This solicitation is for a construction project to renovate and expand the Polytrauma program at the Minneapolis Veterans Affairs Medical Center (VAMC). The project scope includes general construction, electrical, plumbing and other trades to consolidate Polytrauma care services. As a total small business set-aside, only verified Service-Disabled Veteran-Owned Small Businesses (SDVOSBs) may submit offers. The construction magnitude is estimated between $10-20 million. The solicitation is issued by the Department of Veterans Affairs Veterans Health Administration VISN 23. Pricing must include all applicable taxes.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VA Minneapolis Healthcare System
Project Number: 618-22-100
Renovate for Expanded Polytrauma Program - Phase 1 Construction Documents 100% Issued for Bidding
PROJECT MANUAL
Prepared For:
VA Minneapolis Healthcare System 1 Veterans Drive Minneapolis, MN 55417
Prepared By:
Triple C - The A&E Group
121 Washington Ave., N. Suite 400<MyCompanyAddress2>
Laramie, WY 82070
400<
Laramie, WY 82070
OJECT MANUAL
/03
/20
09/12/2022
04/03/2023
Renovate for Expanded Polytrauma Program - Phase 1 Project #: 618-22-100
000110 - 1
VA MINNEAPOLIS HEALTHCARE SYSTEM
RENOVATE FOR EXPANDED POLYTRAUMA PROGRAM - PHASE 1
TABLE OF CONTENTS
SECTION 000110
SECTIONS DIVISION AND SECTION TITLES DATE
DIVISION 00 — SPECIAL SECTIONS
000110 Table of Contents 06-2021 000115 List of Drawing Sheets 06-2020
DIVISION 01 — GENERAL REQUIREMENTS
010000 GENERAL REQUIREMENTS 01-2021
013216.01 ARCHITECTURAL AND ENGINEERING CPM SCHEDULES 03-2020
013216.15 PROJECT SCHEDULES 03-2020
013323 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES 06-2021
013324 ELECTRONIC SUBMITTAL PROCEDURES
013526 SAFETY REQUIREMENTS 07-2020
014219 REFERENCE STANDARDS 11-2020
014500 QUALITY CONTROL 05-2021
014529 TESTING LABORATORY SERVICES 11-2011
014535 SPECIAL INSPECTIONS 06-2021
014535.01 Schedule of Special Inspections Template 04-2018
015719 TEMPORARY ENVIRONMENTAL CONTROLS 01-2021
015816 TEMPORARY INTERIOR SIGNAGE 07-2015
017419 CONSTRUCTION WASTE MANAGEMENT 01-2021
018113 SUSTAINABLE CONSTRUCTION REQUIREMENTS 10-2017
019100 GENERAL COMMISSIONING REQUIREMENTS 10-2015
DIVISION 02 — EXISTING CONDITIONS
024100 DEMOLITION 08-2017
DIVISION 03 — CONCRETE
033053 (SHORT-FORM) CAST-IN-PLACE CONCRETE 01-2021
DIVISION 04 — MASONRY
NOT USED
DIVISION 05 — METALS
054000 COLD-FORMED METAL FRAMING 01-2021
055000 METAL FABRICATIONS 08-2018
DIVISION 06 — WOOD, PLASTICS, AND COMPOSITES
061000 ROUGH CARPENTRY 10-2017
062000 FINISH CARPENTRY 08-2018
DIVISION 07 — THERMAL AND MOISTURE PROTECTION
071300 SHEET WATERPROOFING 01-2021
078400 FIRESTOPPING 01-2021
079200 JOINT SEALANTS 04-2022
079513 Expansion Joint Covers
DIVISION 08 — OPENINGS
081113 HOLLOW METAL DOORS AND FRAMES 01-2021
000110 - 2
081400 INTERIOR WOOD DOORS 01-2021
081710 INTEGRATED DOOR ASSEMBLIES 01-2021
083113 ACCESS DOORS AND FRAMES 01-2021
083213 ICU SLIDING GLASS DOORS 01-2021
083616.13 High Performance Barn (Sliding) Door
087100 DOOR HARDWARE 05/2022
087113 AUTOMATIC DOOR OPERATORS 01-2021
088000 GLAZING 01-2021
089000 LOUVERS AND VENTS 01-2021
DIVISION 09 — FINISHES
090516 SUBSURFACE PREPARATION FOR FLOOR FINISHES 01-2021
092216 NON-STRUCTURAL METAL FRAMING 06-2018
092900 GYPSUM BOARD 04-2020
093013 CERAMICPORCELAIN TILING 01-2021
095100 ACOUSTICAL CEILINGS 12-2018
095416 Luminous Feature Ceiling Panels 095426 Suspended Wood Ceilings
096513 RESILIENT BASE AND ACCESSORIES 01-2021
096516 RESILIENT SHEET FLOORING 05-2018
096519 RESILIENT TILE FLOORING 05-2018
099100 PAINTING 01-2021
DIVISION 10 — SPECIALTIES
101113 CHALKBOARDS AND MARKERBOARDS 01-2021
101133 GLASSBOARDS (MAGNETIC & NON-MAGNETIC) 01-2021
101400 SIGNAGE 01-2021
102113 Toilet Compartments 01-2021
102123 CUBICLE CURTAIN TRACKS 01-2021
102513 PATIENT BED SERVICE WALLS 01-2020
102600 WALL AND DOOR PROTECTION 01-2021
102800 TOILET, BATH, AND LAUNDRY ACCESSORIES 01-2021
104413 FIRE EXTINGUISHER CABINETS 08-2018
105100 Metal Lockers
DIVISION 11 — EQUIPMENT
117300 CEILING MOUNTED PATIENT LIFT SYSTEM 08-2020
DIVISION 12 — FURNISHINGS
122400 WINDOW SHADES 08-2017
122421 LIGHTPROOF SHADES 01-2021
123200 MANUFACTURED WOOD CASEWORK 01-2021
123600 COUNTERTOPS 12-2018
DIVISION 13 — SPECIAL CONSTRUCTION
NOT USED
DIVISION 14 — CONVEYING EQUIPMENT
149200 PNEUMATIC TUBE SYSTEM
DIVISION 20 — MECHANICAL SUPPORT
NOT USED
DIVISION 21 — FIRE SUPPRESSION
210800 COMMISSIONING OF FIRE SUPPRESSION SYSTEMS 11-2016
211313 WET-PIPE SPRINKLER SYSTEMS 06-2015
DIVISION 22 — PLUMBING
220511 COMMON WORK RESULTS FOR PLUMBING 09-2020
220519 Meters and Gauges for Plumbing Piping 09-2020
000110 - 3
220523 GENERAL-DUTY VALVES FOR PLUMBING PIPING 09-2019
220711 PLUMBING INSULATION 09-2019
220800 COMMISSIONING OF PLUMBING SYSTEMS 11-2016
221100 FACILITY WATER DISTRIBUTION 05-2021
221300 FACILITY SANITARY AND VENT PIPING 09-2020
224000 PLUMBING FIXTURES 09-2015
226200 VACUUM SYSTEMS FOR LABORATORY AND HEALTHCARE FACILITIES 09-2015
226300 GAS SYSTEMS FOR LABORATORY AND HEALTHCARE FACILITIES 09-2015
226600 CHEMICAL-WASTE SYSTEMS FOR LABORATORY AND HEALTHCARE
FACILITIES 09-2020
DIVISION 23 — HEATING VENTILATING AND AIR CONDITIONING
230511 COMMON WORK RESULTS FOR HVAC 02-2020
230512 GENERAL MOTOR REQUIREMENTS FOR HVAC AND STEAM GENERATION
EQUIPMENT 02-2020
230541 NOISE AND VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT 02-2020
230593 TESTING, ADJUSTING, AND BALANCING FOR HVAC 02-2020
230711 HVAC AND BOILER PLANT INSULATION 02-2020
230800 COMMISSIONING OF HVAC SYSTEMS 02-2020
230923 DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC 08-2020
232113 HYDRONIC PIPING 02-2020
232123 HYDRONIC PUMPS 02-2020
232213 STEAM AND CONDENSATE HEATING PIPING 02-2020
232500 HVAC WATER TREATMENT 02-2020
233100 HVAC DUCTS AND CASINGS 02-2020
233400 HVAC FANS 02-2020
233600 AIR TERMINAL UNITS 02-2020
233700 AIR OUTLETS AND INLETS 02-2020
234000 HVAC AIR CLEANING DEVICES 03-2020
237300 INDOOR CENTRAL-STATION AIR-HANDLING UNITS 03-2020
238200 CONVECTION HEATING AND COOLING UNITS 03-2020
238216 AIR COILS 03-2020
DIVISION 25 — INTEGRATED AUTOMATION
251010 ADVANCED UTILITY METERING SYSTEM 02-2010
DIVISION 26 — ELECTRICAL
260511 REQUIREMENTS FOR ELECTRICAL INSTALLATIONS 01-2016
260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 01-2017
260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 01-2017
260533 RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS 01-2018
260573 OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY 01-2018
260800 COMMISSIONING OF ELECTRICAL SYSTEMS 11-2016
260923 LIGHTING CONTROLS 01-2018
262200 LOW-VOLTAGE TRANSFORMERS 01-2018
262416 PANELBOARDS 01-2018
262726 WIRING DEVICES 01-2018
262911 MOTOR CONTROLLERS 01-2018
262921 ENCLOSED SWITCHES AND CIRCUIT BREAKERS 01-2017
264100 FACILITY LIGHTNING PROTECTION 01-2017
264313 SURGE PROTECTIVE DEVICES 01-2017
265100 INTERIOR LIGHTING 01-2018
DIVISION 27 — COMMUNICATIONS
270511 REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS 09-2019
270526 GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS 06-2015
270533 RACEWAYS AND BOXES FOR COMMUNICATIONS SYSTEMS 10-2018
270800 COMMISSIONING OF COMMUNICATIONS SYSTEMS 11-2016
000110 - 4
271000 CONTROL, COMMUNICATION AND SIGNAL WIRING 06-2015
271100 TELECOMMUNICATIONS ROOM FITTINGS
271500 COMMUNICATIONS STRUCTURED CABLING 01-2016
274131 MASTER ANTENNA TELEVISION EQUIPMENT AND SYSTEMS 06-2015
275116 PUBLIC ADDRESS AND MASS NOTIFICATION SYSTEMS 10-2018
275123 INTERCOMMUNICATIONS AND PROGRAM SYSTEMS 06-2015
275223 NURSE CALL AND CODE BLUE SYSTEMS 12-2020
DIVISION 28 — ELECTRONIC SAFETY AND SECURITY
280500 COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY 04-2018
280513 CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY 10-
280526 GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY 09-
280528.33 CONDUITS AND BACKBOXES FOR ELECTRONIC SAFETY AND SECURITY 09-
280800 COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS 11-2016
281300 PHYSICAL ACCESS CONTROL SYSTEM 10-2011
282300 VIDEO SURVEILLANCE 09-2011
282313 VIDEO SURVEILLANCE CONTROL, MANAGEMENT AND STORAGE SYSTEM
282600 ELECTRONIC PERSONAL PROTECTION SYSTEM 09-2011
283100 FIRE DETECTION AND ALARM 10-2011
283100 FIRE DETECTION AND ALARM - EXTENSION
285000 SECURITY MANAGEMENT SYSTEM
DIVISION 31 — EARTHWORK
NOT USED
DIVISION 32 — EXTERIOR IMPROVEMENTS
NOT USED
DIVISION 33 — UTILITIES
NOT USED
DIVISION 34 — TRANSPORTATION
NOT USED
DIVISION 35 — WATERWAYS AND MARINE CONSTRUCTION
NOT USED
DIVISION 40 — PROCESS INTERCONNECTIONS
NOT USED
DIVISION 41 — MATERIAL PROCESSING AND HANDLING EQUIPMENT
NOT USED
DIVISION 42 — PROCESS HEATING, COOLING, AND DRYING EQUIPMENT
NOT USED
DIVISION 43 — PROCESS GAS AND LIQUID HANDLING, PURIFICATION AND
STORAGE EQUIPMENT
NOT USED
DIVISION 44 — POLLUTION CONTROL EQUIPMENT
NOT USED
DIVISION 45 — INDUSTRY-SPECIFIC MANUFACTURING EQUIPMENT
NOT USED
DIVISION 46 — WATER AND WASTEWATER EQUIPMENT
NOT USED
DIVISION 48 — ELECTRICAL POWER GENERATION
000110 - 5
NOT USED
This page intentionally left blank.
List of Drawing Sheets
000115 - 1
SECTION 000115
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GENERAL
GI000 COVER SHEET
GI050 GENERAL NOTES
GI100 ARCHITECTURAL 4TH FLOOR EXISTING CONDITIONS PLAN
GI104 LIFE SAFETY PLAN - LEVEL 4 - PHASE 1
GI200 SITE MAP – GROUND LEVEL – PHASE 1
GI204 PHASING PLAN - LEVEL 4 - PHASE 1
GI304 ICRA & PHASING PLAN - LEVEL 4 - PHASE 1
GI314 ICRA & PHASING PLAN - LEVEL 4 - PHASE 1
ARCHITECTURAL
A-001 SYMBOLS & GENERAL NOTES
A-002 ARCHITECTURAL ROOM PROGRAM PLAN - OVERALL
MASTERPLAN
A-003 ARCHITECTURAL ROOM PROGRAM PLAN - PHASE 1
RENOVATION
AD104 ARCHITECTURAL DEMOLITION PLAN - LEVEL 4 - 4H/4K
AD124 ARCHITECTURAL DEMOLITION RCP- LEVEL 4 - 4H/4K
A-104 ARCHITECTURAL FLOOR PLAN - LEVEL 4 - 4H/4K NEW
A-124 ARCHITECTURAL DIMENSIONING PLAN - FOURTH FLOOR
4H/4K
AC104 REFLECTED CEILING PLAN - FIRST FLOOR
AC124 ARCHITECTURAL ENLARGED CEILING PLANS
A-401 ARCHITECTURAL ENLARGED VIEWS - TYPICAL PATIENT
ROOM
A-402 ARCHITECTURAL ENLARGED VIEWS - BARIATRIC PATIENT
ROOM
A-403 ARCHITECTURAL ENLARGED VIEWS
A-404 ARCHITECTURAL ENLARGED VIEWS
A-405 ARCHITECTURAL ENLARGED VIEWS
A-406 ARCHITECTURAL ENLARGED VIEWS
A-410 TYPICAL PATIENT CASEWORK DETAILS
A-512 ARCHITECTURAL DETAILS
A-551 ARCHITECTURAL CEILING DETAILS
A-552 ARCHITECTURAL CASEWORK DETAILS
A-601 DOOR & WINDOW SCHEDULES
A-610 SLIDING DOOR DETAILS
A-720 STANDARD PARTITION TYPES
A-721 PARTITION FRAMING DETAILS
A-730 TYPICAL MOUNTING HEIGHTS
ARCHITECTURAL SIGNAGE
AW001 ARCHITECTURAL SIGNAGE ABBREVIATIONS, SYMBOLS,
GENERAL NOTES AND SCHEDULE
AW104 ARCHITECTURALSIGNAGE PLAN - FOURTH FLOOR 4H/4K
INTERIORS
IN001 INTERIOR GENERAL NOTES, SYMBOLS, ABBREVIATIONS &
FINISH BOARDS
IN104 INTERIOR FLOOR FINISH PLAN - FOURTH FLOOR 4H/4K
000115 - 2
IN124 INTERIOR WALL FINISH PLAN - FOURTH FLOOR 4H/4K
IN501 DETAILS - INTERIOR FINISH
IN601 INTERIOR FINISH LEGEND AND ROOM FINISH SCHEDULE
IN901 INTERIOR 3D CONCEPT IMAGES
EQUIPMENT
Q-104 INTERIOR EQUIPMENT & FURNITURE PLAN - OVERALL
Q-401 INTERIOR EQUIPMENT & FURNITURE PLAN - ENLARGED
VIEW
Q-402 INTERIOR EQUIPMENT & FURNITURE PLAN - ENLARGED
VIEW
Q-601 EQUIPMENT SCHEDULE
FIRE PROTECTION
FX001 FIRE PROTECTION ABBREVIATIONS, SYMBOLS, AND
DETAILS
FXD104 FIRE PROTECTION DEMO PLANS - FOURTH LEVEL - AREA
4H&4K FXD104i FIRE PROTECTION DEMO PLANS - FOURTH LEVEL
INTERSTITIAL - AREA 4H&K
FX104 FIRE PROTECTION PLANS - FOURTH LEVEL - AREA 4H&4K
FX501 FIRE PROTECTION DETAILS AND SCHEDULES
FX502 FIRE PROTECTION DETAILS AND SCHEDULES
FX901 FIRE PROTECTION CUTSHEETS & BASIS OF DESIGN
PLUMBING
P-001 PLUMBING LEGEND
PD103i PLUMBING PLANS - THIRD LEVEL INTERSTITIAL 3D - DEMO
PD104 PLUMBING DEMO PLANS - FOURTH LEVEL - AREA 4H&4K
PD104i PLUMBING PLANS - FOURTH LEVEL INTERSTITIAL 2D -
DEMO
PGD-104i PLUMBING MED GAS PLANS - FOURTH LEVEL
INTERSTITIAL - DEMO
P-103i SANITARY PLANS - THIRD LEVEL INTERSTITIAL - AREA
3H&3K
P-104 PLUMBING PLANS - FOURTH LEVEL - AREA 4H&4K
P-104i PLUMBING PLANS - FOURTH LEVEL INTERSTITIAL - NEW
VENT PIPING PLAN
PP-104i PLUMBING PLANS - FOURTH LEVEL INTERSTITIAL - NEW
DOMESTIC WATER PIPING PLAN
PG104i MED GAS PLUMBING PLANS - FOURTH LEVEL
INTERSTITIAL
P-501 PLUMBING DETAILS
P-601 PLUMBING ISOMETRIC PLAN – NORTH
P-602 PLUMBING ISOMETRIC PLAN - SOUTH
P-701 PLUMBING SCHEDULES
P-901 PLUMBING EQUIPMENT CUTSHEETS / BASIS OF DESIGN
P-902 PLUMBING EQUIPMENT CUTSHEETS / BASIS OF DESIGN
P-903 PLUMBING EQUIPMENT CUTSHEETS / BASIS OF DESIGN
P-904 PLUMBING EQUIPMENT CUTSHEETS / BASIS OF DESIGN
MECHANICAL
M-001 MECHANICAL ABBREVIATIONS AND SYMBOLS
MD-104 MECHANICAL DEMO PLAN - FOURTH LEVEL - AREA 4H&4K
MD-104i MECHANICAL DEMO PLANS - FOURTH LEVEL INTERSTITIAL
- AREA 4K
M-104 MECHANICAL PLANS - FOURTH LEVEL - AREA 4H&4K
M-104i MECHANICAL PLANS - FOURTH LEVEL INTERSTITIAL -
AREA 4H&4K
000115 - 3
MPD-103i MECHANICAL PIPING DEMOVPLAN - THIRD LEVEL
INTERSTITIAL - AREA 3K
MPD-104 MECHANICAL PIPING DEMO PLAN - FOURTH LEVEL - AREA
4H&4K
MPD-104i MECHANICAL PIPING DEMO PLAN - FOURTH LEVEL
INTERSTITIAL - AREA 4H&4K
MP-103i MECHANICAL PIPING PLAN - THIRD LEVEL INTERSTITIAL -
AREA 4H&4K
MP-104 MECHANICAL PIPING PLAN - FOURTH FLOOR - AREA
4H&4K
MP-104i MECHANICAL PIPING PLAN - FOURTH FLOOR
INTERSTITIAL - AREA 4H&4K
M-400 ENLARGED MECHANICAL PLANS
M-401 ENLARGED MECHANICAL PLANS
M-501 MECHANICAL DETAILS
M-502 MECHANICAL DETAILS
M-503 MECHANICAL DETAILS
M-504 MECHANICAL DETAILS
M-505 MECHANICAL DETAILS
M-700 MECHANICAL SCHEDULES
M-701 MECHANICAL SCHEDULES
M-702 MECHANICAL SCHEDULES
M-801 MECHANICAL CONTROL SYMBOL LEGEND AND
ABBREVIATIONS
M-802 MECHANICAL CONTROL DIAGRAMS
M-803 MECHANICAL CONTROL DIAGRAMS
M-804 MECHANICAL CONTROL DIAGRAMS
M-805 MECHANICAL CONTROL DIAGRAMS
M-806 MECHANICAL POINTS SCHEDULE
M-901 MECHANICAL CUTSHEETS & BASIS OF DESIGN
M-902 MECHANICAL CUTSHEETS & BASIS OF DESIGN
M-903 MECHANICAL CUTSHEETS & BASIS OF DESIGN
ELECTRICAL
E-001 ELECTRICAL ABBREVIATIONS AND SYMBOLS
EDL104 ELECTRICAL DEMO LIGHTING RCP - FOURTH LEVEL -
AREA 4H&4K
EDP104 ELECTRICAL DEMO POWER PLANS- FOURTH LEVEL -
4H&4K EDP104i ELECTRICAL DEMO POWER PLAN - FOURTH LEVEL
INTERSTITIAL - AREA 4H & 4K
EL104 ELECTRICAL LIGHTING RCP - FOURTH LEVEL - AREA
4H&4K
EP103 ELECTRICAL POWER PLANS - THIRD LEVEL - AREA 3K
EP104 ELECTRICAL POWER PLANS - FOURTH LEVEL - AREA
4H&4K EP104i ELECTRICAL POWER PLANS - FOURTH LEVEL - AREA
4H&4K INTERSTITIAL
EP400 ELECTRICAL ENLARGED PLANS
E-501 ELECTRICAL DETAILS
E-601 ELECTRICAL ONE-LINE DIAGRAM DEMO - FOURTH LEVEL -
AREA 4H&4K
E-602 ELECTRICAL ONE-LINE DIAGRAMS NEW - FOURTH LEVEL -
AREA 4H&4K
E-603 ELECTRICAL DIAGRAMS
E-701 ELECTRICAL PANEL SCHEDULES - EXISTING
E-702 ELECTRICAL PANEL SCHEDULES - EXISTING
000115 - 4
E-703 ELECTRICAL PANEL SCHEDULES - NEW
E-704 ELECTRICAL PANEL SCHEDULES - NEW
E-705 ELECTRICAL PANEL SCHEDULES - NEW
E-901 ELECTRICAL CUTSHEETS & BASIS OF DESIGN
E-902 ELECTRICAL CUTSHEETS & BASIS OF DESIGN
E-903 ELECTRICAL CUTSHEETS & BASIS OF DESIGN
E-904 ELECTRICAL CUTSHEETS & BASIS OF DESIGN
E-905 ELECTRICAL CUTSHEETS & BASIS OF DESIGN
E-906 ELECTRICAL CUTSHEETS & BASIS OF DESIGN
TELECOMMUNICATION
T-001 TELECOMMUNICATION ABBREVIATIONS AND SYMBOLS
TD104 TELECOMMUNICATIONS DEMO PLANS- FOURTH LEVEL -
4H&4K TD104i TELECOMMUNICATION DEMO PLANS - FOURTH LEVEL
INTERSTITIAL - AREA 4H&4K
TY104 SECURITY PLANS - FOURTH LEVEL - AREA 4H&4K
T-104 TELELCOMMUNICATIONS PLANS - FOURTH LEVEL - AREA
4H&4K T-104i TELECOMMUNICATION PLANS - FOURTH LEVEL
INTERSTITIAL - AREA 4H&4K
T-400 TELECOMMUNICATIONS ENLARGED PLANS
T-501 TELECOMMUNICATION DETAILS
T-601 TELECOMMUNICATIONS RISER DIAGRAMS
T-901 TELECOMMUNICATION CUTSHEETS & BASIS OF DESIGN
T-902 TELECOMMUNICATION CUTSHEETS & BASIS OF DESIGN
T-903 TELECOMMUNICATION CUTSHEETS & BASIS OF DESIGN
T-904 TELECOMMUNICATION CUTSHEETS & BASIS OF DESIGN
Grand total: 139
- - - END - - -
GENERAL REQUIREMENTS
010000 - 1
SECTION 010000
PART 1 - GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 013526, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Renovate for Expanded Polytrauma Program - Phase 1 as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the Contracting Officer’s Representative and Contracting Officer.
C. Offices of Triple C the A&E Group at 2508 29th Avenue NE, Minneapolis, MN 55418, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. Prime Contractor Personal Minimum Requirements:
1. As Required in other parts of the Project Manual and Contract Requirements the following are minimum requirements:
a. The Superintendent shall be an employee of the Prime Contractor with authority to act as the contractor, responsible for the day-to-day operations at the construction site, planning, quality control, verification of delivery of approved material and equipment, subcontractor coordination responsibilities and execution of the complete project as per the contract documents.
1) Superintendent shall have no hands-on construction interaction. In addition, the superintendent shall provide proof to the COR regarding completion of 30 hour OSHA.
2) Superintendent assigned to this project shall not be assigned to any other project and shall only have duties on one project at a time.
3) The Superintendent shall sign-in at the beginning of each day of work and Sign-out at the end of the work day at the Office of Engineering Service. No work shall be performed by any contractors or subcontractors without the presence of the superintendent at the actual work site.
4) The Superintendent shall be responsible for submitting daily work logs to the COR at the end of every work day.
b. Site Safety and Health Officer (SSHO) shall be a separate qualified individual from the Prime Contractor’s Superintendent or CQC System Manager with duties only as the SSHO. See 013526 SAFETY REQUIREMENTS for more information on roles and responsibilities for General Contractor’s staff.
c. CQC System Manager shall be a separate qualified individual from the Prime Contractor’s Superintendent or Site Safety and Health Officer (SSHO) with duties only as the CQC System Manager. See Section 014500 Quality Control for more information on roles and responsibilities for CQC Personnel.
d. The Prime contractor shall provide services of a Project Manager whose responsibilities would include but not be limited to providing support to the Superintendent at the job site and shall be responsible for finance related tasks
010000 - 2 and scheduling.
E. Dig Permit
1. The contractor shall complete the VA dig permit with the COR and submit the Dig Safe notification prior to start of any excavation work.
F. Electrical Work Permit
1. The contractor shall complete the VA Electrical Work Permit with the COR and submit to the COR a minimum of 72 hours prior to start of electrical work within the facility.
G. Welding and Cutting
1. A Hot Work Permit is required. See Section 013526, SAFETY REQUIREMENTS for requirements.
H. Contract Work Hours
1. Normal working hours are 8:00 am to 4:30 pm. Contractors who wish to work other than
“normal working hours” for work to be done during those hours must submit a written request to the Contracting Officer for approval. The request must state that the Contractor is requesting to work other than normal working hours at no additional expense to the Government. Such requests shall be coordinated with the COR and must be submitted to the CO two (2) working days in advance.
2. For certain aspects of work the Contractor shall be required to work off duty hours to perform that part of the work, for continued operations of the Medical Center. After duty hours work shall be coordinated with and approved by the COR.
a. Noisy demolition work, work at building entrances, electrical or other utility work necessary to pass within, above, traverse hallway corridors, temporary shutdowns of utilities for tie-in.
I. Contractor shall perform work in accordance with requirements of “ASHE Construction in a Healthcare Facility”.
J. Contractor shall provide Submittal Exchange®, Autodesk Build® and/or ProCore Project Site dedicated for this project, or approved equal (substitutions must be submitted with Contractor Bid), for the duration of the contract. Contractor will provide VA access to the site. Contractor will keep this site current and will use it for all submittals, RFIs, change documents, Record Drawing, electronic file management, and communication logs for the duration of the contract.
K. Contractor shall provide Infection Control Plan as required by Memorandum 111-40, Subj: VHA Directive 7715 Safety and Health During Construction dated April 6, 2017. Submit to COR for approval prior to the start of work.
L. Prior to commencing work, general contractor shall provide proof that an OSHA designated “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present. CP will have authority letter.
M. Per VA Directive 1085, smoking, vaping and smokeless tobacco are prohibited on the grounds of VA facilities, including in vehicles. This Directive applies to all Prime Contractor and Subcontractor employees.
N. Pricing Proposal transparency requirements:
1. This project requires pricing proposals to include breakdown pricing for the General
Contractor and all subcontractors.
2. All price proposals, shall including subcontractor pricing must include a breakdown of pricing per the format included with this Project Manual. Third-party inspections must be included as a line item in the price proposal. See example at the end of Section 004113
BID FORM.
O. A commissioning plan and commissioning agent resume shall be submitted with contractor bids.
The commissioning agent (CxA) shall be a third-party entity.
010000 - 3
1. The Firm and designated Commissioning Authority shall have been the principal commissioning authority on a least three (3) comparable projects that have been completed within the previous five (5) years.
2. The proposed commissioning firm should be certified by at least one of the following agencies:
a. National Environmental Balancing Bureau (NEBB)
b. AABC Commissioning Group (AGC)
c. Building Commissioning Association (BCxA)
3. The Fire Protection Commissioning Specialist should be a registered Fire Protection Engineer in at least one state.
a. He/she should have a minimum of 5 years’ experience with design, installation, inspection, or testing of fire protection systems, and/or smoke control systems.
4. The Building Envelope Commissioning Specialist should be a Registered Architect in at least one state.
a. He/she should also have a minimum of five (5) years’ experience with design, installation, or inspection of building envelope components.
5. The Controls Commissioning Specialist should have a minimum of 5 years’ experience in design, installation, programming, inspection, or testing of direct digital control systems for HVAC systems.
6. Key members of the Commissioning Authority’s commissioning team should have:
a. Bachelor’s degree in Mechanical, Electrical, Architectural engineering.
b. Professional Engineer license in at least one jurisdiction is desired.
c. Over 5 years field experience in building systems operations, maintenance, and troubleshooting, HVAC system installation, maintenance, and troubleshooting, HVAC Direct Digital Control system installation, programming, maintenance, and troubleshooting, electrical system installation, maintenance, and troubleshooting, other applicable trade contracting experience may be deemed equivalent experience for the bachelor’s degree.
7. Commissioning Services will be provided in accordance with the Department of Veterans Affairs Commissioning Process Manual. Prospective proposers shall review the Whole Building Commissioning Process Manual available on the VA Technical Information Library at http://www.cfm.va.gov/til/.
a. The following tables describe the commissioning services and deliverables to be provided by the Commissioning Agent:
http://www.cfm.va.gov/til/
010000 - 4
Commissioning Team Task/Deliverables Description
Construction Phase
Project Phase/ Cx
Task
Commissioning Task Description Commissioning
Deliverables
Commissioning Kick Off
Meeting
(Construction Phase)
(The kickoff meeting should occur within 60 days of Notice to
Proceed.)
Conduct a “Commissioning Kickoff Meeting” with the Construction Team
Establish the purpose and process for commissioning the project.
Establish the individual roles of each participating commissioning team member.
Review the Construction Phase Commissioning
Plan and Commissioning Specifications.
Review the Commissioning Documents
Review the Project Schedule and discuss how commissioning activities will be incorporated into the master schedule.
Review Draft PFC and FPT; identify pre-requisites for functional testing.
ATTENDEES:
Commissioning Agent, A/E Design Team
Representatives, Contractor’s Commissioning
Representative, Subcontractor’s Commissioning
Representatives, VA RE.
Meeting Minutes
Revised Project
Commissioning Plan
(Include Names/Contact
Information for selected
Commissioning Team
Members)
Duration Schedule for
Commissioning
Activities
Based on the Construction Phase
Commissioning Plan, prepare a duration schedule for the commissioning activities required by the commissioning plan. This duration schedule should be incorporated into the contractor’s project schedule to track all commissioning activities of the commissioning team.
Commissioning Duration
Schedule
(Schedule shall be periodically updated to reflect changes in the project schedule and/or scope.)
010000 - 5
Commissioning Team Task/Deliverables Description
Construction Phase
Project Phase/ Cx
Task
Commissioning Task Description Commissioning
Deliverables
Submittal & Shop
Drawing Review
Review all pertinent project shop drawings necessary to support the Commissioning
Process. Review of the shop drawings is for the purpose of developing appropriate Pre-
Functional Checklists and Systems Functional
Performance Test Procedures. Submittals &
Shop drawings shall be reviewed for commissionability, maintainability and for compliance to the Construction Documents.
Note any issues identified in the Shop Drawing
Review that might compromise the final commissioned system on the ‘Commissioning
Review Log’ and submit comment to the Design
Team and the RE contemporaneously with the
A/E review for resolution.
Comments shall be submitted in accordance with the contractual submittal review time.
Comments shall be provided to the Design
Team no less than 7 days prior to the Submittal
Review Due Date provided that the Cx Agent has no less than 7 days to review the submittals.
ANY ISSUES IDENTIFIED IN THE
SUBMITTAL REVIEW THAT MIGHT REQUIRE
A CONTRACT CHANGE BUT IS NECESSARY
TO MEET DESIGN INTENT SHOULD BE
SPECIFICALLY REFERRED TO THE RE.
Shop Drawing Cx Review
List
Shop Drawing Review
Comments
Construction Phase
Commissioning Plan
Based on the work completed in the items above, the Construction Phase Commissioning
Plan for the project shall be periodically reviewed with the Commissioning Team and updated to reflect changes in project equipment, sequences of operations, scope or schedule and with project personnel.
Revised Project
Commissioning Plan
010000 - 6
Commissioning Team Task/Deliverables Description
Construction Phase
Project Phase/ Cx
Task
Commissioning Task Description Commissioning
Deliverables
Commissioning
Construction
Observations
During the course of construction, the
Commissioning Agent will visit the site to observe the progress of construction with respect to the systems being commissioned.
The focus of the observations will to verify that systems being installed comply with the
Construction Documents and can be successfully configured, operated and maintained.
In addition, site observations visits will be scheduled to include
● Witnessing factory testing and/or contractor equipment/system start up activities;
● Verification of Completed Pre
Functional Checklists
● Verification that the Contractor and his subcontractors are completing and documenting Pre-Test procedures required by the specifications.
● Clarification and technical support for understanding and resolving
Commissioning Issues.
Site Observation Reports
Updated Commissioning
Issues Log
010000 - 7
Commissioning Team Task/Deliverables Description
Construction Phase
Project Phase/ Cx
Task
Commissioning Task Description Commissioning
Deliverables
Commissioning Team
Meetings
The Commissioning Agent will hold regular commissioning team meetings to review progress of the commissioning effort and reinforce individual responsibilities. The team will review schedule, construction sequence, and completed work (PFC, PFT and FPT’s) and outstanding issues on the Commissioning
Issues Log.
Commissioning Team Meetings may be held at the jobsite or by teleconference depending upon the status of construction. While it is imperative that many of the Commissioning Team
Meetings be held in person, during early construction phases, some meetings may be more cost effectively conducted remotely.
Scheduling and location of meetings shall occur by consultation between the Commissioning
Agent and the VA-RE.
The Prime Contractor’s scheduler should attend approximately every other Commissioning
Team Meeting to review the master schedule and any changes that will affect commissioning activities.
Commissioning Meeting
Agenda and Minutes
Updated Commissioning
Issues Log
Develop Final Pre-
Functional Checklists
(PFC’s)
The Commissioning Agent will prepare Pre-
Final Pre Functional Checklists (PFC) for the project and distribute to all Cx Team members for review and comment. The Commissioning
Agent will incorporate review comments and prepare Final PFCs.
An executed PFC submitted by the Prime
Contractor indicates the system and its related equipment is ready for Systems Functional
Performance Testing.
The requirements for Pre Functional Checklists shall be coordinated with the startup requirements specified for each commissioned system. The PFC’s shall be constructed to leverage the specified contractor and vendor start activities to avoid unnecessary duplication.
Pre Functional Checklists
(PFC’s)
010000 - 8
Commissioning Team Task/Deliverables Description
Construction Phase
Project Phase/ Cx
Task
Commissioning Task Description Commissioning
Deliverables
Final Systems
Functional Performance
Test (FPT’s)
Procedures
Based on construction documents and approved submittals, the Commissioning Agent will prepare Pre-Final Systems Functional
Performance Test Procedures (FPT’s) for systems to be commissioned.
Completed Final FPT’s will be distributed to all appropriate members of the Commissioning
Team for review and comment.
Final FPT’s will be issued once comments are reviewed and incorporated into final documents as appropriate.
Pre-Final and Final
Systems Functional
Performance Test
Procedures (FPT’s)
Review Operations &
Maintenance Manuals
The Commissioning Agent shall review
Operations and Maintenance Manuals submitted by contractors for general conformance with specifications and VA’s requirements, including:
If provided with the manuals, Review Preventive
Maintenance Schedules provided as part of the
O&M Manuals for completeness. Verify that data is provided in a manner consistent with VA process for managing Preventive Maintenance tasks.
Review of O&M Manuals will include a review of system and component warranties to confirm conformance with contract requirements and adequate documentation of warranty contact information and VA obligations.
Review of O&M Manuals shall be completed in accordance with the Submittal Review schedule requirements.
Updated Commissioning
Issues Log
Review Contractor
Equipment Startup
Checklists, TAB
Reports and PFC’s
The Commissioning Agent will review all contractor prepared Equipment Startup
Checklists, TAB Reports (including “pencil” daily test results) and PFC’s to confirm that the systems have been subject to appropriate
Quality Control and Start Up procedures prior to initiation of Functional Performance Testing.
Incomplete work, inadequate preparation and deficiencies will note noted and tracked on the
Commissioning Issues Log.
Commissioning Issues Log
010000 - 9
Commissioning Team Task/Deliverables Description
Construction Phase
Project Phase/ Cx
Task
Commissioning Task Description Commissioning
Deliverables
TAB Verification The Commissioning Agent shall work with the
TAB Contractor to verify that all Testing and
Balancing work is conducted in strict accordance with the specified Procedural
Standards for Testing, Adjusting and Balancing by either NEBB or AABC. The Commissioning
Agent shall execute the following tasks:
● Review the TAB Agenda provided by the TAB Contractor to verify that it is complete, thorough and in compliance with the specification and Procedural
Standards requirements.
● On the project site, the CxA shall review the calibration certificates for the instrumentation being used by the TAB
Contractor during the execution of TAB activities to confirm that the instrumentation meets the requirements of the spec and the appropriate
Procedural Standard.
● The CxA shall periodically visit the project site and review the TAB documentation for method, reasonable values, and compliance with the specification, Procedural Standard and
TAB Agenda.
● Upon completion of the TAB activities, the CxA shall visit the project site with the TAB Contractor and the RE. The
TAB Contractor shall demonstrate readings selected by the CxA that demonstrate that the system performance is consistent with the submitted values on the TAB report.
Readings shall include Air Handling Unit total flows, static pressure control values, select outlet flows, building, and space pressures selected by the CxA as critical system operating values.
TAB Agenda Review
Comments
TAB Agenda Review
Meeting Minutes
Field Observation Reports of TAB Inspections
Summary Report of TAB
Verification Readings
010000 - 10
Commissioning Team Task/Deliverables Description
Construction Phase
Project Phase/ Cx
Task
Commissioning Task Description Commissioning
Deliverables
Systems Functional
Performance Testing
The Commissioning Agent will oversee, facilitate, and document all FPT testing.
Execution of FPT’s shall be executed in accordance with the Functional Testing
Procedures published by the Commissioning
Agent. All systems tested in accordance with the FPT’s shall be operated by the contractors in accordance with the approved FPT.
Contractors shall retain responsibility for the installed systems during and after functional testing until substantial completion or final acceptance as determined by the VA.
The Commissioning Agent, in collaboration with the control contractor shall include long term trends (greater than 7 days) of integrated system performance once all systems have been commissioned. The Commissioning
Agent shall provide analysis of these trends to confirm that the installed systems are stable and reliable
Executed Functional
Performance Tests and support documentation.
Long Term Trend Data and
Analysis
Prepare Systems
Manuals
The Commissioning Agent shall work with the design team, contractor and VA to develop
Systems Manuals. Manuals will contain system design, operations and sequence information that describes the design intent, operational features and appropriate operational practices necessary to sustain the system operation in accordance with the Design Narrative and the
VA’s overall objectives for the facility.
Systems Manual will include sections for each major system included in the commissioning process.
Project Systems Manual
010000 - 11
Commissioning Team Task/Deliverables Description
Construction Phase
Project Phase/ Cx
Task
Commissioning Task Description Commissioning
Deliverables
Training Plan Review
The Commissioning Agent shall collaborate with the Prime Contractor and installing subcontractors to develop effective contractor and manufacturer training plans and agendas for general conformance with specifications and
VA’s requirements. Observe training for quality of training and for general conformance with the training plan and agenda.
The CxA shall observe contractor and vendor training for critical systems. The Contractor shall provide and the CxA shall maintain all attendance records and associated agendas and presentations for all training sessions.
Attendance records shall be written original sign in sheets for each training session.
Compiled Training Plan
Individual Training Agendas
Training Attendance Sign In
Sheets
Systems Training
The Commissioning Agent will conduct training sessions to provide systems-level training for
O&M personnel. Training will include:
● Review of system design, capacity, and equipment selection
● Review of system operating sequences
● Review of interconnection with other systems
● Review of Emergency operating procedures
● Review of the Project Systems Manual and its Use
● Student Evaluation forms
The number, duration and scope of the Systems
Training sessions shall be determined by the specific requirements of the project.
The training provided by the CxA does not in any way relieve the Contractor from any specified training obligations.
Systems Training
Presentations (electronic)
010000 - 12
Commissioning Team Task/Deliverables Description
Construction Phase
Project Phase/ Cx
Task
Commissioning Task Description Commissioning
Deliverables
Final Commissioning
Report
The Commissioning Agent shall compile a comprehensive commissioning report documenting all commissioning activities, including but not limited to the following:
● Executive Summary
● Commissioning Scope of Work
● Test methods and results
● Outstanding commissioning issues
● Comprehensive Commissioning Issues
Log, including resolved items and a description of their resolution,
● Commissioning plan,
● Field Observation Reports, Status reports and other field activity documentation,
● Submittal and O&M manual reviews
● Training record
● Completed Pre Functional Checklists
● Completed Functional Performance
Test protocols and support documentation
● Other support documentation developed as part of the execution of the project Construction Phase
Commissioning Process
010000 - 13
Commissioning Team Task/Deliverables Description
Construction Phase
Project Phase/ Cx
Task
Commissioning Task Description Commissioning
Deliverables
Deferred and/or
Seasonal Testing
The Commissioning Agent shall witness and document Systems Functional Performance
Testing that was deferred to allow systems to be tested in appropriate seasonal conditions.
Testing will be conducted in accordance with
Systems Functional Performance Test
Procedures. Testing support will be required from the installing contractors, EMCS Vendor and VA. Requirement for seasonal testing will be incorporated into the project specifications.
As part of the Seasonal Testing Effort, the
Commissioning Agent shall review systems operations with the onsite operations team and reinforce training and best operating practices of the operations team.
Executed Functional
Performance Test and
Support Documents
Warranty Period Site
Visits
The Commissioning Agent shall make quarterly visits to the project site to reinforce training, evaluate performance of the installed systems and provide technical support to the operating team to sustain commissioned performance of the systems.
Warranty Site Visit Reports
010000 - 14
Commissioning Team Task/Deliverables Description
Construction Phase
Project Phase/ Cx
Task
Commissioning Task Description Commissioning
Deliverables
Post-Occupancy
Inspection
Return to the project approximately 10 months after substantial completion to review the building operation with the facility occupants and O&M staff, and to discuss outstanding issues related to commissioning. Provide suggestions for improvements to systems operation including,
● Measurement & Verification Issues,
● Re-Commissioning Tasks, and
● Improvements in Preventive
Maintenance or Operational Strategies
Assist facility staff in developing warranty issues, documents and requests for service to remedy outstanding problems.
As part of the Post Occupancy Inspection, the
Commissioning Agent shall analyze the energy consumption records from the project site (both utility and system generated reports) and provide the team with an analysis of actual system energy performance versus predicted performance. To the extent possible, deficiencies in performance shall be analyzed to provide an understanding of the systems, components or operating strategies that may be operating outside predicted parameters.
Post Occupancy Field Visit
Warranty Issues Report
Systems Energy Review
Report
Report Amendment
Amend Final Commissioning Report to document the Warranty Phase commissioning activities.
Final Report Amendment
1.3 STATEMENT OF BID ITEM(S)
A. Contractor shall completely prepare project site for operations, including demolition and removal of existing site elements, and furnish labor and materials and perform construction work for the Minneapolis VA Medical Center, Project 618-22-100, Renovate for Expanded Polytrauma Program - Phase 1 as required by drawings and specifications. Period of performance is projected to be five-hundred forty (540) calendar days. The work will require the demolition of the interior of the existing 4K ward on the fourth level of Building 70 as required by the drawings and specifications. The project entails the renovation of the 4K ward.
B. Work includes general construction, alterations, and certain other items. Contractor shall provide services but not limited to furnish all supervision, labor, equipment, materials, and
010000 - 15 transportation necessary to accomplish work for the demolition and replacement as required by specifications and drawings.
C. Electrical Work: Electrical work includes all labor, material, equipment and supervision to perform the required electrical construction work on this project including materials and construction equipment to modify the existing systems to provide new electrical, communications and security systems to the renovated space detailed by the construction drawings and specifications.
D. Provide access control for all the required doors, coordinate with the door hardware schedule for additional requirements.
E. Mechanical, Plumbing and Fire Protection Work: Work includes all labor, material, equipment and supervision to perform the required Mechanical, Plumbing and Fire Protection construction work on this project including provide materials and construction equipment as detailed by the construction drawings and specifications.
1. All new mechanical systems shall be addressable and controllable via the existing
Engineering Control Center (ECC) and HVAC Shop. The ECC system shall monitor space conditions and unit status and shall alarm the boiler plant operator or HVAC shop as detailed by the mechanical control drawings and specifications.
F. Existing Fire Protection systems shall be modified, and new systems provided per the construction drawings and specifications.
G. Contractor shall provide modify existing and provide new plumbing piping and fixtures as required by the construction drawings and specifications.
H. Inspections: Comprehensive Third-Party inspections, testing and written reports for all Divisions are required and paid by the General Contractor. Contractor shall employ third party inspection consultants to perform all inspections required by this contract.
I. All new and existing systems within the Scope of Work shall be commissioned (or recommissioned) per Specification 01 91 00.
J. Contractor shall appoint a third-party individual, company, or firm to act as the Commissioning Agent. The Commissioning Agent is the designated person, company, or entity that plans, schedules, and coordinates the commissioning team to implement the commissioning process
K. ITEM I, GENERAL CONSTRUCTION: BASE BID: Work includes general construction, alterations, and necessary removal of existing structures and construction and certain other items.
L. ALTERNATE NO.1: BASE BID except
M. ALTERNATE NO.2: ALTERNATE 1 except The expected construction period of 540 Calendar days includes all pre-construction activity, construction, and post-construction testing, third-party inspections, Owner inspections, and commissioning. Contractor shall submit a comprehensive schedule of work in compliance with 01 32 16.15 PROJECT SCHEDULES (SMALL PROJECTS
DESIGN/BID/BUILD).
1. Contractor shall submit and obtain approval for all project submittals including coordination drawings prior to beginning physical construction.
2. Contractor shall perform Commissioning of all new systems and existing systems impacted by the project according to requirements in sections:
a. 01 91 00 – GENERAL COMMISSIONING REQUIREMENTS.
b. 21 08 00 – COMMISSIONING OF FIRE SUPPRESSION SYSTEMS.
c. 22 08 00 – COMMISSIONING OF PLUMBING SYSTEMS.
d. 23 08 00 – COMMISSIONING OF HVAC SYSTEMS.
e. 26 08 00 – COMMISSIONING OF ELECTRICAL SYSTEMS.
f. 27 08 00 – COMMISSIONING OF COMMUNICATIONS SYSTEMS.
g. 28 08 00 – COMMISSIONING OF SECURITY SYSTEMS.
010000 - 16
3. A detailed commissioning plan is required to ensure that all systems are calibrated, programmed, and all graphic displays are accurate and approved by applicable VA staff.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
B. Refer to specifications for installation requirements for each Division. Refer to drawings for estimated quantities and schematic layouts/locations. Contractor shall provide a complete, commissioned, functioning systems. Contractor shall provide all testing reports prior to the start of commissioning. This project will require night and weekend work, Renovation includes requirements for Testing and Balancing the HVAC for the existing and new systems configuration.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
a. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that escort arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the
Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 087100, DOOR HARDWARE and coordinate.
D. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
010000 - 17
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. permits shall be issued for General Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA Medical Center Facility Manager.
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work.
C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .