52-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf

PDF 135 KB Posted

Attached to
Bristol Township 2026 Road Paving, Inlet Replacement, and Curb Ramp Program
Solicitation number
Not on record
Issued by
Bucks County, Pennsylvania

About this file

This is a Material and Equipment specification section (01 60 00) for the Bristol Township 2026 Road Paving, Inlet Replacement, and Curb Ramp Program in Pennsylvania. The specification establishes requirements for all materials and equipment used in the project, including products, transportation, handling, storage, protection, product options, substitutions, and equipment guarantees. The work encompasses milling, base repair, leveling course, manhole rim adjustments, inlet design and replacements, wearing course installation, and ADA/PennDOT compliant curb ramps with associated sidewalks, curbing, utility adjustments, and sign work across various roads within Bristol Township. All materials and equipment must comply with PennDOT Publication 408 and Township Standards.

The specification requires that all equipment furnished be guaranteed by the manufacturer to be free from defects in workmanship, design, and material for a minimum of 12 months from the date of continuous operation or 18 months from delivery, whichever occurs first. Materials and equipment must be transported and handled according to manufacturer instructions, with prompt inspection upon shipment and appropriate storage and protection measures implemented. Products specified by reference standards or description allow for any compliant product; however, products specified by naming particular manufacturers permit no options or substitutions unless specifically authorized through a formal substitution request process. Substitution requests require three copies of documentation including shop drawings, product data, and certified test results, with the burden of proof on the proposer, and the Engineer reserves the right to require use of listed manufacturers' equipment items specified on the Bid Form.

View the file

Other files

File Type Posted
24-Doc 00 52 00 - AGREEMENT.pdf PDF
56-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
72-Sec 33 41 00 - STORM DRAIN PIPE.pdf PDF
17-Doc 00 21 13.1 - ELECTRONIC BIDDING INSTRUCTIONS.pdf PDF
70-Sec 32 05 19.13 - GEOTEXTILE.pdf PDF
60-Sec 31 11 00 - CLEARING AND GRUBBING.pdf PDF
71-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
58-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
14-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
7-010 Curb Ramp Construction Notes and Details.pdf PDF
36-Doc 00 73 00 - 01 - APPENDIX A COVER.pdf PDF
1-05 2026 Inlet Program Map - Dixon Ave.pdf PDF
57-Sec 03 20 00 - CONCRETE REINFORCEMENT.pdf PDF
47-Sec 01 22 00 - 03 - EXHIBITS E-F.pdf PDF
40-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
59-Sec 31 20 00 - EARTHWORK.pdf PDF
49-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
29-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
35-Doc 00 73 00 - 03 - APPENDIX C COVER.pdf PDF
8-08 BT Curb Ramp Program Plumbridge.pdf PDF
15-Doc 00 11 13 ADVERTISEMENT FOR BIDS-FULL PROGRAM.pdf PDF
12-Doc 00 91 13 - ADDENDA.pdf PDF
6-02 2026 Road Program Striping Details.pdf PDF
74-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
45-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
67-Sec 33 44 14 - STORM INLETS CATCH BASINS ENDWALLS END SECTIONS.pdf PDF
69-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
18-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
3-04 2026 Inlet Program Map - Red Cedar Section.pdf PDF
63-Sec 02 41 16 - DEMOLITION.pdf PDF
5-06 Inlet Layout Sketches.pdf PDF
39-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
62-Sec 31 23 00 - EXCAVATION BACKFILL AND COMPACTION FOR ROADWAYS.pdf PDF
11-Doc 00 01 10 -TABLE OF CONTENTS.pdf PDF
75-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
26-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
37-Doc 00 73 00 - 00 - SUPPLEMENTARY CONDITIONS.pdf PDF
50-Sec 01 22 00 - 02 - EXHIBITS C-D.pdf PDF
48-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
30-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
76-Sec 32 92 00 - FINISH GRADING SEEDING AND SODDING.pdf PDF
10-09 BT Curb Ramp Program Red Cedar.pdf PDF
2-07 Stormwater Details.pdf PDF
25-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
38-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
13-Doc 00 01 15 - LIST OF DRAWINGS.pdf PDF
19-Doc 00 45 13.1 - CONTRACTOR RESPONSIBILITY CERTIFICATION.pdf PDF
23-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
16-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
64-Sec 31 23 33 - EXCAVATION BACKFILL AND COMPACTION.pdf PDF
Show 40 more

Latest 50 of 75 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MATERIAL AND EQUIPMENT

01 60 00-1

SECTION 01 60 00

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Products.

2. Transportation and handling.

3. Storage and protection.

4. Product options.

5. Substitutions.

6. Equipment Guarantee

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Document 00 21 13: Instructions to Bidders: Substitute or “or-equal” items.

2. Section 01 40 00: Quality Control: Product quality monitoring.

1.03 PRODUCTS

A. Do not use materials and equipment removed from existing premises, except as specifically permitted by the Contract Documents.

B. Provide interchangeable components of the same manufacturer for components being replaced.

1.04 TRANSPORTATION AND HANDLING

A. Transport and handle Products in accordance with manufacturer's instructions.

B. Promptly inspect shipments to assure that Products comply with requirements, quantities are correct, and Products are undamaged.

C. Provide equipment and personnel to handle Products by methods to prevent soiling, disfigurement, or damage.

1.05 STORAGE AND PROTECTION

A. Store and protect Products in accordance with manufacturers’ instructions.

B. Store with seals and labels intact and legible.

C. Store sensitive Products in weather tight, climate controlled, enclosures in an environment favorable to Product.

D. For exterior storage of fabricated Products, place on sloped supports above ground.

E. Provide off-site storage and protection when site does not permit on-site storage or protection.

F. Cover Products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of Products.

G. Store loose granular materials on solid flat surfaces in a well-drained area. Prevent mixing with

01 60 00-2 foreign matter.

H. Provide equipment and personnel to store Products by methods to prevent soiling, disfigurement, or damage.

I. Arrange storage of Products to permit access for inspection. Periodically inspect to assure Products are undamaged and are maintained under acceptable condition.

1.06 PRODUCT OPTIONS

A. Products Specified by Reference Standards or by Description Only: Any product meeting those standards or description.

B. Products Specified by Naming One or More Manufacturers: Products of manufacturers named and meeting specifications, no options or substitutions allowed.

C. Products Specified by Naming One or More Manufacturers with a Provision for Substitutions: Submit a request for substitution for any manufacturer not named in accordance with the following Article.

1.07 SUBSTITUTIONS

A. Instructions to Bidders specify time restrictions for submitting requests for Substitutions during the bidding period to requirements specified in this section.

B. Substitutions may be considered when a Product becomes unavailable through no fault of the

Contractor.

C. Document each request with complete data substantiating compliance of proposed Substitution with Contract Documents.

D. A request constitutes a representation that Contractor:

1. Has investigated proposed Product and determined that it meets or exceeds the quality level of the specified Product.

2. Will provide the same warranty for the Substitution as for the specified Product.

3. Will coordinate installation and make changes to other Work which may be required for the

Work to be complete with no additional cost to Owner.

4. Waives claims for additional costs or time extension which may subsequently become apparent.

5. Will reimburse Owner and Engineer for review or redesign services associated with re-approval by authorities.

E. Substitutions will not be considered when they are indicated or implied on shop drawing or Product data submittals, without separate written request, or when acceptance will require revision to the Contract Documents.

F. Substitution Submittal Procedure:

1. Submit three copies of request for Substitution for consideration. Limit each request to one

(1) proposed Substitution.

2. Submit Shop Drawings, Product data, and certified test results attesting to the proposed

Product equivalence. Burden of proof is on proposer.

3. Engineer will notify Contractor in writing of decision to accept or reject request.

G. For each equipment item in which the manufacturer was listed on the Bid Form, Engineer reserves the right to require Contractor to use the equipment item of the listed manufacturer.

01 60 00-3

1.08 EQUIPMENT GUARANTEE

A. All equipment furnished shall be guaranteed by the manufacturer to be free from all defects in workmanship, design and material for a period of not less than 12 months from the date that the equipment is placed in continuous operation or not less than 18 months from the date of delivery to the job site, whichever occurs first.

B. This guarantee shall be in addition to the correction period provided by Contractor under Article 13, paragraph 13.07 of the General Conditions and the Maintenance Bond provided by Contractor under Paragraph 1.09 of the Supplementary Conditions.

C. The manufacturer shall furnish all parts necessary to correct defective work and Contractor shall be responsible for the installation of all parts.

D. If the continuous operation of a piece of equipment is interrupted due to a defect requiring the replacement of the equipment, or part thereof, the equipment manufacturer's 12-month guarantee shall restart from the beginning when the required replacement item is installed and the equipment is returned to continuous operation.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION