A16 - Addendum No. 1.pdf

PDF 51 KB Posted

Attached to
GAOA Buck Hall Recreation Phase 1 Renovation
Solicitation number
12445226R0008
Issued by

About this file

This is an Addendum 1 to contract documents that modifies specifications and architectural requirements across nine distinct items.

Item 1 requires impact-resistant glazing assemblies tested and labeled per ASTM E1886 and ASTM E1996 standards for all Type "A" openings measuring 3'-4" W x 2'-8" H and all 3'-4" W x 9'-4" H aluminum door/frame systems with 2'-0" W x 3'-0" H transom glazing. The requirement applies to complete tested assemblies including glazing, framing, anchorage, and associated components, with all references to tempered glazing only deleted. Item 2 revises roof insulation thickness on Sheet A-905 Detail 4/A-905 to specify 2" rigid insulation for Building 400 (Storage Building) and 4" rigid insulation for Buildings 200 and 700 (Well Houses). Item 3 modifies the door schedule on Sheet A-901 to change all FRP door frame materials from "ALUM" to "FRP" with manufacturer's standard gel-coat finish. Item 4 updates door frame details on sheets 4/A-901, 7/A-901, and 8/A-901 to specify "FRP FRAME" instead of "ALUMINUM FRAME." Item 5 adds requirements in Section 042200 Masonry Specification for integrally pigmented CMU with integral water repellent admixture, coordinated with Note 5 on A-201. Item 6 adds a 20-year weathertightness warranty requirement in Section 074113.16 covering roof panels, flashings, trim, sealants, clips, and associated components. Item 7 adds a general note to G-001 clarifying that new materials, equipment, fixtures, supports, and building components shall be provided unless specifically indicated otherwise, with existing components not to be reused or relocated. Item 8 requires contractors to provide 2" empty conduit for communication service on Sheet E-101 Building 100, terminated 5'-0" outside the building. Item 9 references a revised Specification 314116 Bulkhead Construction Section 1.3.B.1 provided as an attachment.

View the file

Other files

File Type Posted
Amendment 1 -12445226R0008.pdf PDF
A1 -rev RFP Terms and Conditions.docx DOCX document
A17 - Spec Section 314116.pdf PDF
A19 - Geotechnical Report.pdf PDF
A22 - SCDES NPDES Approval.pdf PDF
A21 - CZC Concurrence.pdf PDF
A25 - USACOE Fishing Pier Letter.pdf PDF
A26 - USACOE Shoreline Protection.pdf PDF
A18 - Bathymetric Survey.pdf PDF
A3 - Revised SOI Buck Hall Final.pdf PDF
A20 - Charleston Co Stormwater Permit.pdf PDF
A23 - SCDES Wastewater Permit.pdf PDF
A24 - SCDES Well Permit.pdf PDF
RFP 12445226R0008 Buck Hall P1.pdf PDF
A13 - Past Performance Questionnaire.docx DOCX document
A11 - Appendix A Pics and Illustrations.docx DOCX document
A14 - Experience Questionnaire.pdf PDF
A15 -Bid Schedule Plan.pdf PDF
A3 - SOI Buck Hall Final.pdf PDF
A4 - Specifications Table of Contents.pdf PDF
A6 - Bldg Set pg 1-53 of 53.pdf PDF
A10 - Project Map.pdf PDF
A1 -RFP Terms and Conditions 12445226R0008.docx DOCX document
A2 - SOW Buck Hall Reno 2.0.docx DOCX document
A12 - WD Building SC20250023 Charleston Cnty.pdf PDF
A5 - Specs Manual 2026.pdf PDF
A7 - Site Set pg. 1-109 of 138.pdf PDF
A8 - Site Set p 110-116 of 138 Onsite WW Design (OSE).pdf PDF
A9 - Site Set pg. 133-138 of 138 Kayak Launch (ATM).pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum 1

Item 1 – Impact-Resistant Glazing

Revise the Contract Documents to require impact-resistant glazing assemblies at all Type "A" 3'-4" W x 2'-8" H glazed openings and all 3'-4" W x 9'-4" H aluminum door/frame systems with 2'-0" W x 3'-0" H transom glazing above. Revise Section 088000 accordingly.

Impact-resistant assemblies shall be tested and labeled in accordance with ASTM E1886 and ASTM E1996. Requirement applies to the complete tested assembly, including glazing, framing, anchorage, and associated components.

Delete all references requiring tempered glazing only for these openings.

Revise any window/door details referencing tempered glass only.

Item 2 – Roof Insulation Thickness

Sheet A-905: Revise Detail 4/A-905 to read as follows:

2" RIGID INSULATION @ BUILDING 400 (STORAGE BLDG.) 4” RIGID INSULATION @

BUILDINGS 200 AND 700 (WELL HOUSES).

Item 3 – Door Schedule

Sheet A-901 – Door Schedule: Revise all door types identified as FRP doors as follows:

Frame Material: Change all listed as “ALUM” to “FRP”

Frame Finish: Manufacturer's standard gel-coat finish.

Item 4 – Door Frame Details

Sheet A-901 – Door Head Jamb and Sill details 4/A-901, 7/A-901, 8/A-901: Revise “ALUMINUM FRAME” to “FRP FRAME”.

Item 5 – Pigmented CMU

Section 042200 / Masonry Specification: Add requirement for:

Integrally pigmented CMU

Integral water repellent admixture

Coordinate with Note 5 on A-201.

Item 6 – Roofing Warranties

Section 074113.16 Section, Add Paragraph 1.9: " Provide manufacturer's 20-year weathertightness warranty covering roof panels, flashings, trim, sealants, clips, and associated components required to maintain a weathertight roof system. "

Item 7 – General Clarification for New Construction

G-001 General Notes: Add the following note “Unless specifically indicated otherwise in the Contract Documents, provide new materials, equipment, fixtures, supports, and building components. Existing components are not intended to be reused, relocated, or incorporated into the Work.”

Item 8 – Sheet E-101, Building 100:

Add the following note. “Contractor to provide 2" empty conduit for communication service and terminate 5'-0" outside of building.”

Item 9 – Specification 314116 Bulkhead Construction

Revised 314116, Sec. 1.3.B.1, see attached.