55-Sec 01 55 26 - TRAFFIC REGULATION.pdf

PDF 138 KB Posted

Attached to
Bristol Township 2026 Road Paving, Inlet Replacement, and Curb Ramp Program
Solicitation number
Not on record
Issued by
Bucks County, Pennsylvania

About this file

This is a Traffic Regulation specification document (Section 01 55 26) for Bristol Township's 2026 Road Paving, Inlet Replacement, and Curb Ramp Program in Pennsylvania. The specification outlines the contractor's obligations for maintaining safe and efficient traffic movement during construction activities. The contractor must furnish, erect, and maintain traffic control devices including cones, drums, barricades, flashing lights, directional signs, and trained flagpersons as required by state and local permit requirements. Key deliverables include a Traffic Control Plan, advance notifications to relevant parties, construction parking controls, flagperson services, flares and lights for low-visibility periods, established haul routes, and appropriately positioned traffic signs and signals. The contractor is responsible for maintaining at least one traffic lane during non-working periods and must allow emergency vehicle passage at all times. All property owners and residents must receive written notification three days before milling and paving operations regarding on-street parking restrictions, with the contractor bearing responsibility for towing costs if proper notice is not provided.

Additional requirements mandate that the contractor maintain access to adjacent property driveways and entrances during non-working periods and to the maximum extent feasible during work hours, utilizing steel plates or equivalent decking as necessary. Milled surfaces cannot accommodate traffic for more than six calendar days, and the bituminous wearing course must be installed within seven calendar days of milling commencement. All traffic control equipment and devices must meet approval from the authority having jurisdiction, and the contractor must provide advance notification to the local municipal police department at least ten days prior to any traffic restrictions, with fire companies, school districts, ambulance services, and affected residents receiving at least three days' notice. Upon project completion, the contractor is responsible for removing all traffic control equipment and devices, repairing any installation-related damage, and removing post settings to a depth of two feet.

View the file

Other files

File Type Posted
24-Doc 00 52 00 - AGREEMENT.pdf PDF
56-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
72-Sec 33 41 00 - STORM DRAIN PIPE.pdf PDF
17-Doc 00 21 13.1 - ELECTRONIC BIDDING INSTRUCTIONS.pdf PDF
70-Sec 32 05 19.13 - GEOTEXTILE.pdf PDF
60-Sec 31 11 00 - CLEARING AND GRUBBING.pdf PDF
71-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
58-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
14-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
7-010 Curb Ramp Construction Notes and Details.pdf PDF
36-Doc 00 73 00 - 01 - APPENDIX A COVER.pdf PDF
1-05 2026 Inlet Program Map - Dixon Ave.pdf PDF
57-Sec 03 20 00 - CONCRETE REINFORCEMENT.pdf PDF
47-Sec 01 22 00 - 03 - EXHIBITS E-F.pdf PDF
40-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
59-Sec 31 20 00 - EARTHWORK.pdf PDF
49-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
29-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
35-Doc 00 73 00 - 03 - APPENDIX C COVER.pdf PDF
8-08 BT Curb Ramp Program Plumbridge.pdf PDF
15-Doc 00 11 13 ADVERTISEMENT FOR BIDS-FULL PROGRAM.pdf PDF
12-Doc 00 91 13 - ADDENDA.pdf PDF
6-02 2026 Road Program Striping Details.pdf PDF
74-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
45-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
67-Sec 33 44 14 - STORM INLETS CATCH BASINS ENDWALLS END SECTIONS.pdf PDF
69-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
18-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
3-04 2026 Inlet Program Map - Red Cedar Section.pdf PDF
52-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
63-Sec 02 41 16 - DEMOLITION.pdf PDF
5-06 Inlet Layout Sketches.pdf PDF
39-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
62-Sec 31 23 00 - EXCAVATION BACKFILL AND COMPACTION FOR ROADWAYS.pdf PDF
11-Doc 00 01 10 -TABLE OF CONTENTS.pdf PDF
75-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
26-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
37-Doc 00 73 00 - 00 - SUPPLEMENTARY CONDITIONS.pdf PDF
50-Sec 01 22 00 - 02 - EXHIBITS C-D.pdf PDF
48-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
30-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
76-Sec 32 92 00 - FINISH GRADING SEEDING AND SODDING.pdf PDF
10-09 BT Curb Ramp Program Red Cedar.pdf PDF
2-07 Stormwater Details.pdf PDF
25-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
38-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
13-Doc 00 01 15 - LIST OF DRAWINGS.pdf PDF
19-Doc 00 45 13.1 - CONTRACTOR RESPONSIBILITY CERTIFICATION.pdf PDF
23-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
16-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
Show 40 more

Latest 50 of 75 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TRAFFIC REGULATION

01 55 26-1

SECTION 01 55 26

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. This Section involves the Contractor’s obligations relative to maintaining the safe and efficient movement of traffic in the vicinity of construction.

B. Contractor will be required to furnish, erect, and maintain traffic cones, drums, barricades, flashing danger signal lights, directional signs and provide trained and equipped flagmen as required by the State and local permit requirements to restrict the movement of traffic within the construction areas and to clearly indicate the restrictions well in advance to vehicular traffic.

1.02 SECTION INCLUDES

A. Traffic Control Plan B. Notification C. Construction parking controls.

D. Flag persons.

E. Flares and lights.

F. Haul routes.

G. Traffic signs and signals.

H. Other Requirements I. Removal.

1.03 RELATED SECTIONS

A. Section 01 11 13 - Summary of Work.

B. Section 01 31 00 - Coordination and Meetings: Coordination and Project conditions.

PART 2 - PRODUCTS

2.01 SIGNS, SIGNALS, AND DEVICES

A. Post Mounted and Wall Mounted Traffic Control and Informational Signs: As approved by the authority having jurisdiction.

B. Traffic Control Signals: As approved by the authority having jurisdiction.

C. Traffic Cones and Drums, Flares and Lights: As approved by the authority having jurisdiction.

D. Flagperson Equipment: As required by the authority having jurisdiction.

PART 3 - EXECUTION

3.01 TRAFFIC CONTROL PLAN

A. Contractor shall implement Traffic Control Plan requirements imposed by the Road Opening Permit issued by Bristol Township relative to Work.

3.02 NOTIFICATIONS

A. Contractor shall provide advance notification to any parties so noted in the local municipal Road Opening Permit in accordance with the required time schedule. In any event, the local municipal Police Department shall be notified at least ten (10) days prior to the date Contractor desires to restrict traffic in or along any highways or roads.

B. Contractor shall obtain advance approval from the authority having jurisdiction should it be necessary to restrict traffic in or along any highways or roads, including temporary closure of a road. The following parties shall be notified at least three (3) days in advance:

1. Local Municipal Police

2. Local Fire Company

3. Local School District

01 55 26-2

4. Local Ambulance Service

5. All affected residents

C. At least one lane must be open for traffic during non-working periods and Contractor must be prepared to allow passage of emergency vehicles at any time.

D. The Contractor is responsible for notifying all property owners and residents that on-street parking will not be permitted during work hours. Notifications must be distributed 3 days prior to the milling and paving of each road and should include the specific the dates and times. If proper notice is not given, the Contractor will be responsible for the towing costs necessary to complete the work.

3.03 CONSTRUCTION PARKING CONTROLS

A. Control vehicular parking to prevent interference with public traffic and parking, access by emergency vehicles, and Owner's operations.

B. Monitor parking of construction personnel's vehicles in existing facilities. Maintain vehicular access to and through parking areas.

C. Prevent parking on or adjacent to access roads or in non-designated areas.

3.04 FLAG PERSONS

A. Provide trained and equipped flag persons to regulate traffic when construction operations or traffic encroach on public traffic lanes.

3.05 FLARES AND LIGHTS

A. Use flares and lights during hours of low visibility to delineate traffic lanes and to guide traffic.

3.06 HAUL ROUTES

A. Consult with authority having jurisdiction, establish public thoroughfares to be used for haul routes and site access.

3.07 TRAFFIC SIGNS AND SIGNALS

A. At approaches to site and on site, install at crossroads, detours, parking areas, and elsewhere as needed to direct construction and affected public traffic.

B. Install and operate [automatic] traffic control signals to direct and maintain orderly flow of traffic in areas under Contractor’s control, and areas affected by Contractor’s operations.

C. Relocate as Work progresses, to maintain effective traffic control.

3.08 OTHER REQUIREMENTS

A. Maintain access at all times during non-working periods and to the maximum extent feasible during working periods to all driveways and entrances of adjacent properties. In this regard, use and maintenance of steel plates or other decking across the trench may be necessary to reduce to a minimum interference with access to the adjacent properties.

B. Provide safe decking over open trenches in or along highways or roads during non-work periods by the use and maintenance of steel plates or other decking, which shall have sufficient strength to safely support all traffic including truck loads.

C. Do not allow traffic to drive on any milled surface for more than 6 calendar days. The 1-1/2”-inch bituminous wearing course must be installed within 7 calendar days from the start of the milling operation.

3.09 REMOVAL

A. Remove equipment and devices when no longer required.

B. Repair damage caused by installation.

C. Remove post settings to a depth of 2 feet.

END OF SECTION