66-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf

PDF 120 KB Posted

Attached to
Bristol Township 2026 Road Paving, Inlet Replacement, and Curb Ramp Program
Solicitation number
Not on record
Issued by
Bucks County, Pennsylvania

About this file

This is a technical specification document for restoration of paved surfaces prepared for Bristol Township's 2026 Road Paving, Inlet Replacement, and Curb Ramp Program in Pennsylvania. The specification section covers nine categories of work: temporary paving, permanent paving, asphalt overlay, shoulder restoration, walkway restoration, driveways, concrete curb and gutter repairs, stormwater inlets and piping, and street signage. All work must comply with Pennsylvania Department of Transportation Publication 408 Specifications and related PennDOT standards. The contractor must submit certifications and approvals for all bituminous concrete mixes, concrete design mixes, and aggregate materials prior to work commencement. Temporary paving must be placed within ten working days of trench backfilling and maintained for a minimum of ninety days on state roads. Permanent paving includes base course, leveling course, and wearing course placement using PennDOT Superpave materials with compaction requirements of 10-ton rollers where possible and minimum 5-ton rollers in trenches.

The specification requires contractors to implement traffic control measures per Section 01 55 26 and obtain necessary permits from PennDOT and local municipal agencies. Concrete work must utilize Class AA concrete conforming to Section 704 of PennDOT Publication 408. Walkway restoration specifies 4-inch concrete thickness on 6-inch aggregate base, while driveway restoration for concrete requires 6-inch reinforced concrete on 4-inch aggregate base and asphalt driveways require minimum 2-inch wearing course over 6-inch aggregate base. Curb and gutter repairs must extend to the first expansion joint on either side of damaged areas with new expansion joint material installed. All damaged pavement markings and signage must be restored to their original locations. The contractor bears responsibility for restoring any existing paving outside work limits that is damaged during operations and must maintain all permanent paving throughout the contract maintenance period to the satisfaction of the Resident Project Representative and applicable road departments.

View the file

Other files

File Type Posted
24-Doc 00 52 00 - AGREEMENT.pdf PDF
56-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
72-Sec 33 41 00 - STORM DRAIN PIPE.pdf PDF
17-Doc 00 21 13.1 - ELECTRONIC BIDDING INSTRUCTIONS.pdf PDF
70-Sec 32 05 19.13 - GEOTEXTILE.pdf PDF
60-Sec 31 11 00 - CLEARING AND GRUBBING.pdf PDF
71-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
58-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
14-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
7-010 Curb Ramp Construction Notes and Details.pdf PDF
36-Doc 00 73 00 - 01 - APPENDIX A COVER.pdf PDF
1-05 2026 Inlet Program Map - Dixon Ave.pdf PDF
57-Sec 03 20 00 - CONCRETE REINFORCEMENT.pdf PDF
47-Sec 01 22 00 - 03 - EXHIBITS E-F.pdf PDF
40-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
59-Sec 31 20 00 - EARTHWORK.pdf PDF
49-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
29-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
35-Doc 00 73 00 - 03 - APPENDIX C COVER.pdf PDF
8-08 BT Curb Ramp Program Plumbridge.pdf PDF
15-Doc 00 11 13 ADVERTISEMENT FOR BIDS-FULL PROGRAM.pdf PDF
12-Doc 00 91 13 - ADDENDA.pdf PDF
6-02 2026 Road Program Striping Details.pdf PDF
74-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
45-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
67-Sec 33 44 14 - STORM INLETS CATCH BASINS ENDWALLS END SECTIONS.pdf PDF
69-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
18-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
3-04 2026 Inlet Program Map - Red Cedar Section.pdf PDF
52-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
63-Sec 02 41 16 - DEMOLITION.pdf PDF
5-06 Inlet Layout Sketches.pdf PDF
39-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
62-Sec 31 23 00 - EXCAVATION BACKFILL AND COMPACTION FOR ROADWAYS.pdf PDF
11-Doc 00 01 10 -TABLE OF CONTENTS.pdf PDF
75-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
26-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
37-Doc 00 73 00 - 00 - SUPPLEMENTARY CONDITIONS.pdf PDF
50-Sec 01 22 00 - 02 - EXHIBITS C-D.pdf PDF
48-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
30-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
76-Sec 32 92 00 - FINISH GRADING SEEDING AND SODDING.pdf PDF
10-09 BT Curb Ramp Program Red Cedar.pdf PDF
2-07 Stormwater Details.pdf PDF
25-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
38-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
13-Doc 00 01 15 - LIST OF DRAWINGS.pdf PDF
19-Doc 00 45 13.1 - CONTRACTOR RESPONSIBILITY CERTIFICATION.pdf PDF
23-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
16-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
Show 40 more

Latest 50 of 75 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RESTORATION OF PAVED SURFACES

32 12 23-1

SECTION 32 12 23

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Temporary Paving

2. Permanent Paving

3. Asphalt Overlay

4. Shoulder Restoration

5. Walkway Restoration

6. Driveways

7. Concrete Curb and Gutter Repairs

8. Stormwater Inlets and Piping

9. Street Signage

B. The Details on the Drawings note the specific paving requirements.

1.02 RELATED SECTIONS

A. Related Work specified elsewhere:

1. Section 01 55 26: Traffic Regulation

1.03 QUALITY ASSURANCE

A. Referenced Standards:

1. Pennsylvania Department of Transportation:

a. Publication 408 Specifications

b. Publication 27 - Specification for Bituminous Mixtures (Bulletin 27)

c. Publication 37 - Specification for Bituminous Materials (Bulletin 25)

d. Publication 213 – Temporary Traffic Control Guidelines

1.04 SUBMITTALS

A. Certificates:

1. Submit certification from bituminous and aggregate suppliers attesting that materials conform to the State Specifications in accordance with Section 01 33 00.

2. Submit a PennDOT approved Job Mix Formula for each bituminous concrete mix required.

3. Submit a PennDOT approved Mix Design for each concrete class and use required.

1.05 JOB CONDITIONS

A. Control of Traffic:

1. Take measures to control traffic during repaving operations. Do not allow traffic on repaved areas until authorized by the Resident Project Representative.

2. Employ traffic control measures in accordance with the requirements of Section 01 55 26 including pertinent permits by PennDOT and/or local municipal agencies having jurisdiction.

B. Restore existing paving outside the limits of the Work that is damaged by Contractor's operations, to its original condition at the expense of Contractor.

32 12 23-2

PART 2 - PRODUCTS

2.01 CONCRETE

A. Class AA concrete conforming to Section 704, PennDOT Publication 408 Specifications.

1. Requirements for State approved batch plants, design computations and plant inspection shall apply. The acceptability of concrete will be based on conformance with the Cement Concrete Criteria specified in Section 704 of PennDOT Publication 408 for the required Class of concrete and the results of the specified tests.

2. Concrete design mix shall be submitted to Engineer for approval prior to work commencement. No concrete shall be placed until Engineer has approved the design mix.

2.02 BITUMINOUS PAVING MATERIALS AND AGGREGATES

A. Base Course: PennDOT Superpave (Section 313 of Publication 408).

B. Binder Course: PennDOT Superpave (Section 410 of Publication 408).

C. Leveling Course: PennDOT Superpave (Section 410 of Publication 408).

D. Wearing Course: PennDOT Superpave (Section 410 of Publication 408).

E. Tack Coat: Per Section 460 of PennDOT Publication 408, except revise the first sentence to read:

Emulsified Asphalt, Class E-8 (AASHTO CSS-1h or SS-1h)

F. Joint Seal: Asphalt PG 64-22 Sealant (Publication 408).

G. Coarse Aggregate: PennDOT No. 2A (Section 703 of Publication 408).

H. The acceptability of the material will be based on conformance with the Criteria specified in PennDOT Publication 408 for the required material.

I. Cut sheets/submittals for all paving materials and aggregates shall be submitted to Engineer for approval prior to work commencement. No paving materials and/or aggregates shall be placed until Engineer has approved the material.

PART 3 - EXECUTION

3.01 TEMPORARY PAVING

A. Provide temporary paving immediately upon completion of trench backfilling. Unpaved trenches shall not remain unpaved longer than ten (10) working days after backfilling.

B. Complete trench backfill with coarse aggregate in accordance with the Drawings and Publication 408 requirements.

C. Trim existing paving with minimum one (1) foot cutbacks to remove damaged areas. Cut straight joint lines and right angle offsets.

D. Place temporary paving material consisting of bituminous concrete base course to the required depth shown on the Drawings for the entire width of the trench. Place with a maximum lift thickness of three

(3) inches and compact each lift individually using a trench roller (minimum 5 ton).

E. Continuously maintain temporary paving to the satisfaction of the Resident Project Representative and the State and local municipal road departments having jurisdiction. Temporary paving on State roads must remain in place for a minimum of ninety (90) days.

3.02 PERMANENT PAVING

A. Place bituminous concrete base course on surface of compacted subbase course to compacted thickness (10 ton roller where possible; minimum 5 ton roller in trenches) as shown on Drawings.

B. Place base and wearing courses to compacted thicknesses (10 ton roller) as shown on the Drawings.

Apply tack coat, per Section 32 12 00, on completed base course before placing wearing course should there be a delay between completion of base course and placement of wearing course.

32 12 23-3

C. Place wearing course overlay to compacted thickness (10 ton roller) as and where shown on the Drawings.

D. Compact pavement by rolling to achieve even and smooth finish, without roller marks. Hand compact in areas inaccessible to rolling equipment.

E. Where proposed asphalt paving adjoins existing asphalt paving, seal the joint with Asphalt PG 64-22 Sealant in accordance with Publication 408 Specifications.

F. Replace pavement markings in their former location which were covered or destroyed.

G. Maintain permanent paving to the satisfaction of the Resident Project Representative and the local municipal and State road departments having jurisdiction throughout the Contract maintenance period.

3.03 ASPHALT OVERLAY

A. Where indicated on the Drawings, or directed by the Resident Project Representative, place an asphalt overlay.

B. Construct in accordance with Publication 408 Specifications and Drawings.

C. Replace pavement markings in their former location which were covered or destroyed.

3.04 SHOULDER RESTORATION

A. Restore shoulders in accordance with the Drawings.

3.05 WALKWAY RESTORATION

A. Reconstruct portland cement sidewalks to 4" thickness of concrete placed on a 6" layer of 2A aggregate.

B. Reconstruct portland cement sidewalks to the first joint on either side of the damaged portion. Install expansion joint material.

3.06 DRIVEWAYS

A. Trim concrete and bituminous driveway surfaces to remove damaged areas. Saw cut straight joint lines parallel to the centerline of the trench. Cut offsets at right angles to the trench centerline.

B. Restore existing portland cement concrete driveways with a 6" layer of concrete reinforced with 6 x 6 l0/l0 wire mesh on a 4” layer of AASHTO 57 aggregate.

C. Restore existing asphalt driveways in kind or with minimum 2" layer wearing course over 6" layer of 2A aggregate.

3.07 CONCRETE CURB AND GUTTER REPAIRS

A. Replace curbs and gutters damaged by construction to match existing.

B. Reconstruct curbs and gutters to the first expansion joint on either side of the damaged portion. Install expansion joint material.

3.08 STORMWATER INLETS AND PIPING

A. Repair or replace storm water inlets and piping damaged by construction to match existing inlets.

B. The Resident Project Representative will determine whether the frame and grate assembly of each affected storm water inlet is suitable for reuse once it has been removed by Contractor.

C. Construct or repair storm water inlets and piping in accordance with relevant section of Publication 408 Specifications.

3.09 STREET SIGNAGE

32 12 23-4

A. Reinstall any signage removed to allow for construction activities at the original location.

END OF SECTION