This is a Past Performance Questionnaire template for the Buck Hall Recreation Site Renovation project. The document is designed to be completed by offerors in Section A and then distributed to their references for completion of Section B. References must submit completed questionnaires directly to Penny Zortman (penny.zortman@usda.gov) and Jalisa Sims (jalisa.sims@usda.gov) no later than Thursday, June 25, 2026 by 1:00 PM EST. The questionnaire cannot be submitted by the offeror; it must be received directly from the reference.

The questionnaire evaluates contractor past performance across multiple categories using a six-point rating scale (Excellent, Very Good, Satisfactory, Neutral, Marginal, Unsatisfactory). Key evaluation areas include working relationships, management capability, regulatory compliance, equipment maintenance and operational readiness, personnel management, record-keeping accuracy, environmental and safety compliance, quality standards achievement, quality control procedures, and timeliness of performance. References must provide detailed responses to yes/no questions regarding contractor performance, with explanations required for negative responses. The form also includes space for remarks and additional documentation. This template is associated with the GAOA Buck Hall Recreation Phase 1 Renovation project located in McClellanville, South Carolina, managed by the Department of Agriculture Forest Service.

View the file

Other files

File Type Posted
A18 - Bathymetric Survey.pdf PDF
A16 - Addendum No. 1.pdf PDF
A21 - CZC Concurrence.pdf PDF
A25 - USACOE Fishing Pier Letter.pdf PDF
A26 - USACOE Shoreline Protection.pdf PDF
Amendment 1 -12445226R0008.pdf PDF
A1 -rev RFP Terms and Conditions.docx DOCX document
A17 - Spec Section 314116.pdf PDF
A19 - Geotechnical Report.pdf PDF
A22 - SCDES NPDES Approval.pdf PDF
A3 - Revised SOI Buck Hall Final.pdf PDF
A20 - Charleston Co Stormwater Permit.pdf PDF
A23 - SCDES Wastewater Permit.pdf PDF
A24 - SCDES Well Permit.pdf PDF
RFP 12445226R0008 Buck Hall P1.pdf PDF
A1 -RFP Terms and Conditions 12445226R0008.docx DOCX document
A2 - SOW Buck Hall Reno 2.0.docx DOCX document
A12 - WD Building SC20250023 Charleston Cnty.pdf PDF
A3 - SOI Buck Hall Final.pdf PDF
A4 - Specifications Table of Contents.pdf PDF
A6 - Bldg Set pg 1-53 of 53.pdf PDF
A10 - Project Map.pdf PDF
A11 - Appendix A Pics and Illustrations.docx DOCX document
A14 - Experience Questionnaire.pdf PDF
A15 -Bid Schedule Plan.pdf PDF
A5 - Specs Manual 2026.pdf PDF
A7 - Site Set pg. 1-109 of 138.pdf PDF
A8 - Site Set p 110-116 of 138 Onsite WW Design (OSE).pdf PDF
A9 - Site Set pg. 133-138 of 138 Kayak Launch (ATM).pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Buck Hall Recreation Site Renovation

PRESENT/PAST PERFORMANCE QUESTIONNAIRE

Offerors are to complete Section A, then forward it to their references.

References shall complete and email to Penny Zortman at penny.zortman@usda.gov and Jalisa Sims at jalisa.sims@usda.gov no later than Thursday, June 25, 2026 by 1pm EST.

Attachment 12 must be received directly from the reference, not the offeror.

SECTION A: CONTRACTOR INFORMATION

A. Contractor’s Name and Address: ________________________________________________

B. Point of Contact: ______________________________________________________________

C. Phone #: ____________________________________________________________________

D. Contract Number: ___________________ Contract Type: ____________________

E. Project Title: _________________________________________________________________

F. Period of Performance: _________________________________________________________

G. Brief Description/Scope of Services provided: _________________________________________

H. Authorization is hereby granted to provide the information requested in SECTION B of this questionnaire.

Signature of Authorized Contractor Representative Date

Printed Name and Title of Authorized Contractor Representative

RESPONDENT INFORMATION:

A. Name:______________________________________ B. Position:________________ C. Telephone Number:_____________________ Fax Number: ______________ D. Address:___________________________ E. Relationship and Time Involved with Contractor:___________________ F. Date Questionnaire Completed:_______________________

E
VG
S
N
M
U
Excellent
Very Good
Satisfactory
Neutral
Marginal
Unsatisfactory

CONTRACT PERFORMANCE

1.
Working relationship with your Company
E
VG
S
N
M
U
2.
Did the contractor provide experienced managers and supervisors with the technical and administrative abilities needed to meet contract requirements? If no, please explain.
Yes

No

N/A

3.
Exhibited knowledge of and compliance with government (or other) regulations and industry standards
E
VG
S
N
M
U
4.
Did the contractor provide and properly maintain operational equipment throughout the term of the contract? If no, please explain.
Yes

No

N/A

5.
Did the contractor demonstrate the ability to hire, maintain, and replace, if necessary qualified personnel during the contract? If no, please explain.
Yes

No

N/A

6.
Does the contractor provide timely and accurate records?
Yes

No

N/A

7.
How well did the contractor comply with Environmental, Safety, health and security requirements
E
VG
S
N
M
U
8
Would you award similar contracts to this contractor (If no, Please explain in remarks)
Yes

No

N/A

9.
Contractor’s Overall Performance
E
VG
S
N
M
U

QUALITY OF SERVICE/CONTROL

1.
Contractor’s accomplishment in meeting the quality standards
E
VG
S
N
M
U
2.
Did the contractor provide an effective quality control plan or inspection procedures to meet contract requirements? If no, please explain.
Yes

No

N/A

3.
Overall Quality of Service/Control
E
VG
S
N
M
U

TIMELINESS OF PERFORMANCE

1.
Was the job/contract started and completed on time?. If not, explain
Yes

No

N/A

2.
Did the contractor have a system or method to track progress on all work in progress?
Yes

No

N/A