Attachment 03b - Contract Discrepancy Report Template_2026AUG.pdf
PDF 183 KB Posted
- Attached to
- Turn-key Detention Facilities
- Solicitation number
- 70CDCR26R00000026
- Issued by
-
Immigration and Customs Enforcement
About this file
This is a Contract Discrepancy Report (CDR) template dated August 2026 used to document and resolve performance or compliance issues between federal contracting officers and contractors.
The CDR process consists of three sequential phases. The initiation phase requires the Contracting Officer's Representative (COR) to complete fields 1-7, which include the contract number, CDR identification number, contractor and COR contact information, a detailed description of the discrepancy or problem (with reference to the Performance Work Statement, Performance-Based Navigation/Navigation Data Service, functional category, and QASP rating of "At-Risk" or "Deficient"), the CDR initiation date, and the contractor response due date set by the COR. The contractor then responds in fields 8-10 by explaining the cause of the discrepancy, proposing corrective actions, and outlining preventive measures to avoid recurrence, along with the date of response and contractor representative contact information. In the review phase, the COR completes fields 11-13, providing an evaluation of the contractor's response (acceptable, partial acceptance, or rejection), a recommendation to the Contracting Officer regarding government actions such as payment withholding, deduction, cure notice, or show cause, and the date the CDR is submitted to the Contracting Officer. The final closeout phase requires the Contracting Officer to complete fields 14-15, documenting the decision on the CDR and whether any contractual actions were taken against the contractor, and signing the document. The CO also communicates government actions via contract modification, provides a copy of the final CDR to the COR, and inputs information into the Accountability Tracker on OPTIC, with reference to ICAM Appendix V for additional guidance.
View the file
Other files
Show all 42
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AUG 2026
Contract Discrepancy Report (CDR)
INITIATION OF CDR (COR completes fields 1 through 7 and provides CDR to Contractor)
1. Contract Number:
2. CDR Number (FY## - CDR## example: FY22 - CDR01):
3. To: (Contractor, Company Contact, Contact Information) Contractor:
Manger/Contact:
Contact Information (Email + Phone):
4. From: (Name of Contracting Officer’s Representative (COR) and contact information) Name:
Phone:
Email:
5. Discrepancy or Problem (Describe in Detail: Include reference in PWS or PBNDS/NDS reference/ PWS reference/Functional Category and Rating (“At-Risk” or “Deficient” rating) (see QASP). Attach continuation sheet if necessary and note here.)
6. CDR Initiation Date (Date Sent to Contractor):
7. Contractor Response Due Date (Set by COR):
Contractor Response to CDR (Contractor completes fields 8 through 10 and returns to COR)
8. Contractor Response as To Cause, Corrective Action and Actions to Prevent Recurrence. (Attach continuation sheet if necessary and note here.)
9. Date Contractor Response Returned to COR:
10. CONTRACTOR REPRESENTATIVE Name and Contact Information:
COR REVIEW AND RECOMMENDATION TO CO
Government Evaluation of Contractor Response (COR completes fields 11 through 13 and sends to CO) This section should be completed after the COR and vendor have completed discussions on the CDR, finalized their remedy or corrective action plan, or reached an impasse.
11. COR’s Evaluation of Contractor Response/Resolution Plan: (Acceptable response/plan, partial acceptance of response/plan, rejection. Attach continuation sheet if necessary and note here.)
12. COR’s Recommendation to Contracting Officer for Government Action (Payment withholding, deduction, cure notice, show cause, other, or none. If COR accepts the contractor’s response and/or plan and proposes no further action, state that here. Attach continuation sheet if necessary and note here.)
13. Date CDR Submitted to CO:
CO REVIEW AND CLOSE OUT
CDR CLOSE OUT
Contracting Officer Review *See ICAM Appendix V for additional guidance concerning coordination with OPLA, etc. (CO completes Fields 14 and 15, communicates any government actions via a contract modification, provides a copy of the final CDR to the COR, and inputs the appropriate information into the Accountability Tracker on OPTIC)
14. Contracting Officer’s Decision (Decision on COR requested Government actions or concurrence with no further action, clearly state here how this CDR was resolved. If action was taken against the contractor, clearly outline the action and note the date action was taken. Attach continuation sheet if necessary and note here.)
15. SIGNATURE OF CONTRACTING OFFICER / DATE: