This is a pricing and general conditions breakout template in Excel format for a construction solicitation. The file is designed to enable contractors to itemize and present cost proposals for the restoration project in an organized, structured manner. The spreadsheet appears to serve as an attachment to the solicitation documents, providing a standardized format for bidders to input labor, material, equipment, and other cost categories related to the B35 Theater restoration work at the Alvin C. York Campus in Murfreesboro, Tennessee.

The breakout template is part of a Request for Quote (RFQ) issued under a 100% Service-Disabled Veteran Owned Small Business (SDVOSB) set-aside. The solicitation (36C24926R0055) is for electrical contracting and related wiring installation work under NAICS code 238210, with a small business size standard of $45 million. Contractors must maintain active listings in the System for Award Management (SAM) database and the SBA's SDVOSB directory at the time of offer submission and prior to award. Additionally, the awarded contractor must demonstrate enrollment with VETS4212. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 9 is the procuring agency. This spreadsheet enables standardized cost presentation across all competing SDVOSB contractors responding to this solicitation.

View the file

Other files

File Type Posted
Atch 40 AMEND_4 SCA WD 2015-4641.pdf PDF
Atch 39 AMEND_4 Davis-Bacon WD TN20260191.pdf PDF
S02 AMEND_36C24926R0055 0004 B35.pdf PDF
Atch 26 AMEND_3 _10.06_FS100 - SITE PLAN.pdf PDF
Atch 23 AMEND_3 _ 10_32 17 23 - PAVEMENT MARKINGS.pdf PDF
Atch 21 AMEND_3 _09 93 00 Staining - Transparent Finish.pdf PDF
Atch 31 AMEND_3 _ 10.09_FX103 - AUDITORIUM ATTIC- STAGE NEW WORK.pdf PDF
Atch 22 AMEND_3 _ 10_32 12 16 - ASPHALT PAVING.pdf PDF
Atch 20 AMEND_3 _ 09 01 90.52 - Maintenance Repainting.pdf PDF
S02 AMEND_36C24926R0055 0003 B35.pdf PDF
Atch 35 AMEND_3 Worksheet - S ENG AUTOCAD AUTOCADPUBLIC PDC PROJ 7.xlsx XLSX spreadsheet
Atch 36 AMEND_3 Section 01 45 00 Quality Control.docx DOCX document
Atch 17 AMEND_3 Updated Solicitation 36C24926R0055.pdf PDF
Atch 33 AMEND_3 QUES 186 _doc11604520260625102926.pdf PDF
Atch 34 AMEND_3 Section 01 45 35 Schedule of Special Inspections.docx DOCX document
Atch 38 AMEND_3 VA Mtn Home El Walkway_Geotech Rpt.pdf PDF
Atch 24 AMEND_3 _ 10-10_32 90 00 PLANTING.pdf PDF
Atch 28 AMEND_3 _ Q10.07_FX101 - BASEMENT -1st FLOOR.pdf PDF
Atch 19 AMEND_3 _ 00 01 10 - SPECS - Table Of Contents.pdf PDF
Atch 29 AMEND_3 _ 10.07_FX101 - BASEMENT- 1st FLOOR NEW WORK PLAN.pdf PDF
Atch 30 AMEND_3 _ 10.08_FX102 - BALCONY 2nd FLOOR - CEILING.pdf PDF
Atch 32 AMEND_3 _ 210.05_FD901-WET-PIPE FIRE SUPPRESSION ISOMETRIC.pdf PDF
Atch 25 AMEND_3 _ Limited HazMat Report.pdf PDF
Atch 27 AMEND_3_10.06_FS100 - FIRE SUPPRESSION SITE PLAN.pdf PDF
Atch 37 AMEND_3 Past Performance Questionnaire -PPQ Template.docx DOCX document
Atch 18 AMEND_3 FINISH REVISIONS_ Rev 2 06-30-2026.pdf PDF
S02 AMEND_36C24926R0055 0002 B35.pdf PDF
Atch AMEND_1 Site Visit Attendance Sheet of 621-24-103.pdf PDF
S02 AMEND_36C24926R0055 0001 B35.pdf PDF
S02 SOL 36C24926R0055_1 B35 _ R2.pdf PDF
Atch 16 WD TN20260191 01.02.2026.docx DOCX document
Atch 5_BID SPEC ENG_4288 SUBMITTAL REG.pdf PDF
36C24926R0055_1.docx DOCX document
Atch 3_BID SPEC App1_B35 HazMat Report.pdf PDF
Atch 12 Calc. of Self Performed Work.xlsx XLSX spreadsheet
Atch 9_621-24-103 Drawing part 4 of 6.pdf PDF
Atch 2_BID MAppE_B35 Existing Conditions.pdf PDF
Atch 1_BID SPECIFICATIONS-1.pdf PDF
Atch 4_BID SPEC App2_B35 Historic SHPO.pdf PDF
Atch 13 Contractor EMR Certification Form.docx DOCX document
Atch 6_621-24-103 drawing part 1 of 6.pdf PDF
Atch 11_621-24-103 Drawing part 6 of 6.pdf PDF
Atch 8_621-24-103 drawing part 3 of 6.pdf PDF
Atch 15 WD TN20260191 01.02.2026.docx DOCX document
Atch 7_621-24-103 drawing part 2 of 6.pdf PDF
Atch 10_621-24-103 Drawing part 5 of 6.pdf PDF
Atch 15 Price Breakout Schedule.xlsx XLSX spreadsheet
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GC Breakout

GENERAL CONDITIONS BREAKOUT
When entering a line item for General Conditions costs on Schedule of Values, a breakout of the General Conditions costs must be provided. Per VAAR 852.243-70 Construction Contract Changes-Supplement, paragraph (c)(1), the following contractual restrictions apply: Overhead and Contractor's fee percentages shall be considered to include insurance other than mentioned herein, field and office supervisors and assistants, security police, use of small tools, incidental job burdens, and general home office expenses and no separate allowance will be made. Assistants to office supervisors include all clerical, stenographic and general office help. Incidental job burdens include, but are not necessarily limited to, office equipment and supplies, temporary toilets, telephone and conformance to OSHA requirements. Items such as, but not necessarily limited to, review and coordination, estimating and expediting relative to contract changes are associated with field and office supervision and are considered to be included in the Contractor's overhead and/or fee percentage.
General Condition DescriptionValue
Project Management:$ - 0
Superintendent(s)$ - 0
Safety Manager$ - 0
CPM Scheduler$ - 0
Quality Assurance/Quality Control$ - 0
Project Manager (s)$ - 0
Project Executive$ - 0
Field Office Engineer$ - 0
Field Office Support Staff$ - 0
Project Expeditor$ - 0
Assistant Superintendent (s)$ - 0
Project Manager Subtotal:$ - 0
Bonds and Insurance (excluding any for Subcontractors):$ - 0
Builder’s Risk Insurance$ - 0
General Liability Insurance$ - 0
Security, Payment & Performance Bonds$ - 0
Bonds and Insurance Subtotal:$ - 0
Site Conditions:$ - 0
Temporary Power Consumption (Offices)$ - 0
Temporary Power Consumption (General Site Use)$ - 0
Temporary Water and Sewer Consumption$ - 0
Temporary Water Hookup, Distribution & Meters$ - 0
Temporary Electrical Hookup, Distribution & Meters$ - 0
Temporary Telephone & Network System Installation$ - 0
Temporary Telephone & Internet Consumption Fees$ - 0
Temporary Fire Protection$ - 0
Temporary Heating & Cooling$ - 0
Temporary Fencing$ - 0
Temporary Covered Walkways$ - 0
SWPPP Measures$ - 0
Temporary Entries and Truck Washes$ - 0
Street Cleaning (by G.C.)$ - 0
Traffic Control Measures$ - 0
Temporary Barricades & Signage$ - 0
Temporary Roads & Walkways (install & maintenance)$ - 0
Temporary Lighting$ - 0
Temporary Partitions & Covered Floor Openings$ - 0
Temporary Toilets/Sanitary Measures$ - 0
Temporary Laydown (prep and restoration)$ - 0
Security System/Watchman$ - 0
Pre-construction Photo Documentation$ - 0
Progress Photos$ - 0
Temporary Protection (in place work/adjacent structures)$ - 0
$ - 0
$ - 0
$ - 0
General Conditions Total$ - 0