80GSFC24R0042 FRFP Amendment 4 Final Signed.pdf

PDF 763 KB Posted

Attached to
Program and Analysis Control (PAAC VI) Support Services - Final Request for Propopsal (RFP) Federal contract opportunity
Solicitation number
80GSFC24R0042
Issued by
National Aeronautics and Space Administration Goddard Space Center

About this file

This document is Amendment 4 to NASA Goddard Space Flight Center's Request for Proposals (RFP) 80GSFC24R0042. The amendment makes several key changes: (1) the proposal due date is extended indefinitely due to a government shutdown, with a new amendment to be issued once the shutdown ends; (2) modifications to Cost Volume Instructions now require offerors to identify contract types for significant and non-significant subcontractors; and (3) revisions to Mission Suitability Proposal Instructions clarify requirements for Total Compensation Plans, particularly for significant subcontractors that meet or exceed 20% of the total estimated contract value.

The amendment also updates evaluation criteria for Total Compensation Plans, noting that the government will evaluate these plans in accordance with FAR 52.222-46 and that the evaluation may impact the offeror's Mission Suitability score. Offerors are required to provide detailed compensation information, including direct labor rates, fringe benefits, and supporting data from compensation surveys. The changes aim to provide more transparency and enable a comprehensive assessment of proposed labor costs and compensation strategies for this NASA contract opportunity.

View the file

Other files for this federal contract opportunity

Other files attached to Program and Analysis Control (PAAC VI) Support Services - Final Request for Propopsal (RFP), newest first.
File Type Posted
80GSFC24R0042 FRFP Amendment 5 Final Signed.pdf PDF
Questions and Answers No 2 for FRFP PAAC VI - 10-1-25.pdf PDF
Enclosure 1 - GPM Rev 1 - FRFP.pdf PDF
80GSFC24R0042 FRFP Amendment 3 Final Signed.pdf PDF
Final RFP GPM Exhibits 2-10 All IDIQ by CY Rev 1 - FRFP.xlsx XLSX spreadsheet
Enclosure 2 - Contract Historical Data Rev 1 - FRFP.pdf PDF
80GSFC24R0042 FRFP Amendment 1 - 9-18-25 Final signed.pdf PDF
80GSFC24R0042 FRFP Amendment 2 Final Signed.pdf PDF
80GSFC24R0042 FRFP Amendment 1 - 9-18-25 Final signed.pdf PDF
Attachment A - Statement of Work - Amend 1.pdf PDF
Final RFP Attachment D - IAGP.pdf PDF
Final RFP Attachment E - GFP.pdf PDF
Final RFP Attachment H.2 - OCI Avoidance Plan.pdf PDF
Final RFP Attachment N - Limitations on Subcontracting Report DRD.pdf PDF
Final RFP Enclosure 2 - Contract Historical Data.pdf PDF
Final RFP Attachment G - Contract Historical Data.pdf PDF
Final RFP 80GSFC24R0042 SF33.pdf PDF
Final RFP Attachment B - IDIQ Cost-Type Rate Matrix--All IDI.pdf PDF
Final RFP Attachment J - Contract Data Requirements List (CD.pdf PDF
Final RFP Exhibits 1A-1B GPM IDIQ.xlsx XLSX spreadsheet
Final RFP GPM Exhibits 2-10 All IDIQ by CY.xlsx XLSX spreadsheet
Final RFP Exhibit 11A Total Compensation Rate Build-up Form.xlsx XLSX spreadsheet
Final RFP Attachment A - Statement of Work.pdf PDF
Final RFP Attachment F - Safety and Health Plan.pdf PDF
Final RFP Attachment I -Req Statements List.pdf PDF
Final RFP Attachment K - DD254.pdf PDF
Final RFP Enclosure 1 - GPM.pdf PDF
Final RFP Enclosure 3 - QASP.pdf PDF
Final RFP Exhibit 12 - Past Performance Questionnaire.pdf PDF
Questions and Answers for PAAC VI DRFP Final.pdf PDF
Industry Day Charts Final 3-24-25.pdf PDF
Enclosure 1 - GPM 3-14-25.pdf PDF
80GSFC24R0042 Amendment 1 Final 3-17-25 Signed.pdf PDF
DRFP 80GSFC24R0042 Terms and Conditions Final.pdf PDF
Attachment 1.pdf PDF
Industry Day Notice PAAC VI Virtual Final.pdf PDF
DRFP 80GSFC24R0042 Cover Letter Final.pdf PDF
Attachment C - 533 Attach All IDIQ--Both Onsite and Offsite.pdf PDF
Attachment F - Safety and Health Plan.pdf PDF
Attachment I -Req Statements List.pdf PDF
Enclosure 3 - QASP.pdf PDF
DRFP 80GSFC24R0042 SF33.pdf PDF
DRFP 80GSFC24R0042 Terms and Conditions.pdf PDF
Attachment J - DRDs.pdf PDF
Attachment K - DD254.pdf PDF
Enclosure 4 - Sample Safety and Health Plan.pdf PDF
Attachment A - Statement of Work.pdf PDF
Attachment H - OCI Avoidance Plan.pdf PDF
Exhibit 11A Total Compensation Rate Build-up Form.xlsx XLSX spreadsheet
e-Lirbary on Sam.gov.zip ZIP file
Show all 50

Program and Analysis Control (PAAC VI) Support Services - Final Request for Propopsal (RFP) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to he hour and date specified in the solicitation or as amended, by one of the following me hods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of he document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible )

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

Sherry Barbour, Contracting Officer

The purpose of this amendment is to make changes to RFP 80GSFC24R0042 accordingly.

See page 2 through 5.

NASA/Goddard Space Flight Center 8800 Greenbelt Road Greenbelt, MD 20771

To All Offerors

80GSFC24R0042

1 5

See Block 16C

09/02/2025

10/01/2025

Final RFP 80GSFC24R0042 Amendment 4

1. The proposal due date is extended indefinitely based on the Government shutdown and the uncertain schedule duration of the shutdown. When the shutdown ends, a new amendment will be issued and the due date for proposals will be established.

2. The following paragraphs of clause GSFC 52.215-223 COST VOLUME INSTRUCTIONS (JAN 2025), is revised as indicated by the red font:

FROM:

A "subcontract" is any contract, purchase order, material order, interorganizational transfer, etc. that is a direct cost to this acquisition. The Offeror shall provide sufficient detail to support and explain all costs proposed. For proposal purposes, Significant Subcontractor is defined as Subcontractor or Inter-/Intra-Work Transfer Authorizations (IWTA) having a contract value that equals or exceeds 20% of the Total Estimated Contract Value (Basic and all Options combined). For the purposes of the Cost Volume, a Significant Subcontractor is defined as any subcontractor whose estimated value causes the cumulative percentage of subcontractor work (from lowest to highest percentage of work) to meet or exceed 20% of the total GPM estimated value (basic and all options combined, if applicable). All values are inclusive of fee, but exclusive of any Phase-in.

TO:

A "subcontract" is any contract, purchase order, material order, interorganizational transfer, etc. that is a direct cost to this acquisition. The Offeror shall provide sufficient detail to support and explain all costs proposed. The Offeror shall identify the contract type (ex. FFP, T&M, CPFF etc.) for all Significant and Non-Significant subcontractors.

For the purposes of the Cost Volume, a Significant Subcontractor is defined as any subcontractor whose estimated value causes the cumulative percentage of subcontractor work (from lowest to highest percentage of work) to meet or exceed 20% of the total GPM estimated value (basic and all options combined, if applicable). All values are inclusive of fee, but exclusive of any Phase-in.

3. The following paragraph of clause GSFC 52.215-210 MISSION SUITABILITY PROPOSAL INSTRUCTIONS (COMPETITIVE)(MAY 2022), is being revised as follows:

FROM:

A.7 Total Compensation Plan

The offeror shall submit a total compensation plan (TCP) in accordance with FAR 52.222-46, Evaluation of Compensation for Professional Employees (see FAR 22.1102, 29 CFR 541.702, and Enclosure 1, GPM August 2025. This requirement also applies to each proposed subcontractor determined to be significant/major, in accordance with the definition for a significant/major subcontractor established in the Price or Cost Volume instructions, and which provide at least 20% of the total estimated professional direct labor hours or work year equivalents (WYEs).

The proposed TCP information shall be included in the offeror’s Price or Cost Volume and the subcontractor’s Price or Cost volume, if applicable. Offerors and subcontractors shall ensure the information provided in the TCP is consistent with the data provided in the respective Price or Cost Volume (i.e., Government Pricing Model [GPM]). Offerors shall also ensure the proposed TCP(s) is consistent with other information contained elsewhere in the offeror’s proposal.

The Government will evaluate the offeror’s proposed total compensation plan (TCP) information in accordance with FAR 52.222-46, Evaluation of Compensation for Professional Employees. The Government will consider the realism of the offeror’s total compensation approach and supporting documentation and may also utilize incumbent direct labor rates (when applicable), market data for direct labor rates, and market data for fringe benefit costs, when evaluating the realism of the total compensation proposed.

The Government will also evaluate the TCP for consistency with other information contained elsewhere in the offeror’s proposal.

When the Government does not have insight into the incumbent compensation information for professional labor categories, a comparison to incumbent rates cannot be performed in accordance with the requirements of FAR 52.222-46, Evaluation of Compensation for Professional Employees. In such case, the Government will compare proposed compensation to market data to meet the evaluation requirements of FAR 52.222-46.

Identify the categories of personnel that are in a bona fide executive, administrative or professional capacity as defined by FAR 22.1102 and 29 CFR 541.

Exhibit 11A, Total Compensation Rate Build-up Form, quantifies the firm’s personnel policies, labor rates, and fringe benefits by location (if different), by year. In preparing the total hourly compensation rates (i.e., direct labor rates plus fringe benefit rates) included in this exhibit, input the data used (i.e., paid leave, supplemental pay, insurance, retirement and savings, legally required benefits, and other), considering the traceability of the values to the fringe pool, to calculate the total hourly compensation rate values, including the employer share, by dollar value, of any fringe benefit elements.

Provide supporting data, such as recognized national, regional, and local compensation surveys and studies of professional, public and private organizations, used in establishing the total professional compensation structure.

Offerors and subcontractors proposing to utilize the incumbent workforce should review the incumbent average unburdened hourly direct labor rates provided below for those labor categories for which rates are provided, in order to better understand the current salary levels of the incumbent workforce. This is provided for informational purposes and the labor categories and rates provided in Enclosure 2 – Historical Data may not be identical representations or reflections of labor categories proposed by the offeror under this solicitation nor represent all labor categories utilized for this acquisition. The average direct labor rates, as provided by the Government, are based on data provided by the incumbent contractor as of May 2025 for its workforce (includes subcontractors) and reflects the incumbent’s mapping of its labor classifications to the respective Government standard labor classifications.

TO:

A.7 Total Compensation Plan

The offeror shall submit a total compensation plan (TCP) in accordance with FAR 52.222-46, Evaluation of Compensation for Professional Employees (see FAR 22.1102, 29 CFR 541.702, and Enclosure 1, GPM August 2025. This requirement also applies to each proposed subcontractor determined to be significant/major, in accordance with the definition for a significant/major subcontractor established in the Price or Cost Volume instructions, and meet or exceed 20% of the total GPM estimated value (basic and all options combined)

Exhibit 11A, Total Compensation Rate Build-up Form, quantifies the firm’s personnel policies, labor rates, and fringe benefits by location (if different), by year. In preparing the total hourly compensation rates (i.e., direct labor rates plus fringe benefit rates) included in this exhibit, input the data used (i.e., paid leave, supplemental pay, insurance, retirement and savings, legally required benefits, and other), considering the traceability of the values to the fringe pool, to calculate the total hourly compensation rate values, including the employer share, by dollar value, of any fringe benefit elements.

Provide supporting data, such as recognized national, regional, and local compensation surveys and studies of professional, public and private organizations, used in establishing the total professional compensation structure.

4. The following paragraph of clause GSFC 52.215-311 MISSION SUITABILITY EVALUATION FACTOR. (MAY 2022), is revised as follows:

FROM:

A.7 In accordance with FAR 52.222-46, Evaluation of Compensation for Professional Employees, the Government will evaluate the realism of the offeror’s total compensation plan. The Total Compensation Plan (TCP) required by NFS 1852.231-71 will be evaluated for adequacy, reasonableness and effectiveness for obtaining and maintaining qualified personnel to meet contract requirements. The evaluation criteria described in FAR 52.222-46 for professional employees and the requirements of NFS 1852.231-71 will be applied to all labor categories (including those personnel subject to union agreements, the Service Contract Act, and those exempt from both) in evaluating the total compensation proposed. Professional compensation that is unrealistically low or not in reasonable relationship to the various job categories, may adversely impact the offeror’s Mission Suitability evaluation or may result in rejection of the proposal.”

TO:

A.7 The Government will evaluate the offeror’s total compensation plan (TCP) in accordance with FAR 52.222-46, Evaluation of Compensation for Professional Employees. The evaluation of the Total Compensation Plan may impact the offeror’s Mission Suitability score.

(End of Amendment 4)

2025-10-01T11:35:51-0400
SHERRY BARBOUR

File details come from the government source that posted it. Updated .