75-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf

PDF 115 KB Posted

Attached to
Bristol Township 2026 Road Paving, Inlet Replacement, and Curb Ramp Program
Solicitation number
Not on record
Issued by
Bucks County, Pennsylvania

About this file

This is a technical specification document for polymer modified asphalt joint and crack sealing work under the Bristol Township 2026 Road Paving, Inlet Replacement, and Curb Ramp Program in Pennsylvania. The project involves cleaning and sealing pavement surface joints associated with the removal and replacement of concrete curb and curb ramps. All work must comply with PennDOT Publication 408 and Township Standards, with material, labor, and equipment requirements detailed throughout the specification.

The specification requires PG 64-22 asphalt cement obtained from producers listed in PennDOT Bulletin 15 and meeting requirements of PennDOT Bulletin 25. The polymer modified asphalt mixture must combine two pounds of reclaimed granulated rubber per gallon of asphalt cement, heated to 350°F to 380°F for thirty minutes using an oil-jacketed double wall kettle with agitator. Surface preparation requires cleaning joints and adjacent pavement surfaces for four to six inches on either side of the joint using compressed air at minimum 100 psi, followed by application of the polymer modified asphalt level with the pavement surface using a wand and V-shaped squeegee. Installation cannot occur when air temperature is below 40°F or above 90°F unless otherwise permitted by the Engineer, and bituminous overlay placement must be delayed a minimum of seventy-two hours after sealing unless approved by the Engineer. All material shipments require vendor bills of lading containing certification data, viscosity specifications, penetration values, specific gravity, and statements regarding material compatibility and container contamination status.

View the file

Other files

File Type Posted
24-Doc 00 52 00 - AGREEMENT.pdf PDF
56-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
72-Sec 33 41 00 - STORM DRAIN PIPE.pdf PDF
17-Doc 00 21 13.1 - ELECTRONIC BIDDING INSTRUCTIONS.pdf PDF
70-Sec 32 05 19.13 - GEOTEXTILE.pdf PDF
60-Sec 31 11 00 - CLEARING AND GRUBBING.pdf PDF
71-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
58-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
14-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
7-010 Curb Ramp Construction Notes and Details.pdf PDF
36-Doc 00 73 00 - 01 - APPENDIX A COVER.pdf PDF
1-05 2026 Inlet Program Map - Dixon Ave.pdf PDF
57-Sec 03 20 00 - CONCRETE REINFORCEMENT.pdf PDF
47-Sec 01 22 00 - 03 - EXHIBITS E-F.pdf PDF
40-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
59-Sec 31 20 00 - EARTHWORK.pdf PDF
49-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
29-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
35-Doc 00 73 00 - 03 - APPENDIX C COVER.pdf PDF
8-08 BT Curb Ramp Program Plumbridge.pdf PDF
15-Doc 00 11 13 ADVERTISEMENT FOR BIDS-FULL PROGRAM.pdf PDF
12-Doc 00 91 13 - ADDENDA.pdf PDF
6-02 2026 Road Program Striping Details.pdf PDF
74-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
45-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
67-Sec 33 44 14 - STORM INLETS CATCH BASINS ENDWALLS END SECTIONS.pdf PDF
69-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
18-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
3-04 2026 Inlet Program Map - Red Cedar Section.pdf PDF
52-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
63-Sec 02 41 16 - DEMOLITION.pdf PDF
5-06 Inlet Layout Sketches.pdf PDF
39-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
62-Sec 31 23 00 - EXCAVATION BACKFILL AND COMPACTION FOR ROADWAYS.pdf PDF
11-Doc 00 01 10 -TABLE OF CONTENTS.pdf PDF
26-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
37-Doc 00 73 00 - 00 - SUPPLEMENTARY CONDITIONS.pdf PDF
50-Sec 01 22 00 - 02 - EXHIBITS C-D.pdf PDF
48-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
30-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
76-Sec 32 92 00 - FINISH GRADING SEEDING AND SODDING.pdf PDF
10-09 BT Curb Ramp Program Red Cedar.pdf PDF
2-07 Stormwater Details.pdf PDF
25-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
38-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
13-Doc 00 01 15 - LIST OF DRAWINGS.pdf PDF
19-Doc 00 45 13.1 - CONTRACTOR RESPONSIBILITY CERTIFICATION.pdf PDF
23-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
16-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
64-Sec 31 23 33 - EXCAVATION BACKFILL AND COMPACTION.pdf PDF
Show 40 more

Latest 50 of 75 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

POLYMER MODIFIED ASPHALT JOINT AND CRACK SEALING

32 01 17.61-1

SECTION 32 01 17.61

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Asphaltic Joint and Crack Sealing

1.02 DESCRIPTION OF WORK

A. This work is the cleaning and sealing of pavement surface joints associated with the removal and replacement of concrete curb and curb ramps with polymer modified asphalt.

PART 2 PRODUCTS

2.01 ASPHALT CEMENT PG 64-22

A. Obtain material meeting the requirements of PennDOT Bulletin 25 from a producer listed in Bulletin 15.

1. Quality Control Section 01 40 00

2. Certification

a. General

1) When a bituminous material tank is filled, submit a copy of the required test results to the MTD for verification of compliance with Department specifications.

2) Specify the type of material, tank number, and company lot number of the certificate for cross-reference to the bill of lading.

3) Have a responsible company official sign the certificate.

4) Obtain a verification sample from each batch. A batch is a tank completely filled, partially filled, or refilled with a blend of residual and new material.

5) Test one-half (1/2) sample and forward the results to the MTD. Forward the remaining one-half (1/2) sample to the MTD for testing. The MTD will evaluate quality control on the basis of three (3) consecutive verification samples.

b. Levels of Certification

1) Use the same levels of certification as specified in PennDOT Publication 408, Section 701.1(b)2, except substitute the word “batch” for the word “silo.”

c. Handling and Transportation, Section 01 60 00

1) Furnish the vendor’s bill of lading for each shipment (one copy retained by the vendor and one copy included with the shipment to the project). Use a form acceptable to the MTD, containing the following information:

a) Statement that material has been testing and meets Department specifications.

b) Class of Material

c) Tank Number

d) Company Batch Number

e) Date of Shipment

f) Producer’s Name and Location

g) Name and Location of Consignee, (Bituminous Concrete Plant or

Maintenance District)

32 01 17.61-2

h) Mix or Application Temperatures, Minimum and Maximum

i) Viscosity at 140F

j) Penetration at 77F

k) Trailer Number

l) Specific Gravity of Asphalt Cement at 77F

m) Statement that the material is compatible with job aggregate E-4, E-5, E-10, E-11, E-12, MC-400, and MC-800

n) Percent Bitumen Residue by Weight (for liquid bituminous materials only)

o) Quality of Material

p) Statement that the shipment container was determined to be reasonably free of contamination immediately prior to loading

PART 3 EXECUTION

3.01 GENERAL

A. Provide a mixture of asphalt cement and reclaimed granulated rubber, combined to the specified proportions, or furnish a premixed composition as specified in Section 469.2(c) or (d).

3.02 MIXING PROCEDURES

A. Combine the PG 64-22 and reclaimed granulated rubber to obtain a mixture having proportions of two (2 lbs) pounds of RGR per gallon of asphalt cement. Blend the PG 64-22 and reclaimed granulated rubber in an oil-jacketed double wall kettle (indirect hating) equipped with agitator and two (2") inch hot asphalt pump. Provide separate thermometers for oil bath. Heat and agitate the mixture with the temperature range of 350F - 380F for thirty

(30) minutes. Do not allow the operating temperature in the kettle to exceed 400F.

B. For premixed material, as specified in Section 469.2(c) or (d), obtain the safe heating temperature range and recommended pouring temperature from the manufacturer’s shipping container. Place the material within this temperature range, and as close as possible to the recommended pouring temperature. Maintain a safe heating temperature. Do not maintain any single batch of material at the pouring temperature for more than four (4) hours. Reheat only in accordance with manufacturer’s recommendations.

3.03 SURFACE PREPARATION

A. Apply sealer only after joints and adjacent pavement surfaces are clean, dry, and free of any loose material and debris. Clean the pavement for four (4") to six (6") inches on either side of the joint. Air blast joints immediately prior to sealing. Use a compressed air stream of at least 100 psi measured at the source, or use a hot compressed air lance for cleaning and drying damp cracks in the bituminous pavements. Care should be taken to ensure that damage to the surrounding pavement area from overheating does not occur. Seal joints (1/8) to one (1") inch wide with polymer modified asphalt.

3.04 SEALING

A. Apply polymer modified asphalt to prepared joints, level with the pavement surface, using a wand followed by a standard “V” shaped asphalt squeegee. Leave no more than 1/8 inch buildup. Do not place sealer when the air temperature is below 40F or above 90F, unless otherwise permitted by the Engineer if the hot compressed air lance used can sufficiently warm the crack to ensure adhesion between the pavement and the sealer. Do not place bituminous overlay within seventy-two (72) hours of sealing unless permitted by Engineer.

END OF SECTION