67-Sec 33 44 14 - STORM INLETS CATCH BASINS ENDWALLS END SECTIONS.pdf

PDF 124 KB Posted

Attached to
Bristol Township 2026 Road Paving, Inlet Replacement, and Curb Ramp Program
Solicitation number
Not on record
Issued by
Bucks County, Pennsylvania

About this file

This is a technical specification section for storm inlets, catch basins, endwalls, and end sections required for the Bristol Township 2026 Road Paving, Inlet Replacement, and Curb Ramp Program in Pennsylvania. The specification document outlines the work scope to include storm drainage curb inlets, storm drainage catch basins, storm drainage pipe endwalls, and pipe culvert end sections as part of a broader roadway improvement project. The work must comply with Pennsylvania Department of Transportation Publication 408 Specifications and Publication #72 Standards for Roadway Construction, along with applicable ASTM standards for materials and manufacturing. Precast concrete structures and frames must be supplied by manufacturers with at least five years of satisfactory service history, with acceptable vendors including Monarch Precast Concrete Corporation, Modern Concrete Septic Tank Company, Atlantic Concrete Products, and Oldcastle Precast Company. Frames and grates must be provided by Neenah Foundry Company, E.A. Quirin Machine Shop Inc., or East Jordan Iron Works Inc., or approved equals.

Construction requirements specify that precast units must be placed on a twelve-inch coarse aggregate subbase compacted to 95 percent of dry weight density, while cast-in-place units shall be constructed on undisturbed earth. Inlet boxes must be shaped to channel water flow to outlet pipes and prevent standing water, with pipe projections limited to two inches into inlets and no exposed pipe ends through endwall faces. Materials must meet specified ASTM standards including structural steel (ASTM A36), malleable iron castings (ASTM A47 Grade 35018 domestic), ductile iron castings (ASTM A536 Grade 60-40-18 domestic), and concrete per Section 03 30 53. All backfilling and compaction must comply with Section 31 23 33 requirements and receive approval from the Resident Project Representative prior to execution.

View the file

Other files

File Type Posted
24-Doc 00 52 00 - AGREEMENT.pdf PDF
56-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
72-Sec 33 41 00 - STORM DRAIN PIPE.pdf PDF
17-Doc 00 21 13.1 - ELECTRONIC BIDDING INSTRUCTIONS.pdf PDF
70-Sec 32 05 19.13 - GEOTEXTILE.pdf PDF
60-Sec 31 11 00 - CLEARING AND GRUBBING.pdf PDF
71-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
58-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
14-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
7-010 Curb Ramp Construction Notes and Details.pdf PDF
36-Doc 00 73 00 - 01 - APPENDIX A COVER.pdf PDF
1-05 2026 Inlet Program Map - Dixon Ave.pdf PDF
57-Sec 03 20 00 - CONCRETE REINFORCEMENT.pdf PDF
47-Sec 01 22 00 - 03 - EXHIBITS E-F.pdf PDF
40-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
59-Sec 31 20 00 - EARTHWORK.pdf PDF
49-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
29-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
35-Doc 00 73 00 - 03 - APPENDIX C COVER.pdf PDF
8-08 BT Curb Ramp Program Plumbridge.pdf PDF
15-Doc 00 11 13 ADVERTISEMENT FOR BIDS-FULL PROGRAM.pdf PDF
12-Doc 00 91 13 - ADDENDA.pdf PDF
6-02 2026 Road Program Striping Details.pdf PDF
74-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
45-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
69-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
18-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
3-04 2026 Inlet Program Map - Red Cedar Section.pdf PDF
52-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
63-Sec 02 41 16 - DEMOLITION.pdf PDF
5-06 Inlet Layout Sketches.pdf PDF
39-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
62-Sec 31 23 00 - EXCAVATION BACKFILL AND COMPACTION FOR ROADWAYS.pdf PDF
11-Doc 00 01 10 -TABLE OF CONTENTS.pdf PDF
75-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
26-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
37-Doc 00 73 00 - 00 - SUPPLEMENTARY CONDITIONS.pdf PDF
50-Sec 01 22 00 - 02 - EXHIBITS C-D.pdf PDF
48-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
30-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
76-Sec 32 92 00 - FINISH GRADING SEEDING AND SODDING.pdf PDF
10-09 BT Curb Ramp Program Red Cedar.pdf PDF
2-07 Stormwater Details.pdf PDF
25-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
38-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
13-Doc 00 01 15 - LIST OF DRAWINGS.pdf PDF
19-Doc 00 45 13.1 - CONTRACTOR RESPONSIBILITY CERTIFICATION.pdf PDF
23-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
16-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
64-Sec 31 23 33 - EXCAVATION BACKFILL AND COMPACTION.pdf PDF
Show 40 more

Latest 50 of 75 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STORM INLETS, CATCH BASINS, ENDWALLS, END SECTIONS

33 44 14-1

SECTION 33 44 14

PART 1 - GENERAL

1.01. SECTION DESCRIPTION

A. The Work of This Section Includes, but is not limited to:

1. Storm drainage curb inlets

2. Storm drainage catch basins

3. Storm drainage pipe endwalls

4. Pipe culvert end sections

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Section 01 57 13: Soil Erosion and Sediment Control

2. Section 31 23 33: Excavation, Backfill & Compaction

3. Section 32 92 00: Finish Grading, Seeding, and Sodding

1.03 QUALITY ASSURANCE

A. Reference Standards:

1. American Society for Testing and Materials (ASTM):

A36 Specification for Structural Steel A47 Specification for Malleable Iron Castings A536 Specification for Ductile Iron Castings C32 Specification for Sewer and Manhole Brick C270 Specification for Mortar for Unit Masonry

2. Pennsylvania Department of Transportation

Publication 408 Specifications Publication #72 Standards for Roadway Construction

B. Acceptable Manufacturer:

1. Precast structures, and frames and covers shall be provided by a firm regularly engaged in the manufacture of such products of the types, materials and sizes required, whose products have been in satisfactory use in similar service for not less than five (5) years.

2. Precast structures shall be provided by one of the following manufacturers or approved equal.

• Monarch Precast Concrete Corporation

• Modern Concrete Septic Tank Company

• Atlantic Concrete Products

• Oldcastle Precast Company

3. Frames and grates shall be provided by one of the following manufacturers or approved equal.

• Neenah Foundry Company

• E.A. Quirin Machine Ship, Inc.

33 44 14-2

• East Jordan Iron Works, Inc.

1.04 SUBMITTALS

A. Shop Drawings:

1. Submit detailed shop drawings of inlet units, end walls, and end sections including reinforcing steel details.

1.05 PRODUCT DELIVERY, STORAGE AND HANDLING

A. Precast Concrete Units:

1. After fabrication and curing, transport the units to the job site. Protect until required for installation.

2. Handle to avoid damage to surfaces, edges and corners and to avoid creation of stresses within the units.

B. Other Requirements:

1. Section 01 60 00 also addresses transportation and handling along with storage and protection of materials and equipment.

PART 2 - PRODUCTS

2.01 MATERIALS

A. Coarse Aggregate Subbase:

1. PADOT Number 2A, Type C, Section 703.2, Publication 408 Specifications.

B. Brick: ASTM C32, grade SS, solid

C. Masonry Mortar: ASTM C270, Type S

D. Malleable Iron Castings: ASTM A47, Grade 35018. Domestic

E. Ductile Iron Castings: ASTM A536, Grade 60-40-18. Domestic

F. Structural Grade Carbon Steel: ASTM A36

G. Concrete: Section 03 30 53

2.02 FABRICATIONS

A. Precast Cement Concrete Units:

1. Comply with the requirements of Section 713.2(d), Publication 408 Specifications

B. Inlets and Catch Basins:

1. Comply with the type, design and dimensions shown on the Drawings and in accordance with Publication #72 (RC-34) for precast units.

C. End Walls:

33 44 14-3

1. Comply with the type, design and dimensions shown on the Drawings and in accordance with Publication #72 (RC-31) for precast units.

D. Pipe Culvert End Sections:

1. Comply with the type, design and dimensions shown on the Drawings and in accordance with

Publication #72 (RC-33).

PART 3 - EXECUTION

3.01 EXCAVATION

A. Perform excavation in conjunction with storm pipe installation, Section 33 41 00 and as specified in

Section 31 23 33.

B. Locate inlets, catch basins, endwalls and end section indicated on the Drawings.

3.02 CONSTRUCTION

A. Construct inlets and catch basins of either precast sections or of cast-in-place construction in compliance with the type, design and dimensions shown on the Drawings and in accordance with Publication #72 (RC-34).

l. Place precast units on a 12" coarse aggregate subbase placed in 4" layers compacted to

95% of dry weight density.

2. Construct cast-in-place units on undisturbed earth.

3. Shape bottom of inlet boxes to channel flow of water to the outlet pipe and to prevent water from standing in box.

4. Unless units are cast-in-place, use precast concrete sections or brick to adjust to grade.

Mortar in place.

B. Construct endwalls of either precast units of cast-in-place construction in compliance with the type, design and dimensions shown on the Drawings and in accordance with Publication #72 (RC-31).

1. Cast-in-place endwalls shall be monolithically cast reinforced concrete units.

C. Do not permit pipes to project more than 2" into inlets. Do not expose end of pipe through faces of endwalls.

D. Where indicated on the Drawings, provide pipe culvert end sections in compliance with the design and dimensions shown on the Drawings and in accordance with Publication #72 (RC-33).

E. Where indicated, construct energy dissipator in accordance with Section 31 37 16.

3.03 BACKFILLING

A. Backfill structures only after examination by the Resident Project Representative.

B. Perform backfilling and compaction as specified in Section 31 23 33.

END OF SECTION