49-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf

PDF 108 KB Posted

Attached to
Bristol Township 2026 Road Paving, Inlet Replacement, and Curb Ramp Program
Solicitation number
Not on record
Issued by
Bucks County, Pennsylvania

About this file

Summary

This is a technical specification document outlining coordination and meeting requirements for the Bristol Township 2026 Road Paving, Inlet Replacement, and Curb Ramp Program in Pennsylvania. The specification establishes mandatory coordination protocols to ensure efficient and orderly sequencing of construction activities, including milling, base repair, leveling course, manhole rim adjustments, inlet replacement, and ADA/PennDOT compliant curb ramp installation across multiple roadways within Bristol Township. The document requires the contractor to conduct field engineering services, verify survey control points, and confirm drawing dimensions and elevations prior to construction commencement. A preconstruction meeting must be held after the effective date of the agreement and prior to work commencement, with required attendance from the owner, engineer, resident project representative, contractor, superintendent, and major subcontractors. The specification mandates progress meetings on an as-needed basis throughout the project duration and pre-installation meetings when required by individual specification sections, with all meeting minutes distributed within five working days to relevant parties.

The specification emphasizes contractor responsibility for coordination with concurrent construction contracts and other owner workmen, requiring the contractor to schedule work to avoid conflicts and conduct operations without interference to other contractors' work. The contractor must maintain access to private driveways and accommodate owner and resident access needs throughout construction. Weekly milling and paving schedule updates must be provided to the resident project representative. The contractor bears responsibility for any construction-related damage to private, leased, or owner-owned property on the site and must promptly repair any injuries or damages caused by its operations at its own expense. All work must be performed in accordance with PennDOT Publication 408 and Township Standards, with no claim for extra compensation permitted for delays or hindrances resulting from other contractors' or the owner's work unless specifically permitted elsewhere in the contract documents.

View the file

Other files

File Type Posted
24-Doc 00 52 00 - AGREEMENT.pdf PDF
56-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
72-Sec 33 41 00 - STORM DRAIN PIPE.pdf PDF
17-Doc 00 21 13.1 - ELECTRONIC BIDDING INSTRUCTIONS.pdf PDF
70-Sec 32 05 19.13 - GEOTEXTILE.pdf PDF
60-Sec 31 11 00 - CLEARING AND GRUBBING.pdf PDF
71-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
58-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
14-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
7-010 Curb Ramp Construction Notes and Details.pdf PDF
36-Doc 00 73 00 - 01 - APPENDIX A COVER.pdf PDF
1-05 2026 Inlet Program Map - Dixon Ave.pdf PDF
57-Sec 03 20 00 - CONCRETE REINFORCEMENT.pdf PDF
47-Sec 01 22 00 - 03 - EXHIBITS E-F.pdf PDF
40-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
59-Sec 31 20 00 - EARTHWORK.pdf PDF
29-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
35-Doc 00 73 00 - 03 - APPENDIX C COVER.pdf PDF
8-08 BT Curb Ramp Program Plumbridge.pdf PDF
15-Doc 00 11 13 ADVERTISEMENT FOR BIDS-FULL PROGRAM.pdf PDF
12-Doc 00 91 13 - ADDENDA.pdf PDF
6-02 2026 Road Program Striping Details.pdf PDF
74-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
45-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
67-Sec 33 44 14 - STORM INLETS CATCH BASINS ENDWALLS END SECTIONS.pdf PDF
69-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
18-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
3-04 2026 Inlet Program Map - Red Cedar Section.pdf PDF
52-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
63-Sec 02 41 16 - DEMOLITION.pdf PDF
5-06 Inlet Layout Sketches.pdf PDF
39-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
62-Sec 31 23 00 - EXCAVATION BACKFILL AND COMPACTION FOR ROADWAYS.pdf PDF
11-Doc 00 01 10 -TABLE OF CONTENTS.pdf PDF
75-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
26-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
37-Doc 00 73 00 - 00 - SUPPLEMENTARY CONDITIONS.pdf PDF
50-Sec 01 22 00 - 02 - EXHIBITS C-D.pdf PDF
48-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
30-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
76-Sec 32 92 00 - FINISH GRADING SEEDING AND SODDING.pdf PDF
10-09 BT Curb Ramp Program Red Cedar.pdf PDF
2-07 Stormwater Details.pdf PDF
25-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
38-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
13-Doc 00 01 15 - LIST OF DRAWINGS.pdf PDF
19-Doc 00 45 13.1 - CONTRACTOR RESPONSIBILITY CERTIFICATION.pdf PDF
23-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
16-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
64-Sec 31 23 33 - EXCAVATION BACKFILL AND COMPACTION.pdf PDF
Show 40 more

Latest 50 of 75 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COORDINATION AND MEETINGS

01 31 00-1

SECTION 01 31 00

COORDINATION AND MEETINGS

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. The Work of this Section Includes:

1. Coordination and Project conditions.

2. Field engineering.

3. Preconstruction meeting.

4. Progress meetings.

5. Pre-installation meetings.

6. Construction coordination requirements.

1.02 RELATED SECTIONS

A. Section not used.

1.03 COORDINATION AND PROJECT CONDITIONS

A. Coordinate scheduling, submittals, and Work of the various sections of the Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements, with provisions for accommodating items installed later.

B. Verify utility requirements and characteristics of operating equipment are compatible with building utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, such equipment.

C. Coordinate space requirements, supports, and installation of mechanical and electrical Work which are indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit, as closely as practicable; place runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.

D. In finished areas except as otherwise indicated, conceal pipes, ducts, and wiring within the construction. Coordinate locations of fixtures and outlets with finish elements.

E. Coordinate completion and clean-up of Work of separate sections in preparation for Substantial Completion and for portions of Work designated for Owner’s partial occupancy.

F. After Owner occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner’s activities.

1.04 FIELD ENGINEERING

A. Contractor shall locate survey control and reference points and provide stakeout as required for construction activities. Contractor is responsible for the protection of survey control and reference points and will compensate Owner for re-establishment of survey control and reference points.

B. Verify set-backs and easements; confirm drawing dimensions and elevations.

C. Provide field engineering services. Establish elevations, lines, and levels, utilizing recognized engineering survey practices.

D. Construct Work based on elevations, lines and locations as established, utilizing recognized survey control points and stakeout.

1.05 PRECONSTRUCTION MEETING

A. Engineer will schedule a meeting at the Project site after the Effective Date of the Agreement and prior to commencement of Work and Contractor occupancy, prepare an agenda with copies for participants, and preside at the meeting.

B. Attendance Required: Owner, Engineer, Resident Project Representative, Contractor, Contractor’s Superintendent and major Subcontractors.

C. Agenda:

01 31 00-2

1. Distribution of Contract Documents.

2. Submission of list of Subcontractors, list of Products, schedule of values, and progress schedule.

3. Designation of personnel representing the parties in Contract, and the Engineer.

4. Procedures and processing of field decisions, submittals, substitutions, applications for payments, Change Orders, and Contract closeout procedures.

5. Scheduling.

6. Use of premises by Owner and Contractor.

7. Owner's requirements and occupancy.

8. Construction facilities and controls provided by Owner.

9. Security and housekeeping procedures.

10. Procedures for testing.

11. Procedures for maintaining record documents.

12. Inspection and acceptance of work.

D. Engineer shall record minutes and distribute copies within five (5) working days after meeting to Owner and all other participants.

1.06 PROGRESS MEETINGS

A. Meetings shall be scheduled throughout progress of the Work on an as-needed basis.

B. Resident Project Representative will make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings.

C. Attendance Required: Contractor's superintendent, major Subcontractors and suppliers, Engineer as appropriate to agenda topics for each meeting.

D. Resident Project Representative shall record minutes and distribute copies within five (5) working days after meeting to Owner, Engineer and all other participants.

1.07 PRE-INSTALLATION MEETINGS

A. When required in individual specification sections, convene a pre-installation meeting at the site prior to commencing work of the section.

B. Require attendance of parties directly affecting, or affected by, work of the specific section.

C. Notify Resident Project Representative five (5) working days in advance of meeting date.

D. Prepare agenda and preside at meeting:

1. Review conditions of installation, preparation and installation procedures.

2. Review coordination with related work.

E. Record minutes and distribute copies within five (5) working days after meeting to Owner, Engineer and all other participants.

PART 2 – PRODUCTS

2.01 Not Used.

PART 3 – EXECUTION

3.01 CONSTRUCTION COORDINATION REQUIREMENTS

A. General

1. Construction work under this contract shall not interfere with the operations of the Owner and the general public. Contractor shall be responsible for any construction related damage to private/leased or Owner owned property on the site. Access to private driveways must be maintained at all times during the course of the Work and Contractor shall accommodate periodic needs of the Owner and residents for access to site.

2. Contractor shall provide the Resident Project Representative with weekly milling and paving schedule updates.

01 31 00-3

B. Coordination of Contractor’s, other contractor’s and Owner’s Workmen

1. Contractor is advised that construction of other contracts may be in progress at the same time that this Contract is under construction. Contractor shall schedule his work so as not to conflict or interfere with these other contracts.

2. Contractor shall conduct his operations so as not to interfere with or injure the work of other contractors or workmen performing work for Owner. Contractor shall promptly repair, at his own expense, any injury or damage which may be done to such work by him or his employees, agents, or subcontractors.

3. Contractor shall suspend such part of the Work, or shall carry on the same in such a manner as may be ordered by Engineer when necessary to facilitate the work of such other contractors and workmen of Owner.

4. Any difference which may arise between Contractor and any other contractors or workmen of Owner in regard to their Work shall be determined and adjusted by Owner insofar as Owner has authority.

5. Contractor shall not claim any extra compensation or damages as a result of delays or hindrances which may be caused by the work of such contractors or workmen of Owner, unless specifically permitted elsewhere in the Contract documents.

END OF SECTION