This is a Contractor Crane Operating Checklist for Critical Lifts, serving as a safety compliance and operational verification document for crane operations on federal projects.

The checklist comprises 23 items covering critical safety and operational requirements that contractors must verify before and during crane lifting operations. Key operational requirements include: operator knowledge of load weight and crane rated capacity; crane positioning on level, firm ground with proper outrigger deployment and blocking; clearance of the swing radius from personnel and obstructions; proper load securing, balancing, and hook centering to prevent deflection and side loading; maintenance of clear lift swing paths; use of tag lines for hazardous load rotation; prevention of personnel from standing under or entering load fall zones; adherence to proper signaling procedures; isolated radio communication frequencies for the crane team; prohibition of side and tip loading; smooth acceleration and deceleration; compliance with electrical safety guidelines per NAVFAC P-307; and completion of critical lift regulations with interactive briefings for designated critical lifts. The checklist requires contractor name (printed and signed), location, and date documentation, and must be current, completely filled out, and posted in the crane. The document serves as a standardized safety verification tool to ensure compliance with federal contracting safety requirements for all crane lifting operations.

View the file

Other files

File Type Posted
0100000 C General Information.pdf PDF
1602000 C Electrical.pdf PDF
1604000 C Wastewater.pdf PDF
1601000 C Utility Management.pdf PDF
Attachment J-0200000-05(e) Solid Waste Management Report.pdf PDF
1502000 J Facility Investment.pdf PDF
Attachment J-1502000-05 HVAC and Refrigeration Systems.xlsx XLSX spreadsheet
Attachment J-1502000-07 Interior and Exterior Lighting Systems.xlsx XLSX spreadsheet
Attachment J-1502000-10 Lightning Arrestors and Grounding Devices.xlsx XLSX spreadsheet
Attachment J-1502000-13 Auxiliary Generator Systems.xlsx XLSX spreadsheet
Attachment J-1502000-16 POL Systems.xlsx XLSX spreadsheet
Attachment J-1502000-22 Emergency Lighting Systems.xlsx XLSX spreadsheet
Attachment J-1502000-31 Mass Communication Systems.xlsx XLSX spreadsheet
1503030 J Integrated Solid Waste Management.pdf PDF
1503060 J Pavement Clearance.pdf PDF
Attachment J-1601000-04 (c)- NRL Update Utility Drawings - Chilled Water.pdf PDF
Attachment J-1601000-10 Electrical Assets.xlsx XLSX spreadsheet
Attachment J-1601000-13 UEM-DI Meter Group and the Direct Condition Rating.pdf PDF
1502000 C Facility Investment.pdf PDF
1503030 C Integrated Solid Waste Management.pdf PDF
1503060 C Pavement Clearance.pdf PDF
1606000 C Water.pdf PDF
Attachment J-0200000-04 NAVFAC 4330 INVOICE FORM.xlsx XLSX spreadsheet
Attachment J-0200000-05(b) Form Contractor Significant Incident Report.pdf PDF
Attachment J-0200000-05(f) Directions for Process Material Log Sheets.pdf PDF
Attachment J-0200000-05(j) Crane and Rigging Gear Accident Report.pdf PDF
Attachment J-0200000-11 MAXIMO Data Reporting.pdf PDF
Attachment J-0200000-15 ELINs Blank.xlsx XLSX spreadsheet
1501000 J Facility Management.pdf PDF
Attachment J-1501000-04 - NRL Site Map.pdf PDF
Attachment J-1502000-01 Definitions and Acronyms.pdf PDF
Attachment J-1502000-03 Sample of E_U_R Orders.pdf PDF
Attachment J-1502000-08 Boilers and UPVs.xlsx XLSX spreadsheet
Attachment J-1502000-12 Compressed Air.xlsx XLSX spreadsheet
Attachment J-1502000-19 Manual and Automated Doors.xlsx XLSX spreadsheet
Attachment J-1502000-21 Emergency Eye Wash and Emergency Showers.xlsx XLSX spreadsheet
Attachment J-1502000-24 Exhaust Hood and Duct Systems.xlsx XLSX spreadsheet
Attachment J-1502000-26 Boiler Water Testing and Treatment.xlsx XLSX spreadsheet
Attachment J-1502000-30 Miscellaneous Equipment.xlsx XLSX spreadsheet
Attachment J-1502000-32 Installation Facilities Monitoring.pdf PDF
1601000 J Utilities Management.pdf PDF
Attachment J-1601000-01 Points of Demarcation.pdf PDF
Attachment J-1601000-04 (b)- NRL Update Utility Drawings - Domestic Water.pdf PDF
Attachment J-1601000-04 (d) NRL 13.8KV SINGLE LINE REV-11.pdf PDF
Attachment J-1601000-08 Utility Asset Tagging Guidance.pdf PDF
Attachment J-1601000-12 Water Assets.xlsx XLSX spreadsheet
1604000 J Wastewater.pdf PDF
Pre-Solicitation Notice - NRL FSS.pdf PDF
0200000 C Management and Administration.pdf PDF
Attachment J-0200000-05(a) DBIDS Standard Operating Procedures.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT "A"

CONTRACTOR CRANE OPERATING CHECKLIST FOR CRITICAL LIFTS YES NO

1 Does the operator know the weight of the load to be lifted?

2 Is the load to be lifted within the crane manufacturer's rated capacity in its present configuration?

3 Is the crane level and on firm ground?

4 Are outriggers required?

5 If so, are outriggers fully extended and down, and the load off the wheels.

6 If blocking is required, is the entire surface of the outrigger pad supported, and is the blocking material of sufficient strength to safely support the loaded outrigger pad?

7 If outriggers are not used, is the crane rated for on-rubber lifts by the manufacturer's load chart?

Is the swing radius of the crane counterweight clear of people, obstructions, and accessible areas within the swing area barricaded to prevent injury, damage and unplanned encroachment?

9 Has the hook been centered over the load in such a manner to prevent swing (deflection, side loading, load-moment)?

10 Is the load well secured and balanced in the sling or lifting device before it is lifted (free and clear) more than a few inches?

11 Is the lift swing path clear of obstructions?

12 If rotation of the load being lifted is hazardous, is tag line or restraint line being used?

13 Are personnel prevented from standing or passing under a suspended load?

14 Are personnel prevented from entering the load fall zone?

15 Is the crane operator's attention diverted?

16 Are proper signals being used at all times?

17 If radio communications are used, is the frequency isolated to the crane team.

18 Do the operations ensure that side and tip loading is prohibited?

19 Are start and stop motions in a smooth fluid motion (no sudden acceleration or deceleration)?

20 If operating near electric power lines, are the rules and guidelines understood and adhered to as specified in NAVFAC P-307?

21 Is the lift a critical lift?

22 If so, are critical lift regulations understood, check-off sheets initialed and signed off, and was there an interactive brief conducted with associated personnel?

23 Is Attachment "A" current, filled out completely, and posted in the crane?

Contractor Name (Print Legibly):

Contractor Name (Signature):

Location: Date: