This document is an addendum to the construction project plans and specifications for the Ashland Community Center and Pioneer Hall Renovation in Jackson County, Oregon. The addendum includes a summary of changes to the project drawings, including modifications to the floor plan, lighting fixtures, and addition of floor drains in the restrooms. The renovation project is being managed by the City of Ashland on behalf of Jackson County and involves demolition, structural upgrades, mechanical/electrical/plumbing work, interior and exterior renovations, ADA improvements, and hazardous material abatement.
The solicitation documents do not specify any set-aside designations or restrictions on the types of organizations that can respond. The incumbent contractor and current contract value are also not provided. The project budget and funding sources are also not detailed in the available information. Interested parties should thoroughly review the bid and permit drawings, specifications, and other provided documentation to fully understand the scope of work, response requirements, and evaluation criteria for this state and local contracting opportunity.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ashland Community Center & Pioneer Hall Renovation
SUMMARY OF CHANGES
ADDENDUM #3 Issued 5/8/24
ATTACHMENTS
1. Ashland Community Center:
a. Plan Set Sheets: G0.00, D1.00, A0.10, A2.00, A7.00
ASHLAND COMMUNITY
The drawings have been amended as follows:
1. G0.00 Cover Sheet:
a. Added a note to the plumbing design-build scope to add new floor drains in the restrooms.
2. D1.00 Demo Floor Plan:
a. Called out an existing floor vent in Women’s Restroom 107 which needs to be demolished.
b. Expanded upon keynote #10 to include patching the floor where floor vents are removed.
3. A0.10 Finish Schedules:
a. Revised the luminaire schedule:
i. Changed manufacturer and model number for Fixtures F2, F3, and F4.
ii. Changed the finish of Fixture V1 from CH to AB.
iii. Updated the input watts, voltage, and color temperature for each fixture.
iv. Added dimming function to Fixtures F2 and F4.
4. A2.00 Reflected Ceiling Plan:
a. Added/replaced light fixtures in Main Hall 101.
5. A7.00 Enlarged Plans & Interior Elevations:
a. Added floor drains in Men’s Restroom 108 and Women’s Restroom 107.