This solicitation is for a construction project to renovate space at the Minneapolis VA Health Care System to expand polytrauma care. The project involves general construction, electrical, plumbing and other trades. The total estimated value is between $10-20 million. The solicitation is set aside for verified service-disabled veteran-owned small businesses. Offerors must be verified in VetCert as an SDVOSB. Applicable taxes shall be included in pricing. The agency is the VA Veterans Health Administration VISN 23.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FIRE PROTECTION SYMBOL LEGEND
DRAWING NUMBER WHERE DETAILED
SECTION LETTER
DRAWING NUMBER WHERE DETAILED
DETAIL NUMBER
DRAWING NUMBER WHERE DETAILED
ELEVATION LETTER
SECTION, ELEVATION, AND DETAIL TITLES
FX200
FX500
FX300
ELEVATION
DETAIL
SECTION
FX-100
A
FX500
A
C.P.
DISCHARGE NOZZLE
CONTROL PANEL
CLEAN AGENT FIRE SUPPRESSION
FIRE HOSE VALVE CABINET
FIRE HOSE CABINET
ALARM BELL
WATER MOTOR GONG
PENETRATION
TEST PLUG (PRESS/TEMP)
WH
PRESSURE GAUGE AND GAUGE COCK
NEW PIPE CONNECTION TO EXISTING PIPING
EXISTING PIPE TO BE REMOVED
EXISTING PIPING TO REMAIN
NEW PIPING
FLEXIBLE CONNECTION
ORIFICE UNION
FLANGED UNION
UNION
RISE IN PIPE
DROP IN PIPE
CAPPED OUTLET
SIDE CONNECTION
BOTTOM CONNECTION, 45° OR 90°
TOP CONNECTION, 45° OR 90°
ECCENTRIC REDUCER
REDUCER OR INCREASER
DIRECTION OF FLOW
MAV MANUAL AIR VENT (MAV)
AAV AUTOMATIC AIR VENT (AAV)
AG AIR GAP FITTING
WALL HYDRANT
POINT OF CONNECTION TO EXISTING
KEYED NOTE
SCHEMATIC SYMBOLS
ABBREVIATIONSYMBOL DESCRIPTION
XX
STANDPIPE VALVE
INSPECTOR'S TEST CONNECTION (VERTICAL)DFP
D
FP INSPECTOR'S TEST CONNECTION (HORIZONTAL)
FP WET PIPE FIRE RISERFP
(E)FDC
FDC
FLOW SWITCH
FDC (E) EXISTING FIRE DEPARTMENT INLET CONNECTION
FIRE DEPARTMENT INLET CONNECTIONFDC
FLOW CONTROL VALVE
ATMOSPHERIC VACUUM BREAKER
PRESSURE STYLE VACUUM BREAKER
DIAPHRAGM (PROCESS SYSTEMS)
OS&Y VALVE
GATE VALVE
GLOBE VALVE
BUTTERFLY VALVE
BALL VALVE
CHECK VALVE
WATER PRESSURE REDUCING VALVE
PRESSURE RELIEF VALVE
TEMPERATURE AND PRESSURE RELIEF VALVE
VALVE IN VERTICAL
REDUCED PRESSURE BACKFLOW PREVENTER (RPBP)
DRAIN VALVE
FP ROOF MANIFOLD
AUTO BALL DRIP VALVE
OR OR
OR
ABBREVIATION DESCRIPTIONSYMBOL
VALVE SYMBOLS
ABBREVIATIONS
SYMBOL DESCRIPTION
NEW PENDANT STYLE SPRINKLER HEAD
FP
SP STANDPIPE; WETSP
FP FIRE PROTECTION; WET PIPE
ABBREVIATIONSYMBOL DESCRIPTION
PIPING SYMBOLS
FIRE PROTECTION-INTERIOR
ORDINARY GROUP 1 HAZARD
ORDINARY GROUP 2 HAZARD
OH1
OH2
DEMO PENDANT STYLE SPRINKLER HEAD
UPRIGHT STYLE SPRINKLER HEAD
DEMO UPRIGHT STYLE SPRINKLER HEAD
F.D.C.(E)FIRE DEPARTMENT INLET CONNECTION F.D.C.
REDUCED PRESSURE BACKFLOW PREVENTER
F.H.(E)F.H.
CONSTRUCTION
FIRE HYDRANT
VALVE WITH VALVE BOX
FIRE PROTECTION
POST INDICATOR VALVE
PIV PIV(E)
F F(E)
EXISTINGNEWDESCRIPTION
SITE UTILITY SYMBOLS
DRAWING NUMBER WHERE DETAILED
SECTION LETTER
DRAWING NUMBER WHERE DETAILED
DETAIL NUMBER
SECTION, ELEVATION, AND DETAIL SYMBOLS
FX-100
A
DRAWING NUMBER WHERE DETAILED
ELEVATION LETTER
GENERAL NOTES:
NOTE: NOT ALL ABBREVIATIONS AND
SYMBOLS APPLY TO THIS PROJECT.
1. ALL NEW PIPING FOR SPRINKLER HEADS SHALL BE HARD PIPED. FLEXIBLE CONNECTIONS ARE PERMISSIBLE AS THEY ARE
PERMITTED BY THE VAFPDM.
2. ALL PIPING IN FINISHED ROOMS OR SPACES SHALL BE CONCEALED IN FURRED CHASES OR SUSPENDED CEILINGS, UNLESS
OTHERWISE NOTED.
3. PROVIDE ACCESS PANELS OR DOORS IN INACCESSIBLE CEILINGS AND/OR CHASES FOR ALL VALVES. THEY SHALL BE FURNISHED UNDER DIVISION 23 AND INSTALLED UNDER THE ARCHITECTURAL SPECIFICATION. ACCESS DOOR RATING SHALL MATCH
CLASSIFICATION OF WALL AND CEILING FIRE RATING.
COORDINATE THE LOCATION OF SPRINKLER HEADS AND ACCESS DOORS WITH THE ARCHITECTURAL REFLECTED CEILING PLAN(S).
4. REFER TO THE ARCHITECTURAL DRAWINGS FOR EXACT LOCATION OF ALL FIRE RATED AND/OR SMOKE RATED WALLS AND ASSEMBLIES. ALL PIPE PENETRATIONS OF FIRE, SMOKE AND FULL HEIGHT WALLS SHALL BE CAULKED AIRTIGHT TO THE ADJACENT
STRUCTURE BY MEANS OF U.L. APPROVED FIRE PROOF CAULKING MATERIAL.
5. CONTRACTOR SHALL COORDINATE ALL FIRE PROTECTION PIPING WITH DUCTWORK, PIPING, PLUMBING, STRUCTURAL AND ELECTRICAL SYSTEMS AND SHALL PROVIDE NECESSARY OFFSETS TO AVOID CONFLICTS AND TO MAINTAIN EQUIPMENT ACCESS
AND SERVICEABILITY.
6. CONTRACTOR SHALL FURNISH ALL NECESSARY STRUCTURES, INSERTS, SLEEVES, AND HANGING DEVICES FOR INSTALLATION OF
PIPING.
7. CONTRACTOR SHALL BE RESPONSIBLE FOR PROVIDING ALL NECESSARY MISCELLANEOUS ANGLES, CHANNELS, UNISTRUT, ETC., AS MAY BE REQUIRED TO ADEQUATELY SUPPORT FIRE PROTECTION PIPING AND EQUIPMENT IN A MANNER APPROVED BY THE
ARCHITECT, WHICH WILL NOT OVERLOAD THE BUILDING STRUCTURAL SYSTEM.
8. IT IS CRITICAL THAT THE CONTRACTOR PERFORM A COMPLETE REVIEW OF ALL SUBMITTALS PRIOR TO SUBMISSION TO THE AE/COR. INCOMPLETE, INCORRECT AND UNCLEAR SUBMITTALS WILL BE RETURNED AND MARKED AS "REVISE AND RESUBMIT". ALL SUBMITTALS MUST CLEARLY INDICATE THE EQUIPMENT SELECTIONS FOR THE PROJECT. TECHNICAL DRAWINGS OF COMPLETE ASSEMBLIES, REFLECTING ACCURATE PROJECT CONDITIONS, SHALL BE SUBMITTED WITH EQUIPMENT SELECTIONS TO ENSURE SPACE ALLOWANCES ARE REFLECTED IN THE ACTUAL SPACE AVAILABLE. WHERE SIZE DEVIATIONS DIFFER FROM THE BASIS OF DESIGN, CONTRACTOR SHALL HIGHLIGHT THE DIFFERENCES FOR AE/COR REVIEW WITHIN THE SUBMITTAL. CONTRACTOR SHALL PROVIDE INSTALLATION ROUTE AND VERIFICATION THAT ACCESS POINTS, PLACEMENT ROUTE, SUPPORTS, AND REQUIRED EQUIPMENT CLEARANCES ARE IDENTIFIED ON THE ROUTE DRAWING. SAFETY PROTOCOLS FOR SUBJECT STATION SHALL BE REFLECTED ON EQUIPMENT CLEARANCES. PLATFORMS AND INTERFACE AREAS (FILTER, GAUGES, MONITORS, VALVES, ETC.)
SHALL HAVE PROPER CLEARANCE AS DEFINED BY THE MANUFACTURER, VA SAFETY PERSONNEL AND SERVICE PERSONNEL.
ACCESS POINTS OF USE SHALL BE CLEARLY IDENTIFIED ON THE DRAWINGS.
1. THE DEMOLITION DRAWINGS REFLECT INFORMATION ON EXISTING BUILDING SERVICES GATHERED BY SITE INSPECTION, DISCUSSIONS WITH MAINTENANCE PERSONNEL AND PREVIOUS CONSTRUCTION DRAWINGS. THE EXACT LOCATION, ARRANGEMENT, AND SIZES OF PIPELINES IN THE EXISTING BUILDING MAY BE DIFFERENT FROM THAT SHOWN ON THESE
DRAWINGS.
2. THE CONTRACTOR SHALL COORDINATE THE SHUTDOWN OF EXISTING BUILDING SERVICES FOR REMOVALS WITH OWNER
AUTHORIZED REPRESENTATIVE AND SHALL CONFORM TO THEIR REQUIREMENTS.
3. DISRUPTION OF NORMAL FACILITY ACTIVITIES ARE TO BE KEPT TO AN ABSOLUTE MINIMUM. DUST, DEBRIS, AND FUMES SHALL BE CONTROLLED SO AS NOT TO AFFECT THE HEALTH AND SAFETY OF OCCUPIED AREAS WITHIN THE FACILITY WHICH ARE OUTSIDE THE AREA OF WORK. COORDINATE WITH THE ARCHITECT AND THE OWNER'S REPRESENTATIVE WITH REGARD TO ALL ACTIVITIES TO BE CONDUCTED OUTSIDE OF THE SUITE REMODEL AREA WHICH MAY AFFECT THE OPERATION OF THE FACILITY. THE CONTRACTOR SHALL PROVIDE TEMPORARY VENTILATION (MAINTAIN WORK ZONE AT NEGATIVE PRESSURE), FILTRATION, AIR PURIFIERS, DUST SCREENS, ETC. FOR ALL WORK AREAS AFFECTED BY DEMOLITION FOR NEW INSTALLATION TO MINIMIZE DUST
AND FUMES.
4. THE CONTRACTOR SHALL PRESENT AN AREA BY AREA WORK PLAN WELL IN ADVANCE TO THE ARCHITECT AND THE OWNER'S AUTHORIZED REPRESENTATIVE FOR APPROVAL PRIOR TO BEGINNING WORK. THE WORK PLAN SHALL INCLUDE AN OUTLINE OF ALL ACTIVITIES OF ALL SUBCONTRACTORS. THE CONTRACTOR SHALL COORDINATE WITH THE OWNER'S AUTHORIZED REPRESENTATIVE TO ESTABLISH ACCEPTABLE ROUTING AND ACCESS FOR MATERIALS REQUIRED FOR THE NEW INSTALLATION.
5. GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATION OF ALL TRADES INCLUDING MECHANICAL, PLUMBING, ELECTRICAL, FURNITURE, AND ARCHITECTURAL. ANY DISCREPANCIES SHALL BE REPORTED IMMEDIATELY TO THE ARCHITECT
PRIOR TO START OF WORK.
6. ALL NEW TO EXISTING PIPE CONNECTIONS SHALL BE FIELD VERIFIED PRIOR TO ORDERING AND FABRICATING NEW PIPING OR
FITTINGS.
GENERAL DEMO NOTES:
• CONTRACTOR SHALL REPLACE AND RELOCATE EXISTING FIRE SPRINKLER HEAD DROPS TO SERVE THE NEW SPRINKLERS AT THE
NEW LOCATIONS.
• WHERE REQUIRED, CONTRACTOR SHALL REPLACE EXISTING FIRE PROTECTION BRANCH PIPING TO SERVE THE NEW LOCATIONS.
• CONTRACTOR SHALL PROVIDE COMPLETE FIRE PROTECTION SYSTEM COORDINATION DRAWINGS TO ENSURE ALL REQUIRED
CLEARANCES ARE MAINTAINED AND THAT NO CONFLICTS EXIST WITH ANY OTHER MECHANICAL, PLUMBING, ELECTRICAL, COMMUNICATIONS, OR STRUCTURAL SYSTEMS.
• CONTRACTOR SHALL MAINTAIN COMPLIANCE WITH THE 2022 NFPA 13 FOR ALL SURROUNDING SPACES DURING AND AFTER
RENOVATION.
• FOR TELECOMMUNICATION ROOMS (TR), THE CONTRACTOR IS RESPONSIBLE FOR PROVIDING A NEW FIRE EXTINGUISHER CABINET WITH A TYPE 2A:10B:C FIRE EXTINGUISHER LOCATED NO GREATER THAN 75 FEET AWAY FROM THE NEW TR.
CONTRACTOR TO COORDINATE THE NEW LOCATION WITH THE COR.
FIRE PROTECTION SCOPE OF WORK:
DN DOWN
YH YARD HYDRANT
ABOVE FINISHED FLOOR
ABOVE FINISHED GRADE
BOTTOM OF PIPE
ELEVATION
FINISHED FLOOR ELEVATION
FEET
GALLONS PER MINUTE
HORSEPOWER
HEAD
INCHES
INVERT
NOT APPLICABLE
NOT IN CONTRACT
NUMBER
NORMALLY CLOSED
NORMALLY OPEN
OUTSIDE SCREW AND YOKE
PHASE
POUNDS PER SQUARE INCH GAUGE
STATIC PRESSURE
TYPICAL
YARD BOX
AFF
AFG
BOP
EL
FFE
FT
GPM
HP
HD
IN
INV
NA
NIC
No. # N.C.
N.O.
OS&Y
PSIG
SP
TYP
YB
PH
QUICK RESPONSE SPRINKLERQRS
NOT TO SCALENTS
CONTRACTING OFFICER'S REPRESENTATIVECOR
FIRE ALARM STROBE/HORN WALL MOUNTED
FIRE ALARM STROBE/HORN CEILING MOUNTED
HEAT/SMOKE DETECTORH
PIPE RING HANGER
TOLCO FIG. 200
BAR JOIST OR STEEL
MEMBER BY
STRUCTURAL
1" MIN.
1" MIN.
SPRINKLER PIPE PER
PLAN
ALL THREAD ROD
TOLCO FIG. 100
REVERSIBLE BEAM CLAMP
(TYPICAL)
TOLCO FIG. 65
RESTRAINING STRAP
(TYPICAL)
TOLCO FIG. 69/69R
BASIS OF DESIGN IS TOLCO FIGURE
NUMBERS OR APPROVED EQUAL.
PIPE PER PLAN PIPE RING HANGER
TOLCO FIG. 200
ALL THREAD ROD
TOLCO FIG. 100
USE 3/8" CONCRETE INSERT FOR
UP TO 4" PIPE
USE 1/2" CONCRETE INSERT FOR
6" AND 8" PIPE
INSERT SHALL BE PLACED WITHIN
THICKEST PORTION OF
CONCRETE DECKING, TYPICAL
CONCRETE
DECKING
BASIS OF DESIGN IS TOLCO FIGURE
NUMBERS OR APPROVED EQUAL.
INSERT IS NOT
PERMITTED WITHIN
DECKING VALLEY,
TYPICAL
BASIS OF DESIGN IS TOLCO FIGURE
NUMBERS OR APPROVED EQUAL.
PIPE CLAMP
FOR SWAY
BRACING
TOLCO FIG. 4A
SPRINKLER PIPE PER PLAN
STEEL PIPE
LATERAL
BRACE
NO-THREAD SWIVEL
SWAY BRACE
ATTACHMENT TYP.
TOLCO FIG. 909
SWAY BRACE
ATTACHMENT
TO STEEL
TOLCO FIG. 800
BAR JOIST OR STEEL
MEMBER BY STRUCTURAL
BASIS OF DESIGN IS TOLCO FIGURE
NUMBERS OR APPROVED EQUAL.
SWAY BRACE
ATTACHMENT
TOLCO FIG.
SPRINKLER PIPE PER
PLAN
STEEL PIPE
LATERAL
BRACE
NO-THREAD SWIVEL
SWAY BRACE
ATTACHMENT
TOLCO FIG. 909
SWAY BRACE
ATTACHMENT
TO STEEL
TOLCO FIG. 800
BAR JOIST OR STEEL
MEMBER BY STRUCTURAL
NO-THREAD SWIVEL
SWAY BRACE
ATTACHMENT TYP.
TOLCO FIG. 909
BASIS OF DESIGN IS TOLCO FIGURE
NUMBERS OR APPROVED EQUAL.
"FAST CLAMP" BRANCH LINE
RESTRAINT ATTACHMENT
TYP.
TOLCO FIG. 909
BAR JOIST OR STEEL
MEMBER BY STRUCTURAL
SPRINKLER PIPE PER
PLAN
STEEL PIPE
LATERAL
BRACE
on e-ei gh th in ch o ne fo ot on e-qu ar te r ne fo ot th re e-ei gh th s ne fo ot on e-ha lf ne fo ot th re e-qu ar te r ne fo ot in ch on e ne fo ot on e an d on e-ha lf ne fo ot th re e in es ne fo ot
REVISIONS DATE
General Notes:
GENERAL CONTRACTOR AND/OR ALL SUBCONTRACTORS SHALL FIELD VERIFY ALL DIMENSIONS SHOWN ON THESE PLANS AND SHALL BE RESPONSIBLE FOR VARIATIONS BETWEEN PLAN DIMENSIONS AND ACTUAL FIELD DIMENSIONS. WHERE VARIATIONS ARE FOUND TO OCCUR, THE CONTRACTOR SHALL NOTIFY THE PROJECT ENGINEER IN WRITING PRIOR TO PROCEEDING WITH CONSTRUCTION; NO ADJUSTMENT TO
THE WORK WILL BE MADE WITHOUT THE PRIOR APPROVAL OF THE PROJECT ENGINEER.
GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR GENERAL DEMOLITION INCLUDING REMOVAL OF WALLS, PARTITIONS, DOORS & CEILING & FLOORS. ANY AND ALL CUTTING OF CONCRETE FLOORS, WALLS OR STRUCTURE SHALL BE THE GENERAL CONTRACTOR'S RESPONSIBILITY. CORE DRILLING THROUGH CONCRETE WALLS, FLOORS OR STRUCTURE FOR PIPING OR CONDUIT SHALL BE THE RESPONSIBILITY OF THE SUBCONTRACTOR BY TRADE; FIRESTOPPING OF THESE OPENINGS SHALL BE DONE BY THE RESPECTIVE SUBCONTRACTOR. REMOVAL OF DEBRIS RESULTING FROM DEMOLITION, CUTTING, AND/OR DRILLING IS THE RESPONSIBILITY OF THE GENERAL CONTRACTOR. PATCHING AND REPAIR OF CONCRETE WALLS, FLOOR, OR STRUCTURE SHALL BE THE RESPONSIBILITY OF THE GENERAL CONTRACTOR; THIS WILL BE ACCOMPLISHED UPON COMPLETION OF THE INSTALLATION OF ANY AND ALL UTILITIES INSTALLED
BY THE VARIOUS SUBCONTRACTORS.
Approved: Division Chief
Issue Date Checked Drawn
DrawingNumber
Building Number
Project NumberDrawing Title Project Title
Location Drawing Scale
Approved: Service DirectorPlot Scale U.S. Department of Veterans Affairs
Office of Construction and Facilities Management
FULLY SPRINKLERED
Phase
A
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
321 4 5 6 7 8 9 10
TRUE NORTH
PLAN NORTH
KEYPLAN
A/E:
TRIPLE C - The A/E Group
Mat Perkins
(520) 481-8548
A
B D
EF
G
H
J
K
L
M
C
LINE INDICATES
PHASE 1 SCOPE AREA
B
IM
/6
-2
-1
E x p a n d e d P o ly tr a u m a P ro g ra m P h a s e
/6 -2
-7
.M
P L S
.P O
L Y
T R
A U
M A
.G e n e ra l.
S h e e ts
.r v t
/3
/2
:4
:5
P
M As indicated
04/03/2023 K. Luke K.Hutchinson
618-22-100
1390 - FX001
FIRE PROTECTION ABBREVIATIONS,
SYMBOLS, AND DETAILS
1 Veterans Drive, Minneapolis, MN 55417
B70
RENOVATE FOR EXPANDED
POLYTRAUMA PROGRAM
ISSUED FOR BIDDING
NTS
F2
WIDE FLANGE BEAM CLAMP
NTS
F4
DROP-IN ANCHOR
NTS
F5
LONGITUDINAL BRACE DETAIL
NTS
F7
LATERAL BRACE DETAIL
NTS
F9
4-WAY BRACE DETAIL
04/03/2023
H
H H
HHH
H
H
H
H
H
H
H
H
H
H
H
H
H
H
H
H
H
H
H
H
H
H
H
H
H
H
H
H
H
H
H
H
H
H
H
H H
H
H
H
H
H
HH
H
H
H
H
H
H
H
H
H
H
H
H
H
HH
H
H
H
H H
H
H
H
H
HH
H
H
H
H
H H
H
H
H
H H
H
H
H
H
H
HH
H
H
H
H
4G-109B
4G-111
4G-112
4G-114
4S-6
4H-121
4H-122
4H-123
C4-116
4G-116 4G-115 4G-111C 4G-111B 4G-111A
4H-114
4H-115 4H-116 4H-117
4H-118
4H-120
E
C-6
M-8
4L-101
4L-140
C4-126
C4-115
C4-137
4L-102
4L-102A
4H-102
4H-103
4H-104
4H-105
4H-106
4H-107
4H-109 4H-110
4H-111
4H-113
4G-117
4H-101A
4H-101B
C4-110
C4-114
4H-112
4K-101
4H-108C4-138
4H-108A
STAIRWELL 8
SW8
4K-142A
4K-142
4K-140
4K-140A
4K-138A
4K-138
4K-136
4K-136A
4K-134
4K-134A
4K-133A
4K-133
4K-132
4K-131A
4K-131
4K-129
4K-126
4K-127
4K-125 4K-123 4K-122
C4-132
4K-120
4K-121
4K-119
C4-133
4K-117
4K-109
4K-108
4K-106
4K-104
4K-103
4K-101
4H-108
4K-102
4K-107
4K-113
4K-112
4K-1054K-102A
4K-124
4K-124A
4K-124B
STAIRWELL 7
SW7
4K-118
4K-128
4K-130
4K-130A
4K-121A
4K-115
4K-110
4K-111
C-7
C4-131
4K-114
4K-135
4K-137
4K-139
4K-141
4K-143
C4-135
C4-134
C4-138
C4-127
STAIRWELL 8
SW8
4K-116
TTUUVVWWXX
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
AREA NOT IN SCOPE OF WORK
ALL SPRINKLERS AND FIRE DEVICES ARE EXISTING TO REMAIN
/F1 FXD104 /F1 FXD104
TTUUVVWWXXYY
TYP.
1 TYP.
TYP.
AREA NOT IN SCOPE OF WORK
ALL SPRINKLERS AND FIRE DEVICES ARE EXISTING TO REMAIN
AREA NOT IN SCOPE OF WORK
ALL SPRINKLERS AND FIRE DEVICES ARE EXISTING TO REMAIN
/F6 FXD104 /F6 FXD104
WALL SYMBOL LEGEND
CONTRACTOR SHALL CONFIRM ALL FIRE RATED WALL ASSEMBLIES
PROPOSED EXTERIOR WALL.
SEE WALL SECTIONS
1 HR FIRE AND SMOKE
BARRIER
2 HR FIRE AND SMOKE
BARRIER (SHAFT)
SMOKE BARRIER PARTITION
DEMOLISHED WALL,
FIXTURE OR FURNISHING
EXISTING WALL, FIXTURE
OR FURNISHING TO REMAIN
NOT IN CONTRACT - NO
WORK SCHEDULED
on e-ei gh th ne fo ot on e-qu ar te r ne fo ot th re e-ei gh th s ne fo ot on e-ha lf ne fo ot th re e-qu ar te r ne fo ot in ch on e ne fo ot on e an d on e-ha lf ne fo ot th re e in ne fo ot
REVISIONS DATE
General Notes:
GENERAL CONTRACTOR AND/OR ALL SUBCONTRACTORS SHALL FIELD VERIFY ALL DIMENSIONS SHOWN ON THESE PLANS AND SHALL BE RESPONSIBLE FOR VARIATIONS BETWEEN PLAN DIMENSIONS AND ACTUAL FIELD DIMENSIONS. WHERE VARIATIONS ARE FOUND TO OCCUR, THE CONTRACTOR SHALL NOTIFY THE PROJECT ENGINEER IN WRITING PRIOR TO PROCEEDING WITH CONSTRUCTION; NO ADJUSTMENT TO
THE WORK WILL BE MADE WITHOUT THE PRIOR APPROVAL OF THE PROJECT ENGINEER.
GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR GENERAL DEMOLITION INCLUDING REMOVAL OF WALLS, PARTITIONS, DOORS & CEILING & FLOORS. ANY AND ALL CUTTING OF CONCRETE FLOORS, WALLS OR STRUCTURE SHALL BE THE GENERAL CONTRACTOR'S RESPONSIBILITY. CORE DRILLING THROUGH CONCRETE WALLS, FLOORS OR STRUCTURE FOR PIPING OR CONDUIT SHALL BE THE RESPONSIBILITY OF THE SUBCONTRACTOR BY TRADE; FIRESTOPPING OF THESE OPENINGS SHALL BE DONE BY THE RESPECTIVE SUBCONTRACTOR. REMOVAL OF DEBRIS RESULTING FROM DEMOLITION, CUTTING, AND/OR DRILLING IS THE RESPONSIBILITY OF THE GENERAL CONTRACTOR. PATCHING AND REPAIR OF CONCRETE WALLS, FLOOR, OR STRUCTURE SHALL BE THE RESPONSIBILITY OF THE GENERAL CONTRACTOR; THIS WILL BE ACCOMPLISHED UPON COMPLETION OF THE INSTALLATION OF ANY AND ALL UTILITIES INSTALLED
BY THE VARIOUS SUBCONTRACTORS.
Approved: Division Chief
Issue Date Checked Drawn
DrawingNumber
Building Number
Project NumberDrawing Title Project Title
Location Drawing Scale
Approved: Service DirectorPlot Scale U.S. Department of Veterans Affairs
Office of Construction and Facilities Management
FULLY SPRINKLERED
Phase
A
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
321 4 5 6 7 8 9 10
TRUE NORTH
PLAN NORTH
KEYPLAN
A/E:
TRIPLE C - The A/E Group
Mat Perkins
(520) 481-8548
A
B D
EF
G
H
J
K
L
M
C
GENERAL NOTES
LINE INDICATES
PHASE 1 SCOPE AREA
B
IM
/6
-2
-1
E x p a n d e d P o ly tr a u m a P ro g ra m P h a s e
/6 -2
-7
.M
P L S
.P O
L Y
T R
A U
M A
.M E
P .B
.L
.r v t
/4
/2
:4
:1
A
M As indicated
04/03/2023 K. Luke K.Hutchinson
618-22-100
1390 -
FXD104
FIRE PROTECTION DEMO PLANS - FOURTH
LEVEL - AREA 4H&4K
1 Veterans Drive, Minneapolis, MN 55417
B70
RENOVATE FOR EXPANDED
POLYTRAUMA PROGRAM - PHASE 1
ISSUED FOR BIDDING
1/8" = 1'-0" F6
FIRE PROTECTION DEMO RCP - FOURTH LEVEL - AREA 4K
1/8" = 1'-0"
F1
FIRE PROTECTION DEMO RCP - FOURTH LEVEL - AREA 4H
CONTRACTOR SHALL PROVIDE THE FOLLOWING PRIOR TO
COMMENCEMENT OF WORK FOR REVIEW AND APPROVAL:
A. SHOP DRAWING IDENTIFYING MAIN PIPE SIZES AND LOCATIONS,
LOCATION OF PIPE BRACING, HANGERS AND SPRINKLER HEADS
AND DETAILS
B. CUT SHEETS AND SUBMITTAL FOR ALL PIPING, FITTINGS,
SPRINKLER HEADS, HANGERS AND SUPPORT ATTACHMENTS
A. EXISTING CONDITIONS ARE BASED ON EXISTING PLANS AND FIELD VERIFICATION
WHERE FEASIBLE. ACTUAL CONDITIONS MAY DIFFER FROM THOSE INDICATED.
CONTRACTOR SHALL FIELD VERIFY IN ADVANCE THE LOCATION AND CONDITION OF
THE EXISTING SYSTEMS SHOWN TO BE MODIFIED OR REMOVED. CONTRACTOR TO
NOTIFY ARCHITECT SHOULD CONDITIONS BE FOUND TO DIFFER SIGNIFICANTLY
FROM THE CONSTRUCTION DOCUMENTS.
B. DETAILED SCHEDULE, INCLUDING PROJECTED SERVICE INTERRUPTION DATES WITH
DURATIONS, AND DETAILED PHASING PLAN IS TO BE PROVIDED TO THE COR PRIOR
TO THE START OF WORK. THIS SUBMITTAL MUST BE ACCEPTED BY THE COR PRIOR
TO THE START OF WORK.
C. REFER TO ARCHITECTURAL DRAWINGS FOR EXACT DIMENSIONAL DATA, CEILING
HEIGHTS, AND SQUARE FOOTAGE.
D. CONTRACTOR SHALL COORDINATE ALL WORK WITH BUILDING OWNER AND OTHER
TRADES PRIOR TO CONSTRUCTION.
E. ALL PIPING TO BE ROUTED WITHIN CEILING SPACE OR CONCEALED IN FURRED
CHASES UNLESS NOTED OTHERWISE.
F. ALL AREAS ARE DESIGNED AS LIGHT HAZARD OCCUPANCY UNLESS NOTED
OTHERWISE ON PLAN.
G. ALL SPRINKLERS SYSTEMS SHALL BE INSTALLED IN ACCORDANCE WITH THE 2022
NFPA 13.
H. ALL MATERIALS, DEVICES, HANGERS AND SUPPORTS SHALL BE NEW AND UL LISTED
FOR USE IN FIRE PROTECTION SYSTEMS.
I. ALL NEW SPRINKLERS SHALL BE PROVIDED WITH NEW ESCUTCHEONS TO MATCH
EXISTING BUILDING STANDARDS.
J. INSTALL QUICK RESPONSE SPRINKLERS (QRS) IN ALL AREAS, EXCEPT WHERE
SPECIFICALLY PROHIBITED AS DEFINED BY 2022 NFPA 13.
K. PIPING TO BE SCHEDULE 40 BLACK STEEL WITH CAST IRON FITTINGS.
L. ANY FLOOR, WALL, OR CEILING CUTTING OR FILLING THAT IS REQUIRED TO
COMPLETE THIS PROJECT, THE CONTRACTOR SHALL PATCH AND PAINT AND
RETURN TO MATCH EXISTING CONDITIONS AND FINISHES.
M. CONTRACTOR TO PROVIDE GALVANIC PROTECTION AS REQUIRED AT CONNECTIONS
BETWEEN ALL DISSIMILAR METALS.
N. CONTRACTOR TO VALIDATE AND VERIFY ALL FIRE RATED AND/OR SMOKE RATED
WALLS AND ASSEMBLIES INDICATED ON PLANS IN WORK AREA. PROVIDE ALL PIPING
PENETRATIONS OF FIRE, SMOKE AND FULL HEIGHT WALLS SHALL BE CAULKED
AIRTIGHT TO THE ADJACENT STRUCTURE BY MEANS OF U.L. APPROVED FIRE PROOF
CAULKING MATERIAL. CONTRACTOR SHALL PROVIDE SPECIAL INSPECTIONS OF ALL
UL RATED PENETRATIONS BY A LICENSED INSPECTOR.
O. ALL NEW PIPES TO BE CLEANED AND TESTED PRIOR TO COMMISSIONING.
P. THE SPRINKLER CONTRACTOR SHALL COORDINATE AND PERFORM ALL FIRE
PROTECTION WORK IN ACCORDANCE WITH VA REQUIREMENTS TO ENSURE THAT
CONTINUOUS SPRINKLER COVERAGE IS PROVIDED THROUGHOUT THE PROJECT.
THE SPRINKLER CONTRACTOR SHALL COORDINATE ALL FIRE PROTECTION SYSTEM
SHUTDOWNS, INCLUDING POINTS OF TIE IN, ETC. WITH THE VA PRIOR TO
PERFORMING WORK.
Q. CONTRACTOR IS RESPONSIBLE FOR MAINTAINING COMPLIANCE WITH THE 2022
NFPA 13 FOR SURROUNDING SPACES DURING AND AFTER RENOVATION.
CONTRACTOR IS RESPONSIBLE FOR FIELD VERIFYING SPRINKLER HEAD LOCATIONS
AND PIPING TO BE MODIFIED BY THE RENOVATION PRIOR TO COMMENCING WORK.
R. DURING CONSTRUCTION ENSURE ALL SPRINKLERS ARE THE CORRECT DISTANCE
TO THE DECK WHEN THE CEILING IS NOT INSTALLED.
S. ALL SPRINKLER HEADS WILL BE REPLACED DURING THIS PROJECT. ALL SPRINKLER
HEADS TO BE PENDENT TYPE, SEE HAZARD CHART FOR ADDITIONAL INFORMATION.
NOTE: NOT ALL KEYNOTES
ARE USED ON EACH SHEETKEYNOTES
1. EXISTING PENDENT SPRINKLER HEAD AND BRANCH PIPING TO BE REMOVED BACK
TO NEAREST BRANCH LINE OR MAIN. RECONFIGURE EXISTING SPRINKLER SYSTEM
AS REQUIRED FOR NEW SPRINKLER HEAD LOCATIONS.
2. EXISTING 6" STAND PIPE, FIRE PROTECTION RISER.
3. REMOVE EXISTING HEAT/SMOKE DETECTOR. COORDINATE WITH COR.
4. REMOVE EXISTING FIRE ALARM STROBE/HORN. COORDINATE WITH COR.
5. EXISTING FIRE SUPPRESSION CONTROL VALVE ASSEMBLY TO REMAIN
CONTRACTOR TO COORDINATE SHUTDOWN WITH COR PRIOR TO
COMMENCEMENT OF WORK.
6. EXISTING PIPING DROP FROM INTERSTITIAL SPACE TO PLENUM SPACE BELOW TO
REMAIN. PROTECT IN PLACE.
7. CONTRACTOR TO FIELD COORDINATE EXTENTS OF DEMO FOR EXISTING PIPING
RECONFIGURATION.
8. EXISTING 2-1/2" FDV, T CAP AND PIPING CONNECTED TO STANDPIPE ARE LOCATED
IN PLENUM SPACE ABOVE AND ARE EXISTING TO REMAIN. PROTECT IN PLACE.
SHOWN ON RCP LEVEL FOR COORDINATION AND REFERENCE ONLY.
9. EXISTING 6" STAND PIPE, FIRE PROTECTION RISER AND FIRE SPRINKER PIPING
BETWEEN STANDPIPIES ARE LOCATED IN INTERSTITIAL SPACE ABOVE AND ARE
EXISTING TO REMAIN. SHOWN ON RCP LEVEL FOR COORDINATION AND
REFERENCE ONLY.
10. EXISTING 2-1/2" FIRE LINE DOWN TO PLENUM.
11. EXISTING 2" FIRE LINE DRAIN TO REMAIN, PROTECT IN PLACE.
12. EXISTING 2-1/2" FIRE LINE DOWN TO F.V.C, DEMOLISH AND REPLACE F.V.C ON
NEAREST WALL.
13. EXISTING 4" STANDPIPE TO REMAIN, PROTECT IN PLACE.
TTUUVVWWXX
MECHANICAL
4K-124
WS
WS
ZONE #105
ZONE #106
TYP.
4TH LEVEL INTERSTITIAL
4H
2 1/2" F
2" F
2 1/2" F
2 1/2" F
S M
O K
E Z
O N
E
S M
O K
E Z
O N
E
S M
O K
E Z
O N
E
S M
O K
E Z
O N
E
S M
O K
E Z
O N
E
S M
O K
E Z
O N
E
SMOKE ZONE #_ _ _
SMOKE ZONE #_ _ _
/F1 FXD104i /F1 FXD104i
TTUUVVWWXXYY
WS
WS
ZONE #104
ZONE #107
4TH LEVEL INTERSTITIAL
4H
2 1/2" F
2 1/2" F
2" F
2" F
2" F
TYP.
/F6 FXD104i /F6 FXD104i
WALL SYMBOL LEGEND
CONTRACTOR SHALL CONFIRM ALL FIRE RATED WALL ASSEMBLIES
PROPOSED EXTERIOR WALL.
SEE WALL SECTIONS
1 HR FIRE AND SMOKE
BARRIER
2 HR FIRE AND SMOKE
BARRIER (SHAFT)
SMOKE BARRIER PARTITION
DEMOLISHED WALL,
FIXTURE OR FURNISHING
EXISTING WALL, FIXTURE
OR FURNISHING TO REMAIN
NOT IN CONTRACT - NO
WORK SCHEDULED
on e-ei gh th ne fo ot on e-qu ar te r ne fo ot th re e-ei gh th s ne fo ot on e-ha lf ne fo ot th re e-qu ar te r ne fo ot in ch on e ne fo ot on e an d on e-ha lf ne fo ot th re e in ne fo ot
REVISIONS DATE
General Notes:
GENERAL CONTRACTOR AND/OR ALL SUBCONTRACTORS SHALL FIELD VERIFY ALL DIMENSIONS SHOWN ON THESE PLANS AND SHALL BE RESPONSIBLE FOR VARIATIONS BETWEEN PLAN DIMENSIONS AND ACTUAL FIELD DIMENSIONS. WHERE VARIATIONS ARE FOUND TO OCCUR, THE CONTRACTOR SHALL NOTIFY THE PROJECT ENGINEER IN WRITING PRIOR TO PROCEEDING WITH CONSTRUCTION; NO ADJUSTMENT TO
THE WORK WILL BE MADE WITHOUT THE PRIOR APPROVAL OF THE PROJECT ENGINEER.
GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR GENERAL DEMOLITION INCLUDING REMOVAL OF WALLS, PARTITIONS, DOORS & CEILING & FLOORS. ANY AND ALL CUTTING OF CONCRETE FLOORS, WALLS OR STRUCTURE SHALL BE THE GENERAL CONTRACTOR'S RESPONSIBILITY. CORE DRILLING THROUGH CONCRETE WALLS, FLOORS OR STRUCTURE FOR PIPING OR CONDUIT SHALL BE THE RESPONSIBILITY OF THE SUBCONTRACTOR BY TRADE; FIRESTOPPING OF THESE OPENINGS SHALL BE DONE BY THE RESPECTIVE SUBCONTRACTOR. REMOVAL OF DEBRIS RESULTING FROM DEMOLITION, CUTTING, AND/OR DRILLING IS THE RESPONSIBILITY OF THE GENERAL CONTRACTOR. PATCHING AND REPAIR OF CONCRETE WALLS, FLOOR, OR STRUCTURE SHALL BE THE RESPONSIBILITY OF THE GENERAL CONTRACTOR; THIS WILL BE ACCOMPLISHED UPON COMPLETION OF THE INSTALLATION OF ANY AND ALL UTILITIES INSTALLED
BY THE VARIOUS SUBCONTRACTORS.
Approved: Division Chief
Issue Date Checked Drawn
DrawingNumber
Building Number
Project NumberDrawing Title Project Title
Location Drawing Scale
Approved: Service DirectorPlot Scale U.S. Department of Veterans Affairs
Office of Construction and Facilities Management
FULLY SPRINKLERED
Phase
A
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
321 4 5 6 7 8 9 10
TRUE NORTH
PLAN NORTH
KEYPLAN
A/E:
TRIPLE C - The A/E Group
Mat Perkins
(520) 481-8548
A
B D
EF
G
H
J
K
L
M
C
GENERAL NOTES
LINE INDICATES
PHASE 1 SCOPE AREA
B
IM
/6
-2
-1
E x p a n d e d P o ly tr a u m a P ro g ra m P h a s e
/6 -2
-7
.M
P L S
.P O
L Y
T R
A U
M A
.M E
P .B
.L
.r v t
/3
/2
:2
:4
P
M As indicated
04/03/2023 K. Luke K.Hutchinson
618-22-100
1390 - FXD104i
FIRE PROTECTION DEMO PLANS - FOURTH
LEVEL INTERSTITIAL - AREA 4H&K
1 Veterans Drive, Minneapolis, MN 55417
B70
RENOVATE FOR EXPANDED
POLYTRAUMA PROGRAM - PHASE 1
ISSUED FOR BIDDING
1. EXISTING PENDENT SPRINKLER HEAD AND BRANCH PIPING TO BE REMOVED BACK
TO NEAREST BRANCH LINE OR MAIN. RECONFIGURE EXISTING SPRINKLER SYSTEM
AS REQUIRED FOR NEW SPRINKLER HEAD LOCATIONS.
2. EXISTING 6" STAND PIPE, FIRE PROTECTION RISER.
3. REMOVE EXISTING HEAT/SMOKE DETECTOR. COORDINATE WITH COR.
4. REMOVE EXISTING FIRE ALARM STROBE/HORN. COORDINATE WITH COR.
5. EXISTING FIRE SUPPRESSION CONTROL VALVE ASSEMBLY TO REMAIN,
CONTRACTOR TO COORDINATE SHUTDOWN WITH COR PRIOR TO
COMMENCEMENT OF WORK.
6. EXISTING PIPING DROP FROM INTERSTITIAL SPACE TO PLENUM SPACE BELOW TO
REMAIN, PROTECT IN PLACE.
7. CONTRACTOR TO FIELD COORDINATE EXTENTS OF DEMO FOR EXISTING PIPING
RECONFIGURATION.
8. EXISTING 2-1/2" FDV, T CAP AND PIPING CONNECTED TO STANDPIPE ARE LOCATED
IN PLENUM SPACE ABOVE AND ARE EXISTING TO REMAIN. PROTECT IN PLACE.
SHOWN ON RCP LEVEL FOR COORDINATION AND REFERENCE ONLY.
9. EXISTING 6" STAND PIPE, FIRE PROTECTION RISER AND FIRE SPRINKLER PIPING
BETWEEN STANDPIPIES ARE LOCATED IN INTERSTITIAL SPACE ABOVE AND ARE
EXISTING TO REMAIN. SHOWN ON RCP LEVEL FOR COORDINATION AND
REFERENCE ONLY.
10. EXISTING 2-1/2" FIRE LINE DOWN TO PLENUM.
11. EXISTING 2" FIRE LINE DRAIN TO REMAIN, PROTECT IN PLACE.
12. EXISTING 2-1/2" FIRE LINE DOWN TO F.V.C TO BE DEMOLISHED AND RELOCATED
TO NEW F.V.C.
13. EXISTING 4" STANDPIPE TO REMAIN, PROTECT IN PLACE.
NOT TO SCALE
B2
SUPPRESSION CONTROL VALVE ASSEMBLY AREA K- REFERENCE PHOTOS
1/8" = 1'-0" F6
FIRE PROTECTION DEMO PLAN - FOURTH LEVEL INTERSTITIAL - AREA 4K
1/8" = 1'-0"
F1
FIRE PROTECTION DEMO PLAN - FOURTH LEVEL INTERSTITIAL - AREA 4H
CONTRACTOR SHALL PROVIDE THE FOLLOWING PRIOR TO
COMMENCEMENT OF WORK FOR REVIEW AND APPROVAL:
A. SHOP DRAWING IDENTIFYING MAIN PIPE SIZES AND LOCATIONS,
LOCATION OF PIPE BRACING, HANGERS AND SPRINKLER HEADS
AND DETAILS
B. CUT SHEETS AND SUBMITTAL FOR ALL PIPING, FITTINGS,
SPRINKLER HEADS, HANGERS AND SUPPORT ATTACHMENTS
A. EXISTING CONDITIONS ARE BASED ON EXISTING PLANS AND FIELD VERIFICATION
WHERE FEASIBLE. ACTUAL CONDITIONS MAY DIFFER FROM THOSE INDICATED.
CONTRACTOR SHALL FIELD VERIFY IN ADVANCE THE LOCATION AND CONDITION OF
THE EXISTING SYSTEMS SHOWN TO BE MODIFIED OR REMOVED. CONTRACTOR TO
NOTIFY ARCHITECT SHOULD CONDITIONS BE FOUND TO DIFFER SIGNIFICANTLY
FROM THE CONSTRUCTION DOCUMENTS.
B. DETAILED SCHEDULE, INCLUDING PROJECTED SERVICE INTERRUPTION DATES WITH
DURATIONS, AND DETAILED PHASING PLAN IS TO BE PROVIDED TO THE COR PRIOR
TO THE START OF WORK. THIS SUBMITTAL MUST BE ACCEPTED BY THE COR PRIOR
TO THE START OF WORK.
C. REFER TO ARCHITECTURAL DRAWINGS FOR EXACT DIMENSIONAL DATA, CEILING
HEIGHTS, AND SQUARE FOOTAGE.
D. CONTRACTOR SHALL COORDINATE ALL WORK WITH BUILDING OWNER AND OTHER
TRADES PRIOR TO CONSTRUCTION.
E. ALL PIPING TO BE ROUTED WITHIN CEILING SPACE OR CONCEALED IN FURRED
CHASES UNLESS NOTED OTHERWISE.
F. ALL AREAS ARE DESIGNED AS LIGHT HAZARD OCCUPANCY UNLESS NOTED
OTHERWISE ON PLAN.
G. ALL SPRINKLERS SYSTEMS SHALL BE INSTALLED IN ACCORDANCE WITH THE 2022
NFPA 13.
H. ALL MATERIALS, DEVICES, HANGERS AND SUPPORTS SHALL BE NEW AND UL LISTED
FOR USE IN FIRE PROTECTION SYSTEMS.
I. ALL NEW SPRINKLERS SHALL BE PROVIDED WITH NEW ESCUTCHEONS TO MATCH
EXISTING BUILDING STANDARDS.
J. INSTALL QUICK RESPONSE SPRINKLERS (QRS) IN ALL AREAS, EXCEPT WHERE
SPECIFICALLY PROHIBITED AS DEFINED BY 2022 NFPA 13.
K. PIPING TO BE SCHEDULE 40 BLACK STEEL WITH CAST IRON FITTINGS.
L. ANY FLOOR, WALL, OR CEILING CUTTING OR FILLING THAT IS REQUIRED TO
COMPLETE THIS PROJECT, THE CONTRACTOR SHALL PATCH AND PAINT AND
RETURN TO MATCH EXISTING CONDITIONS AND FINISHES.
M. CONTRACTOR TO PROVIDE GALVANIC PROTECTION AS REQUIRED AT CONNECTIONS
BETWEEN ALL DISSIMILAR METALS.
N. CONTRACTOR TO VALIDATE AND VERIFY ALL FIRE RATED AND/OR SMOKE RATED
WALLS AND ASSEMBLIES INDICATED ON PLANS IN WORK AREA. PROVIDE ALL PIPING
PENETRATIONS OF FIRE, SMOKE AND FULL HEIGHT WALLS SHALL BE CAULKED
AIRTIGHT TO THE ADJACENT STRUCTURE BY MEANS OF UL APPROVED FIRE PROOF
CAULKING MATERIAL. CONTRACTOR SHALL PROVIDE SPECIAL INSPECTIONS OF ALL
UL RATED PENETRATIONS BY A LICENSED INSPECTOR.
O. ALL NEW PIPES TO BE CLEANED AND TESTED PRIOR TO COMMISSIONING.
P. THE SPRINKLER CONTRACTOR SHALL COORDINATE AND PERFORM ALL FIRE
PROTECTION WORK IN ACCORDANCE WITH VA REQUIREMENTS TO ENSURE THAT
CONTINUOUS SPRINKLER COVERAGE IS PROVIDED THROUGHOUT THE PROJECT.
THE SPRINKLER CONTRACTOR SHALL COORDINATE ALL FIRE PROTECTION SYSTEM
SHUTDOWNS, INCLUDING POINTS OF TIE IN, ETC. WITH THE VA PRIOR TO
PERFORMING WORK.
Q. CONTRACTOR IS RESPONSIBLE FOR MAINTAINING COMPLIANCE WITH THE 2022
NFPA 13 FOR SURROUNDING SPACES DURING AND AFTER RENOVATION.
CONTRACTOR IS RESPONSIBLE FOR FIELD VERIFYING SPRINKLER HEAD LOCATIONS
AND PIPING TO BE MODIFIED BY THE RENOVATION PRIOR TO COMMENCING WORK.
R. DURING CONSTRUCTION, ENSURE ALL SPRINKLERS ARE THE CORRECT DISTANCE
TO THE DECK WHEN THE CEILING IS NOT INSTALLED.
S. ALL SPRINKLER HEADS WILL BE REPLACED DURING THIS PROJECT. ALL SPRINKLER
HEADS TO BE PENDENT TYPE, SEE HAZARD CHART FOR ADDITIONAL INFORMATION.
NOTE: NOT ALL KEYNOTES
ARE USED ON EACH SHEETKEYNOTES
H
H
H
HH
H
H
H H
F A
C P
TTUUVVWWXXYY
AREA NOT IN SCOPE OF WORK
SPRINKLERS AND FIRE ALARM
DEVICES ARE EXISTING TO REMAIN
4G-111
4G-112
4G-114
SHAFT
4S-6
4G-116 4G-115 4G-111C 4G-111B 4G-111A
ELEVATORS
E 4L-101
4L-140
4L-102
4L-102A
4J-101
4J-1024J-103
4J-102B 4J-103B
4J-102A4J-103A
C4-142
C4-141
C4-139
NOURISH.
4H-110
BREAK RM
4H-113
TR
4H-114
ELEV. LOBBY
4H-115
ELEV. LOBBY
C4-115
FAMILY CONF.
4H-111
CENTRAL NURSE STATION
4H-107
M LOCKERS
4H-105
TLT
4H-102
TLT
4H-101
W LOCKERS
4H-104
NURSING MOTHERS RM
4H-104A
MED RM
4H-107A
FAMILY ROOM
4H-109
STAFF CORR.
4H-103
CORR.
C4-137
ENTRY CORR.
C4-114
CARTS
C4-126
ANM + 1
4K-101
REC STOR
4K-127
STOR.
4H-108A
DINING ACUTE
4H-108
TLT
4K-103A
CARTS
4K-149
VACANT (FINISH PHASE 2)
4H-100
HAND WASH
4K-152
NURSE MNGR
4H-106
P1:S23 P1:S22
P1:S8
P1:S45
P1:S46 P1:S13
P1:S52
P1:S56 P1:S55
P1:S54 P1:S53
P1:S80P1:S68
P1:S67
P1:S66
N1-18P1:S57
P1:S69
P1:S70
P1:S64
P1:S61
P1:S65
P1:S60
P1:S59
P1:S71
P1:S58
P1:S72
P1:S73
P1:S74
P1:S77 P1:S79
P1:S78
P1:S76
P1:S75
N1-8N1-13
N1-15 N1-14
N1-16 N1-17
N1-25
N1-22N1-21
N1-26
N1-20N1-19
5 5
5 5
TYP.
5 5
6 6
6 6
P1:S38
6' - 11" 7' - 5 1/2"
5' - 0 1/2"
/2
/2
AREA NOT IN SCOPE OF WORK
SPRINKLERS AND FIRE ALARM
DEVICES ARE EXISTING TO REMAIN
5' - 10 1/2" 10' - 0" 10' - 0" 6' - 5 1/2"
" 2' - 10 1/2"
/2
TYP.
/2
5' - 0 1/2" 6' - 11 1/2"
TYP.
2' - 11" 4' - 11"
/2
6' - 4" 6' - 6 1/2"
TYP.
4' - 1"
/2
6' - 2"
HOLD
7' - 6"
6' - 11" 4' - 1 1/2"
5' - 10 1/2" 8' - 0" 4' - 10"
/2
/2
/2
4' - 10"
TYP.
4' - 6"
4' - 8 1/2"
5' - 0 1/2" 8' - 0" 10' - 0" 14' - 0" 7' - 0 1/2"
OFFICE
4H-123
/2
/2
5' - 10" 5' - 1 1/2"
4' - 0"
TYP.
4' - 1"
/2
/2
TYP.
3' - 11 1/2"3' - 11 1/2"
5' - 7 1/2" 10' - 0" 10' - 0" 10' - 0" 8' - 0" 5' - 7 1/2"
2' - 9" 8' - 0"
HOLD
7' - 6"
"TYP.
/2
TYP.
/2
4' - 6 1/2" 7' - 3"
1' - 11"
HOLD
7' - 6" 14' - 0" 5' - 2"
/2
/2
5' - 3 1/2"
TYP.
TYP.
2' - 9" 13' - 8" 14' - 0" 10' - 2" 2' - 3 1/2"
TR IS NOT IN SCOPE.
SPRINKLERS AND FIRE ALARM
DEVICES ARE A PART OF EHRM
SCOPE.
/2
5' - 2 1/2" 4
5' - 0 1/2" 6' - 0" 5' - 7 1/2"
TYP.
1' - 6" 8' - 0" 7' - 2 1/2"
/2
TYP.
5' - 1" 14' - 0" 5' - 11 1/2"
/2
/2
TYP.
3' - 0" 10' - 0" 6' - 1 1/2"
/2
TYP.
CORR.
C4-137A
3' - 9" 8' - 0" 5' - 9"
TYP.
CORR.
C4-137
4' - 5 1/2" 12' - 0" 12' - 0" 12' - 0" 12' - 0" 10' - 0" 12' - 0" 1' - 7 1/2"4
/2
TYP.
4' - 0" 9' - 8" 8' - 0" 4' - 5 1/2"
/2
/2
/2
6' - 8" 6' - 6"
TYP.
7 4
/2
/2
5' - 11"
TYP.
/2
4' - 5"
/2
4' - 10" 5' - 0"
TYP.
H O
L D
/2
/2
6' - 0" 7
/2
5' - 7" 8' - 0" 2' - 1 1/2"
TYP.
HOLD
7' - 6" 3' - 4"
/2
HAC
4H-112
STAIRWELL 8
SW8
/F6 FX104 /F6 FX104
TTUUVVWWXX
STORAGE
4K-116B
SOILED UTILITY
4K-118
CLEAN
4K-117
THERAPIST OFFICE
4K-116C
PRIVATE PT
4K-116D
PRIVATE OT
4K-116A
THERAPY GYM
4K-116
REC THERAPY
4K-128
LINEN
4K-109
LAUNDRY
4K-126
STOR.
4K-121
NOURISH.
4H-110
BREAK RM
4H-113
PATIENT ROOM
4K-123
PATIENT ROOM
4K-122
PATIENT ROOM
4K-120
TLT
4K-119A
TLT
4K-120A
TLT
4K-122A
TLT
4K-123A
LSB
4K-106
SW +1
4K-104
TEAM RM
4K-102
FAMILY CONF.
4H-111
NURSE STN
4K-111
CORR.
C4-127
ANM + 1
4K-101
REC STOR
4K-127
PATIENT ROOM
4K-119
STAFF TLT
4K-107
BARIATRIC / SURGE PATIENT ROOM
4K-103
PATIENT ROOM
4K-105
PATIENT ROOM
4K-108
PATIENT ROOM
4K-110
PATIENT ROOM
4K-112
TLT
4K-105A
TLT
4K-108A
TLT
4K-110A
TLT
4K-112A
PATIENT ROOM
4K-113
PATIENT ROOM
4K-114
TLT
4K-113A
TLT
4K-114A
PATIENT ROOM
4K-115
CORR.
C4-131
TLT
4K-115A
TLT
4K-103A
NURSE
4K-151
NURSE
4K-155
NURSE
4K-154
NURSE
4K-153
NURSE
4K-150
CARTS
4K-149
STAIRWELL 7
SW7
CORR.
C4-132
HAND WASH
4K-152
P1:S1
P1:S2
P1:S3
P1:S4
P1:S5
P1:S6
P1:S7
P1:S30
P1:S31
P1:S32
P1:S35
P1:S37
P1:S34
P1:S24
P1:S26
P1:S25
P1:S27
P1:S29
P1:S28
P1:S33
P1:S47
P1:S48
P1:S36
P1:S41P1:S42
P1:S43P1:S44P1:S12
P1:S11
P1:S10
P1:S9
P1:S14
P1:S15
P1:S16
P1:S17
P1:S18
P1:S19
P1:S20
P1:S21
P1:S22 P1:S23P1:S45
P1:S46
P1:S51
P1:S50
P1:S49
P1:S39
N1-2
N1-3
N1-4
N1-5
N1-6
N1-7
N1-8
N1-9
N1-10
N1-11
N1-12
N1-13
N1-1
5 5
TYP.
5 5
TYP.
P1:S40
MED SUPPLY
4K-125
5' - 10 1/2" 14' - 0" 6' - 10"
/2
7' - 4 1/2" 14' - 0" 5' - 5 1/2"
6' - 4 1/2" 7' - 4"
/2
7' - 4 1/2" 14' - 0" 5' - 4"
HOLD
7' - 6"
/2
5' - 2 1/2"
/2
5' - 2 1/2"
/2
6' - 10 1/2" 14' - 0" 5' - 10"
TYP.
6' - 9 1/2"
5' - 11" 14' - 0" 6' - 9 1/2"
/2
TYP.
5' - 11" 14' - 0" 6' - 9 1/2"
/2
TYP.
6' - 9 1/2"
6' - 9 1/2"
/2
5' - 9" 14' - 0" 6' - 11 1/2"
/2
TYP.
5' - 9" 14' - 0" 6' - 11 1/2"
/2
TYP.
7 6' - 11 1/2"
/2
" 1' - 10"
HOLD
7' - 6"
/2
/2
TYP.
6' - 3" 14' - 0" 10' - 0" 8' - 0" 4' - 11"
6' - 8"
5' - 8"
/2
CHUTE
4K-118A
2' - 11"
/2
/2
5' - 11"
/2
/2
5' - 6 1/2" 4' - 10"
TYP.
/2
2' - 11" 7' - 5 1/2"
TYP.
/2
/2
5' - 8 1/2" 10' - 0" 6' - 4 1/2"
TYP.
5' - 5" 12' - 0" 7' - 4 1/2"
/2
TYP.
/2
/2
TYP.
TYP.
TYP.
4' - 0"
TYP.
4' - 0"
/2
/2
TYP.
TYP.
TYP.
TYP.
4' - 0" 13' - 6" 13' - 6" 4' - 0"
9' - 6" 9' - 6"
/2
TYP.
TYP.
4' - 0"
TYP.
4' - 0"
TYP.
TYP.
TYP.
3' - 4 1/2"
/2
6' - 1" 14' - 0" 6' - 7 1/2"6
/2
6' - 10" 6' - 0"
HOLD
7' - 6" 14' - 0" 5' - 2"
TYP.
/2
6' - 6 1/2" 7' - 2"
TYP.
/2
5' - 2 1/2" 7' - 2"
5' - 2 1/2" 7' - 2"
"7
7' - 4 1/2" 14' - 0" 5' - 4"
/2
/2
/2
6' - 4 1/2" 7' - 4"
TYP.
TYP.
/2
/2
7' - 4 1/2" 14' - 0" 5' - 4"
/2
TYP.
5' - 2 1/2" 7' - 2"
5' - 2 1/2" 7' - 2"
7' - 4 1/2" 14' - 0" 5' - 4"
/2
6' - 4 1/2" 7' - 4"
TYP.
/2
H O
LD
5' - 11 1/2"
HOLD
7' - 6"
TYP.
6' - 9 1/2" 6' - 0"
C4-137
/2
HOLD
7' - 6" 2' - 4 1/2"
2' - 0 1/2"
TYP.
HOLD
7' - 11" 2' - 3"
/2
4' - 0 1/2"
/2
4' - 8 1/2"
/2 "4' - 0 1/2"
4' - 10 1/2"
TYP.
/2
/2
4' - 5"
6' - 11"
TYP.
/2
5' - 11"
/2 " 5' - 0"
6' - 0"
6' - 7" 8' - 0" 2' - 1 1/2"
AREA NOT IN SCOPE OF WORK
SPRINKLERS AND FIRE ALARM
DEVICES ARE EXISTING TO REMAIN
"2' - 11"
5' - 0"
STAIRWELL 8
SW8
6' - 0" 8' - 0" 10' - 0" 2' - 2"
/F2 FX104 /F2 FX104
WALL SYMBOL LEGEND
CONTRACTOR SHALL CONFIRM ALL FIRE RATED WALL ASSEMBLIES
PROPOSED EXTERIOR WALL.
SEE WALL SECTIONS
1 HR FIRE AND SMOKE
BARRIER
2 HR FIRE AND SMOKE
BARRIER (SHAFT)
SMOKE BARRIER PARTITION
DEMOLISHED WALL,
FIXTURE OR FURNISHING
EXISTING WALL, FIXTURE
OR FURNISHING TO REMAIN
NOT IN CONTRACT - NO
WORK SCHEDULED
on e-ei gh th ne fo ot on e-qu ar te r ne fo ot th re e-ei gh th s ne fo ot on e-ha lf ne fo ot th re e-qu ar te r ne fo ot in ch on e ne fo ot on e an d on e-ha lf ne fo ot th re e in ne fo ot
REVISIONS DATE
General Notes:
GENERAL CONTRACTOR AND/OR ALL SUBCONTRACTORS SHALL FIELD VERIFY ALL DIMENSIONS SHOWN ON THESE PLANS AND SHALL BE RESPONSIBLE FOR VARIATIONS BETWEEN PLAN DIMENSIONS AND ACTUAL FIELD DIMENSIONS. WHERE VARIATIONS ARE FOUND TO OCCUR, THE CONTRACTOR SHALL NOTIFY THE PROJECT ENGINEER IN WRITING PRIOR TO PROCEEDING WITH CONSTRUCTION; NO ADJUSTMENT TO
THE WORK WILL BE MADE WITHOUT THE PRIOR APPROVAL OF THE PROJECT ENGINEER.
GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR GENERAL DEMOLITION INCLUDING REMOVAL OF WALLS, PARTITIONS, DOORS & CEILING & FLOORS. ANY AND ALL CUTTING OF CONCRETE FLOORS, WALLS OR STRUCTURE SHALL BE THE GENERAL CONTRACTOR'S RESPONSIBILITY. CORE DRILLING THROUGH CONCRETE WALLS, FLOORS OR STRUCTURE FOR PIPING OR CONDUIT SHALL BE THE RESPONSIBILITY OF THE SUBCONTRACTOR BY TRADE; FIRESTOPPING OF THESE OPENINGS SHALL BE DONE BY THE RESPECTIVE SUBCONTRACTOR. REMOVAL OF DEBRIS RESULTING FROM DEMOLITION, CUTTING, AND/OR DRILLING IS THE RESPONSIBILITY OF THE GENERAL CONTRACTOR. PATCHING AND REPAIR OF CONCRETE WALLS, FLOOR, OR STRUCTURE SHALL BE THE RESPONSIBILITY OF THE GENERAL CONTRACTOR; THIS WILL BE ACCOMPLISHED UPON COMPLETION OF THE INSTALLATION OF ANY AND ALL UTILITIES INSTALLED
BY THE VARIOUS SUBCONTRACTORS.
Approved: Division Chief
Issue Date Checked Drawn
DrawingNumber
Building Number
Project NumberDrawing Title Project Title
Location Drawing Scale
Approved: Service DirectorPlot Scale U.S. Department of Veterans Affairs
Office of Construction and Facilities Management
FULLY SPRINKLERED
Phase
A
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
321 4 5 6 7 8 9 10
TRUE NORTH
PLAN NORTH
KEYPLAN
A/E:
TRIPLE C - The A/E Group
Mat Perkins
(520) 481-8548
A
B D
EF
G
H
J
K
L
M
C
GENERAL NOTES
LINE INDICATES
PHASE 1 SCOPE AREA
B
IM
/6
-2
-1
E x p a n d e d P o ly tr a u m a P ro g ra m P h a s e
/6 -2
-7
.M
P L S
.P O
L Y
T R
A U
M A
.M E
P .B
.L
.r v t
/4
/2
:4
:1
A
M As indicated
04/03/2023 K. Luke K.Hutchinson
618-22-100
1390 - FX104
FIRE PROTECTION PLANS - FOURTH LEVEL -
AREA 4H&4K
1 Veterans Drive, Minneapolis, MN 55417
B70
RENOVATE FOR EXPANDED
POLYTRAUMA PROGRAM - PHASE 1
ISSUED FOR BIDDING
CONTRACTOR SHALL PROVIDE THE FOLLOWING PRIOR TO
COMMENCEMENT OF WORK FOR REVIEW AND APPROVAL:
A. SHOP DRAWING IDENTIFYING MAIN PIPE SIZES AND LOCATIONS,
LOCATION OF PIPE BRACING, HANGERS AND SPRINKLER HEADS
AND DETAILS
B. CUT SHEETS AND SUBMITTAL FOR ALL PIPING, FITTINGS,
SPRINKLER HEADS, HANGERS AND SUPPORT ATTACHMENTS
A. EXISTING CONDITIONS ARE BASED ON EXISTING PLANS AND FIELD VERIFICATION
WHERE FEASIBLE. ACTUAL CONDITIONS MAY DIFFER FROM THOSE INDICATED.
CONTRACTOR SHALL FIELD VERIFY IN ADVANCE THE LOCATION AND CONDITION OF
THE EXISTING SYSTEMS SHOWN TO BE MODIFIED OR REMOVED. CONTRACTOR TO
NOTIFY ARCHITECT SHOULD CONDITIONS BE FOUND TO DIFFER SIGNIFICANTLY
FROM THE CONSTRUCTION DOCUMENTS.
B. DETAILED SCHEDULE, INCLUDING PROJECTED SERVICE INTERRUPTION DATES WITH
DURATIONS, AND DETAILED PHASING PLAN IS TO BE PROVIDED TO THE COR PRIOR
TO THE START OF WORK. THIS SUBMITTAL MUST BE ACCEPTED BY THE COR PRIOR
TO THE START OF WORK.
C. REFER TO ARCHITECTURAL DRAWINGS FOR EXACT DIMENSIONAL DATA, CEILING
HEIGHTS, AND SQUARE FOOTAGE.
D. CONTRACTOR SHALL COORDINATE ALL WORK WITH BUILDING OWNER AND OTHER
TRADES PRIOR TO CONSTRUCTION.
E. ALL PIPING TO BE ROUTED WITHIN CEILING SPACE OR CONCEALED IN FURRED
CHASES UNLESS NOTED OTHERWISE.
F. ALL AREAS ARE DESIGNED AS LIGHT HAZARD OCCUPANCY UNLESS NOTED
OTHERWISE ON PLAN.
G. ALL SPRINKLERS SYSTEMS SHALL BE INSTALLED IN ACCORDANCE WITH THE 2022
NFPA 13.
H. ALL MATERIALS, DEVICES, HANGERS AND SUPPORTS SHALL BE NEW AND UL LISTED
FOR USE IN FIRE PROTECTION SYSTEMS.
I. ALL NEW SPRINKLERS SHALL BE PROVIDED WITH NEW ESCUTCHEONS TO MATCH
EXISTING BUILDING STANDARDS.
J. INSTALL QUICK RESPONSE SPRINKLERS (QRS) IN ALL AREAS, EXCEPT WHERE
SPECIFICALLY PROHIBITED AS DEFINED BY 2022 NFPA 13.
K. PIPING TO BE SCHEDULE 40 BLACK STEEL WITH CAST IRON FITTINGS.
L. ANY FLOOR, WALL, OR CEILING CUTTING OR FILLING THAT IS REQUIRED TO
COMPLETE THIS PROJECT, THE CONTRACTOR SHALL PATCH AND PAINT AND
RETURN TO MATCH EXISTING CONDITIONS AND FINISHES.
M. CONTRACTOR TO PROVIDE GALVANIC PROTECTION AS REQUIRED AT CONNECTIONS
BETWEEN ALL DISSIMILAR METALS.
N. CONTRACTOR TO VALIDATE AND VERIFY ALL FIRE RATED AND/OR SMOKE RATED
WALLS AND ASSEMBLIES INDICATED ON PLANS IN WORK AREA. PROVIDE ALL PIPING
PENETRATIONS OF FIRE, SMOKE AND FULL HEIGHT WALLS SHALL BE CAULKED
AIRTIGHT TO THE ADJACENT STRUCTURE BY MEANS OF U.L. APPROVED FIRE PROOF
CAULKING MATERIAL. CONTRACTOR SHALL PROVIDE SPECIAL INSPECTIONS OF ALL
UL RATED PENETRATIONS BY A LICENSED INSPECTOR.
O. ALL NEW PIPES TO BE CLEANED AND TESTED PRIOR TO COMMISSIONING.
P. THE SPRINKLER CONTRACTOR SHALL COORDINATE AND PERFORM ALL FIRE
PROTECTION WORK IN ACCORDANCE WITH VA REQUIREMENTS TO ENSURE THAT
CONTINUOUS SPRINKLER COVERAGE IS PROVIDED THROUGHOUT THE PROJECT.
THE SPRINKLER CONTRACTOR SHALL COORDINATE ALL FIRE PROTECTION SYSTEM
SHUTDOWNS, INCLUDING POINTS OF TIE IN, ETC. WITH THE VA PRIOR TO
PERFORMING WORK.
Q. CONTRACTOR IS RESPONSIBLE FOR MAINTAINING COMPLIANCE WITH THE 2022
NFPA 13 FOR SURROUNDING SPACES DURING AND AFTER RENOVATION.
CONTRACTOR IS RESPONSIBLE FOR FIELD VERIFYING SPRINKLER HEAD LOCATIONS
AND PIPING TO BE MODIFIED BY THE RENOVATION PRIOR TO COMMENCING WORK.
R. DURING CONSTRUCTION ENSURE ALL SPRINKLERS ARE THE CORRECT DISTANCE
TO THE DECK WHEN THE CEILING IS NOT INSTALLED.
S. ALL SPRINKLER HEADS WILL BE REPLACED DURING THIS PROJECT. ALL SPRINKLER
HEADS TO BE PENDENT TYPE, SEE HAZARD CHART FOR ADDITIONAL INFORMATION.
1. PROVIDE NEW FIRE SUPPRESSION SYSTEM FOR THE RENOVATED AREA. INSTALL
SPRINKLER HEADS AND PIPING HANGERS IN ACCORDANCE WITH THE 2022 NFPA
13. SEE SHEET FX001 FOR ADDITIONAL INFORMATION.
2. EXISTING 6" STAND PIPE, FIRE PROTECTION RISER.
3. EXISTING FIRE SUPPRESSION CONTROL VALVE ASSEMBLY, CONTRACTOR TO
COORDINATE SHUTDOWN WITH COR PRIOR TO COMMENCEMENT OF WORK.
4. EXISTING PIPING DROP FROM INTERSTITIAL SPACE TO PLENUM SPACE BELOW TO
REMAIN, PROTECT IN PLACE.
5. PROVIDE NEW HEAT/SMOKE DETECTOR.
6. PROVIDE NEW FIRE ALARM STROBE/HORN.
7. PROVIDE NEW SPRINKLER HEAD, CONTRACTOR TO ARM OVER TO CLOSEST
EXISTING SPRINKLER PIPING. REFER TO FIRE PROTECTION SPRINKLER SYSTEM
DESIGN CRITERIA CHART FOR SPRINKLER TYPE BASED ON HAZARD
CLASSIFICATION PER ROOM. SPRINKLER HEADS AND FIRE ALARM DEVICES TO BE
CENTERED IN CEILING GRID TILES UNLESS OTHERWISE DIMENSIONED OR NOTED.
COORDINATE FINAL SPRINKLER HEAD AND FIRE ALARM DEVICE LOCATIONS WITH
FINAL LOCATIONS OF THE CEILING GRID TILES. SEE ARCHITECTURAL RCP FOR
ADDITIONAL INFORMATION AND COORDINATION WITH SPRINKLER HEADS, FIRE
ALARM DEVICES AND ARCHITECTURAL CEILING GRID. CONTRACTOR MUST
MAINTAIN REQUIREMENTS WITH THE 2022 NFPA FOR REQUIRED DIMENSIONS FOR
SPRINKLER HEAD LOCATIONS AT ALL TIMES.
8. ARCHITECTURAL FRAMING/WALLS FOR CEILING BULKHEADS, FOR REFERENCE
ONLY. SEE ARCHITECTURAL CEILING PLANS FOR ADDITIONAL INFORMATION.
9. EXISTING 2-1/2" FDV, T CAP AND PIPING CONNECTED TO STANDPIPE ARE LOCATED
IN PLENUM SPACE AND ARE EXISTING TO REMAIN. PROTECT IN PLACE. SHOWN ON
RCP LEVEL FOR COORDINATION AND REFERENCE ONLY.
10. PROVIDE NEW F.V.C FOR THE RENOVATED AREA.
NOTE: NOT ALL KEYNOTES
ARE USED ON EACH SHEET
1/8" = 1'-0" F2
FIRE PROTECTION RCP - FOURTH LEVEL - AREA H
1/8" = 1'-0"
F6
FIRE PROTECTION RCP - FOURTH LEVEL - AREA 4K
KEYNOTES
FATC 5
(E)
FA - 1FA - 2FA - 3FA - 4FA - 5FA - 6FA - 7FA - 8FA - 9FA - 10FA - 11FA - 12FA - 13FA - 14FA - 15FA - 16FA - 17FA - 18FA - 19FA - 20FA - 21FA - 22FA - 23FA - 24FA - 25FA - 27FA - 28FA - 29FA - 30FA - 31FA - 32FA - 33FA - 34FA - 35FA - 36FA - 37FA - 38FA - 39FA - 40FA - 41
FA - 42FA - 43FA - 44FA - 45FA - 46FA - 47FA - 48FA - 49FA - 50FA - 51FA - 52
SP - 1SP - 2SP - 3SP - 4SP - 5SP - 6SP - 7SP - 8SP - 9SP - 10SP - 11SP - 12SP - 13SP - 14SP - 15SP - 16SP - 17
(E) FATC 6
(E) FATC 4
BPS5
(E)
(E) FATC 6
EOL
(N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N)
(N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N)(N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N)
(N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N)
(N) (N) (N) (N) (N) (N)
Note: Provide new duct mounted smoke detectors and fire smoke dampers per mechanical drawings.
Provide fire alarm control points per the schedule above.
(N) (N) (N) (N) (N)(N) (N)
SP - 18SP - 19SP - 20SP - 21SP - 22SP - 25SP - 26
FA - 53FA - 54FA - 55FA - 56FA - 57FA - 58FA - 59FA - 60FA - 61FA - 64FA - 65FA - 66FA - 67FA - 68FA - 69FA - 70FA - 71FA - 72FA - 73FA - 74FA - 75FA - 76FA - 77FA - 78FA - 79
(N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N)(N) (N) (N) (N) (N) (N) (N) (N) (N) (N) (N) on e-ei gh th ne fo ot on e-qu ar te r ne fo ot th re e-ei gh th s ne fo ot on e-ha lf ne fo ot th re e-qu ar te r ne fo ot in ch on e ne fo ot on e an d on e-ha lf ne fo ot th re e in ne fo ot
REVISIONS DATE
General Notes:
GENERAL CONTRACTOR AND/OR ALL SUBCONTRACTORS SHALL FIELD VERIFY ALL DIMENSIONS SHOWN ON THESE PLANS AND SHALL BE RESPONSIBLE FOR VARIATIONS BETWEEN PLAN DIMENSIONS AND ACTUAL FIELD DIMENSIONS. WHERE VARIATIONS ARE FOUND TO OCCUR, THE CONTRACTOR SHALL NOTIFY THE PROJECT ENGINEER IN WRITING PRIOR TO PROCEEDING WITH CONSTRUCTION; NO ADJUSTMENT TO
THE WORK WILL BE MADE WITHOUT THE PRIOR APPROVAL OF THE PROJECT ENGINEER.
GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR GENERAL DEMOLITION INCLUDING REMOVAL OF WALLS, PARTITIONS, DOORS & CEILING & FLOORS. ANY AND ALL CUTTING OF CONCRETE FLOORS, WALLS OR STRUCTURE SHALL BE THE GENERAL CONTRACTOR'S RESPONSIBILITY. CORE DRILLING THROUGH CONCRETE WALLS, FLOORS OR STRUCTURE FOR PIPING OR CONDUIT SHALL BE THE RESPONSIBILITY OF THE SUBCONTRACTOR BY TRADE; FIRESTOPPING OF THESE OPENINGS SHALL BE DONE BY THE RESPECTIVE SUBCONTRACTOR. REMOVAL OF DEBRIS RESULTING FROM DEMOLITION, CUTTING, AND/OR DRILLING IS THE RESPONSIBILITY OF THE GENERAL CONTRACTOR. PATCHING AND REPAIR OF CONCRETE WALLS, FLOOR, OR STRUCTURE SHALL BE THE RESPONSIBILITY OF THE GENERAL CONTRACTOR; THIS WILL BE ACCOMPLISHED UPON COMPLETION OF THE INSTALLATION OF ANY AND ALL UTILITIES INSTALLED
BY THE VARIOUS SUBCONTRACTORS.
Approved: Division Chief
Issue Date Checked Drawn
DrawingNumber
Building Number
Project NumberDrawing Title Project Title
Location Drawing Scale
Approved: Service DirectorPlot Scale U.S. Department of Veterans Affairs
Office of Construction and Facilities Management
FULLY SPRINKLERED
Phase
A
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
321 4 5 6 7 8 9 10
TRUE NORTH
PLAN NORTH
KEYPLAN
A/E:
TRIPLE C - The A/E Group
Mat Perkins
(520) 481-8548
A
B D
EF
G
H
J
K
L
M
C
LINE INDICATES
PHASE 1 SCOPE AREA
B
IM
/6
-2
-1
E x p a n d e d P o ly tr a u m a P ro g ra m P h a s e
/6 -2
-7
.M
P L S
.P O
L Y
T R
A U
M A
.G e n e ra l.
S h e e ts
.r v t
/3
/2
:4
:0
P
M As indicated
04/03/2023 K. Luke N.Wicklund
618-22-100
1390 - FX501
FIRE PROTECTION DETAILS AND
SCHEDULES
1 Veterans Drive, Minneapolis, MN 55417
B70
RENOVATE FOR EXPANDED
POLYTRAUMA PROGRAM
ISSUED FOR BIDDING
NTS
F3
FIRE ALARM RISER
NTS
C2
FIRE PROTECTION WIRE SCHEDULE
on e-ei gh th ne fo ot on e-qu ar te r ne fo ot th re e-ei gh th s ne fo ot on e-ha lf ne fo ot th re e-qu ar te r ne fo ot in ch on e ne fo ot on e an d on e-ha lf ne fo ot th re e in ne fo ot
REVISIONS DATE
General Notes:
GENERAL CONTRACTOR AND/OR ALL SUBCONTRACTORS SHALL FIELD VERIFY ALL DIMENSIONS SHOWN ON THESE PLANS AND SHALL BE RESPONSIBLE FOR VARIATIONS BETWEEN PLAN DIMENSIONS AND ACTUAL FIELD DIMENSIONS. WHERE VARIATIONS ARE FOUND TO OCCUR, THE CONTRACTOR SHALL NOTIFY THE PROJECT ENGINEER IN WRITING PRIOR TO PROCEEDING WITH CONSTRUCTION; NO ADJUSTMENT TO
THE WORK WILL BE MADE WITHOUT THE PRIOR APPROVAL OF THE PROJECT ENGINEER.
GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR GENERAL DEMOLITION INCLUDING REMOVAL OF WALLS, PARTITIONS, DOORS & CEILING & FLOORS. ANY AND ALL CUTTING OF CONCRETE FLOORS, WALLS OR STRUCTURE SHALL BE THE GENERAL CONTRACTOR'S RESPONSIBILITY. CORE DRILLING THROUGH CONCRETE WALLS, FLOORS OR STRUCTURE FOR PIPING OR CONDUIT SHALL BE THE RESPONSIBILITY OF THE SUBCONTRACTOR BY TRADE; FIRESTOPPING OF THESE OPENINGS SHALL BE DONE BY THE RESPECTIVE SUBCONTRACTOR. REMOVAL OF DEBRIS RESULTING FROM DEMOLITION, CUTTING, AND/OR DRILLING IS THE RESPONSIBILITY OF THE GENERAL CONTRACTOR. PATCHING AND REPAIR OF CONCRETE WALLS, FLOOR, OR STRUCTURE SHALL BE THE RESPONSIBILITY OF THE GENERAL CONTRACTOR; THIS WILL BE ACCOMPLISHED UPON COMPLETION OF THE INSTALLATION OF ANY AND ALL UTILITIES INSTALLED
BY THE VARIOUS SUBCONTRACTORS.
Approved: Division Chief
Issue Date Checked Drawn
DrawingNumber
Building Number
Project NumberDrawing Title Project Title
Location Drawing Scale
Approved: Service DirectorPlot Scale U.S. Department of Veterans Affairs
Office of Construction and Facilities Management
FULLY SPRINKLERED
Phase
A
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
321 4 5 6 7 8 9 10
TRUE NORTH
PLAN NORTH
KEYPLAN
A/E:
TRIPLE C - The A/E Group
Mat Perkins
(520) 481-8548
A
B D
EF
G
H
J
K
L
M
C
LINE INDICATES
PHASE 1 SCOPE AREA
B
IM
/6
-2
-1
E x p a n d e d P o ly tr a u m a P ro g ra m P h a s e
/6 -2
-7
.M
P L S
.P O
L Y
T R
A U
M A
.G e n e ra l.
S h e e ts
.r v t
/3
/2
:4
:0
P
M As indicated
04/03/2023 K. Luke K.Hutchinson
618-22-100
1390 - FX502
FIRE PROTECTION DETAILS AND
SCHEDULES
1 Veterans Drive, Minneapolis, MN 55417
B70
RENOVATE FOR EXPANDED
POLYTRAUMA PROGRAM
ISSUED FOR BIDDING
NTS
E1
FIRE PROTECTION LABELING
NTS
B5
HORN-STROBE DETAIL
NTS
B1
SMOKE/HEAT DETECTOR DETAIL
NOT TO SCALE
D5
FIRE ALARM MOUNTING DEVICE LOCATIONS
on e-ei gh th ne fo ot on e-qu ar te r ne fo ot th re e-ei gh th s ne fo ot on e-ha lf ne fo ot th re e-qu ar te r ne fo ot in ch on e ne fo ot on e an d on e-ha lf ne fo ot th re e in ne fo ot
REVISIONS DATE
General Notes:
GENERAL CONTRACTOR AND/OR ALL SUBCONTRACTORS SHALL FIELD VERIFY ALL DIMENSIONS SHOWN ON THESE PLANS AND SHALL BE RESPONSIBLE FOR VARIATIONS BETWEEN PLAN DIMENSIONS AND ACTUAL FIELD DIMENSIONS. WHERE VARIATIONS ARE FOUND TO OCCUR, THE CONTRACTOR SHALL NOTIFY THE PROJECT ENGINEER IN WRITING PRIOR TO PROCEEDING WITH CONSTRUCTION; NO ADJUSTMENT TO
THE WORK WILL BE MADE WITHOUT THE PRIOR APPROVAL OF THE PROJECT ENGINEER.
GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR GENERAL DEMOLITION INCLUDING REMOVAL OF WALLS, PARTITIONS, DOORS & CEILING & FLOORS. ANY AND ALL CUTTING OF CONCRETE FLOORS, WALLS OR STRUCTURE SHALL BE THE GENERAL CONTRACTOR'S RESPONSIBILITY. CORE DRILLING THROUGH CONCRETE WALLS, FLOORS OR STRUCTURE FOR PIPING OR CONDUIT SHALL BE THE RESPONSIBILITY OF THE SUBCONTRACTOR BY TRADE; FIRESTOPPING OF THESE OPENINGS SHALL BE DONE BY THE RESPECTIVE SUBCONTRACTOR. REMOVAL OF DEBRIS RESULTING FROM DEMOLITION, CUTTING, AND/OR DRILLING IS THE RESPONSIBILITY OF THE GENERAL CONTRACTOR. PATCHING AND REPAIR OF CONCRETE WALLS, FLOOR, OR STRUCTURE SHALL BE THE RESPONSIBILITY OF THE GENERAL CONTRACTOR; THIS WILL BE ACCOMPLISHED UPON COMPLETION OF THE INSTALLATION OF ANY AND ALL UTILITIES INSTALLED
BY THE VARIOUS SUBCONTRACTORS.
Approved: Division Chief
Issue Date Checked Drawn
DrawingNumber
Building Number
Project NumberDrawing Title Project Title
Location Drawing Scale
Approved: Service DirectorPlot Scale U.S. Department of Veterans Affairs
Office of Construction and Facilities Management
FULLY SPRINKLERED
Phase
A
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
321 4 5 6 7 8 9 10
TRUE NORTH
PLAN NORTH
KEYPLAN
A/E:
TRIPLE C - The A/E Group
Mat Perkins
(520) 481-8548
A
B D
EF
G
H
J
K
L
M
C
LINE INDICATES
PHASE 1 SCOPE AREA
B
IM
/6
-2
-1
E x p a n d e d P o ly tr a u m a P ro g ra m P h a s e
/6 -2
-7
.M
P L S
.P O
L Y
T R
A U
M A
.G e n e ra l.
S h e e ts
.r v t
/3
/2
:4
:1
P
M
04/03/2023 K. Luke K.Hutchinson
618-22-100
1390 - FX901
FIRE PROTECTION CUTSHEETS & BASIS OF
DESIGN
1 Veterans Drive, Minneapolis, MN 55417
B70
RENOVATE FOR EXPANDED
POLYTRAUMA PROGRAM
ISSUED FOR BIDDING