A16 - Addendum No. 1.pdf
PDF 51 KB Posted
- Attached to
- GAOA Buck Hall Recreation Phase 1 Renovation
- Solicitation number
- 12445226R0008
- Issued by
-
Department of Agriculture Forest Service
About this file
This is an Addendum 1 to contract documents that modifies specifications and architectural requirements across nine distinct items.
Item 1 requires impact-resistant glazing assemblies tested and labeled per ASTM E1886 and ASTM E1996 standards for all Type "A" openings measuring 3'-4" W x 2'-8" H and all 3'-4" W x 9'-4" H aluminum door/frame systems with 2'-0" W x 3'-0" H transom glazing. The requirement applies to complete tested assemblies including glazing, framing, anchorage, and associated components, with all references to tempered glazing only deleted. Item 2 revises roof insulation thickness on Sheet A-905 Detail 4/A-905 to specify 2" rigid insulation for Building 400 (Storage Building) and 4" rigid insulation for Buildings 200 and 700 (Well Houses). Item 3 modifies the door schedule on Sheet A-901 to change all FRP door frame materials from "ALUM" to "FRP" with manufacturer's standard gel-coat finish. Item 4 updates door frame details on sheets 4/A-901, 7/A-901, and 8/A-901 to specify "FRP FRAME" instead of "ALUMINUM FRAME." Item 5 adds requirements in Section 042200 Masonry Specification for integrally pigmented CMU with integral water repellent admixture, coordinated with Note 5 on A-201. Item 6 adds a 20-year weathertightness warranty requirement in Section 074113.16 covering roof panels, flashings, trim, sealants, clips, and associated components. Item 7 adds a general note to G-001 clarifying that new materials, equipment, fixtures, supports, and building components shall be provided unless specifically indicated otherwise, with existing components not to be reused or relocated. Item 8 requires contractors to provide 2" empty conduit for communication service on Sheet E-101 Building 100, terminated 5'-0" outside the building. Item 9 references a revised Specification 314116 Bulkhead Construction Section 1.3.B.1 provided as an attachment.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum 1
Item 1 – Impact-Resistant Glazing
Revise the Contract Documents to require impact-resistant glazing assemblies at all Type "A" 3'-4" W x 2'-8" H glazed openings and all 3'-4" W x 9'-4" H aluminum door/frame systems with 2'-0" W x 3'-0" H transom glazing above. Revise Section 088000 accordingly.
Impact-resistant assemblies shall be tested and labeled in accordance with ASTM E1886 and ASTM E1996. Requirement applies to the complete tested assembly, including glazing, framing, anchorage, and associated components.
Delete all references requiring tempered glazing only for these openings.
Revise any window/door details referencing tempered glass only.
Item 2 – Roof Insulation Thickness
Sheet A-905: Revise Detail 4/A-905 to read as follows:
2" RIGID INSULATION @ BUILDING 400 (STORAGE BLDG.) 4” RIGID INSULATION @
BUILDINGS 200 AND 700 (WELL HOUSES).
Item 3 – Door Schedule
Sheet A-901 – Door Schedule: Revise all door types identified as FRP doors as follows:
Frame Material: Change all listed as “ALUM” to “FRP”
Frame Finish: Manufacturer's standard gel-coat finish.
Item 4 – Door Frame Details
Sheet A-901 – Door Head Jamb and Sill details 4/A-901, 7/A-901, 8/A-901: Revise “ALUMINUM FRAME” to “FRP FRAME”.
Item 5 – Pigmented CMU
Section 042200 / Masonry Specification: Add requirement for:
Integrally pigmented CMU
Integral water repellent admixture
Coordinate with Note 5 on A-201.
Item 6 – Roofing Warranties
Section 074113.16 Section, Add Paragraph 1.9: " Provide manufacturer's 20-year weathertightness warranty covering roof panels, flashings, trim, sealants, clips, and associated components required to maintain a weathertight roof system. "
Item 7 – General Clarification for New Construction
G-001 General Notes: Add the following note “Unless specifically indicated otherwise in the Contract Documents, provide new materials, equipment, fixtures, supports, and building components. Existing components are not intended to be reused, relocated, or incorporated into the Work.”
Item 8 – Sheet E-101, Building 100:
Add the following note. “Contractor to provide 2" empty conduit for communication service and terminate 5'-0" outside of building.”
Item 9 – Specification 314116 Bulkhead Construction
Revised 314116, Sec. 1.3.B.1, see attached.