Attachment 05b - Specifications_Div_21-23-West_Haven_EHRM_IU-689-22-700.pdf
PDF 6 MB Posted
- Attached to
- Z2DA--689-22-700 EHRM IU West Haven VAMC This ONLY for the PCAC VISN 1 Construction MATOC Pool
- Solicitation number
- 36C77626R0106
About this file
This is a comprehensive specifications document for fire protection and plumbing systems as part of the EHRM Infrastructure Upgrades Project #689-22-700 at West Haven VA Medical Center in Connecticut. The document contains detailed technical specifications for wet-pipe sprinkler systems (Section 21 13 13), dry-pipe sprinkler systems (Section 21 13 16), clean agent fire suppression systems (Section 21 22 00), and common work results for plumbing (Section 22 05 11).
The specifications establish rigorous requirements for sprinkler system design, materials, installation, and testing in accordance with NFPA 13, NFPA 25, and NFPA 2001 standards. For wet-pipe systems, contractors must provide UL-listed or FM-approved quick response sprinklers with specific temperature ratings, implement hydraulic calculations using the Area/Density method, and design systems with hazard classifications ranging from light to ordinary hazard occupancies. Dry-pipe systems require latching differential valves, air compressor systems, and quick opening devices for larger volumes, with water delivery time calculations demonstrated to comply with NFPA 13. Clean agent fire suppression systems must utilize agents with global warming potential less than 4000, include addressable intelligent reporting microprocessor-controlled releasing systems per NFPA 72, and provide comprehensive training in six one-hour sessions for general staff and four two-hour sessions for engineering staff. All installations require submittals including detailed working drawings signed by NICET Level III/IV technicians or licensed professional engineers, manufacturer data sheets, hydraulic calculations, as-built drawings in multiple formats (printed, PDF, and AutoCAD), material and testing certificates, and comprehensive operations and maintenance manuals. Contractors must possess valid state fire sprinkler licenses, demonstrate ten years of commercial sprinkler system installation experience, and maintain or have access to clean agent recharging stations with 48-hour recharge capability. The project includes extensive testing requirements including hydrostatic tests, pneumatic tests, flow tests, room pressurization tests, and final system operation verification prior to acceptance by the Contracting Officer's Representative.
View the file
Other files
Show all 42
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
19 DECEMBER 2024
EHRM
INFRASTRUCTURE
UPGRADES
PROJECT #: 689-22-700
WEST HAVEN VA MEDICAL CENTER,
WEST HAVEN, CONNECTICUT
SPECIFICATIONS
DIVISION 21-23
100% SUBMITTAL
CONSTRUCTION DOCUMENT
EHRM INFRASTRUCTURE UPGRADES PROJECT #: 689-22-700
VA MEDICAL CENTER – WEST HAVEN, CT PUB. DATE: 06-01-15
WET PIPE SPRINKLER SYSTEMS 21 13 13 - 01
SECTION 21 13 13
WET-PIPE SPRINKLER SYSTEMS
PART 1 - GENERAL
1.1 DESCRIPTION
A. Design, installation and testing shall be in accordance withNFPA 13.
B. Modification of the existing sprinkler system as indicated on the drawings and as further required by these specifications.
1.2 RELATED WORK
A. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
B. Section 33 10 00, WATER UTILITIES.
C. Section 07 84 00, FIRESTOPPING.
D. Section 09 91 00, PAINTING.
F. Section 28 31 00, FIRE DETECTION AND ALARM.
1.3 DESIGN CRITERIA
A. Design Basis Information: Provide design, materials, equipment, installation, inspection, and testing of the automatic sprinkler system in accordance with the requirements of NFPA 13.
1. Perform hydraulic calculations in accordance with NFPA 13 utilizing the Area/Density method. Do not restrict design area reductions permitted for using quick response sprinklers throughout by the required use of standard response sprinklers in the areas identified in this section.
2. Sprinkler Protection: Sprinkler hazard classifications shall be in accordance with NFPA 13.
The hazard classification examples of uses and conditions identified in the Annex of NFPA 13 shall be mandatory for areas not listed below. Request clarification from the Government for any hazard classification not identified. To determining spacing and sizing, apply the following coverage classifications:
a. Light Hazard Occupancies: Patient care, treatment, data centers, and telecommunication rooms and customary access areas.
b. Ordinary Hazard Group 1 Occupancies: Laboratories, Mechanical Equipment Rooms, Transformer Rooms, Electrical Switchgear Rooms, Electric Closets, and Repair Shops.
c. Ordinary Hazard Group 2 Occupancies: Storage rooms, trash rooms, clean and soiled linen rooms, pharmacy and associated storage, laundry, kitchens, kitchen storage areas, retail stores, retail store storage rooms, storage areas, building management storage, boiler plants, energy centers, warehouse
WET PIPE SPRINKLER SYSTEMS 21 13 13 - 02
spaces, file storage areas for the entire area of the space up to 140 square meters (1500 square feet) and Supply Processing and Distribution (SPD).3. Hydraulic Calculations: Calculated demand including hose stream requirements shall fall no less than 10 percent below the available water supply curve.
4. Water Supply: Base water supply on a flow test at hydrant “H”of:
5. Zoning:
a. For each sprinkler zone provide a control valve, flow switch, and a test and drain assembly with pressure gauge. For buildings greater than two stories, provide a check valve at each control valve.
b. Sprinkler zones shall conform to the smoke barrier zones shown on the drawings.
1.4 SUBMITTALS
A. Submit as one package in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. Prepare detailed working drawings that are signed by a NICET Level III or Level IV
Sprinkler Technician or stamped by a Registered Professional Engineer licensed in the field of
Fire Protection Engineering. As the Government review is for technical adequacy only, the installer remains responsible for correcting any conflicts with other trades and building construction that arise during installation. Partial submittals will not be accepted. Material submittals shall be approved prior to the purchase or delivery to the job site. Suitably bind submittals in notebooks or binders and provide an index referencing the appropriate specification section. In addition to the hard copies, provide submittal items in Paragraphs
1.4(A)1 through 1.4(A)5 electronically in pdf format on a compact disc or as directed by the COR.
Submittals shall include, but not be limited to, the following:
1. Qualifications:
WET PIPE SPRINKLER SYSTEMS 21 13 13 - 03
a. Provide a copy of the installing contractors fire sprinkler and state contractor’s license.
b. Provide a copy of the NICET certification for the NICET Level III or Level IV Sprinkler
Technician who prepared and signed the detailed working drawings unless the drawings are stamped by a Registered Professional Engineer licensed in the field of Fire
Protection Engineering.
c. Provide documentation showing that the installer has been actively and successfully engaged in the installation of commercial automatic sprinkler systems for the past ten years.
2. Drawings: Submit detailed 1:100 (1/8 inch) scale (minimum) working drawings conforming to the Plans and Calculations chapter of NFPA 13. Drawings shall include graphical scales that allow the user to determine lengths when the drawings are reduced in size. Include a plan showing the piping to the water supply test location.
3. Manufacturer’s Data Sheets: Provide data sheets for all materials and equipment proposed for use on the system. Include listing information and installation instructions in data sheets.
Where data sheets describe items in addition to those proposed to be used for the system, clearly identify the proposed items on the sheet.
4. Calculation Sheets:
a. Submit hydraulic calculation sheets in tabular form conforming to the requirements and recommendations of the Plans and Calculations chapter of NFPA 13.
5. Valve Charts: Provide a valve chart that identifies the location of each control valve.
Coordinate nomenclature and identification of control valves with COR. Where existing nomenclature does not exist, the chart shall include no less than the following: Tag ID No., Valve Size, Service (control valve, main drain, aux. drain, inspectors test valve, etc.), and
Location.
6. Final Document Submittals: Provide as-built drawings, testing and maintenance instructions in accordance with the requirements in Section 01 33 23, SHOP DRAWINGS, PRODUCT
DATA, AND SAMPLES. In addition, submittals shall include, but not be limited to, the following:
a. A complete set of as-built drawings showing the installed system with the specific interconnections between the system switches and the fire alarm equipment. Provide a complete set in the formats as follows. Submit items 2 and 3 below on a compact disc or as directed by the COR.
WET PIPE SPRINKLER SYSTEMS 21 13 13 - 04
1) One full size (or size as directed by the COR) printed copy.
2) One complete set in electronic pdf format.
3) One complete set in AutoCAD format or a format as directed by the COR.
b. Material and Testing Certificate: Upon completion of the sprinkler system installation or any partial section of the system, including testing and flushing, provide a copy of a completed Material and Testing Certificate as indicated in NFPA 13. Certificates shall be provided to document all parts of the installation.
c. Operations and Maintenance Manuals that include step-by-step procedures required for system startup, operation, shutdown, and routine maintenance and testing. The manuals shall include the manufacturer's name, model number, parts list, and tools that should be kept in stock by the owner for routine maintenance, including the name of a local supplier, simplified wiring and controls diagrams, troubleshooting guide, and recommended service organization, including address and telephone number, for each item of equipment.
d. One paper copy of the Material and Testing Certificates and the Operations and
Maintenance Manuals above shall be provided in a binder. In addition, these materials shall be provided in pdf format on a compact disc or as directed by the COR.
e. Provide one additional copy of the Operations and Maintenance Manual covering the system in a flexible protective cover and mount in an accessible location adjacent to the riser or as directed by the COR.
1.5 QUALITY ASSURANCE
A. Installer Reliability: The installer shall possess a valid State of Connecticut fire sprinkler contractor's license. The installer shall have been actively and successfully engaged in the installation of commercial automatic sprinkler systems for the past ten years.
B. Materials and Equipment: All equipment and devices shall be of a make and type listed by UL or approved by FM, or other nationally recognized testing laboratory for the specific purpose for which it is used. All materials, devices, and equipment shall be approved by the VA. All materials and equipment shall be free from defect. All materials and equipment shall be new unless specifically indicated otherwise on the contract drawings.
1.6 APPLICABLE PUBLICATIONS
A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.
WET PIPE SPRINKLER SYSTEMS 21 13 13 - 05
*Note: From the date contract documents are provided, the Contractor shall use the most current published versions of all listed standards and references below.
B. National Fire Protection Association (NFPA):
13-13 .......................................... Installation of Sprinkler Systems
25-14 .......................................... Inspection, Testing, and Maintenance of Water-Based Fire
Protection Systems
101-15 ........................................ Life Safety Code
170-15 ........................................ Fire Safety Symbols
C. Underwriters Laboratories, Inc. (UL):
Fire Protection Equipment Directory (2011)
D. Factory Mutual Engineering Corporation (FM):
Approval Guide
PART 2 - PRODUCTS
2.1 PIPING & FITTINGS
A. Piping and fittings for private underground water mains shall be in accordance with NFPA 13.
1. Pipe and fittings from inside face of building 300 mm (12 in.) above finished floor to a distance of approximately 1500 mm (5 ft.) outside building: Ductile Iron, flanged fittings and
316 stainless steel bolting.
B. Piping and fittings for sprinkler systems shall be in accordance with NFPA 13.
1. Plain-end pipe fittings with locking lugs or shear bolts are not permitted.
2. Piping sizes 50 mm (2 inches) and smaller shall be black steel Schedule 40 with threaded end connections.
3. Piping sizes 65 mm (2 ½ inches) and larger shall be black steel Schedule 10 with grooved connections. Grooves in Schedule 10 piping shall be rolled grooved only.
4. Use nonferrous piping in MRI Scanning Rooms.
5. Plastic piping shall not be permitted except for drain piping.
6. Flexible sprinkler hose shall be FM Approved and limited to hose with threaded end fittings with a minimum inside diameter or 1-inch and a maximum length of 6-feet.
2.2 VALVES
A. General:
1. Valves shall be in accordance with NFPA 13.
2. Do not use quarter turn ball valves for 50 mm (2 inch) or larger drain valves.
WET PIPE SPRINKLER SYSTEMS 21 13 13 - 06
B. Control Valve: The control valves shall be a listed indicating type. Control valves shall be UL
Listed or FM Approved for fire protection installations. System control valve shall be rated for normal system pressure but in no case less than 175 PSI.
C. Check Valve: Shall be of the swing type with a flanged cast iron body and flanged inspection plate.
D. Automatic Ball Drips: Cast brass 20 mm (3/4 inch) in-line automatic ball drip with both ends threaded with iron pipe threads.
E. Alarm Check Valve: Alarm check valve shall be UL Listed and Factory Mutual Approved. The alarm check valve shall be listed for installation in the vertical or horizontal position. The alarm check valve shall be equipped with a removable cover assembly, gauge connections on the system side and supply side of the valve clapper, variable pressure trim, and an external bypass to eliminate false water flow alarms. The alarm check valve trim piping shall be galvanized.
Maximum water working pressure to 250 PSI.
F. Backflow Preventer: Provide backflow preventer in accordance with Section 22 05 23, GENERAL-
DUTY VALVES FOR PLUMBING PIPING. Provide means to forward flow test the backflow preventer in accordance with NFPA 13.
WET PIPE SPRINKLER SYSTEMS 21 13 13 - 07
2.4 SPRINKLERS
A. All sprinklers shall be FM approved quick response except “institutional” type sprinklers shall be permitted to be UL Listed quick response. “Institutional” type sprinklers in Mental Health and
Behavior Units shall be UL listed or FM approved quick response type. Maximum break away strength shall be certified by the manufacturer to be no more than 39 kPa (85 pounds). Provide
FM approved quick response sprinklers in all areas, except that standard response sprinklers shall be provided in freezers, refrigerators, elevator hoistways, elevator machine rooms, telecom rooms, data centers, and generator rooms. Provide sprinkler guards in data centers and telecom rooms. The sprinkler guard shall be UL listed or FM approved for use with the corresponding sprinkler.
B. Temperature Ratings: In accordance with NFPA 13 except that sprinklers in elevator shafts and elevator machine rooms shall be no less than intermediate temperature rated and sprinklers in generator rooms shall be no less than high temperature rated.
C. Provide sprinkler guards in accordance with NFPA 13 and when the elevation of the sprinkler head is less than 7 feet 6 inches above finished floor. The sprinkler guard shall be UL listed or FM approved for use with the corresponding sprinkler.
2.5 SPRINKLER CABINET
A. Provide sprinkler cabinet with the required number of sprinkler heads of all ratings and types installed, and a sprinkler wrench for each type of sprinkler in accordance with NFPA 13. Locate adjacent to the riser.
B. Provide a list of sprinklers installed in the property in the cabinet. The list shall include the following:
1. Manufacturer, model, orifice, deflector type, thermal sensitivity, and pressure for each type of sprinkler in the cabinet.
2. General description of where each sprinkler is used.
3. Quantity of each type present in the cabinet.
4. Issue or revision date of list.
2.6 SPRINKLER SYSTEM SIGNAGE
Rigid plastic, steel or aluminum signs with white lettering on a red background with holes for easy attachment. Sprinkler system signage shall be attached to the valve or piping with chain.
WET PIPE SPRINKLER SYSTEMS 21 13 13 - 08
2.8 GAUGES
Provide gauges as required by NFPA 13. Provide gauges where the normal pressure of the system is at the midrange of the gauge.
2.9 PIPE HANGERS, SUPPORTS AND RESTRAINT OF SYSTEM PIPING
Pipe hangers, supports, and restraint of system piping shall be in accordance with NFPA 13.
2.10 WALL, FLOOR AND CEILING PLATES
Provide chrome plated steel escutcheon plates.
2.11 ANTIFREEZE SOLUTION
Antifreeze solution shall be in accordance with NFPA 13 and shall be compatible with use in a potable water supply.
2.12 VALVE TAGS
Engraved black filled numbers and letters not less than 15 mm (1/2 inch) high for number designation, and not less than 8 mm (1/4 inch) for service designation on 19 gage, 40 mm (1-1/2 inches) round brass disc, attached with brass "S" hook, brass chain, or nylon twist tie.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Installation shall be accomplished by the licensed contractor. Provide a qualified technician, experienced in the installation and operation of the type of system being installed, to supervise the installation and testing of the system.
B. Installation of Piping: Accurately cut pipe to measurements established by the installer and work into place without springing or forcing. In any situation where bending of the pipe is required, use a standard pipe-bending template. Concealed piping in spaces that have finished ceilings.
Where ceiling mounted equipment exists, such as in operating and radiology rooms, install sprinklers so as not to obstruct the movement or operation of the equipment. Sidewall heads may need to be utilized. In stairways, locate piping as near to the ceiling as possible to prevent tampering by unauthorized personnel and to provide a minimum headroom clearance of 2250 mm (seven feet six inches). Piping shall not obstruct the minimum means of egress clearances required by NFPA 101. Pipe hangers, supports, and restraint of system piping, and seismic bracing shall be installed accordance with NFPA 13.
C. Welding: Conform to the requirements and recommendations of NFPA 13.
D. Drains: Provide drips and drains, including low point drains, in accordance with NFPA 13. Pipe drains to discharge at safe points outside of the building or to sight cones attached to drains of
WET PIPE SPRINKLER SYSTEMS 21 13 13 - 09
adequate size to readily carry the full flow from each drain under maximum pressure. Do not provide a direct drain connection to sewer system or discharge into sinks. Install drips and drains where necessary and required by NFPA 13. The drain piping shall not be restricted or reduced and shall be of the same diameter as the drain collector.
E. Supervisory Switches: Provide supervisory switches for sprinkler control valves.
F. Waterflow Alarm Switches: Install waterflow alarm switches and valves in stairwells or other easily accessible locations.
G. Inspector's Test Connection: Install and supply in accordance with NFPA 13, locate in a secured area, and discharge to the exterior of the building.
H. Affix cutout disks, which are created by cutting holes in the walls of pipe for flow switches and non-threaded pipe connections to the respective waterflow switch or pipe connection near to the pipe from where they were cut.
I. Provide escutcheon plates for exposed piping passing through walls, floors or ceilings.
J. Clearances: For systems requiring seismic protection, piping that passes through floors or walls shall have penetrations sized 50 mm (2 inches) nominally larger than the penetrating pipe for pipe sizes 25 mm (1 inch) to 90 mm (3 ½ inches) and 100 mm (4 inches) nominally larger for penetrating pipe sizes 100 mm (4 inches) and larger.
K. Sleeves: Provide for pipes passing through masonry or concrete. Provide space between the pipe and the sleeve in accordance with NFPA 13. Seal this space with a UL Listed through penetration fire stop material in accordance with Section 07 84 00, FIRESTOPPING. Where core drilling is used in lieu of sleeves, also seal space. Seal penetrations of walls, floors and ceilings of other types of construction, in accordance with Section 07 84 00, FIRESTOPPING.
L. Where dry pendent sprinklers are used for freezers or similar spaces and they are connected to the wet pipe system, provide an EPDM boot around the dry pendent sprinkler on the heated side and securely seal to the pipe and freezer to prevent condensation from entering the freezer.
M. Provide pressure gauges at each water flow alarm switch location and at each main drain connection.
N. For each fire department connection, provide the symbolic sign given in NFPA 170 and locate
2400 to 3000 mm (8 to 10 feet) above each connection location. Size the sign to 450 by 450 mm
(18 by 18 inches) with the symbol being at least 350 by 350 mm (14 by 14 inches).
WET PIPE SPRINKLER SYSTEMS 21 13 13 - 10
O. Firestopping shall be provided for all penetrations of fire resistance rated construction.
Firestopping shall comply with Section 07 84 00, FIRESTOPPING.
P. MRI Suite: Provide no more than one penetration of the MRI shield enclosure.
Q. Painting of Pipe: In finished areas where walls and ceilings have been painted, paint primed surfaces with two coats of paint to match adjacent surfaces, except paint valves and operating accessories with two coats of gloss red enamel. Exercise care to avoid painting sprinklers.
Painting of sprinkler systems above suspended ceilings and in crawl spaces is not required.
Painting shall comply with Section 09 91 00, PAINTING. Any painted sprinkler shall be replaced with a new sprinkler.
R. Sprinkler System Signage: Provide rigid sprinkler system signage in accordance with NFPA 13 and NFPA 25. Sprinkler system signage shall include, but not limited to, the following:
1. Identification Signs:
a. Provide signage for each control valve, drain valve, sprinkler cabinet, and inspector’s test.
b. Provide valve tags for each operable valve. Coordinate nomenclature and identification of operable valves with COR. Where existing nomenclature does not exist, the Tag
Identification shall include no less than the following: (FP-B-F/SZ-#) Fire Protection, Building Number, Floor Number/Smoke Zone (if applicable), and Valve Number. (E.g., FP-500-1E-001) Fire Protection, Building 500, First Floor East, Number 001.)
2. Instruction/Information Signs:
a. Provide signage for each control valve to indicate valve function and to indicate what system is being controlled.
b. Provide signage indicating the number and location of low point drains.
3. Hydraulic Placards:
a. Provide signage indicating hydraulic design information. The placard shall include location of the design area, discharge densities, required flow and residual pressure at the base of riser, occupancy classification, hose stream allowance, flow test information, and installing contractor. Locate hydraulic placard information signs at each alarm check valve.
S. Repairs: Repair damage to the building or equipment resulting from the installation of the sprinkler system by the installer at no additional expense to the Government.
WET PIPE SPRINKLER SYSTEMS 21 13 13 - 11
T. Interruption of Service: There shall be no interruption of the existing sprinkler protection, water, electric, or fire alarm services without prior permission of the Contracting Officer. Contractor shall develop an interim fire protection program where interruptions involve occupied spaces.
Request in writing at least one week prior to the planned interruption.
3.2 INSPECTION AND TEST
A. Preliminary Testing: Flush newly installed systems prior to performing hydrostatic tests in order to remove any debris which may have been left as well as ensuring piping is unobstructed.
Hydrostatically test system, including the fire department connections, as specified in NFPA 13, in the presence of the Contracting Officers Representative (COR) or his designated representative. Test and flush underground water line prior to performing these hydrostatic tests.
B. Final Inspection and Testing: Subject system to tests in accordance with NFPA 13, and when all necessary corrections have been accomplished, advise COR to schedule a final inspection and test. Connection to the fire alarm system shall have been in service for at least ten days prior to the final inspection, with adjustments made to prevent false alarms. Furnish all instruments, labor and materials required for the tests and provide the services of the installation foreman or other competent representative of the installer to perform the tests. Correct deficiencies and retest system as necessary, prior to the final acceptance. Include the operation of all features of the systems under normal operations in test
3.3 INSTRUCTIONS
Furnish the services of a competent instructor for not less than two hours for instructing personnel in the operation and maintenance of the system, on the dates requested by the COR.
- - - E N D - - -
VA MEDICAL CENTER – WEST HAVEN, CT PUB. DATE: 01-01-15
DRY-PIPE SPRINKLER SYSTEMS 21 13 16 - 01
SECTION 21 13 16
DRY-PIPE SPRINKLER SYSTEMS
PART 1 - GENERAL
1.1 DESCRIPTION
A. Design, installation and testing shall be in accordance with NFPA 13.
B. The design and installation of a hydraulically calculated automatic dry-pipe sprinkler system complete and ready for operation, for those locations as shown on the contract drawings.
1.2 RELATED WORK
A. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
B. Section 33 10 00, WATER UTILITIES.
C. Section 07 84 00, FIRESTOPPING.
D. Section 09 91 00, PAINTING.
E. Section 21 13 13, WET-PIPE SPRINKLER SYSTEMS
F. Section 22 05 23, GENERAL-DUTY VALVES FOR PLUMBING PIPING.
G. Section 28 31 00, FIRE DETECTION AND ALARM.
1.3 DESIGN CRITERIA
A. Design Basis Information: Provide design, materials, equipment, installation, inspection, and testing of the automatic sprinkler system in accordance with the requirements of NFPA 13.
1. Perform hydraulic calculations in accordance with NFPA 13 utilizing the Area/Density method, including all applicable design area increases.
2. Sprinkler Protection: Sprinkler hazard classifications shall be in accordance with NFPA 13.
The hazard classification examples of uses and conditions identified in the Annex of NFPA 13 shall be mandatory. See hazard classification designations in Specification 21 13 13 WET-
PIPE SPRINKLER SYSTEMS. Request clarification from the Government for any hazard classification not identified.
3. Dry-pipe Sprinkler System Volume:
a. Contractor shall indicate the calculated volume of each system on the sprinkler system shop drawings.
b. For dry-pipe sprinkler systems with volumes greater than 1893 L (500 gal) up to 2839 L
(750 gal), provide a quick opening device unless water delivery time calculations indicate the quick opening devices is not required.
DRY-PIPE SPRINKLER SYSTEMS 21 13 16 - 02
c. For dry-pipe sprinkler systems with volumes greater than 2839 L (750 gal), provide calculations for water delivery time. Calculations shall demonstrate compliance with
NFPA 13.
5. Hydraulic Calculations: Calculated demand including hose stream requirements shall fall no less than 10 percent below the available water supply curve.
6. Water Supply: Base water supply on a flow test of:
a. Location: Hydrant # 27 (Near Bld. 30)
7. Provide seismic protection in accordance with NFPA 13. Contractor shall submit load calculations for sizing of sway bracing for systems that are required to be protected against damage from earthquakes.
1.4 SUBMITTALS
A. Submit as one package in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. Prepare detailed working drawings that are stamped by a Registered
Professional Engineer licensed in the field of Fire Protection Engineering. As the Government review is for technical adequacy only, the installer remains responsible for correcting any conflicts with other trades and building construction that arise during installation. Partial submittals will not be accepted. Material submittals shall be approved prior to the purchase or delivery to the job site. Suitably bind submittals in notebooks or binders and provide an index referencing the appropriate specification section. In addition to the hard copies, provide submittal items in Paragraphs 1.4(A)1 through 1.4(A)5 electronically in pdf format on a compact disc or as directed by the COR. Submittals shall include, but not be limited to, the following:
1. Qualifications:
DRY-PIPE SPRINKLER SYSTEMS 21 13 16 - 03
a. Provide a copy of the installing contractors fire sprinkler and state contractor’s license.
b. Provide documentation showing that the installer has been actively and successfully engaged in the installation of commercial automatic sprinkler systems for the past ten years.
2. Drawings: Submit detailed 1:100 (1/8 inch) scale (minimum) working drawings conforming to the Plans and Calculations chapter of NFPA 13. Drawings shall include graphical scales that allow the user to determine lengths when the drawings are reduced in size. Include a plan showing the piping to the water supply test location.
3. Manufacturer’s Data Sheets: Provide data sheets for all materials and equipment proposed for use on the system. Include listing information and installation instructions in data sheets.
Where data sheets describe items in addition to those proposed to be used for the system, clearly identify the proposed items on the sheet.
4. Calculation Sheets:
a. Submit hydraulic calculation sheets in tabular form conforming to the requirements and recommendations of the Plans and Calculations chapter of NFPA 13.
b. For dry-pipe sprinkler systems with volumes more than 2838 L (750 gal), submit calculations for dry-pipe system water delivery time in accordance with NFPA 13.
c. Submit calculations of loads for sizing of sway bracing in accordance with NFPA 13.
5. Valve Charts: Provide a valve chart that identifies the location of each control valve.
Coordinate nomenclature and identification of control valves with COR. Where existing nomenclature does not exist, the chart shall include no less than the following: Tag ID No., Valve Size, Service (control valve, main drain, aux. drain, inspectors test valve, etc.), and
Location.
6. Final Document Submittals: Provide as-built drawings, testing and maintenance instructions in accordance with the requirements in Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. In addition, submittals shall include, but not be limited to, the following:
a. A complete set of as-built drawings showing the installed system with the specific interconnections between the system switches and the fire alarm equipment. Provide a complete set in the formats as follows. Submit items 2 and 3 below on a compact disc or as directed by the COR.
1) One full size (or size as directed by the COR) printed copy.
2) One complete set in electronic pdf format.
DRY-PIPE SPRINKLER SYSTEMS 21 13 16 - 04
3) One complete set in AutoCAD format or a format as directed by the COR.
b. Material and Testing Certificate: Upon completion of the sprinkler system installation or any partial section of the system, including testing and flushing, provide a copy of a completed Material and Testing Certificate as indicated in NFPA 13. Certificates shall be provided to document all parts of the installation.
c. Operations and Maintenance Manuals that include step-by-step procedures required for system startup, operation, shutdown, and routine maintenance and testing. The manuals shall include the manufacturer's name, model number, parts list, and tools that should be kept in stock by the owner for routine maintenance, including the name of a local supplier, simplified wiring and controls diagrams, troubleshooting guide, and recommended service organization, including address and telephone number, for each item of equipment.
d. One paper copy of the Material and Testing Certificates and the Operations and
Maintenance Manuals above shall be provided in a binder. In addition, these materials shall be provided in pdf format on a compact disc or as directed by the COR.
e. Provide one additional copy of the Operations and Maintenance Manual covering the system in a flexible protective cover and mount in an accessible location adjacent to the riser or as directed by the COR.
1.5 QUALITY ASSURANCE
A. Installer Reliability: The installer shall possess a valid State of Pennsylvania fire sprinkler contractor's license. The installer shall have been actively and successfully engaged in the installation of commercial automatic sprinkler systems for the past ten years.
B. Materials and Equipment: All equipment and devices shall be of a make and type listed by UL or approved by FM, or other nationally recognized testing laboratory for the specific purpose for which it is used. All materials, devices, and equipment shall be approved by the VA. All materials and equipment shall be free from defect. All materials and equipment shall be new unless specifically indicated otherwise on the contract drawings.
1.6 APPLICABLE PUBLICATIONS
*Note: From the date contract documents are provided, the Contractor shall use the most current published versions of all listed standards and references below.
DRY-PIPE SPRINKLER SYSTEMS 21 13 16 - 05
B. National Fire Protection Association (NFPA):
13 ............................................... Installation of Sprinkler Systems
25 ............................................... Inspection, Testing, and Maintenance of Water-Based Fire
Protection Systems
101 ............................................. Life Safety Code
170 ............................................. Fire Safety Symbols
C. Underwriters Laboratories, Inc. (UL):
Fire Protection Equipment Directory
D. Factory Mutual Engineering Corporation (FM)Approval Guide
PART 2 PRODUCTS
2.1 GENERAL
Dry-pipe sprinkler systems shall comply with the requirements of NFPA 13.
2.2 PIPING & FITTINGS
A. Piping and fittings for private underground water mains shall be in accordance with NFPA 13.
1. Pipe and fittings from inside face of building 300 mm (12 in.) above finished floor to a distance of approximately 1500 mm (5 ft.) outside building: Ductile Iron, flanged fittings and
316 stainless steel bolting.
B. Piping and fittings for sprinkler systems shall be in accordance with NFPA 13.
1. Plain-end pipe fittings with locking lugs or shear bolts are not permitted.
2. Piping sizes 50 mm (2 inches) and smaller shall be black steel Schedule 40 with threaded end connections.
3. Piping sizes 65 mm (2 ½ inches) and larger shall be black steel Schedule 10 with grooved connections. Grooves in Schedule 10 piping shall be rolled grooved only.
2.3 VALVES
A. General:
1. Valves shall be in accordance with NFPA 13.
2. Do not use quarter turn ball valves for 50 mm (2 inch) or larger drain valves.
B. Control Valve:
1. Shall be a manually operated outside stem and yoke (OS&Y) type.
C. Dry-pipe Valve:
1. Shall be a latching differential type.
DRY-PIPE SPRINKLER SYSTEMS 21 13 16 - 06
2. Shall be complete with trim piping, valves, fittings, pressure gauges, priming water fill cup, velocity drip check, drip cup, and other ancillary components as required for proper operation.
3. For dry-pipe sprinkler systems with volumes more than 1893 L (500 gal), provide a quick opening device unless water delivery time calculations have proven no quick opening device is required.
4. Shall be capable of external reset.
D. Check Valve:
1. Shall be of the swing type with a flanged cast iron body and flanged inspection plate.
E. Automatic Ball Drips: Cast brass 20 mm (3/4 inch) in-line automatic ball drip with both ends threaded with iron pipe threads.
2.4 SPRINKLERS
A. All sprinklers shall be FM approved. All sprinklers shall be upright type. Provide FM Approved standard response sprinklers in generator room.
B. Temperature Ratings: In accordance with NFPA 13 except that sprinklers in elevator shafts and elevator machine rooms shall be no less than intermediate temperature rated and sprinklers in generator rooms shall be no less than high temperature rated.
C. Provide sprinkler guards in accordance with NFPA 13 and when the elevation of the head is less than 7 feet 6 inches above finished floor. The sprinkler guard shall be listed or approved for use with the corresponding sprinkler.
2.5 SUPERVISORY AIR SYSTEM
A. Provide an air supply system in accordance with NFPA 13 and the manufacturers’ requirements.
The air supply system shall be sized to pressurize the sprinkler system to 275 kPa (40 psi) within
30 minutes.
B. Air Compressor: Compressor shall be tank mounted, single stage oil-free type, air-cooled, electric-motor driven, equipped with a check valve, shutoff valve, automatic drain on drip leg, and pressure switch for automatic starting and stopping. Pressure switch settings to start and stop the compressor shall be as required by system conditions. A safety relief valve shall be provided.
DRY-PIPE SPRINKLER SYSTEMS 21 13 16 - 07
2.6 AIR PRESSURE MAINTENANCE DEVICE
Air Pressure Maintenance Device: Air pressure maintenance device shall be UL listed or FM approved and shall automatically reduce supply air pressure to provide the pressure required to be maintained in the piping system. The device shall have a cast bronze body and valve housing complete with diaphragm assembly, spring, filter, ball check to prevent backflow, 1.6 mm (1/16 inch) restriction to prevent rapid pressurization of the system, and adjustment screw. The device shall be capable of reducing an inlet pressure of up to 680 kPa (100 psig) to a fixed outlet pressure adjustable to 70 kPa (10 psig).
2.7 SPRINKLER CABINET
A. Provide sprinkler cabinet with the required number of sprinkler heads of all ratings and types installed, and a sprinkler wrench for each type of sprinkler in accordance with NFPA 13.
B. Provide a list of sprinklers installed in the property in the cabinet. The list shall include the following:
1. Manufacturer, model, orifice, deflector type, thermal sensitivity, and pressure for each type of sprinkler in the cabinet.
2. General description of where each sprinkler is used.
3. Quantity of each type present in the cabinet.
4. Issue or revision date of list.
2.8 SPRINKLER SYSTEM SIGNAGE
Rigid plastic, steel or aluminum signs with white lettering on a red background with holes for easy attachment. Sprinkler system signage shall be attached to the valve or piping with chain.
2.9 SWITCHES
A. OS&Y Valve Supervisory Switches shall be in a weatherproof die cast/red baked enamel, oil resistant, aluminum housing with tamper resistant screws, 13 mm (1/2 inch) conduit entrance and necessary facilities for attachment to the valves. Provide two SPDT switches rated at 2.5 amps at 24 VDC.
B. Alarm Pressure Switches: Activation by any flow of water equal to or in excess of the discharge from one sprinkler. The alarm pressure switch shall be UL Listed or Factory Mutual Approved for the application in which it is used. Activation of the alarm pressure switch shall cause an alarm on the fire alarm system control unit.
C. High/Low Pressure Supervisory Switches: The pressure switch shall be UL Listed or FM Approved and contain two single pole double throw contacts. Each switch shall be adjustable from 70 to
DRY-PIPE SPRINKLER SYSTEMS 21 13 16 - 08
414 kPa (10 to 60 psi). The low pressure switch shall supervise pressure in the system and shall be set to activate at 70 kPa (10 psi) above the dry-pipe valve trip point pressure. The high pressure switch shall supervise pressure in the system and shall be set to activate at 70 kPa (10 psi) above the normal dry-pipe supervisory pressure. Activation of either high or low pressure switch shall cause a supervisory alarm on the fire alarm system control unit.
2.10 GAUGES
Provide gauges as required by NFPA 13. Provide gauges where the normal pressure of the system is at the midrange of the gauge.
2.11 PIPE HANGERS, SUPPORTS AND RESTRAINT OF SYSTEM PIPING
Pipe hangers, supports, and restraint of system piping shall be in accordance with NFPA 13.
2.12 WALL, FLOOR AND CEILING PLATES
Provide chrome plated steel escutcheon plates.
2.13 VALVE TAGS
Engraved black filled numbers and letters not less than 15 mm (1/2 inch) high for number designation, and not less than 8 mm (1/4 inch) for service designation on 19 gage, 40 mm (1-1/2 inches) round brass disc, attached with brass "S" hook, brass chain, or nylon twist tie.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Installation shall be accomplished by the licensed contractor. Provide a qualified technician, experienced in the installation and operation of the type of system being installed, to supervise the installation and testing of the system.
B. Installation of Piping: Accurately cut pipe to measurements established by the installer and work into place without springing or forcing. In any situation where bending of the pipe is required, use a standard pipe-bending template. Conceal piping in spaces that have finished ceilings. In stairways, locate piping as near to the ceiling as possible to prevent tampering by unauthorized personnel and to provide a minimum headroom clearance of 2250 mm (seven feet six inches).
Piping shall not obstruct the minimum means of egress clearances required by NFPA 101. Pipe hangers, supports, and restraint of system piping, and seismic bracing shall be installed accordance with NFPA 13.
C. Welding: Conform to the requirements and recommendations of NFPA 13.
D. Pitching of Pipe: Conform to the requirements of NFPA 13.
DRY-PIPE SPRINKLER SYSTEMS 21 13 16 - 09
E. Drains: Provide drips and drains, including low point drains, in accordance with NFPA 13. Pipe drains to discharge at safe points outside of the building. Do not provide a direct drain connection to sewer system or discharge into sinks.
F. Supervisory Switches: Provide supervisory switches for sprinkler control valves to monitor closure of the valve and for high and low system supervisory air/nitrogen pressure to monitor abnormal system pressures.
G. Pressure Alarm Switches: Install alarm pressure switches in easily accessible locations.
H. Inspector's Test Connection: Install and supply in conformance with NFPA 13, and discharge to the exterior of the building. Locate test connection in an area not susceptible to mechanical damage. For dry-pipe sprinkler systems more than 2800 L (750 gal), provide the number of equivalent sprinkler outlets as calculated for water delivery time in accordance with NFPA 13.
I. Affix cutout disks, which are created by cutting holes in the walls of pipe for non-threaded pipe connections, to the respective pipe connection near to the pipe from where they were cut.
J. Provide escutcheon plates for exposed piping passing through walls, floors or ceilings.
K. Clearances: For systems requiring seismic protection, piping that passes through floors or walls shall have penetrations sized 50 mm (2 inches) nominally larger than the penetrating pipe for pipe sizes 25 mm (1 inch) to 90 mm (3 ½ inches) and 100 mm (4 inches) nominally larger for penetrating pipe sizes 100 mm (4 inches) and larger.
L. Sleeves: Provide for pipes passing through masonry or concrete. Provide space between the pipe and the sleeve in accordance with NFPA 13. Seal this space with a UL Listed through penetration fire stop material in accordance with Section 07 84 00, FIRESTOPPING. Where core drilling is used in lieu of sleeves, also seal space around penetrations. Seal penetrations of walls, floors and ceilings of other types of construction, in accordance with Section 07 84 00, FIRESTOPPING.
M. Firestopping shall be provided for all penetrations of fire resistance rated construction.
Firestopping shall comply with Section 07 84 00, FIRESTOPPING.
N. Painting of Pipe: In finished areas where walls and ceilings have been painted, paint primed surfaces with two coats of paint to match adjacent surfaces, except paint valves and operating accessories with two coats of gloss red enamel. Exercise care to avoid painting sprinklers.
Painting of sprinkler systems above suspended ceilings and in crawl spaces is not required.
Painting shall comply with Section 09 90 00, PAINTING. Any painted sprinkler shall be replaced with a new sprinkler.
O. Locate sprinkler cabinet adjacent to the dry-pipe sprinkler system riser or as directed by COR.
DRY-PIPE SPRINKLER SYSTEMS 21 13 16 - 10
P. Sprinkler System Signage: Provide rigid sprinkler system signage in accordance with NFPA 13 and
NFPA 25. Sprinkler system signage shall include, but not limited to, the following:
1. Identification Signs:
a. Provide signage for each control valve, drain valve, sprinkler cabinet, and inspector’s test.
b. Provide valve tags for each operable valve. Coordinate nomenclature and identification of operable valves with COR. Where existing nomenclature does not exist, the Tag
Identification shall include no less than the following: (FP-B-F/SZ-#) Fire Protection, Building Number, Floor Number/Smoke Zone (if applicable), and Valve Number. (E.g., FP-500-1E-001) Fire Protection, Building 500, First Floor East, Number 001.)
2. Instruction/Information Signs:
a. Provide signage for each control valve to indicate valve function and to indicate what system is being controlled.
b. Provide signage indicating the number and location of low point drains.
3. Hydraulic Placards:
a. Provide signage indicating hydraulic design information. The placard shall include location of the design area, discharge densities, required flow and residual pressure at the base of riser, occupancy classification, hose stream allowance, flow test information, and installing contractor. Locate hydraulic placard information signs at each dry-pipe valve.
Q. Repairs: Repair damage to the building or equipment resulting from the installation of the sprinkler system by the installer at no additional expense to the Government.
3.2 INSPECTION AND TEST
A. Preliminary Testing: Flush newly installed systems prior to performing tests in order to remove any debris which may have been left as well as ensuring piping is unobstructed. Manually demonstrate nitrogen concentration in dry-pipe sprinkler system piping is at least 98%.
Hydrostatically test system, including the fire department connections, pneumatically test system, test air compressor fill time to operating pressure within 30 minutes, and trip test system as specified in NFPA 13, in the presence of the Contracting Officers Representative (COR) or their designated representative. For dry-pipe sprinkler systems with a quick-opening device, the system shall be trip tested with the quick-opening device functioning and with the quick-opening device disabled. Record the time to water delivery for each test. Demonstrate pitch of pipe is in compliance with NFPA 13.
DRY-PIPE SPRINKLER SYSTEMS 21 13 16 - 11
B. Final Inspection and Testing: Subject system to tests in accordance with NFPA 13, and when all necessary corrections have been accomplished, advise COR to schedule a final inspection and test. Connection to the fire alarm system shall have been in service for at least ten days prior to the final inspection, with adjustments made to prevent false alarms. Furnish all instruments, labor and materials required for the tests and provide the services of the installation foreman or other competent representative of the installer to perform the tests. Correct deficiencies and retest system as necessary, prior to the final inspection and testing. Include the operation of all features of the systems under normal operations in test. At the conclusion of final inspection and testing, blow out dry-pipe system piping using compressed air. Verify piping is fully drained, including low point drains.
3.3 INSTRUCTIONS
Furnish the services of a competent instructor for not less than two hours for instructing personnel in the operation and maintenance of the system on the dates requested by the COR.
VA MEDICAL CENTER – WEST HAVEN, CT PUB DATE: 06-01-15
CLEAN AGENT FIRE SUPPRESSION SYSTEM 21 22 00 - 01
SECTION 21 22 00
CLEAN AGENT FIRE SUPPRESSION SYSTEMS
PART 1 - GENERAL
1.1 DESCRIPTION
A. Design, installation and testing of a calculated automatic and manual fixed total flooding clean agent fire extinguishing system and releasing system in accordance with NFPA 2001, NFPA 72, NFPA 70, and NFPA 75 and manufacturer’s written instructions for the locations shown on the contract drawings. The installation shall include all mechanical, controls and electrical components necessary for a complete and operating clean agent fire suppression system.
1.2 RELATED WORK
A. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
D. Section 28 05 13, CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY
E. Section 28 05 28.33, CONDUIT AND BACKBOXES FOR ELECTRONIC SAFETY AND SECURITY
F. Section 28 31 00, FIRE DETECTION AND ALARM
1.3 DESIGN CRITERIA
A. The clean agent fire extinguishing system shall be a fixed total flooding type utilizing clean agent designed to provide a uniform concentration throughout the protected spaces in accordance with NFPA 2001 for a Class C fire.
1. The system shall provide a minimum design concentration by volume, throughout the protected spaces at the minimum anticipated temperature within the protected space.
2. The design concentration within any protected space shall not exceed by volume the no observable adverse effects level (NOAEL). Special means such as mechanical exhaust, shall not be permitted to be used to achieve this criterion.
3. The clean agent shall have a global warming potential (GWP) of less than 4000 and the clean agent shall be readily available throughout the continental United States.
4. Provide the quantity of clean agent as required by NFPA 2001 and manufacturer’s written instructions. Such factors as unenclosed openings (if any), “rundown” time of fans, time required for dampers to close, and any other feature of the facility that could affect concentration shall be taken into consideration.
1.4 SUBMITTALS
A. Submit as one package in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. Prepare detailed working drawings that are signed by a NICET Level IV Special
CLEAN AGENT FIRE SUPPRESSION SYSTEM 21 22 00 - 02
Hazards Suppression Systems Technician. As the Government review is for technical adequacy only, the installer remains responsible for correcting any conflicts with other trades and building construction that arise during installation. Partial submittals will not be accepted. Material submittals shall be approved prior to the purchase or delivery to the job site. Suitably bind submittals in notebooks or binders and provide an index referencing the appropriate specification section. In addition to the hard copies, provide submittal items in Paragraphs 1.4
(A) 1 through 1.4 (A) 5 electronically in pdf format on a compact disc or as directed by the
Contracting Officers Representative (COR). Submittals shall include, but not be limited to, the following:
1. Qualifications:
a. Provide a copy of the installing contractors and state contractors license.
b. Provide a copy of the NICET certification for the NICET Level IV Special Hazards
Suppression System Technician who will prepare and sign the detailed working drawings.
c. Provide documentation showing that the installer has been actively and successfully engaged in the installation of clean agent fire suppression systems for the past ten years.
2. Drawings: Submit detailed 1:100 (1/8 inch) scale (minimum) working plans and drawings of the clean agent fire extinguishing system conforming to NFPA 2001. Submit detailed 1:100
(1/8 inch) scale (minimum) working plans and drawings of the releasing system conforming to NFPA 72. Drawings shall include graphical scales that allow the user to determine lengths when the drawings are reduced in size.
3. Manufacturers Data Sheets:
a. Provide for all materials and equipment proposed for use on the clean agent fire extinguishing system, including the releasing system. Include listing information and installation instructions in data sheets.