55-Sec 01 55 26 - TRAFFIC REGULATION.pdf
PDF 138 KB Posted
- Solicitation number
- Not on record
- Issued by
- Bucks County, Pennsylvania
About this file
This is a Traffic Regulation specification document (Section 01 55 26) for Bristol Township's 2026 Road Paving, Inlet Replacement, and Curb Ramp Program in Pennsylvania. The specification outlines the contractor's obligations for maintaining safe and efficient traffic movement during construction activities. The contractor must furnish, erect, and maintain traffic control devices including cones, drums, barricades, flashing lights, directional signs, and trained flagpersons as required by state and local permit requirements. Key deliverables include a Traffic Control Plan, advance notifications to relevant parties, construction parking controls, flagperson services, flares and lights for low-visibility periods, established haul routes, and appropriately positioned traffic signs and signals. The contractor is responsible for maintaining at least one traffic lane during non-working periods and must allow emergency vehicle passage at all times. All property owners and residents must receive written notification three days before milling and paving operations regarding on-street parking restrictions, with the contractor bearing responsibility for towing costs if proper notice is not provided.
Additional requirements mandate that the contractor maintain access to adjacent property driveways and entrances during non-working periods and to the maximum extent feasible during work hours, utilizing steel plates or equivalent decking as necessary. Milled surfaces cannot accommodate traffic for more than six calendar days, and the bituminous wearing course must be installed within seven calendar days of milling commencement. All traffic control equipment and devices must meet approval from the authority having jurisdiction, and the contractor must provide advance notification to the local municipal police department at least ten days prior to any traffic restrictions, with fire companies, school districts, ambulance services, and affected residents receiving at least three days' notice. Upon project completion, the contractor is responsible for removing all traffic control equipment and devices, repairing any installation-related damage, and removing post settings to a depth of two feet.
View the file
Other files
Show 40 more
Latest 50 of 75 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TRAFFIC REGULATION
01 55 26-1
SECTION 01 55 26
PART 1 - GENERAL
1.01 SECTION DESCRIPTION
A. This Section involves the Contractor’s obligations relative to maintaining the safe and efficient movement of traffic in the vicinity of construction.
B. Contractor will be required to furnish, erect, and maintain traffic cones, drums, barricades, flashing danger signal lights, directional signs and provide trained and equipped flagmen as required by the State and local permit requirements to restrict the movement of traffic within the construction areas and to clearly indicate the restrictions well in advance to vehicular traffic.
1.02 SECTION INCLUDES
A. Traffic Control Plan B. Notification C. Construction parking controls.
D. Flag persons.
E. Flares and lights.
F. Haul routes.
G. Traffic signs and signals.
H. Other Requirements I. Removal.
1.03 RELATED SECTIONS
A. Section 01 11 13 - Summary of Work.
B. Section 01 31 00 - Coordination and Meetings: Coordination and Project conditions.
PART 2 - PRODUCTS
2.01 SIGNS, SIGNALS, AND DEVICES
A. Post Mounted and Wall Mounted Traffic Control and Informational Signs: As approved by the authority having jurisdiction.
B. Traffic Control Signals: As approved by the authority having jurisdiction.
C. Traffic Cones and Drums, Flares and Lights: As approved by the authority having jurisdiction.
D. Flagperson Equipment: As required by the authority having jurisdiction.
PART 3 - EXECUTION
3.01 TRAFFIC CONTROL PLAN
A. Contractor shall implement Traffic Control Plan requirements imposed by the Road Opening Permit issued by Bristol Township relative to Work.
3.02 NOTIFICATIONS
A. Contractor shall provide advance notification to any parties so noted in the local municipal Road Opening Permit in accordance with the required time schedule. In any event, the local municipal Police Department shall be notified at least ten (10) days prior to the date Contractor desires to restrict traffic in or along any highways or roads.
B. Contractor shall obtain advance approval from the authority having jurisdiction should it be necessary to restrict traffic in or along any highways or roads, including temporary closure of a road. The following parties shall be notified at least three (3) days in advance:
1. Local Municipal Police
2. Local Fire Company
3. Local School District
01 55 26-2
4. Local Ambulance Service
5. All affected residents
C. At least one lane must be open for traffic during non-working periods and Contractor must be prepared to allow passage of emergency vehicles at any time.
D. The Contractor is responsible for notifying all property owners and residents that on-street parking will not be permitted during work hours. Notifications must be distributed 3 days prior to the milling and paving of each road and should include the specific the dates and times. If proper notice is not given, the Contractor will be responsible for the towing costs necessary to complete the work.
3.03 CONSTRUCTION PARKING CONTROLS
A. Control vehicular parking to prevent interference with public traffic and parking, access by emergency vehicles, and Owner's operations.
B. Monitor parking of construction personnel's vehicles in existing facilities. Maintain vehicular access to and through parking areas.
C. Prevent parking on or adjacent to access roads or in non-designated areas.
3.04 FLAG PERSONS
A. Provide trained and equipped flag persons to regulate traffic when construction operations or traffic encroach on public traffic lanes.
3.05 FLARES AND LIGHTS
A. Use flares and lights during hours of low visibility to delineate traffic lanes and to guide traffic.
3.06 HAUL ROUTES
A. Consult with authority having jurisdiction, establish public thoroughfares to be used for haul routes and site access.
3.07 TRAFFIC SIGNS AND SIGNALS
A. At approaches to site and on site, install at crossroads, detours, parking areas, and elsewhere as needed to direct construction and affected public traffic.
B. Install and operate [automatic] traffic control signals to direct and maintain orderly flow of traffic in areas under Contractor’s control, and areas affected by Contractor’s operations.
C. Relocate as Work progresses, to maintain effective traffic control.
3.08 OTHER REQUIREMENTS
A. Maintain access at all times during non-working periods and to the maximum extent feasible during working periods to all driveways and entrances of adjacent properties. In this regard, use and maintenance of steel plates or other decking across the trench may be necessary to reduce to a minimum interference with access to the adjacent properties.
B. Provide safe decking over open trenches in or along highways or roads during non-work periods by the use and maintenance of steel plates or other decking, which shall have sufficient strength to safely support all traffic including truck loads.
C. Do not allow traffic to drive on any milled surface for more than 6 calendar days. The 1-1/2”-inch bituminous wearing course must be installed within 7 calendar days from the start of the milling operation.
3.09 REMOVAL
A. Remove equipment and devices when no longer required.
B. Repair damage caused by installation.
C. Remove post settings to a depth of 2 feet.
END OF SECTION