60-Sec 31 11 00 - CLEARING AND GRUBBING.pdf

PDF 134 KB Posted

Attached to
Bristol Township 2026 Road Paving, Inlet Replacement, and Curb Ramp Program
Solicitation number
Not on record
Issued by
Bucks County, Pennsylvania

About this file

This is a technical specification document for clearing and grubbing work associated with Bristol Township's 2026 Road Paving, Inlet Replacement, and Curb Ramp Program in Pennsylvania. The specification outlines the contractor's responsibilities for removing trees, brush, vegetation, debris, fences, walls, signs, and other obstructions within the project limits, as well as grubbing operations to remove stumps, roots, and organic materials to a minimum depth of eight inches below ground surface. Related work includes soil erosion and sediment control, excavation and backfill operations, and finish grading. The contractor is required to notify the Engineer at least 48 hours before beginning clearing work and must coordinate tree removal with the Resident Project Representative. Trees, shrubs, and landscape features designated for preservation must be protected with temporary fencing or barricades, with no materials stored or construction operations conducted within four feet of trees to be saved.

The specification requires topsoil stripping to be staged to limit erosion exposure, with stripped topsoil stockpiled for use in finish grading and prohibited from use as backfill or removal from the site. All debris resulting from clearing and grubbing becomes the property of the contractor and must be disposed of legally at locations outside the project site and public right-of-ways, with written agreements required from property owners receiving deposited debris. Open burning of debris is prohibited. The contractor must restore any injuries to remaining plants using approved arboricultural practices and materials and must replace any trees, shrubs, or plants designated for preservation that are permanently injured or die during construction with like species acceptable to the property owner. Temporary fencing materials specified include four-foot-high picket snow fence or orange mesh plastic construction fencing, with soil-set "T" type fence posts six feet high. Compliance with Pennsylvania Act 287 (1974) regarding utility relocations is required.

View the file

Other files

File Type Posted
24-Doc 00 52 00 - AGREEMENT.pdf PDF
56-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
72-Sec 33 41 00 - STORM DRAIN PIPE.pdf PDF
17-Doc 00 21 13.1 - ELECTRONIC BIDDING INSTRUCTIONS.pdf PDF
70-Sec 32 05 19.13 - GEOTEXTILE.pdf PDF
71-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
58-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
14-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
7-010 Curb Ramp Construction Notes and Details.pdf PDF
36-Doc 00 73 00 - 01 - APPENDIX A COVER.pdf PDF
1-05 2026 Inlet Program Map - Dixon Ave.pdf PDF
57-Sec 03 20 00 - CONCRETE REINFORCEMENT.pdf PDF
47-Sec 01 22 00 - 03 - EXHIBITS E-F.pdf PDF
40-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
59-Sec 31 20 00 - EARTHWORK.pdf PDF
49-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
29-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
35-Doc 00 73 00 - 03 - APPENDIX C COVER.pdf PDF
8-08 BT Curb Ramp Program Plumbridge.pdf PDF
15-Doc 00 11 13 ADVERTISEMENT FOR BIDS-FULL PROGRAM.pdf PDF
12-Doc 00 91 13 - ADDENDA.pdf PDF
6-02 2026 Road Program Striping Details.pdf PDF
74-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
45-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
67-Sec 33 44 14 - STORM INLETS CATCH BASINS ENDWALLS END SECTIONS.pdf PDF
69-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
18-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
3-04 2026 Inlet Program Map - Red Cedar Section.pdf PDF
52-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
63-Sec 02 41 16 - DEMOLITION.pdf PDF
5-06 Inlet Layout Sketches.pdf PDF
39-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
62-Sec 31 23 00 - EXCAVATION BACKFILL AND COMPACTION FOR ROADWAYS.pdf PDF
11-Doc 00 01 10 -TABLE OF CONTENTS.pdf PDF
75-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
26-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
37-Doc 00 73 00 - 00 - SUPPLEMENTARY CONDITIONS.pdf PDF
50-Sec 01 22 00 - 02 - EXHIBITS C-D.pdf PDF
48-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
30-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
76-Sec 32 92 00 - FINISH GRADING SEEDING AND SODDING.pdf PDF
10-09 BT Curb Ramp Program Red Cedar.pdf PDF
2-07 Stormwater Details.pdf PDF
25-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
38-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
13-Doc 00 01 15 - LIST OF DRAWINGS.pdf PDF
19-Doc 00 45 13.1 - CONTRACTOR RESPONSIBILITY CERTIFICATION.pdf PDF
23-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
16-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
64-Sec 31 23 33 - EXCAVATION BACKFILL AND COMPACTION.pdf PDF
Show 40 more

Latest 50 of 75 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CLEARING AND GRUBBING

31 11 00-1

SECTION 31 11 00

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Clearing

2. Grubbing

3. Stripping and stockpiling topsoil

4. Debris disposal

B. Definitions:

1. Clearing is defined as the removal of trees, brush, down timber, rotten wood, rubbish, any other vegetation, and objectionable material at or above original ground elevation not designated to be saved. Clearing also includes removal of fences, walls, guard posts, guard rail, signs, and other obstructions interfering with the proposed work.

2. Grubbing is defined as the removal from below the surface of the natural ground of stumps, roots and stubs, brush, organic materials and debris.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Section 01 57 13: Soil Erosion and Sediment Control

2. Section 31 23 33: Excavation, Backfill and Compaction

3. Section 32 92 00: Finish Grading, Seeding and Sodding

1.03 JOB CONDITIONS

A. Contractor may clear all obstructions within the permanent and temporary construction easements and within the limit of disturbance of Owner's property as absolutely necessary to perform the construction work. Contractor shall leave as many trees as possible within the temporary construction easements and shall not disturb portions of Owner's property beyond the limit of disturbance. Removal of trees shall be coordinated with the Resident Project Representative.

1.04 SUBMITTALS

A. Agreements for Disposal of Debris:

1. Arrange for disposal of debris resulting from clearing and grubbing to locations outside Owner's property, easements and public right-of-ways and obtain a written agreement with the owners of each property where the debris will be deposited.

2. Submit two (2) copies of the agreement with each property owner releasing Owner from responsibility in connection with the disposal of the debris.

PART 2 - PRODUCTS

2.01 MATERIALS

31 11 00-2

A. Temporary Fencing:

1. Undamaged picket snow fence, 4' high, formed of wooden slats, tightly woven with wire cable or orange, open mesh plastic construction fencing, 4' high, or other acceptable, highly visible, weather resistant, easily maintained fencing that provides a substantial barrier.

2. Soil-set fence posts, studded "T" type, 6' high.

B. Tree Wound Dressing:

1. Antiseptic and waterproof, asphalt base.

PART 3 - EXECUTION

3.01 PREPARATION

A. Notify Engineer at least 48 hours prior to beginning any clearing work.

B. Protect benchmarks, utilities, existing trees, shrubs and other landscape features designated for preservation with temporary fencing or barricades satisfactory to the Resident Project Representative. No material shall be stored or construction operation carried on within four

(4) feet of any tree to be saved or within the tree protection fence.

3.02 UTILITY RELOCATIONS

A. Inform all companies, individuals and others owning or controlling facilities or structures within the limits of the work which have to be relocated, adjusted or reconstructed in sufficient time for the utility to organize and perform such work in conjunction with or in advance of Contractor's operations.

B. Comply with the provisions of PA Act 287 (1974) as last amended by PA Act 121 (2008).

3.03 CLEARING

A. Confine clearing as required to within the limits of the public right-of-ways,easements and Owner's property. Attention is called to Paragraph 1.03 of this Section.

B. Fell trees in a manner that will avoid damage to trees, shrubs, and other installations which are to be retained.

C. Where stumps are not required to be grubbed, flushcut with ground elevation.

3.04 GRUBBING

A. Turf clearing and grubbing shall be staged to limit exposure and potential erosion. [For utility construction, stages shall be limited to that length of trench which may be installed and backfilled in one (1)day.]

B. Grub areas within the construction limits to remove roots and other objectionable material to a minimum depth of 8".

C. Remove all stumps within the cleared areas unless otherwise authorized by the Resident

Project Representative.

31 11 00-3

3.05 STRIPPING AND STOCKPILING TOPSOIL

A. Stripping of topsoil shall be staged to limit exposure and potential erosion. [For utility construction, stages shall be limited to that length of trench which may be installed and backfilled in one (1) day.]

B. Strip topsoil to whatever depth it may occur from areas to be excavated, filled, or graded and stockpile at a location approved by the Resident Project Representative for use in finish grading.

C. Topsoil shall not be used as backfill or removed from the site.

3.06 DEBRIS DISPOSAL

A. Trees, logs, branches, brush, stumps, and other debris resulting from clearing and grubbing operations associated with the Work on the Project site and/or within off-site easements/public right-of-ways shall become the property of Contractor and shall be disposed of legally.

B. Debris resulting from the clearing and grubbing work shall not be deposited or buried on the

Project site, easements or public right-of-ways.

C. Open burning of debris is prohibited.

3.07 RESTORATION

A. Repair all injuries to bark, trunk, limbs, and roots of remaining plants by properly dressing, cutting, tracing and painting, using approved arboricultural practices and materials.

B. Replace trees, shrubs and plants designated to be saved which are permanently injured or die during the Contract or the maintenance period as a result of construction operations with like species acceptable to the property owner.

C. Remove protective fences, enclosures and guards upon the completion of the project.

D. Restore guard posts, guard rail, signs and other interferences to the condition equal to that existing before construction operations.

END OF SECTION