54-Sec 01 33 00 - SUBMITTALS.pdf

PDF 118 KB Posted

Attached to
Bristol Township 2026 Road Paving, Inlet Replacement, and Curb Ramp Program
Solicitation number
Not on record
Issued by
Bucks County, Pennsylvania

About this file

This is a Submittals specification section (01 33 00) for the Bristol Township 2026 Road Paving, Inlet Replacement, and Curb Ramp Program in Pennsylvania, establishing procedures and requirements for construction submittals. The project encompasses milling, base repair, leveling course, manhole rim adjustments, inlet design and replacements, wearing course installation, and ADA/PennDOT compliant curb ramp installation along various roads within Bristol Township. Contractors must submit preliminary progress schedules within 10 days of the effective agreement date, with final schedules due within 10 days of the preconstruction conference. All submittals, including construction progress schedules, product data, shop drawings, samples, design data, test reports, and certificates, must be transmitted sequentially to the Engineer with the Contractor's stamp and certification. Contractors must allow 15 days for Engineer review and resubmission for each submittal excluding delivery time. Progress schedules shall be submitted in duplicate with horizontal bar charts showing separate lines for each work section, identifying early and late start/finish dates, float dates, duration, and estimated completion percentages. All work must comply with PennDOT Publication 408 and Township Standards.

The specification requires contractors to provide the number of submittal copies they need plus three copies retained by the Engineer for product data and shop drawings. Product data submissions must identify applicable products, models, and options while supplementing manufacturers' standard data with project-specific information including utility characteristics and connection requirements. Samples must illustrate both functional and aesthetic characteristics with integral parts and attachment devices, coordinated with interfacing work. Revised submittals must identify all changes since previous submissions and include space for Contractor and Engineer review stamps. Certificates from manufacturers, installation subcontractors, or the Contractor must indicate conformance to or exceedance of specified requirements with supporting reference data and affidavits as appropriate. No pricing terms, set-asides, incumbent information, or funding sources are specified in this submittals section document.

View the file

Other files

File Type Posted
24-Doc 00 52 00 - AGREEMENT.pdf PDF
56-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
72-Sec 33 41 00 - STORM DRAIN PIPE.pdf PDF
17-Doc 00 21 13.1 - ELECTRONIC BIDDING INSTRUCTIONS.pdf PDF
70-Sec 32 05 19.13 - GEOTEXTILE.pdf PDF
60-Sec 31 11 00 - CLEARING AND GRUBBING.pdf PDF
71-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
58-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
14-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
7-010 Curb Ramp Construction Notes and Details.pdf PDF
36-Doc 00 73 00 - 01 - APPENDIX A COVER.pdf PDF
1-05 2026 Inlet Program Map - Dixon Ave.pdf PDF
57-Sec 03 20 00 - CONCRETE REINFORCEMENT.pdf PDF
47-Sec 01 22 00 - 03 - EXHIBITS E-F.pdf PDF
40-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
59-Sec 31 20 00 - EARTHWORK.pdf PDF
49-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
29-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
35-Doc 00 73 00 - 03 - APPENDIX C COVER.pdf PDF
8-08 BT Curb Ramp Program Plumbridge.pdf PDF
15-Doc 00 11 13 ADVERTISEMENT FOR BIDS-FULL PROGRAM.pdf PDF
12-Doc 00 91 13 - ADDENDA.pdf PDF
6-02 2026 Road Program Striping Details.pdf PDF
74-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
45-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
67-Sec 33 44 14 - STORM INLETS CATCH BASINS ENDWALLS END SECTIONS.pdf PDF
69-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
18-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
3-04 2026 Inlet Program Map - Red Cedar Section.pdf PDF
52-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
63-Sec 02 41 16 - DEMOLITION.pdf PDF
5-06 Inlet Layout Sketches.pdf PDF
39-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
62-Sec 31 23 00 - EXCAVATION BACKFILL AND COMPACTION FOR ROADWAYS.pdf PDF
11-Doc 00 01 10 -TABLE OF CONTENTS.pdf PDF
75-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
26-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
37-Doc 00 73 00 - 00 - SUPPLEMENTARY CONDITIONS.pdf PDF
50-Sec 01 22 00 - 02 - EXHIBITS C-D.pdf PDF
48-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
30-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
76-Sec 32 92 00 - FINISH GRADING SEEDING AND SODDING.pdf PDF
10-09 BT Curb Ramp Program Red Cedar.pdf PDF
2-07 Stormwater Details.pdf PDF
25-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
38-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
13-Doc 00 01 15 - LIST OF DRAWINGS.pdf PDF
19-Doc 00 45 13.1 - CONTRACTOR RESPONSIBILITY CERTIFICATION.pdf PDF
23-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
16-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
Show 40 more

Latest 50 of 75 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUBMITTALS

01 33 00-1

SECTION 01 33 00

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Submittal procedures.

2. Construction progress schedules.

3. Product data.

4. Shop Drawings.

5. Samples.

6. Design data.

7. Test reports.

8. Certificates.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Section 01 40 00: Quality Control: Manufacturers' field services.

2. Section 01 70 00: Contract Closeout: Contract closeout submittals including maintenance bond, manufacturers’ warranties, and record drawings.

1.03 REFERENCES

A. AGC (Associated General Contractors of America) publication “The Use of CPM in Construction - A Manual for General Contractors and the Construction Industry”.

1.04 SUBMITTAL PROCEDURES

A. Transmit each submittal to Engineer.

B. Sequentially number the transmittal forms. Revise submittals with original number and a sequential alphabetic suffix.

C. Identify Project, Contractor, Subcontractor or supplier; pertinent drawing and detail number, and specification section number, as appropriate.

D. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of Products required, field dimensions, adjacent construction Work, and coordination of information, is in accordance with the requirements of the Work and Contract Documents.

E. Schedule submittals to expedite the Project and to coordinate submission of related items.

F. For each submittal for review, allow 15 days excluding delivery time to and from Contractor.

G. Identify variations from Contract Documents and Product or system limitations which may be detrimental to successful performance of the completed Work.

H. Provide space for Contractor and Engineer review stamps.

I. When revised for resubmission, identify all changes made since previous submission.

J. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report any inability to comply with requirements.

K. Submittals not requested will not be recognized or processed.

1.05 CONSTRUCTION PROGRESS SCHEDULES

A. Submit preliminary progress schedule in duplicate within 10 days after Effective Date of Agreement for review by Engineer.

B. Revise and resubmit as required.

01 33 00-2

C. Submit final progress schedule within 10 days of preconstruction conference or within 10 days upon request of Engineer if no preconstruction conference is to be held.

D. Submit revised progress schedule in duplicate with each Application for Payment, identifying changes since previous version.

E. Submit a horizontal bar chart with separate line for each section of Work, identifying first work day of each week.

F. Show complete sequence of construction by activity, identifying Work of separate stages and other logically grouped activities. Indicate the early and late start, early and late finish, float dates, and duration.

G. Indicate estimated percentage of completion for each item of Work at each submission.

H. Indicate submittal dates required for shop drawings, product data, samples, and product delivery dates, including those furnished by Owner.

1.06 PRODUCT DATA

A. Product Data For Review:

1. Submitted to Engineer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.

2. After review, provide copies and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.

B. Product Data For Information:

1. Submitted for the Engineer’s knowledge as contract administrator or for OWNER.

C. Product Data For Project Closeout:

1. Submitted for Owner’s benefit during and after project completion.

D. Submit the number of copies which Contractor requires, plus three copies which will be retained by Engineer.

E. Mark each copy to identify applicable Products, models, options, and other data. Supplement manufacturers’ standard data to provide information specific to this Project.

F. Indicate Product utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

1.07 SHOP DRAWINGS

A. Shop Drawings For Review:

1. Submitted to Engineer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.

2. After review, produce copies and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.

B. Shop Drawings For Information:

1. Submitted for Engineer’s knowledge as contract administrator or for Owner.

C. Shop Drawings For Project Closeout:

1. Submitted for Owner’s benefit during and after project completion.

D. Indicate special utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

E. Submit the number of opaque reproductions which Contractor requires, plus three copies which will be retained by Engineer.

01 33 00-3

1.08 SAMPLES

A. Samples For Review:

1. Submitted to Engineer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.

2. After review, produce duplicates and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.

B. Samples For Information:

1. Submitted for Engineer’s knowledge as contract administrator or for Owner.

D. Submit samples to illustrate functional and aesthetic characteristics of the Product, with integral parts and attachment devices. Coordinate sample submittals for interfacing work.

E. Include identification on each sample, with full Project information.

F. Submit the number of samples specified in individual specification sections; one of which will be retained by Engineer.

G. Reviewed samples which may be used in the Work are indicated in individual specification sections.

H. Samples will not be used for testing purposes unless specifically stated in the specification section.

1.09 DESIGN DATA

A. Submit for Engineer’s knowledge as contract administrator or for Owner.

B. Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.

1.10 TEST REPORTS

A. Submit for Engineer’s knowledge as contract administrator or for Owner.

B. Submit test reports for information for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.

1.11 CERTIFICATES

A. When specified in individual specification sections, submit certification by the manufacturer, installation/application subcontractor, or Contractor to Engineer, in quantities specified for Product Data.

B. Indicate material or Product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.

C. Certificates may be recent or previous test results on material or Product, but must be acceptable to Engineer.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION