40-Sec 01 11 13 - SUMMARY OF WORK.pdf

PDF 126 KB Posted

Attached to
Bristol Township 2026 Road Paving, Inlet Replacement, and Curb Ramp Program
Solicitation number
Not on record
Issued by
Bucks County, Pennsylvania

About this file

This is a Summary of Work document for Bristol Township's 2026 Road Paving, Inlet Replacement, and Curb Ramp Program in Pennsylvania. The contract encompasses three primary work categories: road paving work including milling, base repair, leveling course, manhole rim adjustments, pavement markings, and wearing course along various township roads; inlet design and replacements at specified locations with contractors responsible for field verification, fabrication, installation, and site restoration; and installation of ADA/PennDOT-compliant curb ramps requiring removal of existing curbs and sidewalks, stone base placement, curb ramp installation with truncated domes, concrete finishing, and utility elevation adjustments. All work must comply with PennDOT Publication 408 and Township Standards. Road paving work cannot begin before June 1, 2026, and construction hours are restricted to 7:30 A.M. to 5:30 P.M. The contractor must provide third-party testing results as required by contract documents and maintain biweekly schedule updates.

The contractor is responsible for protecting all existing utilities and determining their exact locations in accordance with Pennsylvania Act 287. Contractors must provide minimum three-day advance notice to property owners and residents regarding on-street parking restrictions for all three work categories and coordinate signage placement with the township and resident project representative; failure to provide proper notice results in contractor responsibility for towing costs. The work must be performed while existing roadways and utilities remain in operation without jeopardizing system operations. All work requires strict compliance with OSHA Construction Workplace Safety Standards, and contractors must immediately notify the engineer of any observed drainage or ponding issues to develop remediation plans. No products will be supplied by the owner, and the owner will occupy the site throughout the construction period.

View the file

Other files

File Type Posted
24-Doc 00 52 00 - AGREEMENT.pdf PDF
56-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
72-Sec 33 41 00 - STORM DRAIN PIPE.pdf PDF
17-Doc 00 21 13.1 - ELECTRONIC BIDDING INSTRUCTIONS.pdf PDF
70-Sec 32 05 19.13 - GEOTEXTILE.pdf PDF
60-Sec 31 11 00 - CLEARING AND GRUBBING.pdf PDF
71-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
58-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
14-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
7-010 Curb Ramp Construction Notes and Details.pdf PDF
36-Doc 00 73 00 - 01 - APPENDIX A COVER.pdf PDF
1-05 2026 Inlet Program Map - Dixon Ave.pdf PDF
57-Sec 03 20 00 - CONCRETE REINFORCEMENT.pdf PDF
47-Sec 01 22 00 - 03 - EXHIBITS E-F.pdf PDF
59-Sec 31 20 00 - EARTHWORK.pdf PDF
49-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
29-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
35-Doc 00 73 00 - 03 - APPENDIX C COVER.pdf PDF
8-08 BT Curb Ramp Program Plumbridge.pdf PDF
15-Doc 00 11 13 ADVERTISEMENT FOR BIDS-FULL PROGRAM.pdf PDF
12-Doc 00 91 13 - ADDENDA.pdf PDF
6-02 2026 Road Program Striping Details.pdf PDF
74-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
45-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
67-Sec 33 44 14 - STORM INLETS CATCH BASINS ENDWALLS END SECTIONS.pdf PDF
69-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
18-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
3-04 2026 Inlet Program Map - Red Cedar Section.pdf PDF
52-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
63-Sec 02 41 16 - DEMOLITION.pdf PDF
5-06 Inlet Layout Sketches.pdf PDF
39-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
62-Sec 31 23 00 - EXCAVATION BACKFILL AND COMPACTION FOR ROADWAYS.pdf PDF
11-Doc 00 01 10 -TABLE OF CONTENTS.pdf PDF
75-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
26-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
37-Doc 00 73 00 - 00 - SUPPLEMENTARY CONDITIONS.pdf PDF
50-Sec 01 22 00 - 02 - EXHIBITS C-D.pdf PDF
48-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
30-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
76-Sec 32 92 00 - FINISH GRADING SEEDING AND SODDING.pdf PDF
10-09 BT Curb Ramp Program Red Cedar.pdf PDF
2-07 Stormwater Details.pdf PDF
25-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
38-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
13-Doc 00 01 15 - LIST OF DRAWINGS.pdf PDF
19-Doc 00 45 13.1 - CONTRACTOR RESPONSIBILITY CERTIFICATION.pdf PDF
23-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
16-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
64-Sec 31 23 33 - EXCAVATION BACKFILL AND COMPACTION.pdf PDF
Show 40 more

Latest 50 of 75 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUMMARY OF WORK

01 11 13-1

SECTION 01 11 13

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Description of Work.

2. Work by Owner.

3. Work by other parties.

4. Owner supplied Products.

5. Contractor use of site [and premises].

6. Future work.

7. Work sequence of construction.

8. Owner occupancy.

1.02 DESCRIPTION OF WORK

A. ROAD PAVING

This contract consists of a base bid and alternate bid for milling, base repair, leveling course, manhole rim adjustments, pavement markings, and wearing course along various roads within Bristol Township. The roadways and quantities associated with the base bid and each alternate are more fully defined in Exhibits A and B of Section 01 22 00 Measurement and Payment. All material, labor, and equipment necessary shall be in accordance with PennDOT Publication 408 and Township Standards.

B. INLET REPLACEMENTS

This contract consists of a base bid and alternate bid for inlet design and replacements along various roads within Bristol Township. The proposed inlet structure replacements, locations, and quantities associated with the base bid and each alternate are more fully defined in Exhibits C and D of Section 01 22 00 Measurement and Payment. Contractors are responsible for field verifying structure dimensions, existing pipe inverts and sizes, fabricating and installing inlet structures, inlet tops, grates, and performing any landscaping, paving, sidewalk or curb repair required for final restoration.

All material, labor, and equipment necessary shall be in accordance with PennDOT Publication 408 and Township Standards.

C. CURB RAMPS

The Work to be done under this contract associated with curb ramps consists of all labor, equipment, and materials necessary to install curb ramps at specified locations within Bristol Township in accordance with the location specific designs to be provided by the ENGINEER at the pre-construction meeting. The Contractor will remove existing curbs, sidewalks, and/or curb ramps and place and compact the stone base for all curb ramps. The Contractor will install curb ramps, including depressed curb, vertical curb, sidewalk, and ADA/PennDOT compliant truncated domes, in accordance with the specific designs. The Contractor is also to replace any curb and sidewalk that are removed to facilitate the construction of compliant curb ramps in accordance with the contract requirements. The Contractor will remove all forms and finish all concrete surfaces. The Contractor will complete restoration of existing features, including roadway restoration, grading and seeding, incidental to items described in the measurement and payment Section 01 22 00. The Contractor will adjust utility elevations to finish grade, as necessary to facilitate the above work in accordance with ADA/PennDOT grading requirements, and coordinate with the appropriate utility company to accomplish this task. The Contractor will also relocate signage as required to facilitate the above work.

01 11 13-2

D. Contractor will be responsible for providing results of third-party testing performed on site as required by the Contract Documents and in accordance with PennDOT publication 408, section 702 standards.

1.03 WORK BY OWNER

A. No other work is being planned by Owner at the specified locations during construction of the Work under this contract.

1.04 WORK BY OTHER PARTIES

A. The Owner will issue notifications to affected residents regarding curb replacements prior to the scheduled roadwork. Residents have the option to separately contract and complete curb replacements prior to commencement of the contract times. No road paving work is permitted to begin before June 1, 2026.

1.05 OWNER SUPPLIED PRODUCTS

A. No Products are to be supplied and paid for by Owner.

1.06 CONTRACTOR USE OF SITE AND PREMISES

A. The Work under this contract must be accomplished while the existing roadway and utilities are in use. The work that is involved with the existing roadway and utilities must be done so that system operations will not be jeopardized.

B. Contractor shall take all necessary precautions to protect all existing water, gas, electric, communications, sanitary sewer, storm sewer, or other facilities encountered during the course of his operations, to guard against disruption of service. Before beginning Work, Contractor shall determine the location of each facility which is questionable. The location of utilities are not shown on the Drawings and it is the responsibility of Contractor to establish the exact location in accordance with the requirements of Pennsylvania Act 287 (1974) as last amended by Act 121 (2008).

C. FOR ROAD PAVING NOTICES - Contractor is responsible for notifying all property owners and residents a minimum of 3 days prior to milling, paving and/or joint sealant operations that on-street parking will not be permitted during work hours. Notifications must include specific the dates and times for each roadway. If proper notice is not given, the Contractor will be responsible for the towing costs necessary to complete the work. Contractor shall coordinate the schedule and placement of signage with resident project representative and Bristol Township.

D. FOR CURB RAMP NOTICES - Contractor is responsible for notifying all property owners and residents with ramps on their properties via door hanger a minimum of 3 days prior to any work that on-street parking will not be permitted during work hours. Notifications must include specific the dates and times for each curb ramp intersection. If proper notice is not given, the Contractor will be responsible for the towing costs necessary to complete the work.

E. FOR INLET REPLACEMENT NOTICES - Contractor is responsible for notifying any property owners and residents a minimum of 3 days prior to on-street parking will not be permitted during work hours. Notifications must include specific the dates and times for each roadway.

If proper notice is not given, the Contractor will be responsible for the towing costs necessary to complete the work. Contractor shall coordinate the schedule and placement of signage with resident project representative and Bristol Township.

F. Contractor shall conduct all Work in strict compliance with OSHA Construction Workplace Safety Standards.

G. Contractor will be responsible for notifying G&A immediately if they observe/identify any locations of potential drainage/ponding issues while completing the required preconstruction video/photographs or during construction so a plan of action can be created to remediate the issue.

H. Contractor will be responsible for providing schedule updates on a biweekly basis detailing completed work and timeline for anticipated completion of remaining work.

1.07 FUTURE WORK

01 11 13-3

A. No future work is planned.

1.08 WORK SEQUENCE OF CONSTRUCTION

A. Contractor may propose an alternate sequence of construction subject to approval by Engineer.

1.09 OWNER OCCUPANCY

A. Owner will occupy the site during the entire period of construction of construction.

1.10 MUNICIPALITY SPECIFIC REQUIREMENTS

A. Time of Work

Construction at the job site may not begin before 7:30 A.M and must be terminated by 5:30 P.M. This work limitation also includes the moving of equipment.

END OF SECTION