Attachment 16 - APPNDX_A-Commissioning_Plan-VA_CT_West_Haven_EHRM_IU-689-22-700.pdf

PDF 11 MB Posted

Attached to
Z2DA--689-22-700 EHRM IU West Haven VAMC This ONLY for the PCAC VISN 1 Construction MATOC Pool
Solicitation number
36C77626R0106
Issued by

About this file

This is a Draft Commissioning Plan for the Electronic Health Record Modernization (EHRM) Infrastructure Upgrades project at the West Haven VA Medical Center in Connecticut (Project #689-22-700). The plan establishes a comprehensive framework for verifying and documenting that all upgraded building facility systems perform in accordance with design specifications and the owner's operational needs, extending from design phase through a minimum of one year after construction completion.

The commissioning scope includes mechanical and HVAC systems (84 VRF units at 50% test sample, 15 ductless split systems at 100%, 2 air-cooled condensing units, data center CRAC systems, various fans and dampers, steam systems, and emergency power generation equipment); building automation systems with graphical user interface and controllers; electrical and power systems including UPS monitoring, panelboards, transformers, and automatic transfer switches; and low voltage telecommunications systems. The commissioning team consists of the VA Department of Veterans Affairs (COR: Peter Sandor; Contracting Officer: Denise Bailey), design team (Spees Design Build, WSP USA INC, Performance Environmental), the general contractor (to be identified), and Davenergy Solutions Inc. as the Commissioning Authority. Key deliverables include Pre-Functional Checklists (PFCs) and Functional Performance Tests (FPTs) for all commissioned equipment, with PFCs to be completed prior to functional testing and all deficiencies resolved before final project acceptance. The plan establishes defined roles and responsibilities for all team members, communication protocols, scheduling requirements (with commissioning activities integrated into the master construction schedule), and a warranty phase review occurring approximately 10 months into the 12-month warranty period. The project is dated December 19, 2025, and is currently in DRAFT status pending approval from the COR and team acknowledgment.

View the file

Other files

File Type Posted
Attachment 01 - 36C77626R0106 Tech Questions - dated 7-30-26.docx DOCX document
36C77626R0106 0004.docx DOCX document
Attachment 01d - Addendum R1-001EP400Ga_041EP101_041EP702-Door Schedule-EHRM-689-22-700.pdf PDF
Attachment 01c - Addendum R1-A-601-Door Schedule-EHRM-689-22-700.pdf PDF
Attachment 01a - Addendum R1-S-101_S-502-EHRM-689-22-700.pdf PDF
Attachment 01 - 36C77626R0106 Tech Questions - dated 7-31-26.docx DOCX document
Attachment 01b - Addendum R1-087100 Door Hardware Spec-EHRM-689-22-700.pdf PDF
Attachment 01e - Addendum R1-001TN400Ga_041TN101-Door Schedule-EHRM-689-22-700.pdf PDF
Attachment 01 - 36C77626R0106 Tech Questions - dated 7-30-26.docx DOCX document
36C77626R0106 0003.docx DOCX document
Attachment 01a - Addendum R1-A-601-Door Schedule-EHRM-689-22-700.pdf PDF
Attachment 02 - Revised 1442 - 36C77626R0106.docx DOCX document
Attachment 01c -Addendum R1-Structural Drawings-EHRM-689-22-700.pdf PDF
Attachment 01b - 08 71 00 - Door Hardware_Rev1.pdf PDF
36C77626R0106 0002.docx DOCX document
Attachment 01 - Sign-In Sheet - 689-22-700 - EHRM West Haven - 7-13-26.pdf PDF
36C77626R0106 0001.docx DOCX document
Attachment 08 - VOL_3a-ARCH-VA_CT_West_Haven_EHRM_IU-689-22-700.pdf PDF
Attachment 13 - VOL_5c-ELECTRICAL-VA CT West Haven EHRM IU-689-22-700.pdf PDF
Attachment 05c - Specifications_Div_26-28-West_Haven_EHRM_IU-689-22-700.pdf PDF
Attachment 05a - Specifications_Div_00-13-West_Haven_EHRM_IU-689-22-700.pdf PDF
Attachment 19 - APPNDX_D-Geotechnical_Report-VA_CT_West_Haven_EHRM_IU-689-22-700.pdf PDF
Attachment 05b - Specifications_Div_21-23-West_Haven_EHRM_IU-689-22-700.pdf PDF
Attachment 17 - APPNDX_B-Drainage_Rprt-VA_CT_West_Haven_EHRM_IU-689-22-700.pdf PDF
Attachment 07 - VOL_2-STRUCT-VA_CT_West_Haven_EHRM_IU-689-22-700.pdf PDF
Attachment 06 - VOL_1-CIVIL-VA_CT_West_Haven_EHRM_IU-689-22-700.pdf PDF
Attachment 09 - VOL_3b-ARCH-VA_CT_West_Haven_EHRM_IU-689-22-700.pdf PDF
Attachment 22 - 689-22-700 Risk Matrix 2026.pdf PDF
Attachment 21 - APPNDX_F-Topo Survey-VA CT West Haven EHRM IU-689-22-700.pdf PDF
Attachment 18 - APPNDX_C-Environmental_Report-VA_CT_West_Haven_EHRM_IU-689-22-700.pdf PDF
Attachment 15 - VOL_6b-TELECOM-VA_CT_West_Haven_EHRM_IU-689-22-700.pdf PDF
Attachment 11 - VOL_5a-ELECTRICAL-VA CT West Haven EHRM IU-689-22-700.pdf PDF
Attachment 14 - VOL_6a-TELECOM-VA_CT_West_Haven_EHRM_IU-689-22-700.pdf PDF
Attachment 05d - Specifications_Div_31-33-West_Haven_EHRM_IU-689-22-700.pdf PDF
Attachment 10 - VOL_4-MECH-VA_CT_West_Haven_EHRM_IU-689-22-700.pdf PDF
Attachment 20 - APPNDX_E-PSRDM_Conformance_Letter-VA_CT_West_Haven_EHRM_IU-689-22-700.pdf PDF
Attachment 12 - VOL_5b-ELECTRICAL-VA CT West Haven EHRM IU-689-22-700.pdf PDF
Attachment 02 - Site Visit - West Haven.docx DOCX document
Attachment 01 - Limitations on Subcontracting - EHRM West Haven.docx DOCX document
Attachment 03 - Wage Determination CT20260023 Rev 2 dated 5-18-26.pdf PDF
Attachment 04 - Project Information Sheet for Contractors.docx DOCX document
36C77626R0106.docx DOCX document
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX A – COMMISSIONING PLAN

EHRM INFRASTRUCTURE UPDGRADE DESIGN

VA Healthcare System, West Haven, CT 06513

Project #: 689-22-700

APPENDIX A – COMMISSIONING PLAN

VA Project #: 689-22-700 EHRM Infrastructure Upgrades

West Haven VA Medical Center 950 Campbell Ave West Haven, CT 06516

December 19, 2025

DRAFT Commissioning Plan

Prepared by:

DAV Energy Solutions, Inc.

2207 Garnet Ave, Suite I San Diego, CA 92109

(619) 770-8552

DraŌ Commissioning Plan

Project Name: VA CT West Haven EHRM Infrastructure Upgrades Cx Department of Veteran’s Affairs Davenergy Project Number: 61123 Page 1 of 35 December 19, 2025

TABLE OF CONTENTS

Contents

TABLE OF CONTENTS

1. Overview

1.A. Purpose 1.B. DefiniƟon 1.C. ObjecƟves 1.D. AbbreviaƟons/Acronyms

2. Commissioning Team Data 2.A. Commissioning Team InformaƟon 2.B. 3rd Party TesƟng InformaƟon 2.C. Commissioning OrganizaƟon Chart

3. Systems to be Commissioned 3.A. Project DescripƟon 3.B. Systems

4. Roles and ResponsibiliƟes

5. Commissioning Process

5.A. Commissioning Kick-Off MeeƟng - Design Phase 5.B. Commissioning OPR / BOD Review - Design Phase 5.C. Commissioning SpecificaƟon DraŌing - Design Phase 5.D. Commissioning Design Reviews - Design Phase 5.E. Commissioning Controls Review MeeƟng - Design Phase 5.F. Commissioning Kick-Off MeeƟng - ConstrucƟon Phase 5.G. Final Commissioning Plan - ConstrucƟon Phase 5.H. Site ObservaƟon - ConstrucƟon Phase 5.I. Miscellaneous MeeƟngs - ConstrucƟon Phase 5.J. Miscellaneous Management Protocols/Lines of CommunicaƟon - ConstrucƟon Phase 5.K. Field ReporƟng and Logs - ConstrucƟon Phase 5.L. SubmiƩals, NoƟficaƟons, ClarificaƟons - ConstrucƟon Phase 5.M. Start-up Plan - ConstrucƟon Phase 5.N. Pre-FuncƟonal Checklists (PFCs) - ConstrucƟon Phase 5.O. ExecuƟon of Start-up Plan and Pre-FuncƟonal Checklists - ConstrucƟon Phase 5.P. Deficiencies and Non-Conformance - ConstrucƟon Phase 5.Q. Controls Checkout Plan: EMCS and SCADA - ConstrucƟon Phase 5.R. Development of FuncƟonal Performance Test Procedures - ConstrucƟon Phase 5.S. Systems Manual - Acceptance Phase 5.T. ExecuƟon of FuncƟonal Performance TesƟng - Acceptance Phase 5.U. Training and OrientaƟon of Owner Personnel - Acceptance Phase 5.V. Final Commissioning Report - Acceptance Phase 5.W. Warranty Phase Commissioning

6. Schedule 6.A. General Issues 6.B. Project Schedule

7. ConstrucƟon Phase Commissioning Plan Revision History 7.A. Revision History

Davenergy Project Number: 61123 Page 2 of 35 December 19, 2025

Appendices:

Appendix A: Roles & ResponsibiliƟes

Appendix B: Detailed Commissioning Team Roles & ResponsibiliƟes Matrix (per VA spec 01 91 00)

Appendix C: Sample PFC and FPT Forms

Davenergy Project Number: 61123 Page 3 of 35 December 19, 2025

1. Overview

1.A. Purpose

1. The purpose of the Commissioning (Cx) Plan is to provide guidance for the commissioning process and documentaƟon during construcƟon, parƟcularly with respect to parƟcipaƟon, reporƟng, approvals, coordinaƟon and actual lines of communicaƟon by various team members as it relates to submiƩal reviews, development and performance of Pre-FuncƟonal checklists (PFCs) and FuncƟonal Performance Tests (FPTs), and scheduling of Cx acƟviƟes. (Note: Commissioning Authority (CxA) does not provide official direcƟon to other members of the Cx Team, rather, only assistance and management of the commissioning process. In addiƟon, the Cx process is not intended to change the resoluƟon process that is idenƟfied in the respecƟve contracts of Cx Team members.)

a. Provide samples of the forms to be used during the commissioning process (and referenced in this plan). These forms are listed in Appendix A of this document.

b. This plan provides sample Pre-FuncƟonal Checklists (PFCs) and FuncƟonal Performance Test (FPTs) procedures that are not specific to this project, rather, that will be modified into draŌ forms based on the final design package and approved submiƩals. The draŌ forms shall then be submiƩed to the Cx team for review and acceptance. Final versions of the PFCs and FPTs shall incorporate Cx Team comments as well as addiƟonal details provided in the approved equipment submiƩals and control shop drawings.

c. The Cx Plan has been wriƩen in concert with the Statement of Work, however, if conflicts with other contract requirements are idenƟfied, the more stringent criteria shall apply. Conflicts shall be brought to the aƩenƟon of the CxA. All members of the Cx Team shall work together to fulfill their contracted responsibiliƟes and meet the objecƟves of the Contract Documents.

1.B. Deϐinition

1. Commissioning (Cx) - A systemaƟc process of assuring by verificaƟon and documentaƟon, from the design phase to a minimum of one year aŌer construcƟon, that all building facility systems perform interacƟvely in accordance with the design documentaƟon and intent and in accordance with the Owner’s operaƟonal needs, including training of the Owner operaƟons and maintenance personnel.

2. Pre-FuncƟonal Checklists (PFCs) – VerificaƟon checklists developed by the CxA, with input from equipment vendors, to verify that contract design requirements are met and that the system is ready for FPT. This includes checklists for general readiness, pre-funcƟonal tesƟng, training, and other specific requirements.

3. Cx Authority (CxA) – The enƟty idenƟfied by the Owner who draŌs the Cx Plan, witnesses and records the FuncƟonal Performance TesƟng, submits reports on the Cx progress and prepares the Final Cx Report.

Davenergy Project Number: 61123 Page 4 of 35 December 19, 2025

4. Cx Plan – The document that idenƟfies acƟviƟes to be included in the project baseline schedule, PFCs and FuncƟonal Performance Test (FPT) requirements for commissioning. The Cx Plan is submiƩed as a DraŌ Plan during the Design Phase, ConstrucƟon Cx Plan during Project ExecuƟon and updated aŌer approval of equipment submiƩals.

5. Cx Team – Members of the project Cx team shall consist of (but not be limited to) the CxA, the COR, Owner Technical Specialists, the ExecuƟng Contractor (GC) and their Subcontractors, Equipment Vendors, and Title II (A/E).

6. Final Cx Report – The report prepared and submiƩed by the CxA aƩesƟng that all equipment, systems, the O&M manual and Owner training meet contract requirements.

7. FuncƟonal Performance Test (FPT) – DemonstraƟon that each system is operaƟng according to the documented design and contract requirements. Performance tesƟng facilitates bringing the systems from a state of individual substanƟal compleƟon to full dynamic operaƟon.

8. Issues Log – A formal record of equipment and system non-conformance (to contract requirements) idenƟfied by the Cx Team, along with the proposed and final resoluƟons.

9. Owner Project Requirements (OPR) – The project funcƟonal requirements and the measurable performance criteria of how it shall be used and operated.

10. Pre-FuncƟonal TesƟng – Documented tesƟng performed by the execuƟng contractor or equipment vendor during or aŌer start-up. This tesƟng shall be completed prior to scheduling the

FPT.

11. Start-Up – The iniƟal starƟng or acƟvaƟng of dynamic equipment, including compleƟng and submiƫng Pre-FuncƟonal Checklists (PFCs).

12. Test Procedures – A wriƩen protocol that defines methods, personnel, and expectaƟons for tests conducted on components, equipment, assemblies, systems and interfaces among systems.

TesƟng procedures are included in the contract specificaƟons, approved submiƩals, and the ConstrucƟon Cx Plan. The FPT includes the dynamic funcƟons and operaƟons of equipment and systems using manual or monitoring methods under full system operaƟons. Systems shall be tested under various modes, such as during low cooling loads, high loads, component failures, unoccupied, varying outside air temperatures, fire alarm, power failure, etc. Systems shall be run through the Control System’s (EMCS, SCADA) sequences of operaƟon. Components responses shall be verified per the sequence of operaƟon requirements.

13. VerificaƟon – The process by which specific documents, components, equipment, assemblies, systems, and interfaces among systems are documented and are in compliance with the criteria in the contract requirements.

1.C. Objectives

1. Commissioning during the construcƟon phase of this project is intended to achieve the following specific objecƟves of the Contract Documents:

Davenergy Project Number: 61123 Page 5 of 35 December 19, 2025

a. Ensure applicable equipment and systems are installed properly and receive adequate operaƟonal checkout by installing contractors.

b. Verify and document proper funcƟonal performance of equipment and systems.

c. Ensure Contractor has provided O&M documentaƟon as specified by the Owner.

d. Ensure the Owner’s operaƟng personnel is adequately trained.

Davenergy Project Number: 61123 Page 6 of 35 December 19, 2025

1.D. Abbreviations/Acronyms The following abbreviaƟons are used in this Commissioning Plan:

A/E Architect / Engineer of Record HVAC HeaƟng, VenƟlaƟng and Air CondiƟoning

AHJ Authority Having JurisdicƟon IFC Issued For ConstrucƟon

AHU Air Handling Unit IV&V Independent ValidaƟon and VerificaƟon Team

AKA Also known as IST Integrated Systems Test

BOD Basis of Design OWNER Department of Veteran’s Affairs (aka Owner, and/or Client)

BAS Building AutomaƟon System MC Mechanical Contractor

Cx Commissioning NETA NaƟonal Electrical TesƟng AssociaƟon

CxA Commissioning Authority NFPA NaƟonal Fire ProtecƟon AssociaƟon

Cx Plan

Commissioning Plan NTP NoƟce to Proceed

CxT Commissioning Team O&M OperaƟons and Maintenance InstrucƟons

CC ConstrucƟon Checklist (aka PFC) OGC Other Owner Contractor

CM ConstrucƟon Manager OPR Owner’s Project Requirements

CO ContracƟng Officer PES Project ExecuƟon Schedule

COR ContracƟng Officer RepresentaƟve PFC Pre-FuncƟonal Checklist (aka CC)

DCR Daily Commissioning Reports PM Project Manager, Owner

DOM Delivery Order Manager PTN Project Tracking Number

Doc ID Document IdenƟfier QA Quality Assurance

EC Electrical Contractor QC Quality Control

EPO Emergency Power Off RE Resident Engineer

EMCS Energy Management and Control System

RFI Request For InformaƟon

FAT Factory Acceptance Test RFP Request For Proposal

Davenergy Project Number: 61123 Page 7 of 35 December 19, 2025

FPT FuncƟonal Performance Test SUP Start-up Plan

GC General Contractor (aka Contractor) TAB Test, Adjust and Balance subcontractor

OFCI Owner Furnished Contractor Installed

Davenergy Project Number: 61123 Page 8 of 35 December 19, 2025

2. Commissioning Team Data

2.A. Commissioning Team Information List of Commissioning Team Members and Contact InformaƟon

DescripƟon Role Contact Name

Phone/Email

Owner (West Haven

VAMC)

Project Manager (COR) Peter Sandor Peter.sandor@va.gov VA ContracƟng Officer Denise Bailey Denise.bailey4@va.gov VA Resident Engineer

DescripƟon Role Contact Name

Phone/Email

Design

(Spees Design Build / WSP

USA, INC /

Performance Environmental)

Project Manager James Stoddard james@speesdb.com

(504) 350-8777

Architect (Blue Architecture) TBD (206) 590-2118 Mechanical (Spees Design Build)

TBD

(206) 590-2118

Electrical (Spees Design Build) TBD (206) 590-2118 Fire ProtecƟon (Spees Design Build)

TBD

(206) 590-2118

Civil (WSP USA, INC.) TBD (206) 431-2300 Structural (WSP USA, INC.) TBD (206) 431-2300 CommunicaƟons (WSP USA, INC.)

TBD

(206) 431-2300

Environmental (Performance Environmental)

TBD

(412) 616-1173

DescripƟon Role Contact Name

Phone/Email

ConstrucƟon (Company

Name)

Project Manager Superintendent Quality Assurance Project Engineer

DescripƟon Role (Company) Contact Name

Phone/Email

Sub- Contractors

Infrastructure (Company) Mechanical (Company) Electrical (Company) Plumbing (Company) Controls (Company)

Davenergy Project Number: 61123 Page 9 of 35 December 19, 2025

List of Commissioning Team Members and Contact InformaƟon

DescripƟon Role Contact Name

Phone/Email

Fire Alarm & Control (Company)

Security (Company) Test and Balance (Company)

DescripƟon Role (Company) Contact Name

Phone/Email

Commissioning

(VA)

Davenergy SoluƟons Inc.

Project Manager & CxA Andrew Gaffield

(315) 663-5550 Andrew.Gaffield@davenergy.com

Sr. Cx Engineer Alex Boucher

(919) 635-8545 Alexander.Boucher@davenergy.com

Field Cx Engineer Tim Buskell

(719) 648-7207 Ɵm.buskell@davenergy.com

Davenergy Project Number: 61123 Page 10 of 35 December 19, 2025

2.B. 3rd Party Testing Information The table below outlines the list of commissioning team members who will perform the 3rd party equipment tesƟng. The role of the CxA is to confirm the selected 3rd party tesƟng agencies meet the qualificaƟons called out in the division specificaƟons. This informaƟon is normally reviewed during the submiƩal process. Once the equipment is installed, the CxA will also review the tesƟng procedures to confirm their conformance to the equipment specificaƟons and design intenƟon.

List of Commissioning Team Members and Contact InformaƟon Role DescripƟon (Company) Contact Name Phone/Email

3rd Party TesƟng Agents

Grounding & Bonding System TesƟng Agent (Company)

TBD TBD

Electrical Power Monitoring System TesƟng Agent (Company)

TBD TBD

Davenergy Project Number: 61123 Page 11 of 35 December 19, 2025

2.C. Commissioning Organization Chart The organizaƟon chart below highlights the key members associated with the commissioning process. For specific contact names and informaƟon, refer to secƟon 2A and 2B above. The commissioning agent (Davenergy) works for the Owner (VA) and does not have any authority over the other jurisdicƟons.

Figure 1: Commissioning OrganizaƟon Chart

Davenergy Project Number: 61123 Page 12 of 35 December 19, 2025

3. Systems to be Commissioned

3.A. Project Description The overall intent of this project is to upgrade and improve the Electronic Health Record ModernizaƟon (EHRM) infrastructure of the West Haven VA Healthcare campus in West Haven, ConnecƟcut as part of the ongoing naƟonal VA EHRM iniƟaƟve. Per the SOW and the VA-provided HEFP Readiness Assessment, sixty (60) TelecommunicaƟons Rooms (TRs) and 1 Data Center (DC) of the West Haven VAMC are within the scope of this project. Commissioning will include FPT of the mechanical systems within the scope of this project. Commissioning of electrical and telecommunicaƟon systems will consist of submiƩal and report review, as well as site observaƟons and spot checks.

3.B. Systems The following systems shall be commissioned as part of this project. All general references to equipment in this document refer only to the equipment that is specified to be commissioned.

Systems To Be Commissioned Building System System

Component Equipment QuanƟty Test

Sample

Mechanical and HVAC Systems

HVAC Air DistribuƟon

VRF Units 84 50% (5)

Ductless Split System 15 100% Air Cooled Condensing Units 2 100% Data Center CRAC Systems 2 100% Blast Suppression Damper 5 100% Exhaust Fans 7 100%

Supply Fan 1 100% Transfer Fan 6 100% Roof Hood 4 100% Electric Unit Heater 1 100%

ERV 1 100%

Dehumidifier 2 100% Air–Cooled Condensing Unit 2 100%

Steam Systems Clean Steam Generator 1 100% Emergency Power

Generator Fuel Tank 2 100% Fuel Transfer/Polishing System 1 100%

Fuel Oil Pump Skid 1 100% Generator 1 100% Building AutomaƟon System (BAS)

Graphical User Interface Included (1) Building Controllers and Programming Included (1) Sequence of OperaƟons Included 100% (1)

Davenergy Project Number: 61123 Page 13 of 35 December 19, 2025

Systems To Be Commissioned Misc. Systems Fiber Feeds Fiber feeds and IT layouts Included (3)

Rack Sensors Rack Temperature Sensors Included (1) Electrical and Power Systems

Integrated Systems

UPS Monitoring Included (3) Panelboards TBD 100% (2) Transformer TBD 100% (2)

ATS TBD 100% (2)

UPS Systems Included (3) Low Voltage System TesƟng (telecom) Included (3)

Emergency Power VerificaƟon Included (2)

Table / Scope Notes

Note (1) The programming operaƟon of the controllers, sensors, and actuators are all verified during tesƟng of the respecƟve equipment.

Note (2) TesƟng is limited to systems added/modified as part of the project.

Note (3) VerificaƟon consists of submiƩal & report review, as well as site observaƟons

Note (4) TAB validaƟon will be reviewed via provided TAB report and only invesƟgated if FPT issues arise.

Note (5) TesƟng may exceed 50% of units to ensure all Independent Units which do not have redundancy support are tested

4. Roles and Responsibilities

1. The Cx Team consists of Owner RepresentaƟves, Facility Staff, Design Engineer of Record, ConstrucƟon Manager, General Contractor, Subcontractors of the General Contractor, and the Cx Authority.

2. Listed below are general roles and responsibiliƟes for the ConstrucƟon and Acceptance Phase, refer to the project specificaƟons for addiƟonal responsibiliƟes and further clarificaƟons.

3. Unless otherwise agreed upon by the Commissioning Team (CxT) members, the standard review/comment and response periods for all documents shall be two (2) weeks. The CxA shall provide a Cx Comment Form to log and track comments and responses from all team members.

4. Owner

a. The COR is responsible for approving, resolving, and providing direcƟon to Contractors throughout the course of this project. This shall include reviewing and approving transmiƩal of documents and comments among Cx Team members through the use of the approved document control applicaƟon.

b. Owner tasks include:

i. Facilitate the coordinaƟon of the commissioning work by the CxA.

Davenergy Project Number: 61123 Page 14 of 35 December 19, 2025

ii. With the GC and CxA, ensure commissioning acƟviƟes are being included into the Contractor’s master schedule with appropriate duraƟons and linking of predecessor and successor acƟviƟes.

iii. Provide the CxA with a copy of the OPR and BOD documentaƟon prepared by the A/E during the design phase.

iv. Review and approve the Final Commissioning Plan.

v. ParƟcipate in the Cx Kick-Off meeƟng and other Cx Team meeƟngs.

vi. Provide the CxA with copies of all construcƟon documents, addenda, change orders, approved submiƩals and shop drawings relaƟng to commissioned equipment.

vii. Review and approve Pre-FuncƟonal Checklists (PFCs) and FuncƟonal Performance Tests

(FPTs) submiƩed by the CxA, prior to tesƟng.

viii. Review commissioning progress and deficiency reports.

ix. Arrange for facility operaƟng and maintenance personnel to parƟcipate in various commissioning team acƟviƟes (e.g., commissioning tesƟng and training sessions).

x. Assist CxA in coordinaƟng the training of Owner personnel by the ExecuƟng Contractor and Equipment Vendors.

5. Commissioning Authority (CxA)

a. The CxA is not responsible for design concept, design criteria, compliance with codes, design or general construcƟon scheduling, cost esƟmaƟng or construcƟon management. The CxA may assist with problem solving, non-conformance or deficiencies, but ulƟmately that responsibility resides with the COR, GC, or A/E.

b. The primary role of the CxA during the construcƟon phase is to develop, coordinate, oversee and supervise the execuƟon (by contractors) of the commissioning process as described by the Commissioning Plan and required by the specificaƟons, observe and document systems are funcƟoning and performing in accordance with the Contract Documents, assure proper project documentaƟon is provided to the Owner and assure proper training of Owner’s operaƟons personnel is provided.

c. Commissioning Authority tasks include the following:

i. Provide all commissioning documentaƟon electronically to the Owner in source format (e.g., Word, Excel, or PDF).

ii. Work with the GC and the Owner to help integrate commissioning acƟviƟes into the master schedule.

iii. Revise the Cx Plan with input from the Cx Team, as necessary.

iv. Provide responses to comments received on CxA work products (e.g., Cx Plan, PFCs, FPTs, and IST’s) by other Cx Team members.

v. Document, track and update the status of all comments generated by the Cx Team, and as approved by the COR, in the Cx Issues Log (or other document-specific consolidated comment log, which would be maintained separately from the Cx Issues Log) for resoluƟon.

Davenergy Project Number: 61123 Page 15 of 35 December 19, 2025

vi. Conduct a Cx Kick-Off MeeƟng with the Cx Team.

vii. Conduct and document periodic Cx CoordinaƟon MeeƟngs. Cx CoordinaƟon MeeƟngs are generally held more frequently prior to and during the tesƟng phase of the Cx process.

viii. Review and comment on all construcƟon documents, addenda, change orders, approved submiƩals and shop drawings relaƟng to systems being commissioned for compliance with commissioning requirements.

ix. Review and comment on ConstrucƟon MeeƟng Minutes relaƟng to the Cx process and assist in the resoluƟon of any issues.

x. Review, comment and recommend approval (to the COR) of Contractor submiƩals applicable to systems being commissioned.

xi. Develop system level Pre-FuncƟonal Checklists (PFCs) using informaƟon provided by the Contractors (i.e. submiƩals and checkout procedures) and distribute for Contractor use.

xii. Develop FPTs using approved submiƩals (i.e. equipment submiƩals, control shop drawings) with input from the Cx Team (including Contractors).

xiii. Conduct periodic site visits to observe component and system installaƟon. Provide Daily Cx Report to COR aŌer each site visit.

xiv. Review 3rd party tesƟng agency qualificaƟons, tesƟng plan, and tesƟng results. On-site 3rd party tesƟng observaƟons will be made when designated and preferred by the owner.

xv. The CxA shall observe all tesƟng during pre-funcƟonal tesƟng to verify compliance with the Pre-FuncƟonal Checklists (PFCs) that are completed by the Contractors.

xvi. Review and recommend approval (to the COR) of Contractor completed and submiƩed Pre-FuncƟonal Checklists.

xvii. Coordinate with the parƟcipants, witness, and document Contractor execuƟon of all FPTs.

xviii. IdenƟfy, enter, and update deficiencies in Commissioning Issues Log with input from the Cx Team.

xix. Maintain a Commissioning Issues Log with updated status of documentaƟon created during the commissioning process (i.e. PFCs and FPTs). Include any performance tesƟng documentaƟon that the CxA may not have developed or witnessed.

xx. Provide all completed PFCs and FPTs to the COR for review and acceptance.

xxi. Review, comment and recommend approval (to the COR) of Contractor provided warranƟes confirming that the Owner’s responsibiliƟes are clearly defined.

xxii. Prepare Final Commissioning Report.

6. Architect/Engineer

a. A/E Tasks may include the following, as directed by Owner:

i. ParƟcipate in Commissioning Kick-Off meeƟng.

ii. Provide responses to comments received on A/E work products (e.g., Project Manual, drawings, specificaƟons) by other Cx Team members.

Davenergy Project Number: 61123 Page 16 of 35 December 19, 2025

iii. Provide clarificaƟons to design intent as well as operaƟon and control of commissioned systems in areas where the specificaƟons, control drawings or equipment documentaƟon is not sufficient for wriƟng detailed tesƟng procedures.

iv. ParƟcipate in commissioning issue resoluƟons and coordinaƟon meeƟngs.

v. Review and comment on PFCs and FPTs developed by the CxA to ensure the designer’s intent for funcƟonality has been properly interpreted.

7. ConstrucƟon Manager/General Contractor (including Subcontractors, as applicable)

a. Contractor tasks include the following:

i. Assign responsibility of commissioning tasks to Subcontractors.

ii. Facilitate the coordinaƟon of the commissioning work; ensure acƟviƟes are being scheduled into the Contractor’s master schedule with appropriate duraƟons and linking of precursor and successor acƟviƟes.

iii. Provide responses to comments received on GC and Subs work products (e.g., installaƟon tests) by other Cx Team members.

iv. During the submiƩal process, encourage vendors/Subcontractors to comment on whether the specified products are the newest, most current equipment, and applicaƟon is suitable for the project(s).

v. Prepare and maintain an updated detailed commissioning tesƟng schedule.

vi. AƩend the Commissioning Kick-Off meeƟng and other selected commissioning meeƟngs, as necessary, as requested by other Cx Team members.

vii. Review and comment on PFCs and FPTs, to assure they are applicable to demonstrate funcƟonal performance, can actually be performed, will not damage equipment and will not void equipment warranty.

viii. Execute and document compleƟon of checkout plans and PFCs, per contract documents.

ix. Execute FPTs as coordinated by the CxA or COR.

x. Resolve commissioning issues in a Ɵmely manner and prior to Final CompleƟon. NoƟfy Cx

Team in wriƟng of correcƟve acƟons taken.

xi. Sign-off final acceptance on individual checkout plans, PFCs and FPTs as completed and passed.

Davenergy Project Number: 61123 Page 17 of 35 December 19, 2025

5. Commissioning Process This secƟon sequenƟally (as pracƟcal) details the commissioning process by commissioning task or acƟvity. The following descripƟons are intended to indicate the sequence in which the acƟviƟes generally take place, not to fully define the scope of the work. For full details on the commissioning processes and acƟviƟes please see the project commissioning specificaƟons.

5.A. Commissioning Kick-Off Meeting - Design Phase

1. A Cx Kick-Off meeƟng is planned and conducted by the CxA within 10 (Ten) days of NoƟce to

Proceed.

2. In aƩendance are the respecƟve representaƟves of the CxA, Owner, and A/E.

3. At the meeƟng:

a. Design Phase Commissioning team members are introduced.

b. Commissioning process is reviewed as a whole.

c. Management and reporƟng lines are determined for the Design Phase.

d. The processes for compleƟon of commissioning design reviews, comment resoluƟon, and comment tracking are discussed and agreed upon.

e. The DraŌ Commissioning Plan is reviewed, process quesƟons are addressed, lines of reporƟng and communicaƟons determined, and the work products list discussed.

f. Team member(s) general list of responsibiliƟes is defined.

4. The outcome of the meeƟng is an increased understanding by all team members of the commissioning process and their respecƟve responsibiliƟes. The meeƟng provides the CxA addiƟonal informaƟon needed to finalize the ConstrucƟon Phase Commissioning Plan.

5.B. Commissioning OPR / BOD Review - Design Phase

1. The CxA will begin the design phase by first reviewing the OPR to develop a detailed understanding of what the Owner wishes to achieve in the building, as well as how it will operate.

2. AŌer a firm understanding of the OPR, the CxA will review the BOD or DID to understand how the design profession will provide a design that saƟsfies the OPR.

5.C. Commissioning Speciϐication Drafting - Design Phase

1. The CxA will develop the commissioning specificaƟons for use in the construcƟon documents.

2. The commissioning specificaƟons will be developed based on the OPR and the commissioning scope listed above.

The specificaƟons will be provided prior to formal design reviews so that all stakeholders have an opportunity to review and comment.

3. The commissioning specificaƟons will be developed to match the project specificaƟons and include Divisions 1, 23, 26, 27, 28, and other secƟons as needed to ensure commissioning requirements are properly accounted for in the project documents.

Davenergy Project Number: 61123 Page 18 of 35 December 19, 2025

5.D. Commissioning Design Reviews - Design Phase

1. The A/E will develop the construcƟon documents which will be used to guide the construcƟon team in implemenƟng the design.

2. The CxA will parƟcipate in the 35%, 65%, 95% and 100% review documents and formal review by the Owner. The CxA will base the review on conformance to the OPR, the ability to operate and maintain the equipment, and the ability to commission the equipment.

3. At the compleƟon of each formal review cycle the CxA will parƟcipate in a design review comment resoluƟon meeƟng.

a. The meeƟng will be facilitated by either the Owner or the A/E with the intent of resolving as many issues brought up during the design review processes as possible.

5.E. Commissioning Controls Review Meeting - Design Phase

1. A Controls Review meeƟng will be coordinated by the CxA and will include the A/E, and the Owner prior to the 95% design submission by the A/E.

a. The intent of the meeƟng is to facilitate an open dialog between the Owner and the A/E about the controls system, features, alarms and sequences.

b. At the compleƟon of the meeƟng the A/E will revise any/all sequences of operaƟon, alarm requirements, and controls features based on the Owner’s decisions.

5.F. Commissioning Kick-Off Meeting - Construction Phase

1. A Cx Kick-Off meeƟng is planned and conducted by the CxA within forty-five (45) days of the beginning of construcƟon or the CxA’s noƟce to proceed, whichever is later.

2. In aƩendance are the respecƟve representaƟves of the COR, GC, CxA, A/E and the mechanical, and electrical Subcontractors.

3. At the meeƟng:

a. Commissioning team members are introduced.

b. Commissioning process is reviewed.

c. Management and reporƟng lines are determined.

d. The flow of documents and CxA required submiƩals are discussed. This includes design submiƩals, factory witness test reports, installaƟon test reports, detailed acƟvity schedules, tesƟng agency and controls contractor submiƩals.

e. The Commissioning Plan is reviewed, process quesƟons are addressed, lines of reporƟng and communicaƟons determined, and the work products list discussed.

f. Team member(s) general list of responsibiliƟes is defined.

4. The outcome of the meeƟng is an increased understanding by all team members of the commissioning process and their respecƟve responsibiliƟes. The meeƟng provides the CxA addiƟonal informaƟon needed to finalize the ConstrucƟon Phase Commissioning Plan.

Davenergy Project Number: 61123 Page 19 of 35 December 19, 2025

5. Prior to this meeƟng the CxA is given, by the Owner, all drawings and specificaƟons and the construcƟon schedule by trade. The CxA keeps notes and acƟon lists from the meeƟng and distributes them to each team member through the approved document control applicaƟon.

5.G. Final Commissioning Plan - Construction Phase

1. The CxA finalizes the DraŌ ConstrucƟon Phase Commissioning Plan using the informaƟon gathered from the Kick-Off meeƟng.

2. The construcƟon schedule is reviewed, amended and revised, as necessary, to incorporate commissioning acƟviƟes and their duraƟons. The Ɵmeline is fine-tuned as construcƟon progresses.

3. The Cx Plan is approved by the COR and acknowledged by all Cx Team members in the Cx Team Data secƟon of the Cx Plan.

5.H. Site Observation - Construction Phase

1. The CxA shall make periodic visits to the site, as necessary, to witness equipment and system installaƟon.

5.I. Miscellaneous Meetings - Construction Phase

1. The CxA aƩends selected planning and job-site meeƟngs in order to remain informed on construcƟon progress and to update team members involved in commissioning.

2. The GC shall inform the CxA of submiƩed informaƟon regarding subsƟtuƟons, change orders and any requests for informaƟon or Architect’s Supplemental InstrucƟons that may affect commissioning equipment, systems or the commissioning acƟviƟes scheduled.

3. The CxA may review construcƟon meeƟng minutes, change orders, requests for informaƟon or ASIs for the same purpose.

4. During construcƟon, meeƟngs between various commissioning team members shall be scheduled by the CxA, through the COR and GC as required.

5.J. Miscellaneous Management Protocols/Lines of Communication - Construction Phase

1. Informal lines of communicaƟon are permiƩed at all levels among all team members, when warranted. This shall be discussed at the Cx Kick-Off meeƟng.

2. Courtesy copies of communicaƟons are permiƩed at all levels, as needed.

3. Refer to Cx Team Data in secƟon 2 of Cx Plan for specific points of contact.

4. Table 1. Addresses common issues and the associated protocols for communicaƟng within the project team.

Table 1. CommunicaƟon Protocols- ConstrucƟon Phase

Davenergy Project Number: 61123 Page 20 of 35 December 19, 2025

ISSUE PROTOCOL

Requests for InformaƟon (RFI) or formal documentaƟon requests:

At the direcƟon of the COR, the CxA shall bring the issue to the weekly construcƟon progress meeƟng for veƫng prior to entering the issue into the approved document control applicaƟon.

Minor or verbal informaƟon and clarificaƟons:

The CxA issues a memo (or email) for documentaƟon to the COR, GC, and the A/E (or other applicable team members).

NoƟfying contractors of commissioning related deficiencies:

The CxA documents commissioning related deficiencies in the issues log. Commissioning related deficiency issues may not be discussed with contractors prior to noƟfying the COR or GC. The CxA has no authority to provide direcƟon.

Scheduling funcƟonal tests:

The CxA may provide input and perform some coordinaƟon of tesƟng, but does not schedule. The COR and GC are responsible for scheduling the tesƟng.

Scheduling commissioning meeƟngs:

The CxA coordinates with the COR (and the GC) to idenƟfy an acceptable date/Ɵme/locaƟon.

Request for significant changes:

The CxA has no authority to issue change orders. Significant issues shall be brought to the aƩenƟon of the COR and GC.

Minor changes in specified sequences of operaƟons:

The CxA shall not make changes to specified sequences without approval from the COR. The CxA shall suggest recommendaƟons, however, the CxA has no authority to provide direcƟon.

Subcontractors disagreements with requests or interpretaƟons by the CxA:

Subcontractors shall discuss and aƩempt resoluƟon with the CxA first. When warranted, the GC (through the COR) shall resolve the situaƟon. The COR shall provide the final resoluƟon.

5.K. Field Reporting and Logs - Construction Phase

1. The CxA shall issue reports with increasing frequency as the commissioning acƟvity increases.

The CxA may adjust the reporƟng frequency as needed and as approved by the COR.

2. The field reports shall contain (as it relates to funcƟonal tesƟng) an update of the schedule with a list of requested schedule changes and new items (PFCs, FPTs and/or ISTs) added to the schedule, a list of new and outstanding deficiencies, and a descripƟon of commissioning progress corresponding to the plan, etc.

3. The CxA keeps a log of all commissioning-related issues requiring current or future aƩenƟon using a Commissioning Issues Log.

Davenergy Project Number: 61123 Page 21 of 35 December 19, 2025

4. Commissioning Issues Log provides a sample format for tracking the status of documentaƟon and tesƟng for each piece of equipment and system (e.g., installer, or team member responsible for approval dates for checklist and tesƟng forms as well as their compleƟon, etc.).

5. The CxA regularly communicates with all members of the commissioning team, keeping them appraised of commissioning progress and scheduling issues.

6. The CxA shall keep all commissioning materials in an organized format.

5.L. Submittals, Notiϐications, Clariϐications - Construction Phase

1. Standard SubmiƩals

a. SubmiƩal Log. The CxA shall make official requests for any items not listed on the iniƟal submiƩal log through the COR, who may in turn choose to forward request to the GC.

b. Cx focused submiƩal reviews are performed concurrently with the normal A/E submiƩal review.

c. The CxA shall review and comment on submissions relaƟve to commissioning issues expressed in the contract documents - not for general contract compliance (which is the A/E’s responsibility) unless specifically directed by the Owner to do so.

d. CxA recommendaƟons are provided to the COR through the approved document control applicaƟon.

2. Special SubmiƩals, NoƟficaƟons and ClarificaƟons

a. All Cx Team members (i.e. the COR, GC, Subs, A/E) shall noƟfy the CxA of any new design intent or operaƟng parameter changes, added control strategies and sequences of operaƟon, or other change orders that may affect commissioned systems and performance/acceptance criteria during tesƟng.

b. Thirty (30) days prior to performing Owner-contracted tests (i.e. installaƟon tests), GC Subcontractors shall provide complete details of the procedures.

3. The CxA may request addiƟonal design narraƟves from the A/E and from the controls contractor if bid documentaƟon and/or shop drawings are incomplete or insufficient.

4. All Cx RFIs shall be directed to the COR prior to entry into the approved document control applicaƟon. The COR shall assess the issue for discussion at one of the periodic progress meeƟngs. If the issue cannot be resolved at the progress meeƟng, the COR shall advise the CxA to enter the issue into the approved document control applicaƟon. The COR shall be copied on any direct correspondence between the CxA and contractors.

5.M. Start-up Plan - Construction Phase

1. The sequence of start-up tesƟng, within the overall construcƟon and acceptance process, is performed aŌer installaƟon and when all iniƟal Quality Control and inspecƟon tesƟng, concurrently with Pre-FuncƟonal Checklists has been completed and before FuncƟonal Performance TesƟng.

Davenergy Project Number: 61123 Page 22 of 35 December 19, 2025

2. The GC has ulƟmate responsibility for the development of detailed start-up plans for all equipment. The GC typically assigns this responsibility to an applicable subcontractor. The CxA shall develop Pre-FuncƟonal Checklists for the contractor’s use in documenƟng startup of associated equipment and systems as well as documenƟng readiness for funcƟonal performance tesƟng. The manufacturer’s start-up sequence for each piece of equipment shall be used as a starƟng point. The main difference between equipment specific manufacturer startup checks and the Pre-FuncƟonal Checklists (PFCs) is that the PFCs are performed on a system level and cross disciplines (i.e. mechanical, electrical and controls).

3. The Commissioning Issues Log, maintained by the CxA, is uƟlized for tracking the team member(s) responsible for start-up and iniƟal checkout on each part. This informaƟon shall also be indicated on the appropriate Pre-FuncƟonal Checklist.

4. The following procedures shall be used for this project:

a. The subcontractor is responsible for the start-up plan development.

b. The designated subcontractor shall develop the Start-Up Plan and obtain manufacturer installaƟon, start-up and checkout data, including actual field checkout sheets used by the field technicians.

c. Systems that may not have adequate manufacturer start-up and checkout procedures, parƟcularly for components being integrated with other equipment, shall be provided by the subcontractor with necessary detail and documenƟng format for approval, prior to execuƟon.

d. The subcontractor shall create copies of all pages with important instrucƟonal data and procedures (not covered in manufacturer field checkout sheets) from the start-up and checkout manuals. A signature line in the column by each procedure shall be added.

e. The full Start-up Plan shall be transmiƩed by the subcontractor for review and approval. This informaƟon shall be used by the CxA as the starƟng point for PFC development.

5.N. Pre-Functional Checklists (PFCs) - Construction Phase

1. The sequence of Pre-FuncƟonal Checklist compleƟon, within the overall construcƟon and acceptance process, starts with the arrival of cable, devices, and equipment on-site (e.g., ensure proper device or equipment features). This sequence shall conƟnue through iniƟal installaƟon tesƟng and before funcƟonal performance tesƟng.

2. PFCs ensure the equipment and systems are hooked up and operaƟonal to avoid unnecessary delays prior to funcƟonal tesƟng.

3. PFCs are primarily staƟc inspecƟons and procedures to prepare the equipment for iniƟal operaƟon (e.g., oil levels OK, fan belt tension, labels affixed, gages in place, sensor calibraƟon, electrical connecƟons completed, controls connecƟons completed, etc.).

4. Some PFC items entail simple tesƟng of the funcƟon of a component or a piece of equipment, such as measuring the phase rotaƟon on three phase feeders to PDU’s.

Davenergy Project Number: 61123 Page 23 of 35 December 19, 2025

5. Contractors typically perform some, if not many, of the CxA recommended PFC items as a part of their normal operaƟon. However, few contractors document in wriƟng the execuƟon of these checklist items.

a. This project requires all procedures to be documented in wriƟng by the installing technician.

The CxA may not witness the PFC compleƟon, except for tesƟng of larger or more criƟcal pieces of equipment and some spot-checking.

6. PFC requirements are idenƟfied in the commissioning specificaƟons.

7. The CxA shall develop the System Level and Cross Disciplined Pre-FuncƟonal Checklist for review and comment by the Cx Team (including the Subcontractors). The subcontractor’s full startup plan shall be used as a starƟng point for each piece of equipment.

8. During the review and comment of the PFC, the GC shall elect which trade or contractor is responsible for compleƟng each line item (mark in the “Contractor” column).

9. Upon approval of the PFC developed by the CxA, the GC shall assign the PFC to Subcontractors responsible for compleƟon, which shall occur prior to the start of funcƟonal tesƟng.

5.O. Execution of Start-up Plan and Pre-Functional Checklists - Construction Phase

1. Four (4) weeks prior to checkout, all subcontractors and vendors shall confirm the schedule for the iniƟal checkout with the GC. The GC noƟfies the Cx Team of the schedule.

2. The iniƟal checkout is directed, executed and documented by the subcontractor or vendor.

3. Before funcƟonal performance tesƟng can be iniƟated, PFCs for all equipment must be completed and signed as a prerequisite (e.g., installaƟon checks). When all items are complete, the PFC shall be routed for required signatures and then officially submiƩed and forwarded to the CxA for review prior to the start of funcƟonal tesƟng.

4. Each piece of equipment receives a full construcƟon compleƟon checkout by the Contractor. No sampling strategies are permiƩed.

5. The CxA may observe the procedures for each piece of primary equipment, unless there are mulƟple units, when a sampling strategy is implemented.

6. For components of equipment, the CxA observes a sampling of the Pre-FuncƟonal Checklists.

7. The site technician shall document the checkout process. They shall iniƟal and date each line-item task confirming compleƟon of each paragraph procedure(s). The items shall also be checked off on the Pre-FuncƟonal Checklist.

8. Only individuals having direct knowledge of a line item being completed shall check or iniƟal the forms.

Davenergy Project Number: 61123 Page 24 of 35 December 19, 2025

9. Subcontractors and vendors shall execute the Pre-FuncƟonal Checklists and submit a signed copy of the completed Pre-FuncƟonal Checklists, per submiƩal process requirements. The CxA may review Pre-FuncƟonal Checklists in progress, as necessary.

a. On smaller equipment or projects, forms of the Pre-FuncƟonal Checklists (which all contain more than one trade’s responsibility) may be provided to the subcontractors for compleƟon.

On larger projects, each subcontractor may need a full Pre-FuncƟonal Checklist form in order to perform their work concurrently. When warranted, the GC shall consolidate the various porƟons of the checklist into a single comprehensive PFC prior to submission.

10. The CxA will aƩend any major equipment startups. For all other items where the owner wishes to have 3rd party tesƟng, the GC will need to submit qualificaƟons for 3rd party tesƟng. For all systems idenƟfied in secƟon 3B as “witness 3rd party test, review reports”, the CxA will review reports and review qualificaƟons as they come through in submiƩal process and test reports. The 3rd party testers do not work for the CxA, they will be working for the general contractor.

5.P. Deϐiciencies and Non-Conformance - Construction Phase

1. Outstanding items from the Pre-FuncƟonal Checklist procedures that were not completed successfully shall be clearly listed by the applicable subcontractor in the provided space on the PFC or on an aƩached sheet.

2. The PFCs (including listed deficiencies with resoluƟon) shall be submiƩed within two (2) days of test compleƟon for CxA review.

3. The CxA shall work with the GC regarding iniƟal conversaƟons on deficiencies idenƟfied during PFC form compleƟon. If warranted, the CxA shall work with the subcontractors and vendors to correct and review any checklist deficiencies or incomplete items.

4. The installing subcontractors or vendors shall correct all deficient or incomplete areas according to the Pre-FuncƟonal Checklists.

5. The CxA recommends approval of the iniƟal checkout of each system to the COR using the required submiƩal review process in the approved document control applicaƟon.

5.Q. Controls Checkout Plan: EMCS and SCADA - Construction Phase

1. The controls contractor shall develop and submit a wriƩen step-by-step plan. The plan shall describe the intended process in checking the control system and idenƟfy the necessary documentaƟon forms to be uƟlized. In the event that this plan does not sufficiently document or verify proper installaƟon, the CxA shall modify the applicable porƟons of the PFC for this purpose.

2. The controls contractor shall execute the tests assigned to them and provide a qualified technician on site for assistance in performing the controls porƟons of the funcƟonal performance tesƟng.

Davenergy Project Number: 61123 Page 25 of 35 December 19, 2025

5.R. Development of Functional Performance Test Procedures - Construction Phase

1. FuncƟonal Performance TesƟng is the dynamic tesƟng of systems (rather than just components) under full operaƟon (e.g., the chiller pump is tested interacƟvely with the chiller funcƟons to see if the pump ramps up and down to maintain the differenƟal pressure set-point; the UPS system response to varying loads and redundant module failures is tested to verify that the power to load remains in tolerance).

2. Systems are tested under all modes of operaƟon (e.g., during low cooling or heaƟng loads, high loads, component failures, unoccupied, varied outside air temperatures, fire alarm, power failure, simulated NegaƟve Sequence and faults, etc.).

3. Systems are run through all of the control system’s sequences of operaƟon. Components are verified to be funcƟoning as the sequences state.

4. The CxA shall develop the funcƟonal test procedures in a sequenƟal wriƩen form, coordinate, oversee and document the actual tesƟng. TesƟng is usually performed by the installing contractor or vendor. Refer to the “Equipment to Be Commissioned” table in the appendix of this plan.

a. Before FPTs are wriƩen, the CxA shall obtain all requested documentaƟon including, but not limited to, a current list of change orders affecƟng equipment or systems, an updated points list, control sequences, set-points and approved submiƩals.

b. FuncƟonal tesƟng and verificaƟon may be achieved by manual tesƟng (persons manipulate the equipment and observe performance) and/or by monitoring the performance and analyzing the results using the control system’s trend log capabiliƟes or by stand-alone data loggers.

c. The CxA shall use his or her own judgment to recommend which method is most appropriate.

The CxA shall obtain approval from the COR.

d. Level of rigor

i. On this project, all pieces of equipment receive in-depth tesƟng with a high level of rigor.

The CxA shall review the specificaƟons for Owner-contracted, factory or required acceptance tests and determine what further tesƟng may be required. Redundancy is minimized.

ii. Test procedures shall be developed for each piece of commissioned equipment. Sample PFCs and FPTs are provided in Appendix A to illustrate the expected level of rigor for these checklists and test procedures. These are not necessarily site and/or project specific FPTs;

they are provided as a sample of the level of rigor expected. Site/project specific PFCs and FPTs shall be developed and issued separately from this Cx Plan, using approved submiƩals.

e. DraŌ Procedures

i. The CxA shall develop draŌ FPTs verifying proper operaƟon of each piece of equipment and system using the performance requirements in the contract documents. The CxA shall

Davenergy Project Number: 61123 Page 26 of 35 December 19, 2025 obtain clarificaƟon, as needed, from the A/E regarding sequences and operaƟon to develop these tests.

ii. The CxA shall provide the draŌ FPTs to the Cx Team (to include the installing subcontractor) for review and comment on the tesƟng approach, level of rigor, ability to prove system intent, feasibility, safety, warranty and equipment protecƟon.

iii. The CxA shall respond to and incorporate Cx Team comments (as applicable and as approved by the COR).

f. Final Procedures

i. Upon incorporaƟon of the Cx Team comments (as applicable and as approved by the COR), the CxA shall distribute the FPT as Final (aka Approved for Use).

g. Blank copies of the procedures shall be provided by the CxA to the COR with the Final Cx Report for future use by operaƟons staff.

5.S. Systems Manual - Acceptance Phase

1. Standard OperaƟon & Maintenance (O&M) Manuals

a. The O&M Manual and warranty submissions shall consist of a draŌ and a final, per specificaƟon requirements. The draŌ shall consist of O&M Manuals and progress submissions of as-builts.

b. The CxA shall review the O&M Manuals and progress submissions of the as-builts for applicability of use during operator training.

c. In accordance with the Ɵmeline idenƟfied in the specificaƟons, the GC shall provide final documentaƟon and redlined as-builts for commissioned systems to verify compliance with the specificaƟons. This review process does not supersede or replace any reviews provided by the A/E.

d. The CxA shall recommend approval and acceptance of these submissions to the COR.

e. The CxA shall review each equipment warranty and verify all requirements are met to maintain the warranty. The CxA shall advise the COR of approval and acceptance recommendaƟons.

f. When possible, and at no addiƟonal expense to the Owner, the contractor shall provide the required documentaƟon in an electronic, MicrosoŌ Word searchable and fully text retrievable format.

2. As applicable to the scope of the project, the Contractor shall augment the O&M Manuals with systems level content, as required in the specificaƟons.

5.T. Execution of Functional Performance Testing - Acceptance Phase

1. TesƟng Plan/Schedule…