80GSFC24R0042 FRFP Amendment 2 Final Signed.pdf
PDF 756 KB Posted
- Attached to
- Program and Analysis Control (PAAC VI) Support Services - Final Request for Propopsal (RFP) Federal contract opportunity
- Solicitation number
- 80GSFC24R0042
About this file
This document is an Amendment (Amendment 2) to Request for Proposals (RFP) 80GSFC24R0042 issued by NASA/Goddard Space Flight Center, modifying two key clauses related to past performance evaluation. The amendment introduces new provisions for small business subcontractors, specifically allowing offerors to provide one additional referenced contract for each first-tier small business subcontractor not initially included in the reference limitation. The changes clarify that for past performance evaluation purposes, the term "Offeror" encompasses both prime contractors and significant subcontractors, with the prime contractor's performance weighted more heavily.
The amendment also specifies that for Small Business prime offerors, the evaluation will consider the capabilities, past performance, and experience of first-tier small business subcontractors only when the prime offeror cannot independently demonstrate the necessary capabilities, performance, or experience for award. The RFP amendment is dated 09/02/2025, with the solicitation dated 09/19/2025, and applies to a federal contract opportunity at NASA's Goddard Space Flight Center located in Greenbelt, Maryland.
View the file
Other files for this federal contract opportunity
Show all 50
Program and Analysis Control (PAAC VI) Support Services - Final Request for Propopsal (RFP) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to he hour and date specified in the solicitation or as amended, by one of the following me hods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of he document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible )
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
Sherry Barbour, Contracting Officer
The purpose of this amendment is to make changes to RFP 80GSFC24R0042 accordingly.
See page 2 through 3.
NASA/Goddard Space Flight Center 8800 Greenbelt Road Greenbelt, MD 20771
To All Offerors
80GSFC24R0042
1 3
See Block 16C
09/02/2025
09/19/2025
Final RFP 80GSFC24R0042 Amendment 2
1. The following paragraphs of clause GSFC 52.215-230 PAST PERFORMANCE VOLUME (FEB 2025), is revised as indicated by the red font:
FROM:
• List any contracts terminated (partial or complete) within the past 5 years and basis for termination (convenience or default). Include the contract number, name, address, and telephone number of the terminating officer (please verify telephone numbers).
Include contracts that were "descoped" by the customer because of performance or cost problems. (Excluded from the page limitation).
TO:
• List any contracts terminated (partial or complete) within the past 5 years and basis for termination (convenience or default). Include the contract number, name, address, and telephone number of the terminating officer (please verify telephone numbers).
Include contracts that were "descoped" by the customer because of performance or cost problems. (Excluded from the page limitation).
In consideration of 13 C.F.R. §125.2(g), the offeror may provide for consideration, within the established page limitation, one additional referenced contract for each first-tier small business subcontractor not included in the reference limitation established for this volume.
While the reference limitation is considered adequate for the offeror to demonstrate its relevant performance for this evaluation, it is within the offeror’s discretion how these references are allocated across the proposed team. However, should the assessment of additional small business first-tier subcontractors be necessary, provide for each additional reference only, subcontractor name and CAGE code, contract number, contract value, period of performance, and current customer point of contact information (e.g., contracting officer name, email).
2. The following paragraphs of clause GSFC 52.215-330 PAST PERFORMANCE EVALUATION FACTOR (SERVICES). (FEB 2025), is revised as indicated by the red font:
FROM:
For purposes of past performance, the term “Offeror” refers to a prime contractor and its significant subcontractors. Accordingly, the past performance of significant(s) subcontractors shall also be evaluated and attributed to the Offeror. The past performance of a significant subcontractor will be compared to the work proposed to be performed by that subcontractor, and weighted accordingly in assigning the overall past performance adjectival rating to the Offeror. The past performance of the prime contractor will be weighted more heavily than any significant subcontractor or combination of significant subcontractors in the overall past performance evaluation.
Final RFP 80GSFC24R0042 Amendment 2
TO:
For purposes of past performance, the term “Offeror” refers to a prime contractor and its significant subcontractors. Accordingly, the past performance of significant(s) subcontractors shall also be evaluated and attributed to the Offeror. The past performance of a significant subcontractor will be compared to the work proposed to be performed by that subcontractor, and weighted accordingly in assigning the overall past performance adjectival rating to the Offeror. The past performance of the prime contractor will be weighted more heavily than any significant subcontractor or combination of significant subcontractors in the overall past performance evaluation.
The evaluation will consider the capabilities, past performance and experience for each first-tier small business subcontractor in the proposal that is part of the proposed team in accordance with 13 CFR 125.2(g) only when the Small Business prime offeror does not independently demonstrate capabilities, past performance and/or experience necessary for award.
(End of Amendment 2)