CN-370000-CN202-T34CO3.pdf

PDF 5 MB Posted

Attached to
Master Agreement FL|CN202|9b407d6bfa6024fb9fbbd1ce9e29e157
Contract number
CN202
Issued by
Florida

About this file

This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for Statewide Contract CN202. The change order involves the consultant firm Michael Baker International, Inc., represented by Jeff Roberts, P.E., and is managed by FDEP Contract Manager Ralph Perkins. The project is located at Anclote Key Preserve State Park in Pinellas and Pasco County, Florida.

Change Order #3 provides a time extension only, with no adjustment to the task fee amount. The original task end date of June 30, 2022, is extended 185 calendar days to December 31, 2022, to allow for completion of Task 8 (RFI and Shop Drawing Review) and Task 9 (Site Inspections) associated with the Anclote Key Generator Replacement project. The total task amount remains $60,783.52 with no net increase in cost. The change order was approved and executed on June 23, 2022, by all required FDEP and consultant representatives.

View the file

Other files

File Type Posted
CN-370000-CN202-CMC2.pdf PDF
CN-370000-CN202-T10CO1.pdf PDF
CN-370000-CN202-T11.pdf PDF
CN-370000-CN202-T11.pdf.crdownload CRDOWNLOAD file
CN-370000-CN202-T13.pdf PDF
CN-370000-CN202-T14.pdf PDF
CN-370000-CN202-T14CO1.pdf PDF
CN-370000-CN202-T14CO2.pdf PDF
CN-370000-CN202-T17CO1.pdf PDF
CN-370000-CN202-T19.pdf PDF
CN-370000-CN202-T1CO1.pdf PDF
CN-370000-CN202-T20.pdf PDF
CN-370000-CN202-T20CO2.pdf PDF
CN-370000-CN202-T20CO4.pdf PDF
CN-370000-CN202-T26.pdf PDF
CN-370000-CN202-T28CO1.pdf PDF
CN-370000-CN202-T31CO1.pdf PDF
CN-370000-CN202-T32CO4.pdf PDF
CN-370000-CN202-T33.pdf PDF
CN-370000-CN202-T34.pdf PDF
CN-370000-CN202-T34CO1.pdf PDF
CN-370000-CN202-T35.pdf PDF
CN-370000-CN202-T38CO1.pdf PDF
CN-370000-CN202-T41.pdf PDF
CN-370000-CN202-T42.pdf PDF
CN-370000-CN202-T43.pdf PDF
CN-370000-CN202-T43CO1.pdf PDF
CN-370000-CN202-T43CO2.pdf PDF
CN-370000-CN202-T45.pdf PDF
CN-370000-CN202-T45CO5.pdf PDF
CN-370000-CN202-T5.pdf PDF
CN-370000-CN202-T8CO3.pdf PDF
CN-370000-CN202-T9.pdf PDF
CN-370000-CN202-TA12CO1.pdf PDF
CN-370000-CN202-CMC4.pdf PDF
CN-370000-CN202-T10.pdf PDF
CN-370000-CN202-T12.pdf PDF
CN-370000-CN202-T13CO2.pdf PDF
CN-370000-CN202-T15.pdf PDF
CN-370000-CN202-T16.pdf PDF
CN-370000-CN202-T24.pdf PDF
CN-370000-CN202-T25.pdf PDF
CN-370000-CN202-T2CO2.pdf PDF
CN-370000-CN202-T30.pdf PDF
CN-370000-CN202-T31.pdf PDF
CN-370000-CN202-T32CO3.pdf PDF
CN-370000-CN202-T33CO2.pdf PDF
CN-370000-CN202-T36CO2.pdf PDF
CN-370000-CN202-T38.pdf PDF
CN-370000-CN202-T38CO2.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

(Revised 9-26-2018) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN202 34 3 61276C

Anclote Key Preserve State Park Generator Replacement

Michael Baker International

Jeff Roberts,PE,RSP1 850-701-2303 jeff.roberts@mbakerintl.com

Ralph Perkins 850-245-2460 Ralph.Perkins@FloridaDEP.gov

Extension of time only to allow for project completion and project close-out as per attached email dated 6/6/2022 from Michael Baker International.

$ 7,156.16 $ 7,156.16 $ 100.00 $ 60,683.52 $ 60,783.52

$ 0.00 $ 100.00 $ 60,683.52 $ 60,783.52

12/8/2020

6/30/2022

6/30/2022

12/31/2022

Diane Langston Diane Langston Digitally signed by Diane Langston Date: 2022.06.07 08:41:55 -04'00'

John Goss John Goss Digitally signed by John Goss Date: 2022.06.07 09:12:40 -04'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2022.06.07 10:36:16 -04'00'

Jeff Roberts, PE, RSP1 Jeff Roberts Digitally signed by Jeff Roberts Date: 2022.06.20 12:27:29 -04'00'

Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.

Digitally signed by Michael W.

Foster Jr., P.E.

Date: 2022.06.23 11:19:42 -04'00'

$ 0.00

June 6, 2022

Stephen Pindel Assistant Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520 Tallahassee, FL 32399

RE: Statewide Contract: CN202, Task Assignment 34 – Change Order #3 (Time Extension Only)

Anclote Key Generator Replacement Pinellas & Pasco County, FL

Dear Mr. Pindel:

To align with current construction progress on the subject project, Michael Baker International, Inc., is requesting a time extension to the current expiration date of June 30, 2022. We request the expiration of this Task Assignment be extended to 12/31/22 to allow for completion of Task 8 (RFI and Shop Drawing Review) and Task 9 (Site Inspections).

Please let me know if there are any questions or comments.

Sincerely, Jeff Roberts, P.E.

Associate Vice President

Change Order #3 (Time Extension Only) Anclote Key State Park Generator Replacement

Pasco County, FL Statewide Contract CN202, Task Assignment 34

Project Schedule:

Project Schedule is based from estimated duration of calendar days for the contractor to complete each subtask. Schedule assumes consecutive subtasks in order shown unless concurrent subtasks are noted.

Schedule dates will be established after approved and executed contract has been received.

Activity

Subtask Duration (Calendar Days)

Amended Completion Date

Subtask 8 55 Dec. 31, 2022

Subtask 9 150 Dec. 31, 2022

CN202 TA34 CO3 Anclote Key Unsigned.pdf
CN202 TA 34 CO3 Time Extension Request.pdf

File details come from the government source that posted it. Updated .