This document contains the questions and answers from a pre-proposal conference for solicitation number 80JSC023R0003, the United States Deorbit Vehicle opportunity with the National Aeronautics and Space Administration Johnson Space Center. The conference addressed questions on the scope of work, period of performance, acceptance criteria and payment terms for the core CLINs 1 and 2 work to design, develop, integrate, test and deliver the USDV. Additional questions covered the optional CLIN 2A work, the minimum IDIQ value for storage and operations CLINs 3-5, requirements for subcontractor cost submissions, and the timing for potential launch delays.

View the file

Other files

File Type Posted
80JSC023R0003 RFP Question and Answer Part IV.pdf PDF
80JSC023R0003 RFP Amendment 7.pdf PDF
Attachment_L-03_Technical_Resources_Template_Amendment 6.xlsx XLSX spreadsheet
Attachment J-40 Deliverable Items List_Amendment 6.xlsx XLSX spreadsheet
80JSC023R003 USDV RFP Model Contract Attachment J-01 - Data Requirements Deliverable.docx DOCX document
80JSC023R0003 USDV RFP Amendment 6.pdf PDF
80JSC023R0003 USDV RFP Model Contract Amendment 6.docx DOCX document
Attachment L-01C Minor Subcontractor Template Amendment 6.xlsx XLSX spreadsheet
80JSC023R0003 RFP Amendment 4 Questions and Answers.pdf PDF
80JSC023R0003 Model Contract Amendment 5.docx DOCX document
Attachment L-01B USDV Fixed Price Template Amendment 5.xlsx XLSX spreadsheet
Attachment L-01D USDV Hybrid Cost Price Template (CLIN 1 and 2 CPIF) Amendment 5.xlsx XLSX spreadsheet
Attachment L-01A USDV Hybrid Cost Price Template Amendment 5.xlsx XLSX spreadsheet
80JSC023R0003 Amendment 5.pdf PDF
Attachment L-01C Minor Subcontractor Template Amendment 5.xlsx XLSX spreadsheet
80JSC023R0003 USDV RFP Amendment 4.pdf PDF
BG-23-205 USDV RFP Amendment 4 Cover Letter .pdf PDF
Attachment L-01A USDV Hybrid Cost Price Template Amendment 4.xlsx XLSX spreadsheet
BG-23-205 Enclosure 2 USDV RFP Question Template.xlsx XLSX spreadsheet
Attachment L-01C Minor Subcontractor Template Amendment 4.xlsx XLSX spreadsheet
Attachment L-01B USDV Fixed Price Template Amendment 4.xlsx XLSX spreadsheet
80JSC023R0003 Model Contract Amendment 4.docx DOCX document
Attachment L-01D USDV Hybrid Cost Price Template (CLIN 1 and 2 CPIF) Amendment 4.xlsx XLSX spreadsheet
80JSC023R0003 Amendment 3.pdf PDF
Attachment L-03 Technical Resources Template Revised Amendment 3.xlsx XLSX spreadsheet
Final RFP Question and Answer Part II.pdf PDF
80JSC023R003 Amendment 2.pdf PDF
80JSC023R0003 USDV Model Contract Amendment 2.docx DOCX document
Final RFP Questions and Answers.pdf PDF
Attachment L-01A USDV Hybrid Cost Price Template Amendment 1.xlsx XLSX spreadsheet
80JSC023R0003 Amendment 1.pdf PDF
Attachment L-01B USDV Fixed Price Template Amendment 1.xlsx XLSX spreadsheet
80JSC023R0003 USDV PreProposal Conference (Pricing) Presented.pdf PDF
80JSC023R0003 USDV PreProposal Conference Presented Presented.pdf PDF
80JSC023R0003 USDV PreProposal Conference.pdf PDF
80JSC023R0003 USDV PreProposal Conference (Pricing).pdf PDF
Attachment J-40 Deliverable Items List.xlsx XLSX spreadsheet
Attachment L-03 Technical Resources Template.xlsx XLSX spreadsheet
SF33-22.pdf PDF
Attachment L-01C Minor Subcontractor Template.xlsx XLSX spreadsheet
Attachment L-01A USDV Hybrid Cost and Price Template.xlsx XLSX spreadsheet
USDV Final RFP Technical Library File Mapping.pdf PDF
Attachment L-07 Past Performance Matrix.xlsx XLSX spreadsheet
Attachment J-38 DD Form 254 Department of Defense Contract Security Classification Specification.pdf PDF
Attachment L-01B USDV Fixed Price Template.xlsx XLSX spreadsheet
Attachment L-09 Pre-award Survey of Prospective Contractor Accounting System Checklist.pdf PDF
80JSC023R0003 USDV Model Contract.docx DOCX document
Attachment L-10 Prime and Subcontractor Identification and SOW Division of Work Listing.xlsx XLSX spreadsheet
BG-23-118 USDV Final RFP Cover Letter .pdf PDF
80JSC023R0003 USDV RFP.pdf PDF
Show all 50

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Deorbit Vehicle Pre-Proposal Conference Question and Answers

Question

Question Answer

1 The Final RFP states that final acceptance of the USDV will take place prior to entering Dwell if Dwell is necessary. However, the SOW summary of scope for CLIN 3 also states that certain Dwell activities supporting L-12 call up are CLIN 2 scope.

Will NASA please clarify?

It is the Government's intention to complete as much of the AI&T effort as possible prior to Dwell, if Dwell is required, to reduce risk to the government. A System Acceptance Review will be held prior to Dwell, if Dwell is required. If the full scope of the System Acceptance Review contents is not completed prior to Dwell, the C2- 4 System Acceptance and C2-5 Shipment to Acceptance Destination Milestones will remain open during Dwell.

Any assembly, integration, and test activities that are completed in parallel with dwell are included in the CLIN 2 scope. Activities that are related to long-term storage for USDV that are completed during dwell are included in the CLIN 3 scope.

2 Specifically related to the previous question -how does NASA anticipate final acceptance payment working with the AIT scope potentially extending out over several years of dwell? Is acceptance at delivery or after call up? How is payment of AIT scope structured?

USDV acceptance occurs upon successful completion of milestones C2-4 and C2-5.

If the full scope of the System Acceptance Review contents is not completed prior to Dwell, the C2-4 System Acceptance and C2-5 Shipment to Acceptance Destination Milestones will remain open during Dwell. Payment for these milestones will be held until the completion criteria for the milestones are satisfied.

The payment of AIT Scope is in accordance with the Offeror’s proposed Attachment J-30 Work Plan.

3 The RFP implies SAR occurs prior to dwell.

However, this conflicts with the acknowledgment that some CLIN 2 activities may need to occur at the end of dwell. Please clarify that SAR should be conducted after all CLIN 2 work is complete and that SAR is not a prerequisite to dwell.

Please see prior responses to Questions 1 and 2 above.

4 Section 3 of the USDV LV Summary document states that in the event of late USDV delivery, "NASA will utilize the terms and conditions in the USDV contract to resolve the impacts to the Government for the

The methods and specific clauses that are used will be based on the factual circumstances of the situation. The USDV contract does contain multiple clauses including the following clauses to manage delays:

Question Answer delay."

Will NASA please clarify what specific methods NASA would invoke?

• FAR 52.242-15, Stop-Work Order

• FAR 52.242-17, Government Delay of

Work

• FAR 52.249-8, Default

• FAR 52.249-14, Excusable Delay

5 Please clarify intent with respect to the delivery date of 08/01/2028 in clause F.3.

Specifically, does NASA intend to modify this provision to move the delivery date requirement day for day with the launch date, preserving the same "L-" spacing?

The August 1, 2028, date is intended to communicate NASA’s need date which provides ISS end-of-life contingency protection versus the nominally planned deorbit. NASA’s use of the “L-12-month call-up” is to ensure upon call-up that any remaining work can be completed during this timeframe.

If the launch date as documented in Clause F.3 moves, the Government will assess any resulting impacts to the contract based on the factual circumstances of each potential situation.

6 What is the latest NASA would inform contractors of the need to delay the launch and plan for dwell? Is that also intended to be

NLT L-12?

NASA's intention is that a "delay" to USDV launch as a result of a major decision, like ISS extension, would occur NLT L-12 months.

7 Please clarify if NASA intends for CLIN 4 (launch vehicle integration) to cover all launch vehicle product development (such as ICDs), and if CLIN4 should also overlap in time with CLIN 2 and CLIN 3 since LV procurement will presumably happen 2+ years before launch?

Launch Vehicle integration preparation and product development must occur throughout the project lifecycle, therefore scope is included in General Requirements (SOW Section 2.0), CLIN 1 (SOW Section 3.0) and CLIN 2 (SOW Section 4.0). Therefore, there is no expectation to authorize CLIN 4 concurrently for launch vehicle integration preparation since the scope is included in CLIN 1 and CLIN 2.

8 Previous RFPs involving GTAs provided for discussions between offerors and the performing orgs. These conversations were valuable to scope the GTAs. Can NASA provide a mechanism for these discussions?

NASA is able to respond to GTA questions, but due to the Contract blackout period, all GTA-related questions must be routed through the NASA GTA POC, Kristi Duplichen, who will coordinate necessary discussions with the performing orgs.

Question Answer

9 Will NASA please clarify what the total contract value calculation is for small business goals?

The total contract value is all of the CLINs 1 and 2 CORE work, CLIN2A Option and the minimum IDIQ value for CLINs 3-5. There will be one subcontracting plan for the entire contract (all CLINs). Therefore, whatever cost the offeror is proposing for the entire contract, the small business goals will be a percentage of that value.

10 FAR 15.403-1 provides specific situations that are exceptions to certified cost/pricing requirements such as competition and commercial items. Please confirm Major Subs with an exception to certified cost or pricing requirements will not be required to complete Att. L-01A or B.

Offerors’ major subcontractors are required to complete Attachment L-01A or L-01B regardless of the commercial nature of the item. The Government is not requesting Certified Cost/Pricing Data (CCPD) at proposal submission. If the Contracting Officer determines later that adequate price competition does not exist, the Government reserves the right to require submission of CCPD to support evaluation of realistic and reasonable costs/prices. The end item vehicle is not commercial.

The following question was posed during the Pricing Pre-Proposal Conference session:

Question Answer

1 FAR 15.403-1 provides specific situations that are exceptions to certified cost/pricing requirements such as competition and commercial items. Please confirm Major Subs with an exception to certified cost or pricing requirements will not be required to complete Att. L-01A or B.

The Contractor is required to complete attachment regardless of commercial nature of the item. The government not requesting CCPD at proposal submission but only in the event we don’t have adequate competition. The end item vehicle is not commercial.

Accessibility Report

Filename:

PreProposal Conference Question and Answers.pdf

Report created by:

Organization:

[Enter personal and organization information through the Preferences > Identity dialog.]

Summary

The checker found no problems in this document.

Needs manual check: 2

Passed manually: 0

Failed manually: 0

Skipped: 4

Passed: 26

Failed: 0

Detailed Report

Document

Rule Name Status Description

Accessibility permission flag Passed Accessibility permission flag must be set

Image-only PDF Passed Document is not image-only PDF

Tagged PDF Passed Document is tagged PDF

Logical Reading Order Needs manual check Document structure provides a logical reading order

Primary language Passed Text language is specified

Title Passed Document title is showing in title bar

Bookmarks Passed Bookmarks are present in large documents

Color contrast Needs manual check Document has appropriate color contrast

Page Content

Rule Name Status Description

Tagged content Skipped All page content is tagged

Tagged annotations Skipped All annotations are tagged

Tab order Passed Tab order is consistent with structure order

Character encoding Passed Reliable character encoding is provided

Tagged multimedia Passed All multimedia objects are tagged

Screen flicker Passed Page will not cause screen flicker

Scripts Passed No inaccessible scripts

Timed responses Passed Page does not require timed responses

Navigation links Passed Navigation links are not repetitive

Forms

Rule Name Status Description

Tagged form fields Passed All form fields are tagged

Field descriptions Passed All form fields have description

Alternate Text

Rule Name Status Description

Figures alternate text Passed Figures require alternate text

Nested alternate text Passed Alternate text that will never be read

Associated with content Passed Alternate text must be associated with some content

Hides annotation Passed Alternate text should not hide annotation

Other elements alternate text Passed Other elements that require alternate text

Tables

Rule Name Status Description

Rows Passed TR must be a child of Table, THead, TBody, or TFoot

TH and TD Passed TH and TD must be children of TR

Headers Passed Tables should have headers

Regularity Passed Tables must contain the same number of columns in each row and rows in each column

Summary Skipped Tables must have a summary

Lists

Rule Name Status Description

List items Skipped LI must be a child of L

Lbl and LBody Passed Lbl and LBody must be children of LI

Headings

Rule Name Status Description

Appropriate nesting Passed Appropriate nesting

Back to Top

File details come from the government source that posted it. Updated .