberts, P.E., RSP1 Jeff Roberts Digitally signed by Jeff Roberts Date: 2022.12.02 09:02:38 -05'00'
Michael W. Foster, Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2022.12.05 11:25:34 -05'00'
$ 0.00
November 29, 2022
John Goss
Construction Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 1843 Tamiami Trail Osprey, FL 34229
RE: Statewide Contract: CN202, Task Assignment 34 – Change Order #4 (Time Extension Only)
Anclote Key Generator Replacement Pinellas & Pasco County, FL
Dear Mr. Goss:
To align with anticipated construction progress on the subject project, Michael Baker International, Inc., is requesting a time extension to the current expiration date of December 31, 2022. We request the expiration of this Task Assignment be extended to 06/30/2023 to allow for completion of for completion of construction assistance tasks.
Please let me know if there are any questions or comments.
Sincerely, Jeff Roberts, P.E.
Associate Vice President
| CN202 TA34 CO4 Anclote Key Unsigned.pdf |
| TA34_CO4_Anclote Key backup.pdf |