Attachment 3 - 01 00 00.B - Appendix B - Submittal Log.pdf
PDF 139 KB Posted
- Solicitation number
- RFP-36C77626R0033
About this file
This is a Project Submittal Log for the EHRM Infrastructure Upgrades Construction Documents (Project 504-21-700). The document serves as a comprehensive tracking instrument for managing all contractor submittals throughout the construction contract period, requiring the contractor to log each submittal on the day received and maintain complete documentation of submission and approval dates for each item.
The submittal log establishes mandatory procedures across numerous specification sections spanning divisions 01 through 34, covering shop drawings, product data, samples, test reports, certifications, and qualifications for all trades and materials. Key requirements include: submittals must be submitted in electronic PDF format (under 5MB via email, larger files via FTP), complete and sufficient in detail before material acquisition, stamped and signed by the contractor certifying compliance with contract requirements, and accompanied by transmittal forms identifying deviations. The VA review period is 15 working days for standard submittals and 10 working days for RFIs, with approval notations of "Approved," "Approved with Comments," or "Revise and Resubmit." Critical submittal categories include project schedules (within 45 days of Notice to Proceed), commissioning plans and reports, equipment specifications for HVAC, plumbing, electrical, communications, and security systems, structural steel and concrete details, roofing and waterproofing systems, interior finishes, and site utility systems. All submittals require contractor certification of compliance before VA review, with non-compliant materials subject to removal and replacement at contractor expense. The log tracks status (Open/Closed), division, specification section, paragraph number, submittal type, contractor number, dates received and due back, approval status, and revision history, with monthly electronic updates required throughout the project duration.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions Project Location website address
O Open
C Closed
STATUS
(pending, open, or closed) DIVISION
SPECIFICATION
SECTION
NUMBER SPECIFICATION SECTION NAME
PARAGRAPH
NUMBER SUBMITTAL SUBMITTAL TYPE DETAIL
CONTRACTOR
SUBMITTAL
NUMBER
Date
Received from
Owner
Due back to
Owner
(2-Days)
Approved /
Apprvd w. comments/
Revise & resubmit
Add Columns where needed
Resubmittal of previous submittal?
Resubmittal
Date
Forwarded to Name
(consultant, etc.)
Forwarded to
Firm
(consultant, etc.)
Date
Forwarded
(to consult)
Date
Received
Back
Date
Returned to Owner
COR
APPR.
OPEN/CLOSE DIVISION SecNum SecName ParNum Submittal Type Detail dd/mm/yy revise Revision # dd/mm/yy Robbie B&P dd/mm/yy dd/mm/yy dd/mm/yy dd/mm/yy
O 01 01 32 16.15
Project Schedules (Small Projects -
Design-Bid-Build) 1.5.A.
THE COMPLETE PROJECT SCHEDULE
SUBMITTAL
Within 45 calendar days after receipt of Notice to Proceed, the Contractor shall submit for the Contracting Officer's review; three blue line copies of the interim schedule on sheets of paper 765 x 1070 mm (30 x 42 inches) and an electronic file in the previously approved CPM schedule program. The submittal shall also include three copies of a computer-produced activity/event ID schedule showing project duration; phase completion dates; and other data, including event cost. Each activity/event on the computer-produced schedule shall contain as a minimum, but not limited to, activity/event ID, activity/event description, duration, budget amount, early start date, early finish date, late start date, late finish date and total float. Work activity/event relationships shall be restricted to finish-to-start or start-to-start without lead or lag constraints. Activity/event date constraints, not required by the contract, will not be accepted unless submitted to and approved by the Contracting Officer. The contractor
O 01 01 32 16.15
Project Schedules (Small Projects -
Design-Bid-Build) 1.5.B.
THE COMPLETE PROJECT SCHEDULE
SUBMITTAL
Within 30 calendar days after receipt of the complete project interim Project
Schedule and the complete final Project Schedule, the Contracting Officer or his representative, will do one or both of the following
O 01 01 32 16.15
Project Schedules (Small Projects -
Design-Bid-Build) 1.5.C.
THE COMPLETE PROJECT SCHEDULE
SUBMITTAL
The approved baseline schedule and the computer-produced schedule(s) generated there from shall constitute the approved baseline schedule until subsequently revised in accordance with the requirements of this section.
O 01 01 32 16.15
Project Schedules (Small Projects -
Design-Bid-Build) 1.5.D.
THE COMPLETE PROJECT SCHEDULE
SUBMITTAL
The Complete Project Schedule shall contain approximately [________] work activities/events.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.3.A. SUBMITTAL REGISTER
The submittal register will list items of equipment and materials for which submittals are required by the specifications. This list may not be all inclusive and additional submittals may be required by the specifications. The Contractor is not relieved from supplying submittals required by the contract documents but which have been omitted from the submittal register.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.3.B. SUBMITTAL REGISTER
The submittal register will serve as a scheduling document for submittals and will be used to control submittal actions throughout the contract period.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.3.C. SUBMITTAL REGISTER
The VA will provide the initial submittal register in electronic format. Thereafter, the
Contractor shall track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the VA.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.3.D. SUBMITTAL REGISTER
The Contractor shall update the submittal register as submittal actions occur and maintain the submittal register at the project site until final acceptance of all work by
Contracting Officer.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.3.E. SUBMITTAL REGISTER
The Contractor shall submit formal monthly updates to the submittal register in electronic format. Each monthly update shall document actual submission and approval dates for each submittal.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.4.A. SUBMITTAL SCHEDULING
Submittals are to be scheduled, submitted, reviewed, and approved prior to the acquisition of the material or equipment.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.4.B. SUBMITTAL SCHEDULING
Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow time for potential resubmittal.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.4.C. SUBMITTAL SCHEDULING
No delay costs or time extensions will be allowed for time lost in late submittals or resubmittals.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.4.D. SUBMITTAL SCHEDULING
All submittals are required to be approved prior to the start of the specified work activity.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.5.A. SUBMITTAL PREPARATION
Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.5.B. SUBMITTAL PREPARATION
Collect required data for each specific material, product, unit of work, or system into a single submittal. Prominently mark choices, options, and portions applicable to the submittal. Partial submittals will not be accepted for expedition of construction effort. Submittal will be returned without review if incomplete.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.5.C. SUBMITTAL PREPARATION
If available product data is incomplete, provide Contractor-prepared documentation to supplement product data and satisfy submittal requirements.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.5.D. SUBMITTAL PREPARATION
All irrelevant or unnecessary data shall be removed from the submittal to facilitate accuracy and timely processing. Submittals that contain the excessive amount of irrelevant or unnecessary data will be returned with review.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.5.E. SUBMITTAL PREPARATION Provide a transmittal form for each submittal with the following information
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.5.F. SUBMITTAL PREPARATION
The Contractor is responsible for reviewing and certifying that all submittals are in compliance with contract requirements before submitting for VA review. Proposed deviations from the contract requirements are to be clearly identified. All deviations submitted must include a side by side comparison of item being proposed against item specified. Failure to point out deviations will result in the VA requiring removal and replacement of such work at the Contractor's expense.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.5.G. SUBMITTAL PREPARATION Stamp, sign, and date each submittal transmittal form indicating action taken.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.5.H. SUBMITTAL PREPARATION
Stamp used by the Contractor on the submittal transmittal form to certify that the submittal meets contract requirements is to be similar to the following
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.6.A.
SUBMITTAL FORMAT AND
TRANSMISSION
Provide submittals in electronic format, with the exception of material samples. Use
PDF as the electronic format, unless otherwise specified or directed by the
Contracting Officer.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.6.B.
SUBMITTAL FORMAT AND
TRANSMISSION
Compile the electronic submittal file as a single, complete document. Name the electronic submittal file specifically according to its contents.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.6.C.
SUBMITTAL FORMAT AND
TRANSMISSION
Electronic files must be of sufficient quality that all information is legible. Generate
PDF files from original documents so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character
Resolution (OCR) routines are required.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.6.D.
SUBMITTAL FORMAT AND
TRANSMISSION
E-mail electronic submittal documents smaller than 5MB in size to e-mail addresses as directed by the Contracting Officer.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.6.E.
SUBMITTAL FORMAT AND
TRANSMISSION
Provide electronic documents over 5MB through an electronic FTP file sharing system. Confirm that the electronic FTP file sharing system can be accessed from the
VA computer network. The Contractor is responsible for setting up, providing, and maintaining the electronic FTP file sharing system for the construction contract period of performance.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.6.F.
SUBMITTAL FORMAT AND
TRANSMISSION
Provide hard copies of submittals when requested by the Contracting Officer. Up to
3 additional hard copies of any submittal may be requested at the discretion of the
Contracting Officer, at no additional cost to the VA.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.10.A.
VA REVIEW OF SUBMITTALS AND
RFIS
The VA will review all submittals for compliance with the technical requirements of the contract documents. The Architect-Engineer for this project will assist the VA in reviewing all submittals and determining contractual compliance. Review will be only for conformance with the applicable codes, standards and contract requirements.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.10.B.
VA REVIEW OF SUBMITTALS AND
RFIS
Period of review for submittals begins when the VA COR receives submittal from the
Contractor.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.10.C.
VA REVIEW OF SUBMITTALS AND
RFIS
Period of review for each resubmittal is the same as for initial submittal.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.10.D.
VA REVIEW OF SUBMITTALS AND
RFIS
VA review period is 15 working days for submittals.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.10.E.
VA REVIEW OF SUBMITTALS AND
RFIS
VA review period is 10 working days for RFIs.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.10.F.
VA REVIEW OF SUBMITTALS AND
RFIS
The VA will return submittals to the Contractor with the following notations
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.11.A. APPROVED SUBMITTALS
The VA approval of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing, and other information are satisfactory.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.11.B. APPROVED SUBMITTALS
VA approval of a submittal does not relieve the Contractor of the responsibility for any error which may exist. The Contractor is responsible for fully complying with all contract requirements and the satisfactory construction of all work, including the need to check, confirm, and coordinate the work of all subcontractors for the project.
Non-compliant material incorporated in the work will be removed and replaced at the Contractor’s expense.
Add columns as required for tracking additional and revised submittal. Brief over revision requirements
TRIPLE-C Project Submittal Log
Project Name
Project Number
Status Key
Once the submittal is reviewed, a Triple C "submittal review stamp" shall be affixed to a Triple C submittal transmittal, and processed back to the Client or Submitter, as appropriate per contract.
EHRM Infrastructure Upgrades Construction
Documents
504-21-700
Triple C designated staff shall log each submittal into the Project Submittal Log on the day it is received (hardcopy or electronic)
Triple C designated staff shall review the submittal, or process the submittal to another reviewer (internal or consultant) on the day the submittal is received, including all information below, and date due back
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.11.C. APPROVED SUBMITTALS
After submittals have been approved, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
O 01 01 33 23
Shop Drawings, Product Data, and
Samples 1.11.D. APPROVED SUBMITTALS Retain a copy of all approved submittals at project site, including approved samples.
O 01 01 45 00 Quality Control 1.3.A. SUBMITTALS
Government approval is required for all submittals. CQC inspection reports shall be submitted under this Specification section and follow the [Applicable CQC Control
Phase (Preparatory, Initial, or Follow-Up)] [Applicable Specification section] naming convention.
O 01 01 45 00 Quality Control 1.3.B. SUBMITTALS Test Reports
O 01 01 45 00 Quality Control 3.5.A. SUBMITTALS AND DELIVERABLES:
Submittals have to comply with the requirements in Section 01 33 23 Shop Drawings, Product Data, and Samples. The CQC organization is responsible for certifying that all submittals and deliverables are in compliance with the contract requirements. When
Section 01 91 00 General Commissioning Requirements is included in the contract, the submittals required by the section have to be coordinated with the Section 01 33
23 Shop Drawings, Product Data, and Samples to ensure adequate time is allowed for each type of submittal required.
O 01 01 57 19 Temporary Environmental Controls 1.4.A. SUBMITTALS
In accordance with Section, 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND
SAMPLES, furnish the following
O 01 01 57 19 Temporary Environmental Controls 1.4.B. SUBMITTALS
Approval of the Contractor's Environmental Protection Plan will not relieve the
Contractor of responsibility for adequate and continued control of pollutants and other environmental protection measures.
O 01 01 74 19 Construction Waste Management 1.5.A. SUBMITTALS
In accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, and
SAMPLES, furnish the following
O 01 01 74 19 Construction Waste Management 1.5.B. SUBMITTALS
Prepare and submit to the Resident Engineer a written demolition debris management plan. The plan shall include, but not be limited to, the following information
O 01 01 74 19 Construction Waste Management 1.5.C. SUBMITTALS
Designated Manager responsible for instructing personnel, supervising, documenting and administer over meetings relevant to the Waste Management Plan.
O 01 01 74 19 Construction Waste Management 1.5.D. SUBMITTALS
Monthly summary of construction and demolition debris diversion and disposal, quantifying all materials generated at the work site and disposed of or diverted from disposal through recycling.
O 01 01 81 13
Sustainable Construction
Requirements 1.5.A. SUBMITTALS All submittals to be provided by contractor to COR.
O 01 01 81 13
Sustainable Construction
Requirements 1.5.B. SUBMITTALS Sustainability Action Plan
O 01 01 81 13
Sustainable Construction
Requirements 1.5.C. SUBMITTALS Low Pollutant-Emitting Materials Tracking Spreadsheet
Within 30 days after Preconstruction Meeting provide a preliminary Low
Pollutant-Emitting Materials Tracking Spreadsheet. The Low Pollutant-
O 01 01 81 13
Sustainable Construction
Requirements 1.5.D. SUBMITTALS Construction Indoor Air Quality (IAQ) Management Plan
O 01 01 81 13
Sustainable Construction
Requirements 1.5.E. SUBMITTALS Product Submittals
O 01 01 81 13
Sustainable Construction
Requirements 1.5.F. SUBMITTALS Sustainable Construction Progress Reports
Concurrent with each Application for Payment, submit a Sustainable
Construction Progress Report to confirm adherence with Sustainability Action
O 01 01 81 13
Sustainable Construction
Requirements 1.5.G. SUBMITTALS Closeout Submittals Within 14 days after Substantial Completion provide the following
O 01 01 91 00
General Commissioning
Requirements 1.13.A. SUBMITTALS Preliminary Commissioning Plan Submittal
The Commissioning Agent has prepared a Preliminary Commissioning Plan based on the final Construction Documents. The Preliminary Commissioning
O 01 01 91 00
General Commissioning
Requirements 1.13.B. SUBMITTALS Final Commissioning Plan Submittal
Based on the Final Construction Documents and the Contractor’s project team, the Commissioning Agent will prepare the Final Commissioning Plan as
O 01 01 91 00
General Commissioning
Requirements 1.13.C. SUBMITTALS Systems Functional Performance Test Procedure
The Commissioning Agent will submit preliminary Systems Functional
Performance Test Procedures to the Contractor, and the VA for review and
O 01 01 91 00
General Commissioning
Requirements 1.13.D. SUBMITTALS Pre-Functional Checklists
The Commissioning Agent will submit Pre-Functional Checklists to be completed by the Contractor.
O 01 01 91 00
General Commissioning
Requirements 1.13.E. SUBMITTALS Test and Inspection Reports
The Commissioning Agent will submit test and inspection reports to the VA with copies to the Contractor and the Architect/Engineer.
O 01 01 91 00
General Commissioning
Requirements 1.13.F. SUBMITTALS Corrective Action Documents
The Commissioning Agent will submit corrective action documents to the VA
Resident Engineer with copies to the Contractor and Architect.
O 01 01 91 00
General Commissioning
Requirements 1.13.G. SUBMITTALS Preliminary Commissioning Report Submittal
The Commissioning Agent will submit three electronic copies of the preliminary commissioning report. One electronic copy, with review
O 01 01 91 00
General Commissioning
Requirements 1.13.H. SUBMITTALS Final Commissioning Report Submittal
The Commissioning Agent will submit four sets of electronically formatted information of the final commissioning report to the VA. The final submittal
O 01 01 91 00
General Commissioning
Requirements 1.13.I. SUBMITTALS Data for Commissioning
O 02 02 82 11 Traditional Asbestos Abatement 2.4.A. SUBMITTALS
PRE-START MEETING SUBMITTALS
O 02 02 82 11 Traditional Asbestos Abatement 2.4.B. SUBMITTALS
SUBMITTALS DURING ABATEMENT
O 02 02 82 11 Traditional Asbestos Abatement 2.4.C. SUBMITTALS
SUBMITTALS AT COMPLETION OF ABATEMENT
O 02 02 82 13.13 Glovebag Asbestos Abatement 2.5.A. SUBMITTALS PRE-start MEETING SUBMITTALS
O 02 02 82 13.13 Glovebag Asbestos Abatement 2.5.B. SUBMITTALS
SUBMITTALS DURING ABATEMENT
O 02 02 82 13.13 Glovebag Asbestos Abatement 2.5.C. SUBMITTALS
SUBMITTALS AT COMPLETION OF ABATEMENT
O 03 03 30 00 Cast-in-Place Concrete 1.6.A. SUBMITTALS:
Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, and
SAMPLES.
O 03 03 30 00 Cast-in-Place Concrete 1.6.B. SUBMITTALS:
Shop Drawings Reinforcing steel
O 03 03 30 00 Cast-in-Place Concrete 1.6.C. SUBMITTALS:
Mill Test Reports
O 03 03 30 00 Cast-in-Place Concrete 1.6.D. SUBMITTALS:
Manufacturer's Certificates
O 03 03 30 00 Cast-in-Place Concrete 1.6.E. SUBMITTALS:
Testing Agency for Concrete Mix Design
Approval request including qualifications of principals and technicians and evidence of active participation in program of Cement and Concrete
O 03 03 30 00 Cast-in-Place Concrete 1.6.F. SUBMITTALS:
Test Report for Concrete Mix Designs Trial mixes including watercement // fly ash // raMo curves, concrete mix
O 03 03 30 00 Cast-in-Place Concrete 1.6.G. SUBMITTALS:
Shoring and Reshoring Sequence
Submit for approval a shoring and reshoring sequence for flat slab/flat plate portions, prepared by a registered Professional Engineer. As a minimum, O 03 03 30 00 Cast-in-Place Concrete 1.6.H. SUBMITTALS:
Test reports on splitting tensile strength (Fct) of lightweight concrete.
O 04 04 01 00 Maintenance of Masonry 1.4.A. SUBMITTALS Submittal Procedures Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 04 04 01 00 Maintenance of Masonry 1.4.B. SUBMITTALS Manufacturer's Literature and Data
O 04 04 01 00 Maintenance of Masonry 1.4.C. SUBMITTALS Samples
O 04 04 01 00 Maintenance of Masonry 1.4.D. SUBMITTALS Test reports
O 04 04 05 13 Masonry Mortaring 1.4.A. SUBMITTALS Submittal Procedures Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 04 04 05 13 Masonry Mortaring 1.4.B. SUBMITTALS Manufacturer's Literature and Data
O 04 04 05 13 Masonry Mortaring 1.4.C. SUBMITTALS Test Reports Certify each product complies with specifications.
O 04 04 05 13 Masonry Mortaring 1.4.D. SUBMITTALS Certificates Certify each product complies with specifications.
O 04 04 05 13 Masonry Mortaring 1.4.E. SUBMITTALS Qualifications Substantiate qualifications comply with specifications.
O 04 04 05 16 Masonry Grouting 1.4.A. SUBMITTALS Submittal Procedures Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 04 04 05 16 Masonry Grouting 1.4.B. SUBMITTALS Manufacturer's Literature and Data
O 04 04 05 16 Masonry Grouting 1.4.C. SUBMITTALS Sustainable Construction Submittals
O 04 04 05 16 Masonry Grouting 1.4.D. SUBMITTALS Test Reports Certify each product complies with specifications.
O 04 04 05 16 Masonry Grouting 1.4.E. SUBMITTALS Certificates Certify each product complies with specifications.
O 04 04 20 00 Unit Masonry 1.4.A. SUBMITTALS Submittal Procedures Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 04 04 20 00 Unit Masonry 1.4.B. SUBMITTALS Submittal Drawings
O 04 04 20 00 Unit Masonry 1.4.C. SUBMITTALS Manufacturer's Literature and Data
O 04 04 20 00 Unit Masonry 1.4.D. SUBMITTALS Samples
O 04 04 20 00 Unit Masonry 1.4.E. SUBMITTALS Sustainable Construction Submittals
O 04 04 20 00 Unit Masonry 1.4.F. SUBMITTALS Test reports Certify products comply with specifications.
O 04 04 20 00 Unit Masonry 1.4.G. SUBMITTALS Certificates Certify products comply with specifications.
O 04 04 20 00 Unit Masonry 1.4.H. SUBMITTALS Delegated Design Drawings and Calculations Signed and sealed by responsible design professional.
O 05 05 12 00 Structural Steel Framing 1.4.A. SUBMITTALS Submittal Procedures Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 05 05 12 00 Structural Steel Framing 1.4.B. SUBMITTALS Submittal Drawings
O 05 05 12 00 Structural Steel Framing 1.4.C. SUBMITTALS Sustainable Construction Submittals
O 05 05 12 00 Structural Steel Framing 1.4.D. SUBMITTALS Test Reports Certify products comply with specifications.
O 05 05 12 00 Structural Steel Framing 1.4.E. SUBMITTALS Certificates Certify each product complies with specifications.
O 05 05 12 00 Structural Steel Framing 1.4.F. SUBMITTALS Qualifications Substantiate qualifications comply with specifications.
O 05 05 12 00 Structural Steel Framing 1.4.G. SUBMITTALS Delegated Design Drawings and Calculations Signed and sealed by responsible Architect/Engineer.
O 05 05 12 00 Structural Steel Framing 1.4.H. SUBMITTALS Record Surveys Signed and sealed by responsible surveyor or engineer.
O 05 05 31 00 Steel Decking 1.4.A. SUBMITTALS Submittal Procedures Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 05 05 31 00 Steel Decking 1.4.B. SUBMITTALS Submittal Drawings
O 05 05 31 00 Steel Decking 1.4.C. SUBMITTALS Manufacturer's Literature and Data
O 05 05 31 00 Steel Decking 1.4.D. SUBMITTALS Sustainable Construction Submittals
O 05 05 31 00 Steel Decking 1.4.E. SUBMITTALS Certificates Certify each product complies with specifications.
O 05 05 31 00 Steel Decking 1.4.F. SUBMITTALS Qualifications Substantiate qualifications comply with specifications.
O 05 05 31 00 Steel Decking 1.4.G. SUBMITTALS Insurance Certification Assist the Government in preparation and submittal of roof installation
O 05 05 40 00 Cold-Formed Metal Framing 1.4.A. SUBMITTALS
Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND
SAMPLES.
O 05 05 40 00 Cold-Formed Metal Framing 1.4.B. SUBMITTALS Shop Drawings Shop and erection drawings showing steel unit layout, connections to
O 05 05 40 00 Cold-Formed Metal Framing 1.4.C. SUBMITTALS Manufacturer's Literature and Data Showing steel component sections and specifying structural characteristics.
O 05 05 40 00 Cold-Formed Metal Framing 1.4.D. SUBMITTALS
For cold-formed metal framing indicated to comply with certain design loadings, include structural analysis data sealed and signed by the qualified professional engineer who was responsible for its preparation.
O 05 05 50 00 Metal Fabrications 1.3.A. SUBMITTALS
Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND
SAMPLES.
O 05 05 50 00 Metal Fabrications 1.3.B. SUBMITTALS Manufacturer's Literature and Data
O 05 05 50 00 Metal Fabrications 1.3.C. SUBMITTALS Shop Drawings
O 05 05 50 00 Metal Fabrications 1.3.D. SUBMITTALS Manufacturer's Certificates
O 05 05 50 00 Metal Fabrications 1.3.E. SUBMITTALS Design Calculations for specified live loads including dead loads.
O 05 05 50 00 Metal Fabrications 1.3.F. SUBMITTALS
Furnish setting drawings and instructions for installation of anchors to be preset into concrete and masonry work, and for the positioning of items having anchors to be built into concrete or masonry construction.
O 06 06 10 00 Rough Carpentry 1.3.A. SUBMITTALS
Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND
SAMPLES.
O 06 06 10 00 Rough Carpentry 1.3.B. SUBMITTALS Sustainable Design Submittals, as described below
O 06 06 10 00 Rough Carpentry 1.3.C. SUBMITTALS
Shop Drawings showing framing connection details, fasteners, connections and dimensions.
O 06 06 10 00 Rough Carpentry 1.3.D. SUBMITTALS Manufacturer’s Literature and Data
O 06 06 10 00 Rough Carpentry 1.3.E. SUBMITTALS Manufacturer’s certificate for unmarked lumber.
O 06 06 20 00 Finish Carpentry 1.5.A. SUBMITTALS Submittal Procedures Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 06 06 20 00 Finish Carpentry 1.5.B. SUBMITTALS Submittal Drawings
O 06 06 20 00 Finish Carpentry 1.5.C. SUBMITTALS Manufacturer's Literature and Data
O 06 06 20 00 Finish Carpentry 1.5.D. SUBMITTALS Samples
O 06 06 20 00 Finish Carpentry 1.5.E. SUBMITTALS Sustainable Construction Submittals
O 06 06 20 00 Finish Carpentry 1.5.F. SUBMITTALS Certificates Certify // each product complies // products comply // with specifications.
O 06 06 20 00 Finish Carpentry 1.5.G. SUBMITTALS Qualifications Substantiate qualifications comply with specifications.
O 07 07 01 50.19 Preparation for Re-Roofing 1.5.A. SUBMITTALS Submittal Procedures Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 07 07 01 50.19 Preparation for Re-Roofing 1.5.B. SUBMITTALS Submittal Drawings
O 07 07 01 50.19 Preparation for Re-Roofing 1.5.C. SUBMITTALS Manufacturer's Literature and Data
O 07 07 01 50.19 Preparation for Re-Roofing 1.5.D. SUBMITTALS Photographs Document existing conditions potentially affected by roofing operations
O 07 07 01 50.19 Preparation for Re-Roofing 1.5.E. SUBMITTALS Field Inspection Reports
O 07 07 01 50.19 Preparation for Re-Roofing 1.5.F. SUBMITTALS Infrared Roof Moisture Survey Report.
O 07 07 08 00
Facility Exterior Closure
Commissioning 1.6.A. SUBMITTALS
The commissioning process requires review of selected SubmiNals that pertain to the systems to be commissioned. The Commissioning Agent will provide a list of submittals that will be reviewed by the Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to
Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, and SAMPLES for further details.
O 07 07 08 00
Facility Exterior Closure
Commissioning 1.6.B. SUBMITTALS
The commissioning process requires SubmiNal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.
O 07 07 13 00 Sheet Waterproofing 1.3.A. SUBMITTALS
Submit in accordance with SecMon 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 07 07 13 00 Sheet Waterproofing 1.3.B. SUBMITTALS Manufacturer's Literature and Data
O 07 07 13 00 Sheet Waterproofing 1.3.C. SUBMITTALS CerMficates
O 07 07 13 00 Sheet Waterproofing 1.3.D. SUBMITTALS Samples
O 07 07 21 13 Thermal Insulation 1.4.A. SUBMITTALS Submittal Procedures Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 07 07 21 13 Thermal Insulation 1.4.B. SUBMITTALS Submittal Drawings
O 07 07 21 13 Thermal Insulation 1.4.C. SUBMITTALS Manufacturer's Literature and Data
O 07 07 21 13 Thermal Insulation 1.4.D. SUBMITTALS Sustainable Construction Submittals
O 07 07 21 23 Loose-Fill Insulation 1.4.A. SUBMITTALS Submittal Procedures Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 07 07 21 23 Loose-Fill Insulation 1.4.B. SUBMITTALS Manufacturer's Literature and Data
O 07 07 21 23 Loose-Fill Insulation 1.4.C. SUBMITTALS Samples
O 07 07 21 23 Loose-Fill Insulation 1.4.D. SUBMITTALS Sustainable Construction Submittals
O 07 07 22 00 Roof and Deck Insulation 1.4.A. SUBMITTALS Submittal Procedures Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 07 07 22 00 Roof and Deck Insulation 1.4.B. SUBMITTALS Submittal Drawings
O 07 07 22 00 Roof and Deck Insulation 1.4.C. SUBMITTALS Manufacturer's Literature and Data
O 07 07 22 00 Roof and Deck Insulation 1.4.D. SUBMITTALS Samples
O 07 07 22 00 Roof and Deck Insulation 1.4.E. SUBMITTALS Sustainable Construction Submittals
O 07 07 22 00 Roof and Deck Insulation 1.4.F. SUBMITTALS Qualifications Substantiate qualifications meet specifications.
O 07 07 27 27
Fluid-Applied Membrane Air Barrier, Vapor Permeable 1.4.A. SUBMITTALS Submittal Procedures Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 07 07 27 27
Fluid-Applied Membrane Air Barrier, Vapor Permeable 1.4.B. SUBMITTALS Manufacturer's Literature and Data
O 07 07 27 27
Fluid-Applied Membrane Air Barrier, Vapor Permeable 1.4.C. SUBMITTALS Sustainable Construction Submittals
O 07 07 27 27
Fluid-Applied Membrane Air Barrier, Vapor Permeable 1.4.D. SUBMITTALS Test reports
O 07 07 27 27
Fluid-Applied Membrane Air Barrier, Vapor Permeable 1.4.E. SUBMITTALS Certificates Certify each product complies with specifications.
O 07 07 27 27
Fluid-Applied Membrane Air Barrier, Vapor Permeable 1.4.F. SUBMITTALS Qualifications Substantiate qualifications comply with specifications.
O 07 07 27 27
Fluid-Applied Membrane Air Barrier, Vapor Permeable 1.4.G. SUBMITTALS Installation Audit
O 07 07 40 00 Roofing and Siding Panels 1.5.A. SUBMITTALS
Submit in accordance with SecMon 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND
SAMPLES.
O 07 07 40 00 Roofing and Siding Panels 1.5.B. SUBMITTALS Sustainable Design Submittals, as described below
O 07 07 40 00 Roofing and Siding Panels 1.5.C. SUBMITTALS Samples Metal panel, 152 mm (6 inch) square, showing finish, each color and texture.
O 07 07 40 00 Roofing and Siding Panels 1.5.D. SUBMITTALS Shop Drawings
// Wall // // and roof // panels, showing details of construction and installation. // Collateral steel framing // // U value // thickness and kind of
O 07 07 40 00 Roofing and Siding Panels 1.5.E. SUBMITTALS Manufacturer's Literature and Data // Wall // // and roof // panels
O 07 07 40 00 Roofing and Siding Panels 1.5.F. SUBMITTALS Fire Test Report Report of fire test by recognized testing laboratory for fire rating specified, O 07 07 40 00 Roofing and Siding Panels 1.5.G. SUBMITTALS Manufacturer’s Certificates Indicating manufacturer’s qualifications specified.
O 07 07 40 00 Roofing and Siding Panels 1.5.H. SUBMITTALS Installer qualifications.
O 07 07 40 00 Roofing and Siding Panels 1.5.I. SUBMITTALS Manufacturer warranty.
O 07 07 54 23
Thermoplastic Polyolefin (TPO)
Roofing 1.5.A. SUBMITTALS Submittal Procedures Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 07 07 54 23
Thermoplastic Polyolefin (TPO)
Roofing 1.5.B. SUBMITTALS Submittal Drawings
O 07 07 54 23
Thermoplastic Polyolefin (TPO)
Roofing 1.5.C. SUBMITTALS Manufacturer's Literature and Data
O 07 07 54 23
Thermoplastic Polyolefin (TPO)
Roofing 1.5.D. SUBMITTALS Samples
O 07 07 54 23
Thermoplastic Polyolefin (TPO)
Roofing 1.5.E. SUBMITTALS Sustainable Construction Submittals
O 07 07 54 23
Thermoplastic Polyolefin (TPO)
Roofing 1.5.F. SUBMITTALS Certificates Certify products comply with specifications.
O 07 07 54 23
Thermoplastic Polyolefin (TPO)
Roofing 1.5.G. SUBMITTALS Qualifications Substantiate qualifications comply with specifications.
O 07 07 54 23
Thermoplastic Polyolefin (TPO)
Roofing 1.5.H. SUBMITTALS Field quality control reports.
O 07 07 54 23
Thermoplastic Polyolefin (TPO)
Roofing 1.5.I. SUBMITTALS Temporary protection plan. Include list of proposed temporary materials.
O 07 07 54 23
Thermoplastic Polyolefin (TPO)
Roofing 1.5.J. SUBMITTALS Operation and Maintenance Data
O 07 07 60 00 Flashing and Sheet Metal 1.5.A. SUBMITTALS
Submit in accordance with SecMon 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 07 07 60 00 Flashing and Sheet Metal 1.5.B. SUBMITTALS Shop Drawings For all specified items, including
O 07 07 60 00 Flashing and Sheet Metal 1.5.C. SUBMITTALS Manufacturer's Literature and Data For all specified items, including
O 07 07 60 00 Flashing and Sheet Metal 1.5.D. SUBMITTALS CerMficates Indicating compliance with specified finishing requirements, from applicator
O 07 07 71 00 Roof Specialties 1.5.A. SUBMITTALS
Submit in accordance with SecMon 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 07 07 71 00 Roof Specialties 1.5.B. SUBMITTALS Sustainable Design Submittals, as described below
O 07 07 71 00 Roof Specialties 1.5.C. SUBMITTALS Samples Representative sample panel of color-anodized aluminum not less than 101 x
O 07 07 71 00 Roof Specialties 1.5.D. SUBMITTALS Shop Drawings Each item specified showing design, details of construction, installation and
O 07 07 71 00 Roof Specialties 1.5.E. SUBMITTALS Manufacturer's Literature and Data Each item specified.
O 07 07 71 00 Roof Specialties 1.5.F. SUBMITTALS CerMficates Stating that aluminum has been given specified thickness of anodizing.
O 07 07 72 00 Roof Accessories 1.4.A. SUBMITTALS
Submit in accordance with SecMon 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 07 07 72 00 Roof Accessories 1.4.B. SUBMITTALS Sustainable Design Submittals, as described below
O 07 07 72 00 Roof Accessories 1.4.C. SUBMITTALS Samples Submit representative sample panel of color anodized aluminum not less than
O 07 07 72 00 Roof Accessories 1.4.D. SUBMITTALS Shop Drawings Each item specified showing design, details of construction, installation and
O 07 07 72 00 Roof Accessories 1.4.E. SUBMITTALS Manufacturer's Literature and Data Each item specified.
O 07 07 72 00 Roof Accessories 1.4.F. SUBMITTALS CerMficates Stating that aluminum has been given specified thickness of anodizing.
O 07 07 81 00 Applied Fireproofing 1.3.A. SUBMITTALS
Submit in accordance with SecMon 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 07 07 81 00 Applied Fireproofing 1.3.B. SUBMITTALS Sustainable Design Submittals, as described below
O 07 07 81 00 Applied Fireproofing 1.3.C. SUBMITTALS Installer qualificaMons.
O 07 07 81 00 Applied Fireproofing 1.3.D. SUBMITTALS Testing laboratory accreditations.
O 07 07 81 00 Applied Fireproofing 1.3.E. SUBMITTALS Manufacturer's Literature and Data
O 07 07 81 00 Applied Fireproofing 1.3.F. SUBMITTALS CerMficates
O 07 07 81 00 Applied Fireproofing 1.3.G. SUBMITTALS Miscellaneous
O 07 07 84 00 Firestopping 1.3.A. SUBMITTALS
Submit in accordance with SecMon 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 07 07 84 00 Firestopping 1.3.B. SUBMITTALS Sustainable Design Submittals, as described below //1. Volatile organic compounds per volume as specified in
O 07 07 84 00 Firestopping 1.3.C. SUBMITTALS Installer qualificaMons.
O 07 07 84 00 Firestopping 1.3.D. SUBMITTALS Inspector qualifications.
O 07 07 84 00 Firestopping 1.3.E. SUBMITTALS Manufacturer's Literature and Data
O 07 07 84 00 Firestopping 1.3.F. SUBMITTALS List of FM, UL, or WH classificaMon number of systems installed.
O 07 07 84 00 Firestopping 1.3.G. SUBMITTALS CerMfied laboratory test reports for ASTM E814
O 07 07 84 00 Firestopping 1.3.H SUBMITTALS Manufacturer's CerMficates aNesMng compliance with specified requirements.
O 07 07 92 00 Joint Sealants 1.5.A. SUBMITTALS
Submit in accordance with SecMon 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 07 07 92 00 Joint Sealants 1.5.B. SUBMITTALS Sustainable Design Submittals, as described below
O 07 07 92 00 Joint Sealants 1.5.C. SUBMITTALS Installer qualifications.
O 07 07 92 00 Joint Sealants 1.5.D. SUBMITTALS Contractor certification.
O 07 07 92 00 Joint Sealants 1.5.E. SUBMITTALS Manufacturer's installaMon instrucMons for each product used.
O 07 07 92 00 Joint Sealants 1.5.F. SUBMITTALS Cured samples of exposed sealants for each color.
O 07 07 92 00 Joint Sealants 1.5.G. SUBMITTALS Manufacturer's Literature and Data
O 07 07 92 00 Joint Sealants 1.5.H. SUBMITTALS Manufacturer warranty.
O 07 07 95 13 Expansion Joint Cover Assemblies 1.5.A. SUBMITTALS Submittal Procedures Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 07 07 95 13 Expansion Joint Cover Assemblies 1.5.B. SUBMITTALS Submittal Drawings
O 07 07 95 13 Expansion Joint Cover Assemblies 1.5.C. SUBMITTALS Manufacturer's Literature and Data
O 07 07 95 13 Expansion Joint Cover Assemblies 1.5.D. SUBMITTALS Samples Submit 300 mm (12 inch) long samples.
O 07 07 95 13 Expansion Joint Cover Assemblies 1.5.E. SUBMITTALS Sustainable Construction Submittals
O 07 07 95 13 Expansion Joint Cover Assemblies 1.5.F. SUBMITTALS Qualifications Substantiate qualifications comply with specifications.
O 07 07 95 13 Expansion Joint Cover Assemblies 1.5.G. SUBMITTALS Certificates Indicate products comply with specifications.
O 07 07 95 13 Expansion Joint Cover Assemblies 1.5.H. SUBMITTALS Operation and Maintenance Data
O 08 08 11 13 Hollow Metal Doors and Frames 1.4.A. SUBMITTALS Submittal Procedures Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 08 08 11 13 Hollow Metal Doors and Frames 1.4.B. SUBMITTALS Submittal Drawings
O 08 08 11 13 Hollow Metal Doors and Frames 1.4.C. SUBMITTALS Manufacturer's Literature and Data
O 08 08 11 13 Hollow Metal Doors and Frames 1.4.D. SUBMITTALS Sustainable Construction Submittals
O 08 08 11 13 Hollow Metal Doors and Frames 1.4.E. SUBMITTALS Test reports Certify // each product complies // products comply // with specifications.
O 08 08 11 13 Hollow Metal Doors and Frames 1.4.F. SUBMITTALS Qualifications Substantiate qualifications comply with specifications.
O 08 08 14 00 Interior Wood Doors 1.4.A. SUBMITTALS Submittal Procedures Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 08 08 14 00 Interior Wood Doors 1.4.B. SUBMITTALS Submittal Drawings
O 08 08 14 00 Interior Wood Doors 1.4.C. SUBMITTALS Manufacturer's Literature and Data
O 08 08 14 00 Interior Wood Doors 1.4.D. SUBMITTALS Samples
O 08 08 14 00 Interior Wood Doors 1.4.E. SUBMITTALS Sustainable Construction Submittals
O 08 08 14 00 Interior Wood Doors 1.4.F. SUBMITTALS Test Reports Indicate // each product complies // products comply // with specifications.
O 08 08 14 00 Interior Wood Doors 1.4.G. SUBMITTALS Operation and Maintenance Data
O 08 08 31 13 Access Doors and Frames 1.4.A. SUBMITTALS Submittal Procedures Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 08 08 31 13 Access Doors and Frames 1.4.B. SUBMITTALS Submittal Drawings
O 08 08 31 13 Access Doors and Frames 1.4.C. SUBMITTALS Manufacturer's Literature and Data
O 08 08 31 13 Access Doors and Frames 1.4.D. SUBMITTALS Sustainable Construction Submittals
O 08 08 71 00 Door Hardware 1.6.P. SUBMITTALS
SubmiNals shall be in accordance with SecMon 01 33 23, SHOP DRAWINGS, PRODUCT
DATA AND SAMPLES. Submit 6 copies of the schedule per Section 01 33 23. Submit 2 final copies of the final approved schedules to VAMC Locksmith as record copies
(VISN Locksmith if the VAMC does not have a locksmith).
O 08 08 71 00 Door Hardware 1.6.Q. SUBMITTALS Hardware Schedule Prepare and submit hardware schedule in the following form
O 08 08 71 00 Door Hardware 1.6.R. SUBMITTALS Samples and Manufacturers' Literature
O 08 08 71 00 Door Hardware 1.6.S. SUBMITTALS CerMficate of Compliance and Test Reports
Submit certificates that hardware conforms to the requirements specified herein. Certificates shall be accompanied by copies of reports as referenced.
The testing shall have been conducted either in the manufacturer's plant and certified by an independent testing laboratory or conducted in an independent laboratory, within four years of submittal of reports for approval.
O 09 09 05 16
Subsurface Preparation for Floor
Finishes 1.3.A. SUBMITTALS
Submit in accordance with SecMon 01 33 23, SHOP DRAWINGS, PRODUCT DATA and
TEST DAT
O 09 09 05 16
Subsurface Preparation for Floor
Finishes 1.3.B. SUBMITTALS
WriNen approval confirming product compaMbility with subfloor material manufacturer and the flooring manufacturer
O 09 09 05 16
Subsurface Preparation for Floor
Finishes 1.3.C. SUBMITTALS Product Data
O 09 09 05 16
Subsurface Preparation for Floor
Finishes 1.3.D. SUBMITTALS Test Data
O 09 09 22 16 Non-Structural Metal Framing 1.4.A. SUBMITTALS
Submit in accordance with SecMon 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 09 09 22 16 Non-Structural Metal Framing 1.4.B. SUBMITTALS Manufacturer's Literature and Data
O 09 09 22 16 Non-Structural Metal Framing 1.4.C. SUBMITTALS Shop Drawings
O 09 09 22 16 Non-Structural Metal Framing 1.4.D. SUBMITTALS Test Results Fire rating test designation, each fire rating required for each assembly.
O 09 09 29 00 Gypsum Board 1.4.A. SUBMITTALS
Submit in accordance with SecMon 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 09 09 29 00 Gypsum Board 1.4.B. SUBMITTALS Manufacturer's Literature and Data
O 09 09 29 00 Gypsum Board 1.4.C. SUBMITTALS Shop Drawings
O 09 09 29 00 Gypsum Board 1.4.D. SUBMITTALS Samples
O 09 09 29 00 Gypsum Board 1.4.E. SUBMITTALS Test Results
O 09 09 29 00 Gypsum Board 1.4.F. SUBMITTALS CerMficates
Certify that gypsum board types, gypsum backing board types, cementitious backer units, and joint treating materials do not contain asbestos material.
O 09 09 51 00 Acoustical Ceilings 1.5.A. SUBMITTALS Submittal Procedures Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 09 09 51 00 Acoustical Ceilings 1.5.B. SUBMITTALS Submittal Drawings
O 09 09 51 00 Acoustical Ceilings 1.5.C. SUBMITTALS Manufacturer's Literature and Data
O 09 09 51 00 Acoustical Ceilings 1.5.D. SUBMITTALS Samples
O 09 09 51 00 Acoustical Ceilings 1.5.E. SUBMITTALS Sustainable Construction Submittals
O 09 09 51 00 Acoustical Ceilings 1.5.F. SUBMITTALS Certificates Certify // each product complies // products comply // with specifications.
O 09 09 51 00 Acoustical Ceilings 1.5.G. SUBMITTALS Qualifications Substantiate qualifications comply with specifications.
O 09 09 51 00 Acoustical Ceilings 1.5.H. SUBMITTALS Operation and Maintenance Data
O 09 09 65 13 Resilient Base and Accessories 1.4.A. SUBMITTALS Submittal Procedures Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 09 09 65 13 Resilient Base and Accessories 1.4.B. SUBMITTALS Manufacturer's Literature and Data
O 09 09 65 13 Resilient Base and Accessories 1.4.C. SUBMITTALS Samples
O 09 09 65 13 Resilient Base and Accessories 1.4.D. SUBMITTALS Sustainable Construction Submittals
O 09 09 65 13 Resilient Base and Accessories 1.4.E. SUBMITTALS Operation and Maintenance Data
O 09 09 65 16 Resilient Sheet Flooring 1.4.A. SUBMITTALS Submittal Procedures Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 09 09 65 16 Resilient Sheet Flooring 1.4.B. SUBMITTALS Manufacturer's Literature and Data
O 09 09 65 16 Resilient Sheet Flooring 1.4.C. SUBMITTALS Samples
O 09 09 65 16 Resilient Sheet Flooring 1.4.D. SUBMITTALS Sustainable Construction Submittals
O 09 09 65 16 Resilient Sheet Flooring 1.4.E. SUBMITTALS Certificates Certify // each product complies // products comply // with specifications.
O 09 09 65 16 Resilient Sheet Flooring 1.4.F. SUBMITTALS Qualifications Substantiate qualifications comply with specifications.
O 09 09 65 19 Resilient Tile Flooring 1.3.A. SUBMITTALS
Submit in accordance with SecMon 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND
SAMPLES.
O 09 09 65 19 Resilient Tile Flooring 1.3.B. SUBMITTALS Sustainable Design Submittals as described below //
O 09 09 65 19 Resilient Tile Flooring 1.3.C. SUBMITTALS Manufacturer's Literature and Data
O 09 09 65 19 Resilient Tile Flooring 1.3.D. SUBMITTALS Samples
O 09 09 65 19 Resilient Tile Flooring 1.3.E. SUBMITTALS Shop Drawings
O 09 09 65 19 Resilient Tile Flooring 1.3.F SUBMITTALS Test Reports
O 09 09 68 00 Carpeting 1.4.A. SUBMITTALS
Submit in accordance with SecMon 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 09 09 68 00 Carpeting 1.4.B. SUBMITTALS Sustainable Design Submittals as described below
O 09 09 68 00 Carpeting 1.4.C. SUBMITTALS Product Data
O 09 09 68 00 Carpeting 1.4.D. SUBMITTALS Samples
O 09 09 68 00 Carpeting 1.4.E. SUBMITTALS Shop Drawings Installers layout plan showing seams and cuts for sheet carpet and carpet
O 09 09 68 00 Carpeting 1.4.F. SUBMITTALS Maintenance Data Carpet manufacturer’s maintenance instructions describing recommended
O 09 09 68 00 Carpeting 1.4.G. SUBMITTALS Installer’s Qualifications.
O 09 09 68 00 Carpeting 1.4.H SUBMITTALS Manufacturer’s warranty.
O 09 09 91 00 Painting 1.3.A. SUBMITTALS
Submit in accordance with SecMon 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 09 09 91 00 Painting 1.3.B. SUBMITTALS Sustainable Design Submittals as described below
O 09 09 91 00 Painting 1.3.C. SUBMITTALS Painter qualificaMons.
O 09 09 91 00 Painting 1.3.D. SUBMITTALS Manufacturer's Literature and Data
O 09 09 91 00 Painting 1.3.E. SUBMITTALS Sample Panels
O 09 09 91 00 Painting 1.3.F SUBMITTALS Sample of idenMty markers if used.
O 09 09 91 00 Painting 1.3.G SUBMITTALS Manufacturers' CerMficates indicaMng compliance with specified requirements
O 10 10 14 00 Signage 1.4.A. SUBMITTALS
Submit in accordance with SecMon 01 33 00, SHOP DRAWINGS, PRODUCT DATA AND
SAMPLES.
O 10 10 14 00 Signage 1.4.B. SUBMITTALS Sustainable Design SubmiNals, as described below
O 10 10 14 00 Signage 1.4.C. SUBMITTALS Interior Sign Samples Sign panels and frames, with letters and symbols, for each sign type.
O 10 10 14 00 Signage 1.4.D. SUBMITTALS Exterior Sign Samples 152 x 152 mm (6 x 6 inches) samples of each color and material.
O 10 10 14 00 Signage 1.4.E. SUBMITTALS Manufacturer's Literature
O 10 10 14 00 Signage 1.4.F. SUBMITTALS Sign LocaMon Plan, showing locaMon, type and total number of signs required.
O 10 10 14 00 Signage 1.4.G. SUBMITTALS Shop Drawings Scaled for manufacture and fabrication of sign types. Identify materials, show
O 10 10 14 00 Signage 1.4.H SUBMITTALS Full size layout paNerns for dimensional leNers.
O 10 10 14 00 Signage 1.4.I SUBMITTALS Manufacturer’s qualifications.
O 10 10 14 00 Signage 1.4.J SUBMITTALS Installer’s qualifications.
O 10 10 14 00 Signage 1.4.K SUBMITTALS Structural calculations.
O 10 10 44 13 Fire Extinguisher Cabinets 1.3.A. SUBMITTALS
Submit in accordance with SecMon 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 10 10 44 13 Fire Extinguisher Cabinets 1.3.B. SUBMITTALS Manufacturer's Literature and Data Fire extinguisher cabinet including installation instruction and rough opening
O 10 10 56 26 Mobile Storage Shelving 1.3 SUBMITTALS Warranty
O 12 12 31 00 Manufactured Metal Casework 1.4.A. SUBMITTALS:
Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
O 13 13 05 41
Seismic Restraint Requirements for
Non-Structural Components 1.4.A. SUBMITTALS
Submit a coordinated set of equipment anchorage drawings prior to installaMon including
O 13 13 05 41
Seismic Restraint Requirements for
Non-Structural Components 1.4.B. SUBMITTALS
Submit prior to installaMon, a coordinated set of bracing drawings for seismic protection of piping, with data identifying the various support-to-structure connections and seismic bracing structural connections, include
O 13 13 05 41
Seismic Restraint Requirements for
Non-Structural Components 1.4.C. SUBMITTALS
Submit prior to installaMon, bracing drawings for seismic protecMon of suspended ductwork and suspended electrical and communication cables, include
O 13 13 05 41
Seismic Restraint Requirements for
Non-Structural Components 1.4.D. SUBMITTALS
Submit design calculaMons prepared and sealed by the registered structural engineer specified above in paragraph 1.3
O 13 13 05 41
Seismic Restraint Requirements for
Non-Structural Components 1.4.E. SUBMITTALS
Submit for concrete anchors, the appropriate ICBC evaluaMon reports, OSHPD pre-approvals, or lab test reports verifying compliance with OSHPD Interpretation of
Regulations 28-6.
O 21 21 08 00
Commissioning of Fire Suppression
System 1.6.A. SUBMITTALS
The commissioning process requires review of selected Submittals. The
Commissioning Agent will provide a list of submittals that will be reviewed by the
Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to Section 01 33 23 SHOP DRAWINGS, PRODUCT
DATA, and SAMPLES for further details.
O 21 21 08 00
Commissioning of Fire Suppression
System 1.6.B. SUBMITTALS
The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.
O 21 21 13 13 Wet-Pipe Sprinkler Systems 1.4.A. SUBMITTALS
Submit as one package in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. Prepare detailed working drawings that are signed by a NICET Level III or Level IV Sprinkler Technician or stamped by a Registered
Professional Engineer licensed in the field of Fire Protection Engineering. As the
Government review is for technical adequacy only, the installer remains responsible for correcting any conflicts with other trades and building construction that arise during installation. Partial submittals will not be accepted. Material submittals shall be approved prior to the purchase or delivery to the job site. Suitably bind submittals in notebooks or binders and provide an index referencing the appropriate specification section. In addition to the hard copies, provide submittal items in
Paragraphs 1.4(A)1 through 1.4(A)5 electronically in pdf format on a compact disc or as directed by the COR. Submittals shall include, but not be limited to, the following
O 22 22 05 11 Common Work Results for Plumbing 1.4.B. SUBMITTALS
InformaMon and material submiNed under this secMon shall be marked "SUBMITTED
UNDER SECTION 22 05 11, COMMON WORK RESULTS FOR…
This is the start of the file's text. The full file is on GovTribe.