Final RFP Attachment C - 533 Attach All IDIQ--Both Onsite an.pdf

PDF 109 KB Posted

Attached to
Program and Analysis Control (PAAC VI) Support Services - Final Request for Propopsal (RFP) Federal contract opportunity
Solicitation number
80GSFC24R0042
Issued by
National Aeronautics and Space Administration Goddard Space Center

About this file

This document is a Financial Management Reporting Requirements attachment for a NASA Request for Proposal (RFP 80GSFC24R0042) dated June 2014. The attachment details the financial reporting obligations for the contractor, specifying that NASA 533 series reports must be submitted following NASA Procedural Requirements NPR 9501.2E. Contractors are required to provide individual and cumulative reports for each Task Order, breaking down costs by specific categories including prime and subcontractor direct labor hours (onsite and offsite), direct labor costs, overhead expenses, other direct costs (ODCs), and total estimated costs.

The reporting requirements mandate detailed financial documentation, including a variance narrative for any cost or labor hour fluctuations exceeding 10%, explaining reasons, impacts, and corrective actions. Reporting timelines are strict: the initial report is due within 30 working days after contract award, monthly reports by the 10th working day after the accounting period closes, and quarterly reports by the 15th day preceding the reported quarter. The reports must comprehensively track expenses across multiple cost elements, from direct labor and overhead to General and Administrative (G&A) expenses, and include a fixed fee calculation, ultimately presenting a total Cost-Plus-Fixed-Fee (CPFF) amount.

View the file

Other files for this federal contract opportunity

Other files attached to Program and Analysis Control (PAAC VI) Support Services - Final Request for Propopsal (RFP), newest first.
File Type Posted
80GSFC24R0042 FRFP Amendment 5 Final Signed.pdf PDF
80GSFC24R0042 FRFP Amendment 4 Final Signed.pdf PDF
Questions and Answers No 2 for FRFP PAAC VI - 10-1-25.pdf PDF
Enclosure 1 - GPM Rev 1 - FRFP.pdf PDF
80GSFC24R0042 FRFP Amendment 3 Final Signed.pdf PDF
Final RFP GPM Exhibits 2-10 All IDIQ by CY Rev 1 - FRFP.xlsx XLSX spreadsheet
80GSFC24R0042 FRFP Amendment 1 - 9-18-25 Final signed.pdf PDF
80GSFC24R0042 FRFP Amendment 2 Final Signed.pdf PDF
80GSFC24R0042 FRFP Amendment 1 - 9-18-25 Final signed.pdf PDF
Attachment A - Statement of Work - Amend 1.pdf PDF
Final RFP Attachment D - IAGP.pdf PDF
Final RFP Attachment E - GFP.pdf PDF
Final RFP Attachment H.2 - OCI Avoidance Plan.pdf PDF
Final RFP Attachment N - Limitations on Subcontracting Report DRD.pdf PDF
Final RFP Enclosure 2 - Contract Historical Data.pdf PDF
Final RFP Attachment G - Contract Historical Data.pdf PDF
Final RFP 80GSFC24R0042 SF33.pdf PDF
Final RFP Attachment B - IDIQ Cost-Type Rate Matrix--All IDI.pdf PDF
Final RFP Attachment J - Contract Data Requirements List (CD.pdf PDF
Final RFP Exhibits 1A-1B GPM IDIQ.xlsx XLSX spreadsheet
Final RFP GPM Exhibits 2-10 All IDIQ by CY.xlsx XLSX spreadsheet
Final RFP Exhibit 11A Total Compensation Rate Build-up Form.xlsx XLSX spreadsheet
Final RFP Attachment A - Statement of Work.pdf PDF
Final RFP Attachment F - Safety and Health Plan.pdf PDF
Final RFP Attachment I -Req Statements List.pdf PDF
Final RFP Attachment K - DD254.pdf PDF
Final RFP Enclosure 1 - GPM.pdf PDF
Final RFP Enclosure 3 - QASP.pdf PDF
Final RFP Exhibit 12 - Past Performance Questionnaire.pdf PDF
Questions and Answers for PAAC VI DRFP Final.pdf PDF
Industry Day Charts Final 3-24-25.pdf PDF
Enclosure 1 - GPM 3-14-25.pdf PDF
80GSFC24R0042 Amendment 1 Final 3-17-25 Signed.pdf PDF
DRFP 80GSFC24R0042 Terms and Conditions Final.pdf PDF
Attachment 1.pdf PDF
Industry Day Notice PAAC VI Virtual Final.pdf PDF
DRFP 80GSFC24R0042 Cover Letter Final.pdf PDF
Attachment C - 533 Attach All IDIQ--Both Onsite and Offsite.pdf PDF
Attachment F - Safety and Health Plan.pdf PDF
Attachment I -Req Statements List.pdf PDF
Enclosure 3 - QASP.pdf PDF
DRFP 80GSFC24R0042 SF33.pdf PDF
DRFP 80GSFC24R0042 Terms and Conditions.pdf PDF
Attachment J - DRDs.pdf PDF
Attachment K - DD254.pdf PDF
Enclosure 4 - Sample Safety and Health Plan.pdf PDF
Attachment A - Statement of Work.pdf PDF
Attachment H - OCI Avoidance Plan.pdf PDF
Exhibit 11A Total Compensation Rate Build-up Form.xlsx XLSX spreadsheet
e-Lirbary on Sam.gov.zip ZIP file
Show all 50

Program and Analysis Control (PAAC VI) Support Services - Final Request for Propopsal (RFP) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT C

FINANCIAL MANAGEMENT REPORTING

REQUIREMENTS

JUNE 2014

RFP 80GSFC24R0042

CONTRACT TBD

Contract TBD Attachment C

(06/2014) 2

FINANCIAL MANAGEMENT REPORTING REQUIREMENTS

Financial Management Reports shall be submitted by the Contractor on the NASA 533 series reports, in accordance with the instructions on the reverse of the forms, NASA Procedural Requirements NPR 9501.2E entitled "NASA Contractor Financial Management Reporting,” dated May 27, 2011, and additional instructions issued by the Contracting Officer.

a. Level of Detail

An individual 533 Report shall be provided for each Task Order in addition to a cumulative 533 Report summarizing all Task Orders issued. The reports shall contain a breakdown of hours and costs by the elements of cost categories listed in Section d below.

b. Variance Narrative Reporting

In accordance with Section 3.6 of NPR 9501.2, the Contractor shall include a narrative explanation for variances exceeding plus or minus 10 percent (+/- 10%) between the Total Direct Labor Hours (prime and subcontractors) and/or Total Estimated Cost amount shown in the prior month and the Actual Total Direct Labor Hours and/or Actual Total Cost amount shown in the current month for each individual task order. (For example, the Total Estimated Cost amount shown for June in column 8a in the May NF 533M and the Actual June Total Cost amount shown in column 7a in the June NF 533M.)

Each variance narrative shall explain the: (1) reason for the variance, (2) impact(s) on the individual task order, and (3) specific corrective action(s) being taken or to be taken.

c. Distribution

The Contractor shall distribute 533 reports to each addressee indicated in the contract clause entitled, "Financial Management Reporting." The Contractor shall submit an initial report in the NF 533Q format within 30 working days after contract award.

After the initial report, the NF 533M reports shall be distributed not later than the tenth (10th) working day following the close of the contractors' monthly accounting period.

The 533Q reports shall be distributed not later than the fifteenth (15th) day of the month preceding the quarter being reported. The NF 533M need not be submitted in months in which an NF 533Q is submitted.

d. Reporting Requirements

Each individual report shall, at a minimum, provide cost data by the following elements of cost categories:

1. Prime Direct Labor Hours:

Attachment C

(06/2014) 3

Prime Direct Labor Hours - Onsite (List applicable labor categories)

Prime Direct Labor Hours – Offsite

Total Prime Direct Labor Hours

2. Subcontractor Direct Labor Hours:

Subcontractor A Direct Labor Hours – Onsite

Subcontractor A Direct Labor Hours – Offsite (List applicable labor categories)

Subcontractor B Direct Labor Hours – Onsite (List applicable labor categories) Subcontractor B Direct Labor Hours – Offsite (List applicable labor categories)

Subcontractor C Direct Labor Hours – Onsite (List applicable labor categories) Subcontractor C Direct Labor Hours – Offsite

Total Subcontractors Direct Labor Hours

3. Total Prime and Subcontractors Direct Labor Hours:

Total Prime and Subcontractors Hours – Onsite Total Prime and Subcontractors Hours – Offsite

Total Prime and Subcontractors Direct Labor Hours

4. Prime Direct Labor Costs:

Prime Direct Labor Costs - Onsite

Prime Direct Labor Costs – Offsite

Total Prime Direct Labor Costs

5. Prime Overhead Expenses:

Attachment C

(06/2014) 4

Onsite Overhead

Offsite Overhead

Total Prime Overhead

6. Other Direct Costs (ODCs):

a. Subcontracts (list separately, Subcontractor A, B, C, etc.)

b. Material

c. Travel

d. Other (specify)

Total ODCs

7. Subtotal (Direct Labor, Overhead & ODCs)

8. G&A Expense

9. Total Estimated Cost

10. Fixed Fee

11. Total Cost-Plus-Fixed-Fee (CPFF)