This is a technical specification section for asphalt paving work as part of the Renovate B34 Clock Tower for Physical Therapy project (VA Project Number 621-24-112, dated 09-01-15).
The specification establishes requirements for hot asphalt concrete pavement composition, mixing, construction, and protection. Materials must conform to the latest State Highway Department specifications and include aggregates (crushed stone, gravel, sand) with specified size gradations, asphalt cement (penetration grade 50/60), prime coat (cut-back type, grade MC-250), tack coat (uniformly emulsified, grade SS-1H), and a fibrated chemical type asphalt sealer. Aggregate gradation requirements are detailed by sieve size, with liquid asphalt comprising 5 to 6.5 percent of combined dry aggregates. The contractor must provide a Registered Professional Land Surveyor to establish and control pavement alignments, grades, elevations, and cross sections. Submittals required include aggregate and asphalt test reports, job-mix formula certifications, material safety data sheets, and one copy of State Highway Department specifications. Construction execution requirements specify hot plant-mixed materials delivered at 143–160°C, placement at minimum 138°C, subgrade preparation with proof-rolling using 45-tonne dump trucks, base course spreading and compaction, asphaltic concrete rolling in at least two directions, and seal coat application. Finished paving must achieve specified smoothness tolerances (no deviation greater than 3mm in 1.8m). New asphalt paving requires one year curing before seal coat application; if sealed sooner, two spray-applied coats are required. The specification also addresses weather limitations (minimum 10°C atmospheric temperature, no fog or rain), material receipt requirements (tarpaulin covered, minimum 130°C temperature), and final cleanup and traffic protection until sealer cures.
View the file
Other files
Show all 47
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Renovate B34 Clock Tower for Physical Therapy VA Project Number: 621-24-112
09-01-15
ASPHALT PAVING
32 12 16 - 1
SECTION 32 12 16
ASPHALT PAVING
PART 1 - GENERAL
1.1 DESCRIPTION
This work shall cover the composition, mixing, construction upon the prepared subgrade, and the protection of hot asphalt concrete pavement.
The hot asphalt concrete pavement shall consist of an aggregate or asphalt base course and asphalt surface course constructed in conformity with the lines, grades, thickness, and cross sections as shown. Each course shall be constructed to the depth, section, or elevation required by the drawings and shall be rolled, finished, and approved before the placement of the next course.
1.2 RELATED WORK
A. Laboratory and field testing requirements: Section 01 45 29, TESTING
LABORATORY SERVICES.
B. Subgrade Preparation: Paragraph 3.3 and Section 31 20 00, EARTH MOVING.
C. Pavement Markings: Section 32 17 23, PAVEMENT MARKINGS.
1.3 INSPECTION OF PLANT AND EQUIPMENT
The COR shall have access at all times to all parts of the material producing plants for checking the mixing operations and materials and the adequacy of the equipment in use.
1.4 ALIGNMENT AND GRADE CONTROL
The Contractor’s Registered Professional Land Surveyor shall establish and control the pavement (aggregate or asphalt base course and asphalt surface course) alignments, grades, elevations, and cross sections as shown on the Drawings.
1.5 SUBMITTALS
A. In accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND
SAMPLES, furnish the following:
B. Data and Test Reports:
1. Aggregate Base Course: Sources, gradation, liquid limit, plasticity index, percentage of wear, and other tests required by State Highway
Department.
2. Asphalt Base/Surface Course: Aggregate source, gradation, soundness loss, percentage of wear, and other tests required by State Highway
Department.
3. Job-mix formula.
C. Certifications:
09-01-15
ASPHALT PAVING
32 12 16 - 2
1. Asphalt prime and tack coat material certificate of conformance to
State Highway Department requirements.
2. Asphalt cement certificate of conformance to State Highway
Department requirements.
SPEC WRITER NOTE: Add required certification to Subparagraph 3.
3. Job-mix certification - Submit plant mix certification that mix equals or exceeds the State Highway Specification.
D. One copy of State Highway Department Specifications.
E. Provide MSDS (Material Safety Data Sheets) for all chemicals used on ground.
PART 2 - PRODUCTS
2.1 GENERAL
A. Aggregate base and asphalt concrete materials shall conform to the requirements of the following and other appropriate sections of the latest version of the State Highway Material Specifications, including amendments, addenda and errata. Where the term "Engineer" or
"Commission" is referenced in the State Highway Specifications, it shall mean the VA COR or VA Contracting Officer.
SPEC WRITER NOTE: Add any construction requirements not adequately specified in the State Highway Spec.
2.2 AGGREGATES
A. Provide aggregates consisting of crushed stone, gravel, sand, or other sound, durable mineral materials processed and blended, and naturally combined.
B. Subbase aggregate (where required) maximum size: 38mm(1-1/2").
C. Base aggregate maximum size:
1. Base course over 152mm(6") thick: 38mm(1-1/2");
2. Other base courses: 19mm(3/4").
D. Asphaltic base course:
1. Maximum particle size not to exceed 25.4mm(1”).
2. Where conflicts arise between this specification and the requirements in the latest version of the State Highway
Specifications, the State Specifications shall control.
E. Aggregates for asphaltic concrete paving: Provide a mixture of sand, mineral aggregate, and liquid asphalt mixed in such proportions that the percentage by weight will be within:
09-01-15
ASPHALT PAVING
32 12 16 - 3
Sieve Sizes Percentage Passing
19mm(3/4") 100
9.5mm(3/8") 67 to 85
6.4mm(1/4") 50 to 65
2.4mm(No. 8 mesh) 37 to 50
600µm(No. 30 mesh) 15 to 25
75µm(No. 200 mesh) 3 to 8 plus 50/60 penetration liquid asphalt at 5 percent to 6-1/2 percent of the combined dry aggregates.
2.3 ASPHALTS
A. Comply with provisions of Asphalt Institute Specification SS2:
1. Asphalt cement: Penetration grade 50/60
2. Prime coat: Cut-back type, grade MC-250
3. Tack coat: Uniformly emulsified, grade SS-1H
2.4 SEALER
A. Provide a sealer consisting of suitable fibrated chemical type asphalt base binders and fillers having a container consistency suitable for troweling after thorough stirring, and containing no clay or other deleterious substance.
B. Where conflicts arise between this specification and the requirements in the latest version of the State Highway Specifications, the State
Specifications shall control.
PART 3 - EXECUTION
3.1 GENERAL
The Asphalt Concrete Paving equipment, weather limitations, job-mix formula, mixing, construction methods, compaction, finishing, tolerance, and protection shall conform to the requirements of the appropriate sections of the State Highway Specifications for the type of material specified.
3.2 MIXING ASPHALTIC CONCRETE MATERIALS
A. Provide hot plant-mixed asphaltic concrete paving materials.
1. Temperature leaving the plant: 143 degrees C(290 degrees F) minimum, 160 degrees C(320 degrees F) maximum.
2. Temperature at time of placing: 138 degrees C(280 degrees F) minimum.
09-01-15
ASPHALT PAVING
32 12 16 - 4
3.3 SUBGRADE
A. Shape to line and grade and compact with self-propelled rollers.
B. All depressions that develop under rolling shall be filled with acceptable material and the area re-rolled.
C. Soft areas shall be removed and filled with acceptable materials and the area re-rolled.
D. Should the subgrade become rutted or displaced prior to the placing of the subbase, it shall be reworked to bring to line and grade.
E. Proof-roll the subgrade with maximum 45 tonne (50 ton) gross weight dump truck as directed by VA COR or VA Contracting Officer. If pumping, pushing, or other movement is observed, rework the area to provide a stable and compacted subgrade.
3.4 BASE COURSES
A. Subbase (when required)
1. Spread and compact to the thickness shown on the drawings.
2. Rolling shall begin at the sides and continue toward the center and shall continue until there is no movement ahead of the roller.
3. After completion of the subbase rolling there shall be no hauling over the subbase other than the delivery of material for the top course.
B. Base
1. Spread and compact to the thickness shown on the drawings.
2. Rolling shall begin at the sides and continue toward the center and shall continue until there is no movement ahead of the roller.
3. After completion of the base rolling there shall be no hauling over the base other than the delivery of material for the top course.
C. Thickness tolerance: Provide the compacted thicknesses shown on the
Drawings within a tolerance of minus 0.0mm (0.0") to plus 12.7mm
(0.5").
D. Smoothness tolerance: Provide the lines and grades shown on the
Drawings within a tolerance of 5mm in 3m (3/16 inch in ten feet).
E. Moisture content: Use only the amount of moisture needed to achieve the specified compaction.
3.5 PLACEMENT OF ASPHALTIC CONCRETE PAVING
A. Remove all loose materials from the compacted base.
B. Apply the specified prime coat, and tack coat where required, and allow to dry in accordance with the manufacturer’s recommendations as approved by the Architect or Engineer.
09-01-15
ASPHALT PAVING
32 12 16 - 5
C. Receipt of asphaltic concrete materials:
1. Do not accept material unless it is covered with a tarpaulin until unloaded, and unless the material has a temperature of not less than
130 degrees C(280 degrees F).
2. Do not commence placement of asphaltic concrete materials when the atmospheric temperature is below 10 degrees C (50 degrees F), not during fog, rain, or other unsuitable conditions.
D. Spreading:
1. Spread material in a manner that requires the least handling.
2. Where thickness of finished paving will be 76mm (3") or less, spread in one layer.
E. Rolling:
1. After the material has been spread to the proper depth, roll until the surface is hard, smooth, unyielding, and true to the thickness and elevations shown own the drawings.
2. Roll in at least two directions until no roller marks are visible.
3. Finished paving smoothness tolerance:
a. No depressions which will retain standing water.
b. No deviation greater than 3mm in 1.8m (1/8" in six feet).
3.6 APPLICATION OF SEAL COAT
A. Prepare the surfaces, mix the seal coat material, and apply in accordance with the manufacturer’s recommendations as approved by the
Architect or Engineer.
B. Achieve a finished surface seal which, when dry and thoroughly set, is smooth, tough, resilient, of uniform black color, and free from coarse textured areas, lap marks, ridges, and other surface irregularities.
C. When sealing new asphalt paving wait an entire year to allow for the expansion and contraction of a year’s cycle of both warm and cool temperatures. This allows for the asphalt’s oils to properly cure and begin oxidation before applying a seal coat.
D. When seal coating in less than a year apply two coats, spray applied.
This application method is preferred for less than a year application when there is still plenty of asphalt cement present for the seal coat to bond to.
SPEC WRITER NOTE: Use the paragraph below when repair work occurs on existing asphalt paving.
09-01-15
ASPHALT PAVING
32 12 16 - 6
E. When seal coating existing paving that has new asphalt patches, apply two coats sprayed to the existing asphalt and a single lighter coat on new patch work, just enough to make the color of the new patches match the rest of the reseal coated paving.
SPEC WRITER NOTE: use the paragraph below when resealing existing paving for maintenance purposes.
3.7 PROTECTION
Protect the asphaltic concrete paved areas from traffic until the sealer is set and cured and does not pick up under foot or wheeled traffic.
3.8 FINAL CLEAN-UP
Remove all debris, rubbish, and excess material from the work area.
- - - E N D - - -
| SPEC WRITER NOTE: Delete or add information between // ---- // and any other items applicable to project. Any item added to the text shall be covered under Applicable Publications and Products and the paragraphs renumbered. |
| PART 1 - GENERAL |
| 1.1 DESCRIPTION |
| 1.2 RELATED WORK |
| 1.3 INSPECTION OF PLANT AND EQUIPMENT |
| 1.4 ALIGNMENT AND GRADE CONTROL |
| 1.5 SUBMITTALS |
| PART 2 - PRODUCTS |
| 2.1 GENERAL |
| 2.2 AGGREGATES |
| 2.3 ASPHALTS |
| 2.4 SEALER |
| PART 3 - EXECUTION |
| 3.1 GENERAL |
| 3.2 MIXING ASPHALTIC CONCRETE MATERIALS |
| 3.3 SUBGRADE |
| 3.4 BASE COURSES |
| 3.5 PLACEMENT OF ASPHALTIC CONCRETE PAVING |
| 3.6 APPLICATION OF SEAL COAT |
| //F. When resealing existing paving 5, 10, 15 years and older, that is oxidized and is very light in color, squeegee apply the first coat of seal coat and spray on a second coat. Two coats are preferred in older paving when the asphalt cement has oxid... |
| 3.7 PROTECTION |
| 3.8 FINAL CLEAN-UP |