This is a Price Breakout Schedule template that contractors must use when submitting proposals for construction projects to the VA Network Contracting Office 9. The template requires contractors to provide detailed cost breakdowns organized by construction divisions (General Conditions, Concrete, Masonry, Metals, HVAC, Electrical, Plumbing, etc.) with labor, material, and equipment costs itemized for each line item. Contractors must break down costs to the greatest degree possible and cannot submit lump sum prices for entire divisions or subdivisions when further breakdown is feasible.

The template mandates specific administrative information including the applicable VA Medical Center, proposal date, job title, project number, and solicitation number. All divisions must be listed even if not applicable to the project. Overhead is calculated at 10% of subtotal, profit at 10%, and bond/fee/permits/licenses at 3%, with a 6% tax applied to materials. The instructions emphasize that lump sum breakdowns are not acceptable, that Government is not bound to accept any subsequent price breakdown provided, and that contractors should provide thorough initial breakdowns in their best interest. This template or an equivalent providing the same level of detail is required for all proposals submitted to VA Network Contracting Office 9 as of June 30, 2016.

View the file

Other files

File Type Posted
Atch 40 AMEND_4 SCA WD 2015-4641.pdf PDF
Atch 39 AMEND_4 Davis-Bacon WD TN20260191.pdf PDF
S02 AMEND_36C24926R0055 0004 B35.pdf PDF
Atch 26 AMEND_3 _10.06_FS100 - SITE PLAN.pdf PDF
Atch 23 AMEND_3 _ 10_32 17 23 - PAVEMENT MARKINGS.pdf PDF
Atch 21 AMEND_3 _09 93 00 Staining - Transparent Finish.pdf PDF
Atch 31 AMEND_3 _ 10.09_FX103 - AUDITORIUM ATTIC- STAGE NEW WORK.pdf PDF
Atch 22 AMEND_3 _ 10_32 12 16 - ASPHALT PAVING.pdf PDF
Atch 20 AMEND_3 _ 09 01 90.52 - Maintenance Repainting.pdf PDF
S02 AMEND_36C24926R0055 0003 B35.pdf PDF
Atch 35 AMEND_3 Worksheet - S ENG AUTOCAD AUTOCADPUBLIC PDC PROJ 7.xlsx XLSX spreadsheet
Atch 36 AMEND_3 Section 01 45 00 Quality Control.docx DOCX document
Atch 17 AMEND_3 Updated Solicitation 36C24926R0055.pdf PDF
Atch 33 AMEND_3 QUES 186 _doc11604520260625102926.pdf PDF
Atch 34 AMEND_3 Section 01 45 35 Schedule of Special Inspections.docx DOCX document
Atch 38 AMEND_3 VA Mtn Home El Walkway_Geotech Rpt.pdf PDF
Atch 24 AMEND_3 _ 10-10_32 90 00 PLANTING.pdf PDF
Atch 28 AMEND_3 _ Q10.07_FX101 - BASEMENT -1st FLOOR.pdf PDF
Atch 19 AMEND_3 _ 00 01 10 - SPECS - Table Of Contents.pdf PDF
Atch 29 AMEND_3 _ 10.07_FX101 - BASEMENT- 1st FLOOR NEW WORK PLAN.pdf PDF
Atch 30 AMEND_3 _ 10.08_FX102 - BALCONY 2nd FLOOR - CEILING.pdf PDF
Atch 32 AMEND_3 _ 210.05_FD901-WET-PIPE FIRE SUPPRESSION ISOMETRIC.pdf PDF
Atch 25 AMEND_3 _ Limited HazMat Report.pdf PDF
Atch 27 AMEND_3_10.06_FS100 - FIRE SUPPRESSION SITE PLAN.pdf PDF
Atch 37 AMEND_3 Past Performance Questionnaire -PPQ Template.docx DOCX document
Atch 18 AMEND_3 FINISH REVISIONS_ Rev 2 06-30-2026.pdf PDF
S02 AMEND_36C24926R0055 0002 B35.pdf PDF
Atch AMEND_1 Site Visit Attendance Sheet of 621-24-103.pdf PDF
S02 AMEND_36C24926R0055 0001 B35.pdf PDF
S02 SOL 36C24926R0055_1 B35 _ R2.pdf PDF
Atch 16 WD TN20260191 01.02.2026.docx DOCX document
Atch 5_BID SPEC ENG_4288 SUBMITTAL REG.pdf PDF
Atch 14 General Conditions Breakout.xlsx XLSX spreadsheet
36C24926R0055_1.docx DOCX document
Atch 3_BID SPEC App1_B35 HazMat Report.pdf PDF
Atch 12 Calc. of Self Performed Work.xlsx XLSX spreadsheet
Atch 9_621-24-103 Drawing part 4 of 6.pdf PDF
Atch 2_BID MAppE_B35 Existing Conditions.pdf PDF
Atch 1_BID SPECIFICATIONS-1.pdf PDF
Atch 4_BID SPEC App2_B35 Historic SHPO.pdf PDF
Atch 13 Contractor EMR Certification Form.docx DOCX document
Atch 6_621-24-103 drawing part 1 of 6.pdf PDF
Atch 11_621-24-103 Drawing part 6 of 6.pdf PDF
Atch 8_621-24-103 drawing part 3 of 6.pdf PDF
Atch 15 WD TN20260191 01.02.2026.docx DOCX document
Atch 7_621-24-103 drawing part 2 of 6.pdf PDF
Atch 10_621-24-103 Drawing part 5 of 6.pdf PDF
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Breakdown LOCATION: Solicitation Number: Project Number Project Title Proposal Date

PRICE BREAKOUT SCHEDULE
When entering a line item for General Conditions costs on Schedule of Values, a breakout of the General Conditions costs must be provided. Per VAAR 852.243-70 Contract Changes-Supplement, paragraph (c)(1), the following contractual restrictions apply: Overhead and Contractor's fee percentages shall be considered to include insurance other than mentioned herein, field and office supervisors and assistants, security police, use of small tools, incidental job burdens, and general home office expenses and no separate allowance will be made. Assistants to office supervisors include all clerical, stenographic and general office help. Incidental job burdens include, but are not necessarily limited to, office equipment and supplies, temporary toilets, telephone and conformance to OSHA requirements. Items such as, but not necessarily limited to, review and coordination, estimating and expediting relative to contract changes are associated with field and office supervision and are considered to be included in the Contractor's overhead and/or fee percentage.
SPEC/COST CODEDESCRIPTIONLABORMATERIALEQUIPMENTDIVISION TOTALS
General Conditions$0.00
Superintendent
Project Manager
Field Office Engineer
Builder's Risk Insurance
Other Project Specific Liability Insurance
Site Maintenance and Protection
Progress Photos (per contract specifications)
Dumpsters
Office Trailer
Storage Trailer/POD/CONEX
Telephone (Cell and/or Landline)
Signage (per contract specifications and/or drawings)
Travel (must comply with Federal Travel Regulations)
Lodging (must comply with Federal Travel Regulations)
Record Document Preparation
As-builts (per contract specifications)
Weather Protection (per contract specifications)
Infection Control (per contract specifications)
Information Technology (Internet, etc.)
DIVISION 1GENERAL REQUIREMENTS$0.00
Shop Drawings, Product Data, & Samples
Safety Requirements
Reference Standards
Quality Control
Testing Laboratory Services
Special Inspections
Temporary Environmental Controls
Construction Waste Management
General Commissioning Requirements
DIVISION 2Existing Conditions$0.00
Site Survey
Demolition
Traditional Asbestos Abatement
DIVISION 3CONCRETE$0.00
Cast in Place Concrete
Cast in Place Concrete (short form)
DIVISION 4MASONRY$0.00
Masonry Mortaring
DIVISION 5Metals$0.00
Structrural Steel Framing
Metal Fabrications
DIVISION 6Wood, plastics and Composites$0.00
Rough Carpentry
Finish Carpentry
DIVISION 7THERMAL AND MOISTURE PROTECTION$0.00
Thermal Insulation
Flashing and Sheet Metal
Roof Specialties
Roof Accessories
Firestopping
Joint Sealants
DIVISION 8Openings$0.00
Hollow Metal Doors & Frames
Interior Wood Doors
Intensive Care Unit Entrances
Door Hardware
Low Energy Power Assist Door Operators
Glazing
DIVISION 9FINISHES$0.00
Subsurface Prep for Floor Finishing
Schedule for Finishes
Non Struct Metal Framing
Gypsum Board
Ceramic/Porcelain Tiling
Acoustical Ceilings
Resilient Base and Accessories
Resilient Sheet Flooring
Resilient Tiling Flooring
Resinous Epoxy Base With Vinyl Chip Broadcast (RES 2)
Carpeting
Painting
High-Build Glazed Coatings
DIVISION 10Specialties$0.00
Chalkboards and Markerboards
Signage
Cubicle Curtain Tracks
Wall & Door Protection
Toilet, Bath, & Laundry Accessories
Fire Extinguisher Cabinets

DIVISION 11 EQUIPMENT $0.00

DIVISION 12Furnishings$0.00
Window Shades
Manufactured Metal Casework
Manufactured Wood Casework
Countertops
DIVISION 13Special Construction$0.00
Seismic Restraint Requirements for Non- Structural Components
DIVISION 21Fire Suppression$0.00
Wet-Pipe Sprinkler Systems
DIVISION 22Plumbing$0.00
Common Work Results for Plumbing
Meters and Gages for Plumbing piping
General-Duty Valves for Plumbing Piping
General Motor Requirements for Plumbing Equipment
Meters and Gauges for Plumbing Piping
General Duty Valves for Plumbing Piping
Plumbing Insulation
Facility Water Distribution
Facility Sanitary & Vent Piping
Facility Storm Drainage
Packaged Pedestal Drainage Pump Units
Plumbing Fixtures
Vacuum Systems for Laboratory & Healthcare Facilities
Gas Systems for Laboratory & Healthcare Facilities
DIVISION 23Heating, Ventilating and Air Conditioning HVAC$0.00
Common work results for Boiler and Steam Generation
Common Work Results for HVAC
Testing, Adjusting and Balancing for HVAC
General Motor Requriments for HVAC and Steam Generation Equipment
Noise and Vibration Control for HVAC Piping and Equipment
Testing, Adjusting and Balancing for HVAC
HVAC and Boiler Plant Insulation
Commissioning of HVAC Systems
Instrumentation and Control for Boiler Plant
Boiler Plant Piping System
Direct Digital Control System for HVAC
Hydronic Piping
Hydronic Pumps
Steam & Condensate Heating Piping
Steam Condensate Pumps
HVAC Water Treatment
HVAC Ducts and Casing
HVAC Fans
Air Terminal Units
Air Outlets & Inlets
HVAC Air Cleaning Devices
Indoor Central Station Air Handling units
DIVISION 26ELECTRICAL$0.00
Requirements for Electrical Installations
Low-Voltage Electrical Power Conductors and Cables
Grounding and Bonding for Electrical Systems
Raceway & Boxes for Electrical Systems
Overcurrent Protective Device Coordination Study
Low-voltage Bussed Junction Box
Commissioning of Electrical Systems
DVA/USACE Projects Commissioning of Electrical Systems
Motor Control Centers
Motor Controllers
Lighting Controls
Wiring Devices
Enclosed Switches & Circuit Breakers
Facility Lightening Protection
Interior Lighting
DIVISION 27COMMUNICATIONS$0.00
Requirements for Communications Installations
Raceways & Boxes for Communications Systems
Commissioning of Communications Systems
Control, Communication and Signal Wiring
Communications Equipment Room Fittings
Communications Structured Cabling
Nurse Call & Code Blue Systems
DIVISION 28ELECTRONIC SAFETY AND SECURITY$0.00
Common Work Results for Electronic Safety and Security
Conductors and Cables for Electronic Safety and Security
Conduits & Backboxes for Electronic Safety & Security
Physical Access Control System
Fire Detection & Alarm
DIVISION 31EARTHWORK$0.00
Earthwork
DIVISION 32EXTERIOR IMPROVEMENTS$0.00
Cement & Concrete for Exterior Improvements
DIVISION 33$0.00
Steam Energy Distribution
TOTALS
TOTAL LABOR$0.00

TOTAL MATERIALS $0.00

TAX FOR MATERIALS 6% $0.00

TOTAL EQUIPMENT $0.00

DIVISION GRAND TOTALS $0.00

DIVISION GRAND TOTALS$0INSTRUCTIONS
TAX FOR MATERIALS$0
1. Contract breakdowns must include the applicable VA Medical Center, the date the proposal was provided to the VA, the job title, project number, and the solicitation number;
SUBTOTAL$0
OVERHEAD10%$02. Lump sum price breakdowns will not be accepted. Lump sum price breakdowns are defined as a single price provided by the contractor for one division or subdivision when each division or subdivision can be broken down by price to a greater degree;
PROFIT10%$0
SUBTOTAL$0
3. Divisions must still be listed even if not applicable to the construction requirement;
BOND/FEE
PERMITS/LICENSES3%$04. The template above does not include all possible divisions or subdivisions needed for the fictitious requirement referenced above. It is only provided as an example of what would be acceptable to the VA Network Contracting Office 9 -Construction Team as of 6-30-2016. Contractors shall provide all prices for each categorical column above and break down each specific division to the greatest degree possible, similar to what is referenced above. Utilizing this template in the contractor's proposal does not in any way require the Government to accept any subsequent price breakdown that is provided by the contractor or prevent the Government from requesting a further price breakdown. Therefore, it is in the Governments and contractor’s best interest to provide a thorough price breakdown initially; and

GRAND TOTAL $0

5. This template, or another template that would be provide the same kind of information referenced above, is required for all proposals provided to the VA Network Contracting Office 9 - Construction as of 6-30-2016.